Assignment 3

This document contains information about an assignment for a project management course on the NPTEL learning platform. It provides details about the assignment such as the due date that has passed and questions related to project life cycles, phases, selection methods, and appraisal. The questions assess knowledge on topics covered in lessons about types of projects, the project life cycle, selection methods, and maturity models. It allows students to submit answers and checks responses against accepted answers.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views

Assignment 3

This document contains information about an assignment for a project management course on the NPTEL learning platform. It provides details about the assignment such as the due date that has passed and questions related to project life cycles, phases, selection methods, and appraisal. The questions assess knowledge on topics covered in lessons about types of projects, the project life cycle, selection methods, and maturity models. It allows students to submit answers and checks responses against accepted answers.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

28/07/2020 Project management for managers - - Unit 3 - Week-2

(https://swayam.gov.in) (https://swayam.gov.in/nc_details/NPTEL)

[email protected]

NPTEL (https://swayam.gov.in/explorer?ncCode=NPTEL) » Project management for managers (course)

Announcements (announcements)

About the Course (https://swayam.gov.in/nd1_noc19_mg31/preview) Ask a Question (forum)

Progress (student/home) Mentor (student/mentor)

Unit 3 - Week-2

Course
outline Assignment 2
How to access The due date for submitting this assignment has passed. Due on 2019-08-21, 23:59 IST.
the portal As per our records you have not submitted this assignment.

Week-1 1) Which of the following is longest phase of a Project life cycle in terms of time? 1 point

Concept phase
Week-2
Implementation phase
Lesson-6 Types Planning phase
of Projects and
Termination phase
Project Life
Cycle (unit? No, the answer is incorrect.
unit=13&lesson=14) Score: 0
Accepted Answers:
Lesson-7
Implementation phase
Project Life
Cycle Phases & 2) Arrange the following elements of the Project Cycle in the right order: 1 point
Project A- Project Appraisal
Appraisal (unit?
B- Feasibility Analysis
unit=13&lesson=15)
C- Negotiation
Lesson-8 D- Project Selection
Methods of
Project A-B-C-D
Selection- I B-A-C-D
(unit?
unit=13&lesson=16) B-A-D-C
A-B-D-C
Lesson-9
Methods of No, the answer is incorrect.
Project Score: 0
Selection- II Accepted Answers:
B-A-D-C

https://onlinecourses.nptel.ac.in/noc19_mg31/unit?unit=13&assessment=110 1/3
28/07/2020 Project management for managers - - Unit 3 - Week-2

(unit? 3) Which is not a Project Management Maturity Model? 1 point


unit=13&lesson=17)
SEI’s (Software Engineering Institute)
Lesson-10
Methods of Center for Business Practices
Project ETI (Education Technical Institute)
Selection
Kerzner’s model
(MCDM -I)
(unit? No, the answer is incorrect.
unit=13&lesson=18) Score: 0
Accepted Answers:
Quiz : ETI (Education Technical Institute)
Assignment 2
(assessment? 4) What is the correct sequence of Project Life Cycle phases? 1 point
name=110)
Initiation, Implementation, Planning and Project Clean-up
Solution for
Assignment - 2 Initiation, Project Clean-up, Planning and Implementation
(unit? Initiation, Project Clean-up, Implementation and Planning
unit=13&lesson=134)
Initiation, Planning, Implementation and Project Clean-up
Feedback week-
No, the answer is incorrect.
2 (unit? Score: 0
unit=13&lesson=20) Accepted Answers:
Initiation, Planning, Implementation and Project Clean-up
Week-3
5) Which of the following is not a part of technical project appraisal? 1 point
Week-4
Engineering aspects
Week-5 Location
Process
Week-6 Pricing options
No, the answer is incorrect.
Week-7 Score: 0
Accepted Answers:
Week-8 Pricing options

6) Project identification is generally done through _______________? 1 point


Week-9
Brainstorming
Week-10
Questionnaire

Week-11 Fundamental analysis


Technical analysis
Week-12 No, the answer is incorrect.
Score: 0
DOWNLOAD Accepted Answers:
VIDEOS Brainstorming

7) Which of the following activity is not a part of development phase? 1 point


Text
Transcription Schematics
Resources
WEEKLY
FEEDBACK Cash flowing
FORM Procurement
No, the answer is incorrect.
Score: 0
Accepted Answers:
Procurement

8) BCG Matrix is used for? 1 point

https://onlinecourses.nptel.ac.in/noc19_mg31/unit?unit=13&assessment=110 2/3
28/07/2020 Project management for managers - - Unit 3 - Week-2

Project appraisal
Project selection
Project controlling
Project budgeting
No, the answer is incorrect.
Score: 0
Accepted Answers:
Project selection

9) Which of the following is not a brainstorming activity? 1 point

Vision for future growth


Long term objectives
Testing
SWOT analysis
No, the answer is incorrect.
Score: 0
Accepted Answers:
Testing

10)New ventures by fresh entrepreneur/promotor are _____________? 1 point

Greenfield projects
Brownfield projects
Conglomerate projects
Concentric projects
No, the answer is incorrect.
Score: 0
Accepted Answers:
Greenfield projects