BUILDING WORKS
Hong Kong Standard Method of Measurement of Building Works - Fourth Edition
Authorised between
The Hong Kong Institute of Surveyors,
The Hong Kong Construction Association Ltd.,
The Hong Kong Government Architectural Services Department,
The Hong Kong Institution of Engineers,
The Hong Kong Electrical & Mechanical Contractors’ Association,
The Chartered Institution of Building Services Engineers, and
The Association of Cost Engineers (Hong Kong Region).
ISBN:988-98402-4-3
All rights reserved. No part of this publication covered by the above copyright may be reproduced, stored in a retrieval system or
transmitted in any form or by any means without the prior permission of the copyright owners.
Preface to Fourth Edition 2005 i
The Hong Kong Standard Method of Measurement of Building Works, since its first Edition in 1962, has evolved to meet the changing methods of construction
and contracting procedures, through the second edition in 1966 and the third edition in 1979. This fourth edition, initiated by The Royal Institution of Chartered
Surveyors (Hong Kong Branch) was subsequently prepared under the auspices of The Hong Kong Institute of Surveyors. It includes sections for Building
Services, which were previously published as a separate document in its first edition in 1993.
The new tabulated format for this fourth edition is based upon the United Kingdom SMM 7, but the Elemental format used in SMM 7 has, by general consent,
not been followed and the Trade Section maintained as being more suitable for the Hong Kong Contracting and Sub-contracting procedures.
It is hoped that the systematic tabulated format will make for easy reference and facilitate the compilation of standard phraseology for libraries of descriptions
and for computerisation.
November, 2005.
ii
Preface to First Edition 1962 iii
The vast development of the building industry in Hong Kong during the past decade has created a wide-spread realisation of the importance and usefulness of Bills of
Quantities. Local conditions have not justified the adoption of the English Standard Method of Measurement, which nevertheless has been followed in a general sense in
Government and private practice and adapted mainly by including most labours with the relative items. Adaptation, however, has been completely arbitrary, depending upon
the discretion or inclination of the individual surveyor. The Services have for some while had their own “Rules of Measurement” for the Far East which is restricted in general
use and application in Hong Kong. Building Contractors, while becoming more and more “B.Q. conscious”, have at the same time been faced with a growing diversity of
methods of measurement which has not only been deleterious to scientific estimating but has in fact resulted in the occurrence of serious errors.
The time, then, has clearly arrived for the introduction of a local standard method of measurement. To this end a meeting of Chartered Quantity Surveyors appointed a Sub-
Committee to consider ways and means of procedure. This Sub-Committee was subsequently joined by representatives of the local building industry to form a Joint Commit-
tee which has now produced this First Edition. In general the procedure was as follows:-
(a) the surveyor members prepared a preliminary draft to be handed trade-by-trade to the builder members for reference to their association for comment or amendment;
(b) the full committee met from time to time to discuss and agree progressively a secondary draft;
(c) the secondary draft was distributed to all interested parties for comment and suggestions;
(d) the full committee considered all suggestions received for adoption or rejection and agreed a final draft.
No attempt has been made to cover every possible item which could arise but rather to produce in the first instance a document ensuring consistency of measurement of those
items normally encountered in the Colony.
It is recommended by the Joint Committee that this document be reviewed annually to consider any revisions or addenda that may become advisable.
H. Miller (Chairman)
R. B. Hanna
C. R. Holmes
J. A. Lilley
J. V. Moore
K. E. N. Goodbourn (vice C. R. Holmes)
S. K. Ho
W. L. Yau
January, 1962.
Preface to Second Edition 1966
The First Edition of this Standard Method of Measurement, published in January 1962, was very well received by quantity surveyors and building contractors and has done
much to foster a growing confidence in Hong Kong in the system of tendering on Bills of Quantities. The document has been adopted for use by all professional surveyors
throughout the Colony and has now been recognised by The Royal Institution of Chartered Surveyors as a basis for local professional examinations.
After the First Edition had been in use for some three years a Standing Joint Committee, comprising equal representation from surveyors and the building industry, was
appointed to keep under review possible amendments and revisions. Suggestions were invited from all local quantity surveyors and building contractors and the Committee
wishes to express its thanks to all who by their response have contributed towards the publication of this Second Edition. It is gratifying to note that, after careful consideration
of all suggestions received, the actual number of revisions incorporated is small and of a minor nature and will therefore cause little disturbance in adopting the later edition.
H. Miller (Chairman)
K. E. N. Goodbourn
D. G. Levett
S. K. Ho
W. L. Yau
G. Yeh
Mr. R. B. Hanna and Mr. G. Luk kindly served on the committee during the temporary absence of Mr. H. Miller and Mr. W. L. Yau respectively.
June, 1966.
iv
Preface to Third Edition 1979 v
The Standard Method of Measurement as first published in 1962 and revised in 1966 has provided a standard for the preparation of Bills of Quantities for a large volume of
building works both in the Public and Private sectors; it is incorporated into the Conditions of Contract for Public Works and the Standard Form of Building Contract issued
under the sanction of The Hong Kong Institute of Architects, The Royal Institution of Chartered Surveyors (Hong Kong Branch) and The Society of Builders, Hong Kong; it is
recognised by The Royal Institution of Chartered Surveyors as a basis for local professional examinations; and it has been translated into Chinese and published as an
ancillary document.
In view of the advancement in engineering technology and architectural design and the ever increasing sophistication of the construction industry in Hong Kong it was decided
that it was necessary to publish a revised edition.
The Committee appointed to administer revisions to the Standard Method of Measurement invited local quantity surveyors and building contractors to submit suggestions for
the improvement and amplification of the document in the light of their experience in its use. All of the suggested alterations were carefully considered, revisions were made
where applicable and new sections such as Demolitions and Alterations, Piling and Caissons, Prestressed Concrete Work and Proprietary Demountable Partitions were
incorporated.
In addition the opportunity was taken to re-edit the document completely to remove uncertainties in interpretation whilst retaining the original intent.
Whilst an appreciable number of alterations have been made, there are very few which involve fundamental changes in the previously prescribed methods of measurement,
the majority of the changes are to update the document in line with the developments in building methods; to make clear the intention, where there appears to be possibility
of misinterpretation; to improve the style or to remove inconsistencies within the document.
The proposal to change from the present system of measurement of mixed earth and rock excavation to a system where rock is measured separately as an “extra over” item
was discussed at length without resolution, the Committee being divided in its views of the practicality of the separate measurement of rock in the Hong Kong situation. The
item was left for further consideration by the Committee when preparing the next Edition.
The Third Edition will become operative on 1st February 1979 and is post dated accordingly.
In view of the decision to adopt the use of the Metric System in the construction industry for all new projects initiated after 1st April 1977 the Third Edition has been published
in metric. It was considered unwarranted to produce an Imperial version as well as the Metric version, although a limited number of contracts already in various stages of
planning will be based upon Imperial Units after this edition becomes operative.
Bills of Quantities prepared after 31st January 1979 in Imperial measurement will be based on this Third Edition, but units of measurement, and any staging or sizes required
to be stated, shall be as detailed in Appendix A.
The Committee expresses its gratitude to the Surveyors and Builders who submitted suggestions for the improvement of the document and to those Specialists who
contributed to the re-drafting of the insurance clauses and the drafting of the piling clauses.
The Committee expresses its special gratitude to the Sub-Committee responsible for carrying out so enthusiastically and so thoroughly the monumental task of translating the
Second Edition into Chinese. The members of this Sub-Committee were :-
B. J. White (Chairman)
K. E. N. Goodbourn
D. G. Levett
John H. P. Lok
Charles C. C. Wong
John W. L. Loo
Other gentlemen who have served on the Committee during the preparation of this edition are :-
H. Miller, the Chairman of the Joint Committee from its inception until his retirement from Hong Kong, R. B. Hanna and Geoffrey M. T. Yeh.
September, 1978.
vi
SUMMARY OF CONTENTS vii
viii
ix
DETAILED CONTENTS (continued)
XIII WOOD WORKS 99 (j) Metal Profiled Sheet Roof Coverings and Wall Claddings 131
(a) Structural Timber 99 (k) Fixed Partitions and Demountable Partitions 133
(b) General Clauses 100 (l) Toilet Cubicle Partitions and Office Cubicle Partitions and Fittings 135
(c) Flooring 101 (m) Suspended Ceilings 136
(d) Raised Access Floors 102 (n) Windows and Glazed Doors 138
(e) Sheet Linings / Claddings, Timber Suspended Ceilings, (o) Shop Fronts 139
Unframed Trims, Insulation, Proofing Works and Fire Stops 103 (p) Curtain Walling 141
(f) Profiled Sheet Roof Coverings and Wall Claddings 107 (q) Furniture, Fittings, Shelving, Racks, Playground Equipment etc. 142
(g) Fixed Partitions and Demountable Partitions 108 XVI PLASTERING AND PAVING 143
(h) Toilet Cubicle Partitions, Office Cubicle Partitions and Fittings 110 (a) Spatterdash 143
(i) Doors, Hatches, Ventilators and the like and Frames and Linings 111 (b) Lathing and Plasterboard 143
(j) Stairs, Handrails and Balustrades 113 (c) General Clauses 144
(k) Furniture, Fittings, Shelving, Racks, Playground Equipment etc. 114 (d) In-situ Surface Finishes and Screeds or Backings 145
(l) Minor Buildings and Structures mainly of Timber Construction 115 (e) Tile and Slab Finishes 148
(m) Insulation / Proofing Works / Fire Stops 116 (f) Rubber and Plastic Sheet or Carpet Sheet / Tile Finishes
XIV IRONMONGERY 117 and the like 151
XV STEEL AND METAL WORKS 119 XVII MECHANICAL INSTALLATIONS 153
(a) Structural Steel 119 (a) General Clauses 153
(b) Linings, Coverings and Cladding 122 (b) Equipment 154
(c) Roofing and Flashings etc. 123 (c) Sanitary and Laboratory Fittings 155
(d) Doors, Gates, Shutters, Grilles and Hatches 124 (d) Pipework 156
(e) Framed Work, Stairs, Handrails and Balustrades 125 (e) Gutters 160
(f) Fencing and Gates 127 (f) Ductwork 161
(g) Minor Buildings and Structures mainly of Metal Construction 128 (g) Insulation 164
(h) Sundries 129 (h) Protective Coverings and Finishings 166
(i) Raised Access Floors 131 (i) Sundries 169
DETAILED CONTENTS (continued)
x
I USE OF TABULATED FORMAT 1
2.2 The method of measurement for work not covered by the clauses of this Standard Method of > = Greater than/exceeding
Measurement, and also deviations from, or qualifications to, this Standard Method of ≤ = Equal to or less than/not exceeding
Measurement, shall be stated in the Preambles to the Bills of Quantities or in the description of
< = Less than
the items to which they apply. The method adopted for work not covered shall, as far as possible,
conform to that given in this document for similar work. dia. = Diameter
min. = Minimum
3. APPLICABILITY OF METHODS OF MEASUREMENT max. = Maximum
3.1 The methods of measurement laid down shall equally apply to the preparation of Bills of Prov’ = Provisional
Quantities before the work is commenced and to the measurement of finished work.
14. DAYWORKS
8. WORK MEASURED NET
14.1 As Contractors have differing practices in:
8.1 Unless otherwise stated, all work shall be measured net as fixed in its place.
(a) the number of hours included in a normal working day;
(b) payment of overtime rates for hours worked in excess of a normal working day;
9. ORDER OF DIMENSIONS (c) payment of overtime rates for Sundays and Labour Holidays,
9.1 In giving dimensions the order should be consistent, and generally in the sequence of length, some provision should be made in Dayworks Schedules for the differentials to be priced,
width and height. probably as percentage on-costs over the normal working days and normal working hours 08:00
to 18:00 hours. Where ‘shift’ work is envisaged that should be separately provided for.
10. DESCRIPTIONS OF ITEMS In general, rates may be different for:
10.1 Notwithstanding these principles of measurement, proprietary items may be measured in a - Normal Working Days
manner appropriate to the manufacturer’s tariff or customary practice. - Sundays
10.2 The descriptions of items in Bills of Quantities may refer to other documents or drawings and any - Labour Holidays
reference to such information shall be understood to fulfil any requirements of these principles of
measurement; alternatively, reference may be made to published information. and at times:
- 08:00 to 18:00 hours
- 18:00 to 24:00 hours
11. COSTS HELD TO BE INCLUDED IN ITEMS
- 00:00 to 04:00 hours
11.1 Each item shall, unless otherwise stated, be held to include:
- 04:00 to 08:00 hours
(a) Labour and all costs in connection therewith;
(b) Materials, goods and all costs in connection therewith (e.g. conveyance, delivery,
unloading, storing, returning packings, handling, hoisting, lowering);
(c) Fitting and fixing materials and goods in position;
(d) Use of plant;
(e) All cutting and waste;
(f) Establishment charges, overhead charges and profit.
