Building Measurement: Section 1: Masonry Take-Off List

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 14

BUILDING

MEASUREMENT
1. INTRODUCTION
Section 1: Masonry Take-off list
Takeoff list is the most required components of any of project. They gives both the client and the
contractor the outline of the total material cost required for the contract. Takeoffs varies from simple to complex depe
takeoff.
Groundwork estimate sheet is also used in the estimation of both the exterior and interior
framing, cabinet and finishes of carpentry. To determine the rough estimate the materials to be
used are listed first with their functions and the parts in which they are used and then calculation is done to get the est
The Builder will tender a price to suppliers
The builder can choose the supplier offering the best price, checking quality and availability at
the same time.
The builder will accept a tender and ask to have materials onsite at a specified time.
Groundwork estimate sheet is also used in the estimation of both the exterior and interior
framing, cabinet and finishes of carpentry. To determine the rough estimate the materials to be used are listed first wi
factors are you should consider when creating that takeoff.
Below is a take-off of groundwork of the project.
Section 3: Cost Analysis
Item Details Est. Cost Actual Cost
Variance

Face Bricks Everyday Life Bricks range - Engage colour $16,964.00 $17,800.00 -$836.0 0
13,411 bricks required

Flashings Average $1.50 per m $495.00 $450.00 $45.00


Shipping
Method
Shipping
Terms
Delivery
Date
Truck + crane 7 days 02/02/2019
Quantity Unit Description Unit Price Total
13,411 Face Everyday Life Bricks range - Engage $1.15 $15422 Bricks
colour
Sub Total $15422

GST $15422

Total $16964
330 m required
Mortar

Mortar Mix 20kg


20 Kg bag covers 20 bricks
Cleaning
Down
Clean brick face and hose down
Lintels Average $25.00 per m

19 m required

Labour Average cost of bricklayer $1.00 a brick


Total
Section 3: Roof Flame and CTake-Off List
Takeoff list is the most required components of any of project. They gives both the client and
the contractor the outline of the total material cost required for the contract. Takeoffs varies from simple to complex d
takeoff.
Carpentry estimate sheet is also used in the estimation of both the exterior and interior framing,
cabinet and finishes of carpentry. To determine the rough estimate the materials to be used are listed first with their fu
to get the estimate quantity.
Below is a take-off of carpentry framing of the interior walls of the garage of Huron County
Ambulance Station encompassing Rooms 100 including all the walls.
Requirements
1. Stud framing
This is the vertical frame in a building of the wall with a small cross section than a post and they are used to carry the
prevent the building from lifted off by severe wind and earthquake.
2. plywood sheathing
This is the layer of material attached to the frame of the roof, floor and wall assembled on the residential and commer
together from the surface is made of hardwood while inside is of softwood.
3. Air Barrier
It is a membrane attached to control air leakage into and out of the building. It is an essential component in a building
the building. It is divided into air barrier material, air accessories, barrier system, and air barrier
component and air assemblies. They takes a lot of forms which can be mechanically membrane,
self-adhered, fluid applied, closed cell medium and polyurethane.
4. Items incidental to the framing
These are the necessary requirement in carpentry but they do not require an illustration or
description because they are either used in small quantity or their price is relatively small. Example of incidental carp
How to estimate framing materials.
Construction materials estimation starts with counting of the frame lumbers .for the wall we
count the number of stud, horizontal plates for both top and bottom of the wall and the number of sheets of the requir
The takeoff of carpentry construction is first done by sketching the wall frame and identify
overall height and length of the wall and sizes of opening like doors and windows. The following is the interior plan o
1. Interior plans of different sections of the garage
The dimensions of the garage that needs to be furnished is; exterior dimensions is length of 50.75 feet, width 36.75 fe
36.25 and the height of 14 ft. The floor and ceiling plan are shown below.
Figure 1. Ground floor plan
Figure 2.Ceiling plan
Figure 3.Roof plan
2. Calculating the studs.
The number of studs required for the project is calculated by use of this procedure; the total wall length is determined
to opening 5 feet wide and to the total add 15 % for wasted material.
3. Estimating the plywood sheathing.
To calculate the number of 5 by 8 inches sheets of sheathing required for framing, first the area of the wall is determin
by 40 and value rounded to nearest whole number which is the number of sheets to cover the
whole area.
TAKE-OFF LIST
CODE Description Check/Complete
01000 Interior Wood stud wall
01001 2x6 framing (16” c/c) Complete

01002 5/8” plywood sheathing Complete


01003 Air barrier Complete

01004 Plywood glue complete


01009 Items incidental to the framing Complete

DIMENSIONS
Description No. Length Width Height/Depth Conversion Quantity

FORWARD FROM PAGE:

1 Interior stud wall


Length of the wall 50.25
2
+36.25+ 14 = 100.5ft
3
4
5 2x6 studs at 16” o/c
6 100.5 ÷ 0.70= 144 1
7 Add studs each corner +3
Add studs at each opening
8
+5
Total studs 144+ 3 + 5 =
9
152 152 14 2128
10
11 5/8” plywood sheathing 2 100.5 14 1407
12
13 Air Barrier 1 125.25 13.33 1669.59
14
15
16

17 Fasteners 0.70lbs/100LF
18 2x6 Studs 2128
19 2124/100 21 0.70 14.7 LBS
20

21

22
PAGE TOTAL
Section 4: Query sheets
simple to complex depending on the size and scope of the project. Due to its importance of cost estimation, this article sheds ligh

on is done to get the estimate quantity.

e used are listed first with their functions and the parts in which they are used and then calculation is done to get the estimate qua

Variance

-$836.0 0

$45.00
om simple to complex depending on the size and scope of the project. Due to its importance of cost estimation, this article sheds

listed first with their functions and the parts in which they are used and then calculation is done

ey are used to carry the vertical structural loads. They holds in place the windows, doors, insulation and interior finishing. They
residential and commercial construction.it is used to form the surface in which materials can be applied. Plywood sheathing is m

component in a building enclosing the air pressure and ensures comfortable environment within

mple of incidental carpentry items include nails, plywood gum and other tools used.

r of sheets of the required for the interior side of the wall.

ing is the interior plan of different section within the office.

0.75 feet, width 36.75 feet and the height is 14 ft and the interior dimension is length 50.75 by width

all length is determined in feet, add 3 for each stud in each corner that is 90 o and add four to 45ocorners.2 studs are added for eac

a of the wall is determined and then the area of openings is subtracted the remaining area divided

/Complete

ete

ete
ete

ete
ete

Quantity UOM

2128 LF

1407 SF

1669.59 SF

LBS
stimation, this article sheds light on how a construction takeoff is crafted and the core components of takeoff are, and what some

is done to get the estimate quantity. Takeoffs varies from simple to complex depending on the size and scope of the project. Due
st estimation, this article sheds light on how a construction takeoff is crafted and the core components of takeoff are, and what so

on and interior finishing. They are slender than posts and beams .They also fastened to the plates to
pplied. Plywood sheathing is made of layers made up of very thin ply or wood that are glued

orners.2 studs are added for each intersection or an opening that is 5feet wide and one stud
f takeoff are, and what some factors are you should consider when creating that

and scope of the project. Due to its importance of cost estimation, this article sheds light on how a construction takeoff is crafted
nts of takeoff are, and what some factors are you should consider when creating that
construction takeoff is crafted and the core components of takeoff are, and what some

You might also like