HK SMM 4 4
II GENERAL PRINCIPLES 5
14. DAYWORKS (continued) 15. PROVISIONAL AND PRIME COST SUMS (continued)
14.2 Labour shall be paid for on an hourly basis, in the manner suggested above. There should be no (b) The term ‘Prime Cost Sum’ shall mean a sum provided for work or services to be executed
further percentage addition on , the quoted labour rates which will be deemed to include for: by a Nominated Sub-Contractor or for materials or goods to be obtained from a Nominated
Supplier. Such sum shall be deemed to be exclusive of any profit or attendance required by
(a) Wages, bonuses and all allowances paid to operatives directly engaged on dayworks
the Contractor and provision shall be made for the addition thereof.
(including gangers and charge hands working with their gangs and those operating
mechanical plant and transport) in accordance with the appropriate employment
agreement, or where no such agreement exists, the actual payments made to the work
people concerned; 16. WORK UNDER RESERVOIR, RIVER OR SEA WATER
(b) Site supervision, including the cost of foremen and walking gangers and staff insurances; 16.1 All work executed in or under reservoir, river or sea water shall be given separately stating the
levels of high and low water where applicable.
(c) Establishment charges, overhead charges and profit;
(d) Use and maintenance of small hand tools and appliances, non-mechanical plant and
equipment, such as ladders, trestles, stages, bankers, scaffolding, temporary track, 17. WORK IN COMPRESSED AIR
wagons, skips, tarpaulins and all similar items. 17.1 All work required to be carried out in compressed air shall be given separately.
14.3 The costs of materials in dayworks shall be the nett invoiced costs, including delivery to site.
A schedule may be given containing provisional quantities of different materials for the work to
be carried out on a dayworks basis. 18. WORK OUTSIDE THE CURTILAGE OF THE SITE
A percentage item shall be given to enable the Contractor to quote for the inclusion of 18.1 Work outside the curtilage of the site shall be separately identified.
establishment charges, overhead charges and profit.
14.4 The costs of construction plant and vehicles (excluding the cost of operators and drivers who 19. WORK IN EXISTING BUILDINGS
shall be included in labour above) shall be paid for at the rates entered in the schedule for the net
working hours during which the plant is engaged on dayworks, and excluding any standing or 19.1 Work in existing buildings shall be separately identified. Such work is defined as work on, or in, or
idle time, except that plant held on standby by written request from the Architect shall be paid for. immediately under work existing before the current project.
The quoted rates will be deemed to include for: 19.2 Where the premises are occupied, this shall be stated and any restrictions on access or timing or
(a) Transportation costs for plant not already available on the site; disposal of debris, and disposition of plant and materials, shall be given.
(b) Site supervision, hire charges, insurances, consumable stores, fuel and maintenance. 19.3 Where the Contractor is required to arrange access to tenanted areas, separately with each
tenant, this shall be stated and the work kept separate from the work in common areas.
A percentage item shall be given to enable the Contractor to quote for the inclusion of
establishment charges, overhead charges, profit and for any further costs imposed by the above
limitations.
20. TEMPORARY WORKS
20.1 Where the Contractor is required to provide, or to take over existing, temporary works,
15. PROVISIONAL AND PRIME COST SUMS descriptions shall include, where appropriate, references to provision and erecting or taking over
and repairing, maintaining (duration stated), adapting (details stated), handing over to the
15.1 The use of the terms ‘Provisional Sums’ and ‘Prime Cost Sums’ shall be made in conformity with Employer or succeeding Contractor or clearing away and making good all works disturbed.
the following definitions unless otherwise provided in the Conditions of Contract:
(a) The term ‘Provisional Sum’ shall mean a sum provided for work or for costs which cannot
be entirely foreseen, defined or detailed at the time the tendering documents are issued;
HK SMM 4 6
II GENERAL PRINCIPLES 7
APPENDIX “A” to Section II - GENERAL PRINCIPLES
Being Classification of Building Services Works into Systems for Billing Purposes.
Systems, together with their equipment, pipework, ductwork, insulation, trunking, ducting, cable trays, conduits and sundries shall be classified as follows and given under appropriate headings.
The wordings in this list are for reference only, and actual wording should follow those used in the drawings and specifications.
DISPOSAL SYSTEMS VENTILATION/AIR-CONDITIONING/HEATING/REFRIGERATION SYSTEMS
Laboratory/Industrial Waste Drainage Sea Water
Sewage Pumping/Treatment Cooling Water
Incineration Plant Chilled Water
Condensate Drainage
PLUMBING AND WATER SUPPLY, AIR, PETROL, FUEL OIL AND GAS SYSTEMS
General Supply/Extract
Sanitary & Laboratory Fittings
Toilet Extract
Soil, Waste, Ventilation and Rainwater Pipes
Kitchen Extract
Gutters
Car Parking Extract
Potable Water
Smoke Extract/Smoke Control
Hot and Cold Water
Safety Cabinet/Fume Cupboard Extract
Pressurised Water
Fume Extract
Flushing Water
Anaesthetic Gas Extract
Irrigation
Dust Collection
Grey Water
Air-Conditioning
Fountains/Water Features
Window/Wall/Split Type Air-Conditioning Units
Treated/Deionised/Distilled Water
Air Curtains
Swimming Pool Water Treatment
Air and Gas Supply and Distribution ELECTRICAL SUPPLY/POWER/LIGHTING SYSTEMS
Compressed/Instrument Air Electrical Generation Plant
Medical/Laboratory Gas HV Supply/Distribution/Public Utility Supply
Natural Gas LV Supply/Public Utility Supply
Liquid Petroleum Gas General Lighting and Small Power
Vacuum Extra Low Voltage Supply
Steam DC Supply
Uninterrupted Power Supply
FIRE SERVICES INSTALLATION
Electric Underfloor Heating
Fire Hose Reels
Local Electric Heating Units
Wet Risers
Earthing/Lightning Protection and Bonding
Sprinklers
Deluge
Fire Hydrants
Gas Fire Fighting
Foam Fire Fighting
Fire Detection and Alarm
Chilled Water
Cooling Water
APPENDIX “A” to Section II - GENERAL PRINCIPLES (continued)
Being Classification of Building Services Works into Systems for Billing Purposes.
Systems, together with their equipment, pipework, ductwork, insulation, trunking, ducting, cable trays, conduits and sundries shall be classified as follows and given under appropriate headings.
The wordings in this list are for reference only, and actual wording should follow those used in the drawings and specifications.
COMMUNICATIONS/SECURITY/CONTROL SYSTEMS
Telecommunications
Staff Paging/Location
Public Address/Sound Amplification
Centralised Dictation
Radio/TV/CCTV
Projection
Advertising Display
Clocks
Data Transmission
Access Control
Security Detection and Alarm
Earthing and Bonding
Lightning Protection
Electromagnetic Screening
Building Automation including Central Control
HK SMM 4 8
III PRELIMINARIES 9
(See Section II - General Principles)
(a) Preliminary Particulars
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Employer and 1. The names of the Item
Consultants Employer and
Consultants are stated.
2. Where appropriate and
known, the names of the
Main Contractors,
Nominated Sub-
Contractors (where
known) shall also be
given.
2. Description of the 1. A general description of Item M.1 Detailed description
Works the Works comprised in needs to be given only
the Bills of Quantities when the equivalent
shall be given. information is not
indicated on the drawings
2. The size of the building
provided.
and height above and
below ground level are
stated together with the
number of storeys.
3. Site and Inspection 1. The position of the site 1. Attention drawn to any Item
shall be described with adjacent or abutting
any particulars as to buildings
access and any limitations
as to the extent and
position of the working
space.
2. Contractors tendering
shall be advised to visit
the site and inspect trial
holes (if any) and shall be
informed where keys may
be obtained, if required,
and where the drawings
and other documents may
be seen.
3. Any stipulation as to use
or disposal of sand,
gravel or rock that may
be found on the site are
stated.
(a) Preliminary Particulars (continued)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
4. Division of the 1. Where possession of Item
Works into Sections the site is to be given in
sections at different
dates, particulars shall be
given.
2. Where the Works are to
be executed in any
specific order or in
sections, particulars shall
be given.
HK SMM 4 10
III PRELIMINARIES 11
(c) General Matters
Items shall be given in respect of the following unless they are already covered in the Schedule of Clause Headings given in accordance with item III (b).5.1 hereof.
HK SMM 4 12
III PRELIMINARIES 13
HK SMM 4 14
III PRELIMINARIES 15
30. Water 1. Water for the Works, Item 1. If made available by the C.1 applies.
including that for Employer, details and
Nominated Sub- conditions are stated.
Contractors and any
necessary temporary
plumbing and storage
31. Lighting and Power 1. Lighting and power for Item
the Works, including that
for Nominated Sub-
Contractors and any
necessary temporary
wiring and meters
HK SMM 4 16
III PRELIMINARIES 17
HK SMM 4 18
IV DEMOLITIONS AND ALTERATIONS 19
(See Section II - General Principles)
(a) Demolitions
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally M.1 Works involving the D.1 Old materials arising C.1 Giving notice to S.1 Setting aside and
removal of materials from demolitions shall Government Departments storing on site materials
(a) The location of existing buildings to be demolished shall be shown on tender drawings.
containing asbestos, become the property of and Public Utility remaining the property of
(b) Where buildings to be demolished contain prestressed members this shall be stated. toxic, dangerous or other the Contractor unless Companies, if their the Employer or those for
hazardous materials are otherwise stated. installations will be re-use
each given separately affected, and for the
under a heading. disconnection of services
are deemed to be
M.2 Where old materials
included in the rates.
which have become the
property of the Contractor C.2 The rates for works
as stated in D.1. hereof involving the removal of
are permitted to be used asbestos, toxic, dangerous
in work is measured as or other hazardous
new, they are so materials are deemed to
described. No adjustment include for the provision
is made to the measured and subsequent removal
quantities of or rates for of protective screens and
new work in which such enclosures, unless
old materials are used. separately measured, and
provision of protective
M.3 Shoring and
measures for workmen,
scaffolding incidental to
the public and adjoining
demolitions are given in
properties.
the descriptions of the
items. Other shoring, e.g. C.3 The rates for clearing
to old buildings left away old materials and
standing is given in debris containing asbestos
accordance with item or asbestos products,
IV (d).1 hereof. toxic, dangerous or other
hazardous materials are
deemed to include for
their being deposited in a
dump site approved for
the purpose.
IV DEMOLITIONS AND ALTERATIONS
HK SMM 4 20
IV DEMOLITIONS AND ALTERATIONS 21
(b) Alterations
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally M.1 for Demolitions D.1 Old materials arising C.1, C.2 and C.3 for S.1 to S.5 for Demolitions
applies equally to this from alterations shall Demolitions apply equally apply equally to this Sub-
(a) The scope and location of the work relative to the existing layout, indicating the existing buildings, shall
Sub-section. become the property of to this Sub-section. section.
be shown on tender drawings.
the Contractor unless
M.2 Alterations works C.4 Shoring, scaffolding,
(b) Where buildings in which structural alterations are required contain prestressed members, this shall be otherwise stated. Old
which the Surveyor working platforms and
stated. materials permitted to be
considers would be most temporary supports
used in work measured
conveniently priced on incidental to alterations is
as new are so described.
the site are grouped deemed included in the
No adjustment is made to
together and given under items.
the measured quantities
an appropriate sub-
of or rates for new work C.5 Alterations works are
heading.
in which such old deemed to include for all
M.3 Alterations works are materials are used. new fixing or jointing
described or grouped materials required.
D.2 Location is stated
according to location.
relative to existing
M.4 Shoring to old building.
buildings etc. left standing
is given in accordance
with Sub-section (d)
hereof.
HK SMM 4 22
IV DEMOLITIONS AND ALTERATIONS 23
(d) Shoring
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Shoring 1. Position and type of Item 1. Providing and erecting D.1 Shoring is other than C.1 Obtaining licenses S.1 Design details, where
shoring stated, and the temporary support and paying fees and not at the discretion of
2. Taking over existing
nature of the structure to incidental to demolitions providing all necessary the Contractor
shoring and repair as
be shored with sufficient or alterations. wedges, cramps,
necessary
details for identification fastenings and bolts,
stated 3. Maintaining, duration welding and painting is
stated deemed to be included.
4. Adapting, details stated
5. Clearing away and
making good all works
disturbed
6. Cutting holes in the
structure, details stated
HK SMM 4 24
V PILING AND CAISSONS 25
(See Section II - General Principles)
(a) Piling General
(Clauses applicable to all Piling sections)
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1 Generally S.1 Details of treatments
and coatings of piles
The following general information, where available, shall be given:
(a) Ground level in relation to high and low water tables and Ordinance Principal Datum
(b) Soil investigation reports, nature of strata and details of any bore holes
(c) The various levels from which piling frames will operate
(d) Conditions under which Contractors will be permitted to carry out their own soil investigations during
the tender period
(e) Details of special provisions in respect of noise suppression, noisy working, time limitations and
vibration limitations other than Statutory requirements
(f) Any particular requirement regarding phasing or sequence of driving piles
(g) Any limitations on driving methods
HK SMM 4 26
V PILING AND CAISSONS 27
HK SMM 4 28
V PILING AND CAISSONS 29
HK SMM 4 30
V PILING AND CAISSONS 31
TRIAL PILES
12. Trial piles M.5 Trial piles are C.4 Movement of piling frames S.3 If retention on site of
measured in accordance into position and about the site, Trial Pile Equipment is
with the rules for any necessary excavation or required this is stated.
production piles. filling required to place the
frames, raising or lowering the
frames and any staging, barges
or the like required to support
the frames, are deemed to be
included.
(d) Cast In-Situ Concrete Piles in Driven Casings (continued)
TEST LOADING PILES
13. Test loading of piles 1. Type of pile and test nr 1. First test loading C.5 Temporary pile caps
load to be applied stated and provision of all
2. Subsequent test
anchors, platforms,
loadings
loading materials and the
like are deemed to be
included.
HK SMM 4 32
V PILING AND CAISSONS 33
(e) Bored Piles
(See Section V (a) Piling General)
TRIAL PILES
9. Trial piles M.6 Trial piles are C.6 Movement of piling S.5 If retention on site of
measured in accordance frames into position and Trial Pile Equipment is
with the rules for about the site, any required this is stated.
production piles. necessary excavation or
filling required to place the
frames, raising or lowering
the frames and any
staging, barges or the like
required to support the
frames, are deemed to be
included in the item.
HK SMM 4 34
V PILING AND CAISSONS 35
(e) Bored Piles (continued)
TESTING
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
10. Test loading of piles 1. Type of pile and test nr 1. First test loading C.7 Temporary pile caps
load to be applied stated and provision of all
2. Subsequent test
anchors, platforms,
loadings
loading materials and the
like are deemed to be
included.
11. Sonic test m M.7 Measured from cut-off C.8 Sonic tubes and S.6 Grouting materials
level to toe of pile grouting up holes upon
completion of test are
deemed to be included.
12. Concrete coring test 1. Diameter of core and m 1. Starting level of drilling M.8 Depths measured in C.8 applies.
grouting requirements below commencement stages of 15.00 m
(nr C.9 This work is deemed
stated level stated in stages of
to include:
stated) 15.00 m
(a) Movement of the
equipment about the site
(b) Extracting, labelling,
boxing and transporting
cores to a testing
laboratory
13. Vibration test nr
(f) Steel Piles
(See Section V (a) Piling General)
HK SMM 4 36
V PILING AND CAISSONS 37
HK SMM 4 38
V PILING AND CAISSONS 39
(g) Caissons
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally M.1 It is stated whether C.1 The rates for caisson
caisson works are works are deemed to include
The following general information, where available, shall be given:
measured from existing for additional linings or other
(a) Ground level in relation to high and low water tables and Ordinance Principal Datum levels or from stated barriers above ground around
(b) Soil investigation reports, nature of strata and details of any bore holes reduced levels. the shafts, and temporary
covers over the shafts, to be
(c) The various levels from which caisson works will be commenced M.2 If caissons are
provided for safety
measured from existing
(d) Conditions under which Contractors will be permitted to carry out their own soil investigations during requirements.
levels in sloping ground
the tender period the commencing level
(e) Details of special provisions in respect of noise suppression, noisy working, time limitations and shall be deemed to be
vibration limitations other than Statutory requirements that at the centre point of
each caisson.
(f) Any particular requirement regarding phasing or sequence of sinking shafts and constructing caissons
(g) Any limitations on working methods
(h) Whether or not blasting is permitted and any special requirements regarding blasting
(i) Requirements with regard to ventilation of shafts, precautions against noxious gases, lighting in and
access to shafts, lifting appliances and any other safety or special precautions
CAISSON EXCAVATION
CAISSON LININGS
5. Caisson linings 1. Fully described with the m M.3 Linings are measured
minimum internal from the level at which
diameter stated shaft excavation
commences.
6. Bottom kerbs 1. Fully described nr
7. Steel rings at bottom 1. Fully described nr
8. Linings to enlarged 1. Fully described nr
bases
9. Breaking up the 1. Minimum internal m C.3 Any necessary
lining above finished diameter of the lining (nr excavation and clearing
casting level of the stated stated) away is deemed to be
concrete core included in the item.
HK SMM 4 40
V PILING AND CAISSONS 41
(g) Caissons (continued)
CAISSON CORES
HK SMM 4 42
V PILING AND CAISSONS 43
HK SMM 4 44
VI EXCAVATION 45
(See Section II - General Principles)
(a) Excavation
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally S.1 Special requirements
in respect of upholding
Where practicable the nature of the soil shall be described and attention drawn to any existing trial holes.
and maintaining the
sides of earthworks
S.2 Whether or not
blasting is permitted and
any special restrictions
regarding same given
S.3 Any requirements in
respect of phasing or
sequencing of excavation
HK SMM 4 46
VI EXCAVATION 47
HK SMM 4 48
VI EXCAVATION 49
HK SMM 4 50
VI EXCAVATION 51
HK SMM 4 52
VI EXCAVATION 53
(b) Underpinning
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally M.1 Underpinning work,
including concrete,
A description of the work to be underpinned shall be given, stating the length, the depth of the underpinning
brickwork, tanking and
and the limit of the length to be carried out in one operation.
the like is given under a
separate heading.
HK SMM 4 54
VI EXCAVATION 55
10. Tanking
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
HK SMM 4 56
VII CONCRETE WORKS 57
(See Section II - General Principles)
(a) Concrete
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally M.1 Labours to existing C.1 Each item of concrete S.1 Composition and mix
work are measured. work is deemed to include (or strength requirement)
for forming grooves (other of the concrete
M.2 All concrete work is
than in fair faced concrete
measured cube except S.2 Particulars of any
to form ornamental
as hereinafter provided. tests required, both of
features), chases, mortices,
materials and the finished
M.3 Thickness of beds, grouting in balusters,
work
slabs, walls and the like bolts, dowels and the like
is stated. with cement, holes for S.3 Requirements for
M.4 Any treatment of the pipes, etc., ≤ 150 mm compaction
face of concrete, other diameter, openings ≤ S.4 Requirements for
than that required by Sub- 0.025 m2 sectional area, placing in position by a
section (d) C.3 hereof, and the required steel particular method, or
beyond ordinary trimming bars to these pouring at stated speeds.
depositing, spreading and holes and openings and Work to which these
levelling are measured making good and any requirements apply given
separately and given other sundry items of a separately
super. like nature.
HK SMM 4 58
VII CONCRETE WORKS 59
HK SMM 4 60
VII CONCRETE WORKS 61
HK SMM 4 62
VII CONCRETE WORKS 63
HK SMM 4 64
VII CONCRETE WORKS 65
(c) Reinforcement
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally M.1 Each type of steel is S.1 Quality of steel stated
given separately, e.g.
S.2 Particulars given of
Mild Steel, High Yield
any tests required
Steel, etc.
S.3 Any special
restrictions in regard to
hot or cold bending
2. Bar reinforcement 1. Nominal size stated 1. General reinforcement kg 1. Round bars C.1 Variations in weight
due to rolling margin
2. General reinforcement 2. Indented bars
deemed to be included
> 12 m in length, given in
3. Square bars
stages of 3 m C.2 Cutting to lengths,
and bending deemed to
3. Links, stirrups and
be included
binders
C.3 Tying wire, precast
4. Spacers and chairs
concrete or proprietary
designed by the Engineer
spacer blocks and chairs
5. Helical reinforcement and supports (other than
6. Reinforcement bent to spacers, chairs and
curve supports designed by the
Engineer) and ordinary
spacer rods deemed to
be included
3. Threading ends of 1. Sizes of bars stated nr
bars for couplers by
others
4. Couplers 1. Fully described nr M.2 Only couplers C.4 Couplers, other than
included in the Engineer’s those included in the
design are measured. design deemed to be
included
C.5 Threading ends of
bars, where required, is
deemed to be included.
5. Fabric reinforcement 1. Descriptions include the 1. Weight stated m2 1. Flat fabric M.3 Fabric reinforcement C.6 Notchings around
extra materials in laps is measured the nett area obstructions and bending
2. Fabric specially bent to
which are also described covered. deemed to be included
curve.
M.4 No deduction is made
for openings ≤ 1.00 m2.
6. Proprietary anti- 1. Described in detail m
burglar reinforcement. including manufacturer’s
reference
(d) Formwork
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally M.1 Except where D.1 Formwork left-in is C.1 All formwork is S.1 Kind and quality of
otherwise stated, that which is not designed deemed to include all materials and propping
formwork is measured to to remain in position but is necessary materials and requirements for
concrete surfaces of the nonetheless impossible to work for erection, permanent formwork
finished structure which remove. supporting, easing,
S.2 Construction and/or
require support during striking and removal, and
D.2 Permanent formwork lining of formwork which
casting. for re-propping as
is that which is designed is not at the discretion of
required.
M.2 Formwork is to remain in position. the Contractor.
measured super except C.2 Coating with release
S.3 Kind and quality of
as hereinafter provided. agents is deemed to be
the formed finishes
included in the rates for
M.3 No deductions made required
formwork.
for openings ≤ 1.00 m2.
S.4 ‘Formwork to produce
C.3 ‘Formwork to produce
M.4 Formwork left-in and formed finishes’ being
a formed finish’ is deemed
permanent formwork are formwork required to
in addition to include for
each measured produce certain
all necessary sheet lining
separately, except where standards of finishes
materials, forms or linings
more detail is required in
and treating the face of S.5 ‘Specified Formwork’
item (d).5 and 6 hereof.
the concrete to produce being formwork which is
M.5 Formwork to produce the required formed finish. not at the discretion of
a formed finish is the Contractor, i.e. the
C.4 Formwork is deemed
measured separately and Engineer/Architect may
to include for splayed
the finish described. specify the construction
edges, notchings,
and/or lining materials.
allowance for overlaps
and passings at angles,
battens, fillets for chases,
recesses, chamfered
edges and the like and
splayed angles.
HK SMM 4 66
VII CONCRETE WORKS 67
HK SMM 4 68
VII CONCRETE WORKS 69
HK SMM 4 70
VII CONCRETE WORKS 71
HK SMM 4 72
VII CONCRETE WORKS 73
HK SMM 4 74
VIII BRICKWORK AND BLOCKWORK 75
(See Section II - General Principles)
(a) Brickwork and Blockwork
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally M.1 Labours to existing C.1 Each item of
work are each measure Brickwork and Block
separately. Walling is deemed to
include:
M.2 Deductions are
measured the nett sizes (a) All rough and fair
of the openings and cuttings
recesses; no deductions
(b) Wedging and pinning
are made for openings ≤
0.10 m2. (c) Raking out joints to
form key
M.3 Deductions are made
for string courses, cills, (d) Raking out joints for
lintols, and the like only and pointing flashings
to the extent of full brick (e) Labour eaves filling
courses in the height.
(f) Plumbing angles and
M.4 Brickwork and block forming square and
walling circular on plan rebated reveals
are measured the mean
length. (g) Notches, forming or
leaving or cutting chases
(h) Holes and mortices
and cutting and pinning
and making good
(i) Centering
(j) And any other sundry
items of a like nature
(a) Brickwork and Blockwork (continued)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
2. Brick walls 1. Walls > one and a half 1. Various thicknesses all m2 1. Vertical walls D.1 Tapering walls are S.1 Kind and quality and
bricks thick, and a grouped together, wall of diminishing size of bricks
3. Brickwork in filling 2. Tapering walls with one
multiple of half a brick in reduced to one brick thickness.
openings face battering S.2 Bond
thickness thickness and described
D.2 Thickness stated for
4. Isolated piers and as reduced brickwork 3. Tapering walls with both S.3 Composition and mix
tapering walls is mean
chimney stacks faces battering of mortar
thickness.
grouped together
4. Walls built battering S.4 Type of pointing
D.3 Walls built battering
5. Dwarf walls
are sloping walls with
supporting fittings,
parallel sides.
tanks and the like,
grouped together
2. Walls ≤ one and a half 1. Thickness stated m2
bricks thick
3. Walls not a multiple of 1. Thickness stated, m2
half a brick thick description includes for
all cutting
4. Hollow walls 1. Thickness of inner and m2
outer skins and the width
of cavity stated and
disposition of ties
described
5. Brickwork in backing to 1. Description includes for m2
masonry all cutting
6. Extra over brickwork m2 1. General faces S.5 Bond
for fair face
2. Built overhand S.6 Composition and mix
of mortar
3. To battering faces,
described S.7 Type of pointing
4. To curved faces
7. Closing cavities of 1. Materials and method of m
brick hollow walls, at closing described
ends or at openings
8. Arches 1. Height on face and 1. Arches of varying m M.5 Arches are measured
width of exposed portion shapes and types are the mean length on face
of soffit stated given separately and the number stated.
9. Arches of unusual 1. Fully described nr
outline
HK SMM 4 76
VIII BRICKWORK AND BLOCKWORK 77
HK SMM 4 78
VIII BRICKWORK AND BLOCKWORK 79
HK SMM 4 82
IX DRAINAGE (including Underground Pipe Ducts) 83
HK SMM 4 84
X WATERPROOFING (See Section II - General Principles) 85
(a) Asphalt
(b) Liquid Membrane Waterproofing
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally M.1 Work required to be C.1 Work is deemed to S.1 For asphalt work, the
carried out in sections, include: kind and quality of
such as in underpinning (a) Carrying out the work materials including
and to retaining walls, is at any height underlays and
given separately. (b) All temporary rules reinforcement, thickness
(c) Laying to falls and and number of coats and
M.2 No deduction is made
currents, and intersections preparation of underlying
for voids ≤ 0.50 m2.
to work to falls and surfaces
currents
S.2 For liquid membrane
(d) All narrow widths,
work materials are fully
arrises, fair and rounded
described including
edges and turn-ins
priming, number of coats,
(e) Laps, cutting, notching
bonding between coats,
and bending of underlay
preparation of underlying
and reinforcement
surface and any surface
(f) Work carried out in
treatment of final coat.
sections is deemed to
include for jointing
between sections
(g) Working to metal or
other flashings and
working against frames of
manhole covers, duct
covers and the like
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
2. Coverings to 1. Tanking and damp- m2 1. Horizontal M.3 Work is measured the D.1 Work in confined C.2 Roof ventilators S.3 Details and spacing
surfaces proofing net area covered. situations is defined as deemed to be included of roof ventilators
2. Sloping
where at least 0.60 m
2. Roof coverings
3. On soffits working space cannot be
4. Vertical provided.
HK SMM 4 86
X WATERPROOFING 87
(a) Asphalt (continued)
(b) Liquid Membrane Waterproofing (continued)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
19. Solar protection by 1. Application rates of 1. Size of stone chippings m2 S.4 Method of application
dressing with bitumen bitumen and stone stated
and application of stone chippings stated
chippings
20. Application of 1. Number of coats stated m2
reflective paint to
asphalt surfaces
21. Testing Item S.5 Details stated
X WATERPROOFING 88
(c) Felt Roofing
(d) Sheet Membrane Waterproofing
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally M.1 No deduction is made C.1 Work is deemed to S.1 Kind and quality of
for voids ≤ 0.50 m2. include: materials, including
underlays, description of
(a) Carrying out the work
each layer, type of
at any height
bonding between layers,
(b) All narrow widths nature and preparation of,
(c) Laying to falls and and method of fixing to,
currents the underlying surface
HK SMM 4 88
X WATERPROOFING 89
(c) Felt Roofing (continued)
(d) Sheet Membrane Waterproofing (continued)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
6. Linings to gutters 1. Average exposed face m C.4 Lining to gutters,
girth stated dishings to channels and
7. Dishings to channels
coverings to curbs are
8. Coverings to curbs deemed to include edges,
dressing over tilting fillets,
turning nibs into grooves,
ends, angles and
intersections, outlets and
extra materials for turning
into grooves.
9. Linings to cesspools, 1. Exposed face size nr C.5 Linings to cesspools
sumps and the like stated and sumps are deemed to
include internal angles
and outlets.
10. Cutting, fitting and nr M.3 Added together
dressing to outlet pipes irrespective of size
11. Cutting, fitting and
dressing to gullies
12. Cutting, fitting and
dressing around pipes
or railing standards and
the like and forming
collars around them
13. Solar protection by 1. Application rates of 1. Size of stone chippings m2 S.3 Method of application
dressing with bitumen bitumen and stone stated
and application of stone chippings stated
chippings
14. Application of 1. Number of coats stated m2
reflective paint to felt
roof covering
15. Testing Item S.4 Details stated
HK SMM 4 90
XI STONE WORKS 91
(See Section II - General Principles)
(a) Stone Construction
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally M.1 Labours to existing C.1 Stone works are S.1 Kind and quality of
work are measured. deemed to include all materials, and for rubble
cuttings and labours, walling whether random
M.2 Curved work is
hoisting, setting, jointing or squared stones, built
measured the mean
and pointing. with or without mortar. If
length.
built dry, without mortar,
C.2 Uncoursed work is
M.3 Granite, marble or whether the interstices
deemed to include
slate tiling is measured in are filled with stone
levelling the top.
accordance with Section chippings or spalls
XVI (e). C.3 Work is deemed to
S.2 The nature of the
include bedding and
face finish
pointing frames.
S.3 Composition and mix
of mortar
S.4 Thickness of joints
and type of pointing
HK SMM 4 92
XI STONE WORKS 93
(b) Stone Facings to Structural Backgrounds (including Cast Stone, Marble and Granite)
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally M.1 Work is measured, D.1 Internal and external C.1 The work is deemed S.1 Kind and quality of
unless otherwise stated, work are each measured to include: materials
the nett unplastered area separately. (a) Fair joints S.2 Size, shape and
covered. (b) Working over and thickness of units
D.2 The thickness stated
M.2 No deductions are is the thickness exclusive around obstructions S.3 Nature of base
made for voids ≤ 0.50 m2. of keys, grooves and the (c) Additional labour for S.4 Preparatory work,
like. overhand work bonding agents and
M.3 Work to ceilings and
(d) Cutting coating backs
beams over 3.50 m
above floor (measured to (e) Drainage holes S.5 Nature of finished
ceiling level in both (f) Preparatory work, surface, including any
cases) is so described, bedding mortars, sealing and/or polishing
stating the height in adhesives, bonding S.6 Treatment of joints
further 1.50 m stages. agents and additives S.7 Layout of joints
M.4 Curved work is so (g) Fixing devices S.8 Mechanical fixing
described. (h) Coating backs and devices with spacing
cleaning, sealing and stated
polishing faces S.9 Adhesives
HK SMM 4 94
XI STONE WORKS 95
(b) Stone Facings to Structural Backgrounds (including Cast Stone, Marble and Granite) (continued)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
8. Strings 1. Height or width stated 1. Girth on face stated m C.5 Strings and aprons
are deemed to include for
9. Aprons
fair edges, rounded and
bullnosed edges, ends,
angles and ramps.
10. Linings to channels 1. Horizontal m C.6 Linings to channels
are deemed to include
2. To falls
arrises, rounded edges,
coves, ends, angles,
intersections and outlets.
11. Skirtings 1. Height stated m 1. Raking C.7 Skirtings and kerbs
12. Kerbs 1. Height and width stated m 2. Following profile of are deemed to include fair
treads and risers edges, rounded edges,
ends, angles and ramps.
13. Bands in walls 1. Decorative bands 1. Described m 1. If set in walls or floors
of a different material
14. Bands in floors 2. Bands recessed from
this is stated
general surface
3. Bands projecting from
general surface
4. Bands of differing
finished surface from
general surface
15. Panels in walls 1. Decorative panels nr
16. Panels in floors 2. Panels recessed from
general surface
3. Panels projecting from
general surface
4. Panels of differing
finished surface from
general surface
17. Split or polished M.5 Measured in
granite, marble or slate accordance with Section
tiling XVI (e)
(b) Stone Facings to Structural Backgrounds (including Cast Stone, Marble and Granite) (continued)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
18. Corner pieces 1. Dimensioned description nr
------------------------------------
2. Manufacturer’s
reference
19. Items extra over the 1. Special units m D.3 Special units include
work in which they --------- non-standard units to
2. Access units
occur produce fair edges,
nr
3. Isolated special units internal and external
angles, moulded edges
and coved junctions.
20. General counter tops 1. Dimensioned m C.8 Counter tops, seats
description --------- and shelves are deemed
21. Seats
to include fair edges,
nr
22. Shelves rounded edges, bullnosed
edges, ends and angles.
23. Fascias to counters m C.9 Fascias, skirtings
and shelves and splashbacks to
counter tops, seats and
24. Skirtings to counters
shelves are deemed to
and shelves
include fair edges,
25. Splashbacks to rounded edges, bullnosed
counters edges, ends and angles.
26. Bathroom and toilet 1. If in one piece, stated 1. Description includes nr
vanitory slabs profiled edges, upstands,
aprons and openings and
supports and fixings.
27. Accessories 1. Separating membranes, m2
thickness stated
2. Movement joints 1. Dimensioned description m D.4 Movement joints S.10 Method of fixing
3. Cover strips include expansion joints.
4. Dividing strips
28. Carved, engraved or 1. Fully described nr
raised lettering,
symbols and the like
HK SMM 4 96
XII ROOF TILING 97
(See Section II - General Principles)
(a) Chinese Roof Tiling
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally M.1 Work is measured C.1 Each item is deemed S.1 Kind, quality and size
nett area covered. to include for carrying out of materials
the work at any height
M.2 Sloping work, vertical
and for all narrow widths.
work and curved work are
each given separately.
M.3 No deduction is made
for voids ≤ 0.50 m2.
HK SMM 4 98
XIII WOOD WORKS 99
(See Section II - General Principles)
(a) Structural Timber
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally M.1 All sizes are nominal D.1 Metal fasteners, C.1 Work is deemed to S.1 Kind and quality of
sizes unless stated to be included in C.1, is defined include all labours and materials
finished sizes. as toothed connectors, jointing, nailing, screwing
S.2 Method of fixing
split ring connectors or and bolting, including
M.2 Wrought timbers are where not at discretion
shear plate connectors. bolts, nuts, washers and
given separately. of the Contractor
plate washers and metal
M.3 Unless otherwise fasteners. S.3 Methods of jointing
stated all work is and forms of construction,
measured nett as fixed in where not at the discretion
place and no allowance is of the Contractor
made in measurement for
S.4 Preservative
laps or joints.
treatments applied as
part of production
processes
HK SMM 4 100
XIII WOOD WORKS 101
(c) Flooring
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Block flooring 1. Sizes of blocks or 1. Traversing for and m2 M.3 Floors are measured C.1 Floors bedded in S.1 Nature of base
parquet fingers, pattern, nature of polishing stated nett area covered mastic or adhesive are stated
2. Parquet flooring
method of jointing and (measured over borders deemed to include the
bedding materials stated as item (c).6 hereof). mastic or adhesive.
3. Parquet flooring in 1. Sizes of fingers, pattern, m2 C.2 Where described as
preformed panels method of jointing, size on backing and/or
and description of panels moisture resisting
and bedding materials membranes, these are
stated deemed included.
4. Strip flooring 1. Width and thickness of m2 1. Where strip flooring is C.3 Sub-bases and batten
strips, method of jointing fixed to battens, the systems are deemed to be
and fixing to sub-base battens and method of included.
material, bedding fixing them and fixing the
materials or battens strips to the battens is
described.
2. Alternatively, where the
batten system is a
proprietary one a
catalogue reference is
given.
5. Nosings 1. Described, if tongued to m
flooring this is stated
6. Items measured extra 1. Borders 1. Described m M.4 Borders are measured
over block parquet or the mean girth.
strip flooring
7. Accessories 1. Movement joints 1. Dimensioned m D.1 Movement joints S.2 Method of fixing
description include expansion joints.
2. Cover strips
3. Dividing strips
8. Access traps 1. Described nr
9. Mat wells
(d) Raised Access Floors
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Floors 1. Thickness of panels 1. Height of cavity stated m2 1. Patterned, details stated C.1 Raised access floors S.1 Supporting systems
stated are deemed to include:
S.2 Frames to panels
(a) Panels, supporting
S.3 Method of fixing
structures, adhesives,
2. Ramps 1. Thickness, length and nr M.2 The height stated for bearing pads and the like
width stated ramps is the height at
(b) Cutting and notching
each end.
and extra supports
3. Items measured 1. Special panels 1. Dimensioned description nr
extra over the floors in
which they occur
4. Skirtings 1. Dimensioned m M.3 Skirtings and C.2 Skirtings and
description perimeter edge trims not perimeter edge trims are
5. Perimeter edge trims
executed as part of the deemed to include ends
access floors are and angles.
measured in items
(e).13 and 19 hereof.
HK SMM 4 102
XIII WOOD WORKS 103
(e) Sheet Linings/Claddings, Timber Suspended Ceilings, Unframed Trims, Insulation, Proofing Works and Fire Stops
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally M.1 Where grounds and/ D.1 Insulation/proofing C.1 All work is deemed to
or backings are included work/fire stops include: include nailing, adhesives,
in the item this is stated. screwing, cutting, splayed
Flexible sheets, insulating
or rounded edges,
M.2 Work fixed with plugs boards and other
notching, holes, housing
and screws or with screws materials, where not
ends, ship-lap joints,
and cups is so described. specified as part of
mitres, ends, and shaped
another section, laid,
M.3 Where work is fixed ends, angles, junctions,
hung, or fixed horizontally,
with screws other than heading joints, short
sloping or vertically as
ordinary steel, or if lengths and the like.
waterproofing, vapour
pelleting is required, it is
barriers, fire stops, fire
so stated.
barriers, isolating
M.4 Work to ceilings and membranes, sound
beams over 3.50 m above insulation or thermal
floor (measured to ceiling insulation.
level in both cases) except
to staircase areas, it is so
described stating the
height in further 1.50 m
stages.
(e) Sheet Linings/Claddings, Timber Suspended Ceilings, Unframed Trims, Insulation, Proofing Works and Fire Stops (continued)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
2. Sheet linings 1. To walls m2 M.5 No deduction is made D.2 Internal and external
for voids ≤ 0.50 m2. work are each measured
3. Sheet claddings 2. To ceilings and slides
separately.
and soffits of beams M.6 Sides and soffits of
beams are included in the
3. To roofs
item of ceilings and sides
4. To fittings and soffits of beams.
5. Others M.7 Where work is to be in
2
panels to design it is
4. Laminated plastic 1. Backing and adhesive m measured separately
sheeting stated and described.
M.8 Where work requires
tongued angles, chamfers,
rebates, grooves and the
like, this is stated.
HK SMM 4 104
XIII WOOD WORKS 105
(e) Sheet Linings/Claddings, Timber Suspended Ceilings, Unframed Trims, Insulation, Proofing Works and Fire Stops (continued)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
5. Fabric linings 1. Fabric lining and any m2 C.2 Work is deemed to
foam or other backing and include for extra material
adhesive or other method in laps and edge fixings.
of fixing stated
6. Supports for 1. Skeleton grounds, 1. Fixed to soffit, m2 C.3 Work is deemed to
suspended ceilings described background and method include trimming and extra
of fixing described supports and framing
2, Framework, described
around light fittings,
2. Suspended from soffit,
3. Framework for shaped diffusers, speakers and
hangers and spacing
ceiling, described the like. and, where
described with depth of
suspended, for working
suspension ≤ 150 mm
around obstructions and
3. Ditto with depth of services etc.
suspension 150 mm -
500 mm
4. Ditto with depth of
suspension stated
thereafter in 1.50 m
stages.
7. Supports for m2
upstands in suspended
ceilings
8. Ceiling tiles or 1. Described m2 S.1 Required fire ratings,
panels fixed to wood decibel reduction ratings,
framing etc. are stated.
9. Acoustic linings 1. Described 1. Sheets m2 1. Plain areas M.6, M.7 and M.8 apply. D.2 applies. S.2 Extent of laps, where
2. Quilts 2. Across members, M.9 Insulation linings, D.3 Horizontal includes not at the discretion of the
10. Insulation linings
centres of members proofing works and fire the upper surface of any Contractor
11. Proofing linings 3. Boards
stated stops are only measured sloping structure ≤ 45O
12. Fire stops 4. Loose fill independently in this Sub- from the horizontal.
3. Between members,
section where not
centres of members D.4 Vertical includes the
specified as part of
stated upper surface of any
another work section.
sloping structure > 45O
4. Horizontal
from the horizontal.
5. Vertical
D.5 To soffits includes the
6. To soffits underside of any
7. To structural steel horizontal or sloping
framing structure.
(e) Sheet Linings/Claddings, Timber Suspended Ceilings, Unframed Trims, Insulation, Proofing Works and Fire Stops (continued)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
13 Skirtings 1. Dimensioned description, 1. Where services are to m M.10 Work is measured
built up work is so be located within built up nett length as fixed.
14. Architraves
described. work, this is so stated.
M.11 Work tongued on or
15. Picture rails
housed is so described.
16. Dado or chair rails
M.12 Where grounds and/
17. Cornices or backings are included
18. Cappings in the item, this is stated.
19. Others
HK SMM 4 106
XIII WOOD WORKS 107
HK SMM 4 108
XIII WOOD WORKS 109
6. Access panels
5. Fixings for heavy 1. Sinks nr D.4 Heavy fittings are C.6 Fixings for heavy S.11 Type of additional
fittings in fixed those requiring additional fittings are deemed to support
2. Cupboards
partitions support. include additional
3. Others, details stated supports and any cutting
of boarding, trim or
jointing.
6. Sliding and folding M.7 Sliding and folding
partitions partitions are measured in
accordance with the rules
for sliding and folding
doors in Sub-section (i)
hereof.
7. Holes in glass panels M.8 Holes in glass panels
are measured in
accordance with Section
XX Glazing.
(h) Toilet Cubicle Partitions, Office Cubicle Partitions and Fittings
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally C.1 All integral S.1 Kind and quality of
components, holes, etc. materials
The following information shall be provided:
performed at factory and
S.2 Method of
(a) Scope and location of the work connecting and fixing
construction
(b) The services to be located within the partitions devices, supporting legs
and brackets. S.3 Method of bedding,
jointing and pointing
C.2 Cutting and fitting
around obstructions etc. S.4 Details of
and holes for services ironmongery to be
and bedding and pointing included
frames as required. S.5 Proprietary partitions
have catalogue numbers
stated
HK SMM 4 110
XIII WOOD WORKS 111
(i) Doors, Hatches, Ventilators and the like and Frames and Linings
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Flush doors 1. Size, thickness and 1. Single leaf doors nr 1. Rebated stiles, rounded M.1 Glass and glazing C.1 All doors are deemed S.1 Surface treatment
construction stated, and --------- stiles, meeting stiles, beads are measured to include fitting and applied as part of the
2. Folding doors
facings and applied Sets beads and mouldings separately. hanging. production process
mouldings etc. described 3. Swinging doors stated
M.2 Folding doors are C.2 Folding doors include S.2 Bedding, jointing and
4. Sliding doors measured separately, the labours to meeting stiles. pointing compounds
5. Sliding and folding extreme width of each
C.3 Swinging doors
doors leaf is stated in the
include rounded edges to
description.
stiles.
M.3 Doors with shaped
C.4 All items are deemed
heads are so described,
to include bedding and
measured the extreme
pointing frames as
size as square and given
required.
separately.
2. Items measured 1. Openings for glass 1. Size and edge treatment nr 1. Louvres have
extra over flush doors stated dimensioned description
2. Louvered openings
3. Framed and panelled 1. Sectional sizes of stiles, 1. Single leaf doors nr 1. Rebated stiles, rounded
doors rails, transoms, muntins, --------- stiles, meeting stiles,
2. Folding doors
panels and the like given Sets beads and mouldings are
and size and number of 3. Swinging doors described
panels and glazed or 4. Sliding doors 2. Doors with diminished
louvred panels stated
5. Sliding and folding stiles so described
doors 3. Doors with panels of
unusual shaped or
arrangement are so
described.
4. Fire rated doors and 1. Dimensioned description 1. Ironmongery described Sets 1. Fire rating stated M.4 Fire rated doors are
frames of doors, frames and/or measured complete with
linings frames and ironmongery
and glazing etc.
(i) Doors, Hatches, Ventilators and the like and Frames and Linings (continued)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
5. Louvres and frames 1. Size, thickness and 1. Louvres have nr 1. Sectional sizes of
construction stated dimensioned description frames stated
6. Service hatches and nr
frames
7. Duct access doors, nr
panels and trapdoors
and frames
8. Door frames 1. Overall sizes of doors 1. Solid and built-up nr 1. Frames incorporating
or door sets given, and frames or linings given fanlights or side lights
9. Door linings
cross-section of members separately, grounds or given separately and the
stated backings described and fanlight or sidelight
included in the item described
2. Rebated heads and
jambs or hollowed jambs
described
10. Trims and architraves M.5 Trims and architraves
are measured in
accordance with Sub-
section (e) hereof.
HK SMM 4 112
XIII WOOD WORKS 113
2. Wood facings to nr
stairs of construction
other than timber
3. Handrails 1. Dimensioned description m
with method of jointing
handrail stated. If
hollowed for and screwed
to metal core this is
stated
4. Items measured 1. Ramps nr C.1 Plain ends deemed to
extra over handrails be included
2. Wreaths
3. Bends
4. Ornamental ends
5. Balustrades 1. Dimensioned description m
with spacing of balusters
stated
6. Items measured 1. Ramps nr C.1 applies.
extra over balustrades
2. Wreaths
3. Bends
4. Ornamental ends
5. Opening portions,
details stated
6. Method of jointing
handrail stated
(k) Furniture, Fittings, Shelving, Racks, Playground Equipment etc.
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Furniture 1. Drawing reference and/ 1. Description includes nr 1. Where these items are M.1 Alternatively these C.1 For items provided by S.1 Such information as
or dimensioned ironmongery and/or metal to be provided by the items may be measured the Employer, accepting is appropriate to the
2. Fittings
description as appropriate fittings, glass panels etc. Employer for the in detail in accordance delivery on site, storing procurement, design,
3. Shelving with background for fixing which are to be included Contractor to fix, the with the appropriate rules. and handling are deemed execution, supply and/or
4. Racks stated in the item. method of fixing is stated. to be included. manufacture of the item
and its incorporation in
5. External furniture 2. For items provided by
the Works
and equipment the Employer, the
provision by the S.2 Finishes and surface
6. Sign boards and Contractor of any treatments applied in
signage additional components, manufacture or off site
7. Playground etc. is stated.
S.3 Finishes and surface
equipment treatments applied on
8. Others site
HK SMM 4 114
XIII WOOD WORKS 115
HK SMM 4 116
XIV IRONMONGERY 117
(See Section II - General Principles)
HK SMM 4 118
XV STEEL AND METAL WORKS 119
(See Section II - General Principles)
(a) Structural Steel
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally S.1 Types and grades of
materials
The following information shall be shown either on location drawings or on other drawings accompanying
the Bills of Quantities. S.2 Methods of
fabrication
(a) The position of the work in relation to other parts of the work and of the proposed buildings
S.3 Details of welding
(b) The types and sizes of structural members and their positions in relation to each other
tests and X-rays
(c) Details of connections or of the reactions, moments and axial loads at connection points
S.4 Details of
performance tests
(a) Structural Steel (continued)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
2. Columns 1. Framing, fabrication 1. Joists kg 1. Castellated M.1 The items listed in the D.1 Wires, cables, rods C.1 Items for fabrication
and erection 1st column are headings and bars include sag and erection are deemed
3. Beams 2. Channels 2. Tapered
under which the various rods, ties and the like. to include for:
4. Bracing 3. Angles 3. Curved sections in the 3rd
(a) Shop and site rivets
5. Purlins and cladding 4. Tees 4. Cambered column are measured.
and black bolts, nuts and
rails M.2 The mass of framing washers
5. Tubular sections 5. Weights of sections
6. Grillages stated members is measured
6. Plates (b) Welding, welding
from their overall lengths
7. Built-up columns, tests and X-rays
7. Wires with no deductions for
trestles and towers splay cuts or mitred ends (c) Performance tests
8. Cables or of the mass of metal
8. Built-up trusses and (d) Packings where
girders 9. Rods removed to form notches required for connections,
and holes. caps and bases
10. Bars
M.3 No allowance is made (e) Wedging and grouting
11. Others for the mass of weld under bases
fillets, black bolts, nuts,
washers, rivets and
protective coatings for
rolling margins.
9. Overhead crane rails 1. Framing, fabrication 1. Joists kg 1. Curved M.4 Where structural steel
and erection is not a major part of the
2. Channels 2. Weight of sections
structure it shall be
2. Details of fixing clips stated
3. Angles grouped according to
and resilient pads and
4. Tees bearing levels for hoisting
fittings stated
and fixing which shall be
5. Tubular sections stated in stages of 3.00 m
6. Plates above ground level.
HK SMM 4 120
XV STEEL AND METAL WORKS 121
HK SMM 4 122
XV STEEL AND METAL WORKS 123
HK SMM 4 124
XV STEEL AND METAL WORKS 125
HK SMM 4 126
XV STEEL AND METAL WORKS 127
HK SMM 4 128
XV STEEL AND METAL WORKS 129
(h) Sundries
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally S.1 Kind and quality of
materials
S.2 Method of
construction
S.3 Surface finishes and
treatments applied as
part of the production
process
HK SMM 4 130
XV STEEL AND METAL WORKS 131
HK SMM 4 132
XV STEEL AND METAL WORKS 133
HK SMM 4 134
XV STEEL AND METAL WORKS 135
(l) Toilet Cubicle Partitions and Office Cubicle Partitions and Fittings
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally C.1 Cubicle partitions are S.1 Kind and quality of
deemed to include all materials
The following information shall be provided:
integral components, S.2 Method of
(a) Scope and location of the work holes, etc. preformed at construction
(b) The services to be located within the partitions factory and connecting
and fixing devices, S.3 Method of bedding,
supporting legs and jointing and pointing
brackets. S.4 Details of
C.2 Work is deemed to ironmongery to be
include cutting and fitting included
around obstructions etc. S.5 Proprietary partitions
and holes for services have catalogue numbers
and bedding and pointing stated
frames as required.
HK SMM 4 136
XV STEEL AND METAL WORKS 137
4. Composite metal 1. Dimensioned description, 1. Number of units and nr 1. Glazing beads described (h) Stripping protective
windows overall size and drawing number and size of coverings or coatings
2. Ironmongery described
reference stated coupling mullions and C.2 Composite aluminium
5. Composite metal
transoms stated, and units are deemed to
windows and doors
number of fixed lights include for galvanised
and number and type of steel strengtheners inside
opening lights stated mullions and transoms.
6. Remote control gears 1. Dimensioned description, nr
stating number of lights to
be opened
HK SMM 4 138
XV STEEL AND METAL WORKS 139
HK SMM 4 140
XV STEEL AND METAL WORKS 141
HK SMM 4 142
XVI PLASTERING AND PAVING 143
(See Section II - General Principles)
(a) Spatterdash
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Spatterdash 1. To all surfaces m2 M.1 All surfaces are
measured together.
HK SMM 4 144
XVI PLASTERING AND PAVING 145
HK SMM 4 146
XVI PLASTERING AND PAVING 147
HK SMM 4 148
XVI PLASTERING AND PAVING 149
17. Movement joints 1. Dimensioned description m D.1 Movement joints S.6 Method of fixing
include expansion joints.
18. Cover strips
19. Division strips
20. Non-slip inserts 1. Described m
21. Filling in to trench 1. Width and thickness m 1. Where jointing is
covers stated required to line with
adjoining work it is so
22. Filling in to insets, 1. Sizes stated m
stated.
manhole covers and
mat sinkings
23. Accessories 1. Nosings 1. Dimensioned m C.5 Nosings are deemed
description to include working
2. Cover strips
finishes thereto.
3. Dividing strips
C.6 Mitred regular and
irregular angles are
deemed to be included.
HK SMM 4 150
XVI PLASTERING AND PAVING 151
(f) Rubber and Plastic Sheet or Carpet Sheet/Tile Finishes and the like
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally M.1 Work measured under D.1 Rounded internal and C.1 Work is deemed to S.1 Kind and quality and
this Sub-section includes external angles > 100 mm include: size of materials
synthetic rubber, radius are classified as S.2 Nature and number of
(a) Rounded internal and
linoleum, cork, rubber, curved work.
external angles ≤ 100 mm underlays
vinyl sheeting, fibreglass
radius S.3 Nature of base
membrane, ball court
finishes, acoustic (b) Seams and fair joints S.4 Method of fixing and
sheetings, carpet and (c) Fixing at perimeter treatment of joints
carpet tiles, artificial
turfing, and the like. Each (d) Cutting and fitting up S.5 Extent of laps
type of work is grouped to frames and metalwork S.6 Types of seams
under a separate and around pipes and
heading. bracket ends and the like S.7 Pattern, width and
laying direction of
materials
S.8 Surface treatment
8. Skirtings 1. Height stated 1. Flush m 1. Pattened, details stated C.5 Work to skirtings and
------------------------------------ kerbs is deemed to
9. Kerbs 2. Raking 2. Inserts, size or section include fair, rounded,
2. Height and width stated
stated beaded and moulded
3. Vertical
edges, coved junctions,
ends, angles and ramps.
(f) Rubber and Plastic Sheet or Carpet Sheet/Tile Finishes and the like (continued)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
10. Movement joints 1. Dimensioned description m D.2 Movement joints S.9 Method of fixing
include expansion joints.
11. Cover strips
12. Division strips
13. Non-slip inserts 1. Described m
14. Filling in to pipe 1. Width stated 1. Where jointing is m
trench covers required to line with
adjoining work it is so
15. Filling in to insets, 1. Sizes stated nr
stated.
manhole covers and
mat sinkings
16. Line marking on m M.2 Where paint type to S.10 Method of application
sports pavings be measured in if not at the Contractor’s
accordance with the rules discretion
17. Letters or figures on nr
for Section XXI Painting.
sports pavings
18. Accessories 1. Nosings 1. Dimensioned description m C.6 Nosings are deemed
to include:
(a) Working finishes
thereto
(b) Mitred regular and
irregular angles
2. Cover strips m
3. Dividing strips
4. Stair rods and similar nr
fixings
HK SMM 4 152
XVII MECHANICAL INSTALLATIONS 153
(See Section II - General Principles)
(a) General Clauses Applicable to all Mechanical Sections
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally M.1 Where composite D.1 Bonding is defined as C.1 Assembling and S.1 Any regulations,
units are supplied by the permanent joining of jointing together the rules, bye-laws and the
(a) A general description of the installations shall be given where it is not evident from the drawings
others, particulars are metallic parts to form an component parts of like with which the
required to be provided by this document.
included in the description electrically conductive composite units, including installations are required
(b) Detailed specifications shall be provided together with drawings indicating the scope of the work. of any assembly work path which will assure providing any necessary to comply
involved. electrical continuity and connecting flanges and
S.2 Kind and quality of
has the capacity to jointing materials are
M.2 Work is identified materials
conduct safely any deemed to be included.
whether internal, external
current likely to be S.3 Gauge or thickness
or in plant rooms. C.2 All necessary drilling
imposed. and substance of
of the background and
M.3 Temporary work and materials
provision of fixings, nails,
removal of temporary
bolts, nuts, holes, screws, S.4 Any tests with which
work and making good
plugs, shot fired pins and materials, plant and
shall each be so
the like are deemed to be equipment are required
described.
included. to comply
M.4 In the event that only
C.3 Plates, discs and S.5 Pressure and
a performance
labels for identification of temperature ratings
specification is available,
plant, equipment, S.6 Priming and/or
preamble clauses are
appliances, pipes, valves painting off site and
included in the bills,
and the like are deemed proprietary finishes or
stating that the rates are
to be included. surface treatment applied
to include for all costs of,
and costs in connection C.4 Instruction notices, as part of the production
with, the design, supply warning signs for plant, process are described
and installation of the equipment, appliances, stating whether applied
complete installation. pipes, valves and the like before or after fabrication
are deemed to be or assembly.
M.5 Systems, together
included.
with their equipment,
pipework, ductwork, C.5 Brackets and methods
insulation and sundries, of support are deemed to
are classified as shown in be included.
Appendix “A” to Section II
C.6 Bonding is deemed to
General Principles.
be included in the items in
which they occur. Where
items of equipment are
supplied by others the
bonding is deemed to be
included in the items of
fixing the equipment.
(b) Equipment
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Chillers 1. Type and duty stated 1. Cross-reference to nr C.1 Each item is deemed
drawings or specification to include:
2. Cooling towers
(a) All necessary
3. Air handling units
assembly
4. Fans
(b) Orientation
5. Boilers
(c) Alignment
6. Chimneys
(d) Levelling and bolting
7. Tanks down
8. Heat exchangers (e) Provision of shims
9. Pumps and packing pieces
HK SMM 4 154
XVII MECHANICAL INSTALLATIONS 155
HK SMM 4 156
XVII MECHANICAL INSTALLATIONS 157
10. Flow and return 1. Length and size stated nr M.8 Flow and return S.4 Method of
header pipes and number and size of header pipes forming part construction and method
each branch stated of plant or equipment are of jointing ends
included with the plant or
equipment.
HK SMM 4 158
XVII MECHANICAL INSTALLATIONS 159
HK SMM 4 160
XVII MECHANICAL INSTALLATIONS 161
(f) Ductwork
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally M.1 Composite supports D.1 Final supports are C.1 Work is deemed to S.1 Method of jointing
are measured in kg and any element between the include:
(a) Any regulations, rules, bye-laws and the like with which the installations are required to comply. S.2 Method of fixing and
the number stated. structure or support
(a) Any necessary drilling brackets and all methods
structure and the
of the background and of support including
ductwork.
provision of nails, bolts, proprietary and specialist
nuts, holes, screws, support systems and
plugs, shot-fired pins and spring compensated
the like components
(b) Provision and
installation of stiffeners
and all straps and
hangers, rods, test holes,
bungs and the like
including proprietary and
specialist support
systems and spring
compensated components
(c) All joints, including
joints between ducts of
differing materials
(d) Everything necessary
for all jointing
(e) Final supports
(f) Expansion joints
(g) Flexible connections
between ducts and plant,
including transformation
pieces and special duct
fittings
(h) Air turning vanes, test
points, cleaning eyes,
access doors and the like
(f) Ductwork (continued)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
2. Ductwork rectangular 1. Size, gauge or 1. Type of material m2 M.2 Ductwork rectangular C.2 Work is deemed to
in section thickness and type stated in section is measured include all in-line fittings.
over all in-line fittings,
C.3 Work is deemed to
short running lengths and
include all cutting of
branches, (but not
ductwork to fittings,
through items of in-line
equipment and ancillaries,
equipment).
and providing all
M.3 Where an in-line necessary materials, heat,
reduction in size (given by bolts, nuts, washers and
circumference/perimeter) everything necessary for
occurs at a reducer or tee making joints and
etc., the largest size shall connections.
be measured for the full
length of the fitting.
3. Ductwork circular or 1. Size and type stated m M.3 applies. C.3 applies.
oval in section
4. In-line fittings to 1. Bends nr M.4 Reducing fittings,
circular or oval ducts, 2. Branches tapers and transformation
measured extra over 3. Elbows pieces are identified by
the ducts in which they the largest sectional size.
4. Tees
occur
5. Reducers
6. Reducing branches
7. Reducing tees
8. Transformation pieces
9. Tapers
10. Offsets
11. Spigot outlets
12. Others
5. Ancillaries 1. Silencers 1. Size and type and nr
2. Flow meters specification stated
3. Plenums
4. Nozzles
5. Cowls
6. Grilles
7. Diffusers
8. Louvres
9. Fire Dampers
10. Splitter dampers
11. Volume control
dampers
12. Others
HK SMM 4 162
XVII MECHANICAL INSTALLATIONS 163
HK SMM 4 164
XVII MECHANICAL INSTALLATIONS 165
HK SMM 4 166
XVII MECHANICAL INSTALLATIONS 167
HK SMM 4 168
XVII MECHANICAL INSTALLATIONS 169
(i) Sundries
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Supports for 1. Pylons 1. Described and, where nr
pipework necessary, method of
2. Poles
fixing and nature of
3. Pole Stays structure stated
4. Others
2. Catenary cables 1. Number, type and size 1. Eye bolts, shackles and m
stated straining screws and
method of fixing stated in
description
3. Marking the 1. Where the nature of the Item
positions of all holes, work necessitates any of
mortices, chases and these to be formed during
the like in the structure construction, the relevant
particulars are given
4. Testing, setting to 1. Details of any phased Item C.1 Providing instruments
work and any testing, setting to work and consumables is
commissioning required and commissioning deemed to be included.
required
5. Allowance for the Item D.1 Fuel in the context of
cost of all necessary this item, shall not be
fuel in connection with construed as including
testing, setting to work electricity which is
and any commissioning already provided under
required Section III item (c).31.
6. Preparation of all 1. All requirements, Item
detailed design including the information
drawings required required, method of
presentation and number
7. Preparation of any Item
of copies stated
working drawings
required
8. Preparation of any Item
builders’ works
drawings required
9. Preparation of “as Item
fitted” record drawings
required
10. Provision of any 1. Detailed requirements Item
mock-ups and/or are given
prototypes as specified
(i) Sundries (continued)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
11. Maintenance other 1. Scope and duration of Item M.1 If maintenance is
than that required maintenance required required beyond the
under defects liability including provision of contract defects liability
consumable spares period, this shall be given
stated separately on a schedule
basis and shall be the
subject of a separate
agreement.
12. Tuition of Employer’s 1. Scope and duration of Item
staff tuition stated
13. Provision of manuals 1. All requirements Item
including information
required, method of
presentation and number
of copies stated
14. Provision of spares 1. Detailed requirements Item
and tools stated
15. Sleeves through Item C.2 Packing the space
walls, floors and between the pipes and
ceilings etc. the sleeve is deemed to
be included.
16. Fire stopping 1. Material to be used Item
described
17. Disconnecting, 1. Type of equipment and Item
setting aside and purpose of disconnection
refixing for the stated
convenience of other
trades
HK SMM 4 170
XVIII ELECTRICAL INSTALLATIONS 171
(See Section II - General Principles)
(a) General Clauses Applicable to all Electrical Sections
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally M.1 Where composite D.1 Bonding is defined as C.1 Assembling and S.1 Any regulations,
units are supplied by the permanent joining of jointing, together the rules, bye-laws and the
(a) A general description of the installations shall be given where it is not evident from the drawings
others, particulars are metallic parts to form an component parts of like with which the
required to be provided by this document.
included in the description electrically conductive composite units including installations are required
(b) Detailed specifications shall be provided together with drawings indicating the scope of the work. of any assembly work path which will assure providing any necessary to comply
involved. electrical continuity and connecting flanges, and
S.2 Kind and quality of
has the capacity to jointing materials are
M.2 Work is identified materials
conduct safely any deemed to be included.
whether internal, external
current likely to be S.3 Gauge or thickness
or in plant rooms. C.2 All necessary drilling
imposed. and substance of
of the background and
M.3 Temporary work and materials
provision of fixings, nails,
removal of temporary
bolts, nuts, holes, screws, S.4 Any tests with which
work and making good
plugs, shot fired pins and materials, plant and
shall each be so described.
the like are deemed to be equipment are required
M.4 In the event that only included. to comply
a performance
C.3 Plates, discs and S.5 Type and voltage of
specification is available,
labels for the identification main electricity supply
preamble clauses are
of plant, equipment, stating the location of the
included in the bills
cables, switches and the main supply point
stating that the rates are
like are deemed to be S.6 Priming and/or
to include for all costs of,
included. painting off site and
and costs in connection
with the design, supply C.4 Instruction notices, proprietary finishes or
and installation of the warning signs for plant, surface treatment applied
complete system. equipment, cables, as part of the production
switches and the like are process are described
M.5 Systems, together
deemed to be included. stating whether applied
with their equipment,
before or after fabrication
trunking, ducting, cable C.5 Brackets and methods
or assembly
trays and sundries are of support are deemed to
classified as shown in be included.
Appendix “A” to Section II
C.6 Bonding is deemed to
General Principles.
be included in the items in
which they occur. Where
items of equipment are
supplied by others, the
bonding is deemed
included in the item of
fixing equipment.
(b) Equipment and Switchgear
(See Section XVIII(a) - General Clauses)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Switchgear and 1. Prime movers 1. Type, rated capacity nr 1. Particulars of M.1 Type, SPN/TPN, C.1 Connecting cable
equipment and reference to drawing component parts and number of ways and rated ends or cable tails are
2. Motors
or specification given details of any materials capacity are given where deemed to be included.
3. Fans required for assembly are appropriate.
C.2 Couplings to, and
4. Mechanical drives given.
forming holes for conduit
5. Batteries entry are deemed to be
included.
6. Rectifiers
C.3 Connections between
7. Circuit breakers trunking and equipment
8. Feeder pillars and switchgear, including
the use of flanges and/or
9. Transformers forming apertures are
10. Fuse & link deemed to be included.
disconnecting boxes C.4 Connections between
11. Isolating switches busbar trunking,
equipment and switchgear
12. Change-over switches are deemed to be
13. Switch-fuses included.
14. Fused-switches C.5 Links, fuses, circuit
breakers, gland plates,
15. Distribution boards terminal boxes and the
16. Contactors like, which form part of
the items are deemed to
17. Starters be included.
18. Busbar chambers
19. Others
HK SMM 4 172
XVIII ELECTRICAL INSTALLATIONS 173
(c) Conduits (except in Final Circuits)
(See Section XVIII(a) - General Clauses)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Conduits 1. Type and external size 1. On surface m M.1 Conduit is measured D.1 Concealed conduits C.1 Draw wires, draw
stated, where draw wires, over all conduit fittings, are deemed to include cables, conduit boxes,
2. Concealed
draw cables and the like boxes, short running conduits embedded in conduit fittings and the
to be provided for use by 3. Run in chase lengths and branches. concrete or in floor like, except those required
others they are given in 4. Others screeds. to be measured under
the description item (c).2 hereof, are
D.2 Conduits run in
deemed to be included.
chases, unless otherwise
stated, do not include C.2 Bending, cutting,
cutting away and making screwing and provision of
good. all conduit fixings and
fittings (except those
D.3 The term ‘conduit
required under item (c).2
fittings and fixings’ is
hereof, are deemed to be
deemed to include
included.
saddles, tees, elbows,
bends, cover plates, C.3 Components and the
bushes, locknuts, forming of holes for
stopping plugs, reducing making connections of
bushesand the like. conduit into trunking and
the like are deemed to be
included.
2. Items measured as 1. Outlet boxes 1. Type and size stated nr C.3 applies
extra over the conduit 2. Adaptable boxes C.4 Cutting and jointing to
in which they occur 3. Floor trap boxes conduits are deemed to
4. Purpose made boxes be included.
5. Junction boxes C.5 Cover plates to boxes
6. Boxes required for are deemed to be included.
drawing in cables
7. Flameproof boxes
8. Expansion joints
9. Pedestal boxes
10. Others
3. Flexible conduits 1. Size and type stated 1. Overall length stated nr M.2 Flexible conduits are C.3 applies
and adaptors described in stages of 0.50 m measured fully extended.
C.6 Cutting, jointing and
providing all conduit
fittings are deemed to be
included.
(d) Trunking and Busbar Trunking
(See Section XVIII(a) - General Clauses)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Trunking 1. Size and type of m M.1 Trunking is measured C.1 All supports and joints
trunking stated,number over all short lengths and and jointing are deemed
and size of any branches. to be included.
compartments given,
C.2 Cutting and jointing
type of covers and
trunking or busbar
method of jointing stated.
trunking to fittings is
Pin racks, where required
deemed to be included.
stated in the description
2. Items measured extra 1. Bends nr
over the trunking in
2. Reducing bends
which they occur
3. Tees
4. Reducing tees
5. Crosses
6. ReducinDg crosses
7. Reducers
8. Fire barriers
9. Others
3. Busbar trunking 1. Capacity and type of 1. Type, number and rated m D.1 Busbar trunking is
trunking stated capacity of conductors defined as including
stated busway and the like.
4. Items measured as 1. Elbows nr
extra over the busbar
2. Tees
trunking in which they
occur 3. Reducers
4. Expansion fittings
5. Others
5. Busbar trunking 1. Tap-off units 1. Type, size and rated nr
fittings and accessories capacity where
2. Feeder units
applicable, stated
3. Flanged ends
4. Special fittings
5. Special supports
6. Fire barriers
7. Others
HK SMM 4 174
XVIII ELECTRICAL INSTALLATIONS 175
(e) Trays and Ladders
(See Section XVIII(a) - General Clauses)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Trays 1. Type and size stated m M.1 Trays and ladders are C.1 All joints are deemed
measured over all short to be included.
2. Ladders
running lengths and C.2 Cutting and jointing
branches. trays and ladders to
3. Items measured extra 1. Stop ends nr M.2 Reducing fittings are fittings are deemed to be
over trays in which they identified by the larger included.
2. Bends
occur size of tray or ladder. C.3 Cutting openings in
3. Tees
4. Items measured extra trays is deemed to be
over ladders in which 4. Reducing tees included.
they occur 5. Crosses
6. Offsets
7. Reducers
8. Others
(f) Cables (except in Final Circuits)
(See Section XVIII(a) - General Clauses)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Cables 1. Laid in trench 1. Type, size, number and m M.1 Cables are measured C.1 Colour coding or other
2. Laid in open duct size of cores and rating the net length between identification markings are
stated. Components for equipment, control gear, deemed to be included.
3. Laid on arm or hanger supporting cables given fittings, accessories and
in the description. (See C.2 Determining circuits
4. Fixed to cable tray, the like, except that the
however alternative and lacing into circuit
ladder or other surface following standard
measurement in item groups are deemed to be
5. Drawn into allowances are added for
(f).7 hereof.) included.
underground pipe duct tails:
(nett length of pipe duct (a) 0.30 m on each cable
measured) entering fittings and
6. Laid or drawn into accessories
trunking (b) 0.60 m on each cable
7. Drawn into conduit entering equipment and
8. Suspended from switch gear
insulators or catenaries
9. Wrapped around
pipework or equipment
10. Drawn into existing
conduits
11. Drawn into existing
ducts
12. Drawn into existing
trunking
2. Cable joints 1. Type and size of cable nr C.3 Materials and heat for
stated. Joint-boxes, making the joints are
sealing-boxes and the like deemed to be included.
given in the description
3. Line taps 1. Size and type of cable nr
C.4 Shrouds, if required,
stated
are deemed to be included.
4. Cable termination nr
C.5 Shrouds, locknuts,
glands
bushes, earth tags and
cable lugs are deemed to
be included.
5. Cable termination 1. Type of box and type nr
C.6 Insulating materials,
boxes and size of cable being
jointing materials, lock nuts,
terminated stated
bushes and the like are
deemed to be included.
HK SMM 4 176
XVIII ELECTRICAL INSTALLATIONS 177
HK SMM 4 178
XVIII ELECTRICAL INSTALLATIONS 179
(h) Fittings and Accessories
(See Section XVIII(a) - General Clauses)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Luminaires 1. Description includes nr 1. Form of suspension or C.1 All boxes, connector
reflectors, shades, lamps support, where required, blocks, and connecting of
and the like, and the shall be stated. cable tails and all
method of starting or necessary bushes,
reference made to the nipples, locknuts and the
specification or drawings, like and fixing in position
where appropriate. are deemed to be
included.
2. Ancillary fittings 1. Clocks 1. Description includes all nr
associated items such as
2. Alarm bells
boxes and cover plates.
3. Others
3. Accessories 1. Switches 1. Rated capacity, type of nr
each accessory and
2. Socket outlets
number of gangs in each
3. Thermostats accessory stated.
4. Bell pushes
5. Signal indicating units
6. Stop/start push buttons
7. Others
(i) Earthing, Lightning Protection and Bonding
(See Section XVIII(a) - General Clauses)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Cables M.1 Cables shall be
measured in accordance
with item (f).1 hereof.
2. Tapes 1. Type and size stated. m M.2 Tapes are measured C.1 The rates for tapes
Description includes all the net length. are deemed to include:
saddles, cleats, clips,
(a) Bends, twists and
holdfasts, and the like
through joints
with type and spacing
stated. (b) Connections and
junctions
(c) All saddles, cleats,
clips, holdfasts and the
like
3. Air terminations 1. Type, size and method nr C.2 Connecting electrodes
of connection stated to conductors, other than
4. Test clamps
by thermal welds, is
5. Earth electrodes deemed to be included.
6. Thermal welds
7. Others
8. Bonding 1. Bonding included in D.1 Bonding is defined in
items in Sub-sections (a) Sub-section (a).D.1
to (h) hereof hereof.
2. Bonding other than that M.3 Bonding for
defined in Sub-section requirements other than
(a).D.1 hereof measured those described in Sub-
in detail section (a).D.1 hereof is
measured in accordance
with items 1 to 7 hereof.
3. Bonding other than that 1. Description states nr
defined in Sub-section whether tape, cable only
(a).D.1 hereof may or cable and conduit
alternatively be installation and, where
enumerated. appropriate, size of cable,
type of conduit and final
connections.
HK SMM 4 180
XVIII ELECTRICAL INSTALLATIONS 181
(j) SUNDRIES
(See Section XVIII(a) - General Clauses)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Marking the 1. Where the nature of the Item
positions of all holes, work necessitates any of
mortices, chases and these to be formed during
the like in the structure construction, the relevant
particulars given
2. Testing, setting to 1. Details of any phased Item C.1 Providing instruments
work and any testing, setting to work and consumables deemed
commissioning and commissioning to be included
required required
3. Allowance for the Item D.1 Fuel, in the context
cost of all necessary of this item, shall not be
fuel in connection with construed as including
testing, setting to work electricity which is already
and any commissioning provided under Section III
required (c).31.
4. Preparation of all 1. All requirements, Item
detailed design including the information
drawings required required, method of
presentation and number
5. Preparation of any Item
of copies stated
working drawings
required for approval
6. Preparation of any Item
builders’ works
drawings required for
approval
7. Preparation of “as Item
fitted” record drawings
required
8. Provision of any 1. Detailed requirements Item
mock-ups and/or stated
prototypes as specified
9. Maintenance other 1. Scope and duration of Item M.1 If maintenance is
than that required maintenance required required beyond the
under defects liability including provision of contract defects liability
consumable spares, period, this shall be given
stated separately on a schedule
basis and shall be the
subject of a separate
agreement.
(j) Sundries (continued)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
10. Tuition of Employer’s 1. Scope and duration of Item
staff tuition stated
11. Provision of manuals 1. All requirements Item
including information
required, method of
presentation and number
of copies stated
12. Provision of spares 1. Detailed requirements Item
and tools stated
13. Earth electrodes 1. Any concrete surrounds nr C.2 Excavation is deemed
required stated to be included.
14. Supports for cables 1. Pylons 1. Described and, where nr
necessary, method of
2. Poles
fixing and nature of
3. Hut posts structure stated
4. Wall brackets
5. Pole brackets
6. Pole stays
7. Others
15. Catenary cables 1. Number, type and size 1. Eye bolts, shackles and m
stated straining screws and
method of fixing stated in
the description
16. Sleeves through Item C.3 Packing the space
walls, floors and between the pipes,
ceilings etc. conduits or cables and
the associated sleeves is
deemed to be included.
17. Fire stopping 1. Materials to be used Item
described
18. Disconnecting, 1. Type of equipment and Item
setting aside and purpose of disconnection
refixing for the stated
convenience of other
trades
HK SMM 4 182
XIX COMMUNICATIONS/SECURITY/CONTROL SYSTEMS HONG KONG STANDARD METHOD OF MEASUREMENT OF BUILDING WORKS - FOURTH EDITION 183
(See Section II -- General Principles)
(a) General Clauses Applicable to all Communications/Security/Control Systems Sections
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally M.1 Where composite D.1 Bonding is defined as C.1 Assembling and S.1 Any regulations,
units are supplied by the permanent joining of jointing, together the rules, bye-laws and the
(a) A general description of the installations shall be given where it is not evident from the drawings
others, particulars are metallic parts to form an component parts of like with which the
required to be provided by this document.
included in the description electrically conductive composite units, including installations are required
(b) Detailed specifications shall be provided together with drawings indicating the scope of the work. of any assembly work path which will assure providing any necessary to comply
involved. electrical continuity and jointing materials and
S.2 Kind and quality of
has the capacity to connecting flanges is
M.2 Temporary work, materials
conduct safely any deemed to be included.
removal of temporary
current likely to be S.3 Gauge or thickness
work and making good C.2 All necessary drilling
imposed. and substance of
are each so described. of the background and the
materials
provision of fixings, nails,
M.3 Systems, together
bolts, nuts, holes, screws, S.4 Any tests with which
with their trunking,
plugs, shotfired pins and materials, plant and
ducting, cable trays and
the like are deemed to be equipment are required
conduits (unless
included. to comply
associated with more than
one installation) are C.3 Plates, discs and S.5 Priming and/or
classified as shown in labels for the identification painting off site and
Appendix “A” to Section II of plant, equipment, proprietary finishes or
General Principles. cables, switches and the surface treatment applied
like are deemed to be as part of the production
M.4 Work is identified
included. process are described
whether internal, external
stating whether applied
or in plant rooms. C.4 Instruction notices,
before or after fabrication
warning signs for control
M.5 In the event that only or assembly
equipment, cable
a performance
equipment control
specification is available,
switches, accessories
preamble clauses shall
and the like are deemed
be included in the bills
to be included.
stating that the rates are
to include for all costs of, C.5 Brackets and methods
and costs in connection of support are deemed to
with, the design, supply be included.
and instalation of the
C.6 Bonding is deemed to
complete system.
be included in the items in
which they occur. Where
items of equipment are
supplied by others the
bonding is deemed
included in the item of
fixing equipment.
(b) Equipment
(See Section XIX(a) - General Clauses)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Central equipment 1. Central processing units 1. Described (or referred nr C.1 Interfacing, connecting,
to in the equipment interconnecting cables,
2. Master stations
schedule/ appropriate jointing and making all
3. Operator stations specification clause) busbar, cable, conduit,
4. Control console trunking and cable tray
connections and the like
5. Display units and the provision of all
6. Printers associated components is
deemed to be included in
7. Disc drive units the items of equipment.
8. Amplifiers C.2 Cable and conduit
9. Others connections from power
source/UPS units to all
2. Peripheral equipment 1. Data gathering panels nr equipment are deemed
2. Splitters included in the equipment
items.
3. Distribution process
units
4. Others
3. Provision of all Item D.1 Software includes C.3 Fees and charges for
software, including those for the operating software patents and
back-up copies systems and applications. licenses are deemed to be
included in the item.
4. Uninterruptible 1. Units including batteries Item
power supply units and chargers, all supply
(UPS) and interconnecting wiring
etc., battery type, standby
time and rated capacity
stated
HK SMM 4 184
XIX COMMUNICATIONS/SECURITY/CONTROL SYSTEMS 185
(c) Distribution and Principal Interconnections
(See Section XIX(a) - General Clauses)
HK SMM 4 186
XIX COMMUNICATIONS/SECURITY/CONTROL SYSTEMS 187
HK SMM 4 188
XIX COMMUNICATIONS/SECURITY/CONTROL SYSTEMS 189
(e) Sundries
(See Section XIX(a) - General Clauses)
HK SMM 4 190
XX GLAZING 191
(See Section II - General Principles)
(a) General Glazing (including Acrylic and Polycarbonate Sheets)
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally M.1 Glass measured in C.1 Work is deemed to S.1 Kind, quality and
this Sub-section is for include: thickness of glass
general glazing to
(a) Putty or glazing S.2 Kind and quality of
windows, doors etc.
compounds glazing compounds and
M.2 Glass in the following sealants
(b) Sprigs or glazing clips
positions are measured
S.3 Method of glazing
in the appropriate Sub- (c) Bedding in glazing
sections of Section XIII tape, wash leather, S.4 Method of securing
Wood Works and XV rubber, neoprene, butyl or including details of
Steel and Metal Works: other plastic and the like gaskets, glazing strips
where so described and channels
(a) Fixed and
demountable partitions (d) Where bedded in S.5 Nature of frame or
wood frames with wooden surround
(b) Office partitions
beads the taking off and
S.6 Fire rated panes
(c) Shop fronts replacing the beads
have fire rating stated
(d) Curtain walling (e) Drilling or forming all
holes for fixing or for
(e) Furniture and fittings
ironmongery and the like
etc.
HK SMM 4 192
XX GLAZING 193
HK SMM 4 194
XXI PAINTING 195
(See Section II - General Principles)
(a) General Clauses Applicable to the following Sub-sections (b) through (e)
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally M.1 Work on concrete, D.1 Work is deemed to be C.1 All work shall be S.1 Kind and quality of
brick, plaster, stone, internal unless otherwise deemed to include: materials
metal, wood or other described.
(a) Multicoloured work S.2. Materials required to
surface is in each case
D.2 Multi-coloured work is and cutting to line be applied and/or
given separately.
defined as the application finished by a particular
(b) Preliminary
M.2 The area or girth of more than one colour method stated
preparatory work before
measured is the area or on an individual surface.
application S.3 Preliminary
girth covered including On walls and columns
preparation work before
allowances for the extra and on ceilings and (c) Rubbing down
application
girth of edges, mouldings, beams, it is defined as between coats
panels, sinkings, the application, in one (d) Painting on beads,
corrugations, flutings, room, of more than one hinges and other fittings,
carvings, enrichments colour on walls and brackets, bolts, lugs and
and the like unless columns, or on ceilings the like, and attached
otherwise provided for and beams. pipework and conduits
herein. painted at the same time
M.3 Work on existing and in the same material
surfaces is given and colour as the surface
separately and to which they are attached
preparatory treatment of
existing decoration such
as washing down,
burning off, stripping and
the like is stated in the
description.
IV DEMOLITIONS AND ALTERATIONS
(a) General Clauses Applicable to the following Sub-sections (b) through (e) (continued)
INFORMATION PROVIDED MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Generally (continued) M.4 Work required to be
executed on members
before fixing is so
described.
M.5 Work to ceilings and
beams, where the ceiling
is > 3.50 m from the floor
is so described, the
height being stated in
stage of 1.50 m
M.6 No deduction is made
for voids ≤ 0.50 m2.
M.7 Descriptions include
preparatory work such as
knotting and stopping,
priming and sealing coats.
The number of
undercoats and finishing
coats is stated.
HK SMM 4 196
XXI PAINTING 197
(b) Painting and Similar Work
(See Section XXI (a) - General Clauses)
HK SMM 4 198
XXI PAINTING 199
(d) Signwriting
(See Section XXI (a) - General Clauses)
CLASSIFICATION TABLE MEASUREMENT DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
RULES INFORMATION
1. Lines 1. Dimensioned description 1. Straight m
2. Broken lines 2. Curved
3. Arrow heads or tails nr
4. Letters, numerals nr
5. Stops and nr
punctuation marks
6. Chinese characters nr
7. Symbols or logos nr
HK SMM 4 202
XXII LANDSCAPING 203
ALPHABETICAL INDEX
Framed Works, Metal XV P.125 Lathing XVI P.143 Partitions, Toilet Cubicle XIII P.110
Frames & Linings, Wood XIII P.111 Lightning Protection XVIII P.180 Partitions, Wood, Glazed XIII P.108
Furniture, Metal XV P.142 Linings, Sheet Metal XV P.122 Pipework XVII P.156
Furniture, Wood XIII P.114 Liquid Membrane Waterproofing X P.85 Pipework, Accessories XVII P.158
G Luminaires XVIII P.179 Pipework, Ancillaries XVII P.158
Gates, Collapsible Gates, Metal XV P.124 M Pipework Supports XVII P.157
Glass Shelves XX P.194 Macadam XVI P.145 Planking & Strutting, incl Excavation VI P.46
Glass Balustrades & Parapets XX P.193 Marble Facings XI P.94 Plant Pots & Containers XXII P.203
Glass Block Walls & Panels VIII P.77 Marble Tiling XVI P.148 Planting XXII P.202
Glass Wall Linings XX P.193 Mechanical Equipment XVII P.153 Plasterboard XVI P.143
Glazed Wood Partitions XIII P.108 Mechanical Installations, Sundries XVII P.169 Plastering XVI P.143
Glazing - General Glazing XX P.191 Mechanical Installations XVII P.153 Plastic Sheet Finishes XVI P.151
Granite Facings XI P.94 Mechanical Section General Clauses XVII P.153 Playground Equipment, Wood XIII P.114
Granite Tiling XVI P.148 Metal Doors, Gates, Shutters, Grilles XV P.124 Playground Equipment, Metal XV P.142
Granolithic Finishes, Terrazzo XVI P.145 Metal Hatches XV P.124 Polishing & Clear Finishing XXI P.198
Grass Seeding & Turfing XXII P.201 Metal Works for Structural Timber XVII P.99 Polycarbonate Sheet Glazing XX P.191
Grilles, Screens & Louvres, Metal XV P.124 Minimum Deductions II P.4 Precast Concrete VII P.70
Gun Applied Reinforced Concrete VII P.64 Minor Buildings & Structures, Metal XV P.128 Precast Concrete Piles V P.28
Gutters XVII P.160 Minor Buildings & Structures, Wood XIII P.115 Precast Prestressed Concrete VII P.73
H Mirror Wall Linings XX P.193 Prestressed Concrete VII P.71
Handrails, Metal XV P.125 Mirrors XX P.194 Prime Cost Sums II P.5
Handrails, Wood XIII P.113 Moon Gates, Stone XI P.93 Profiled Metal Sheet Roof Coverings XV P.131
Hardcore & Granular Filling VI P.50 Mosaic Tiling XVI P.148 Profiled Sheet Roof & Wall Claddings XIII P.107
Hatches, Wood XIII P.111 Mulching Planting Areas XXII P.203 Profiled Metal Sheet Wall Claddings XV P.131
Heat Exchangers XVII P.154 N Proprietary Roof Tiling XII P.98
Hydroseeding XXII P.201 O Protective Coverings & Finishings XVII P.166
I Office Cubicle Partitions, Metal XV P.135 Provisional Sums II P.5
In-situ Surface Finishes & Screeds XVI P.145 Office Cubicle Partitions, Wood XIII P.110 Pumps XVII P.154
Insulation to Ductwork XVII P.165 Overhead Crane Rails XV P.120 Q
Insulation to Equipment XVII P.165 P R
Insulation to Pipework XVII P.164 Painting, General Clauses XXI P.195 Racks, Wood XIII P.114
Insulation to Wall Linings, Claddings etc. XIII P.103 Paperhanging including Sheet Plastic & Fabric Linings Raised Access Floors, Metal XV P.131
Ironmongery XIV P.117 XXI P.199 Raised Access Floors, Wood XIII P.102
J Parquet Flooring XIII P.101 Removal of Water III P.16
K Partitions, Demountable, Wood XIII P.108 Rendering XVI P.145
L Partitions, Fixed, Wood XIII P.108 Reservoir, Works Under II P.5
Laboratory & Sanitary Fittings XVII P.155 Partitions, Office Cubicle XIII P.110 River, Works Under II P.5
Landscaping XXII P.201 Partitions, Sliding and Folding XIII P.109 Roads & Paving XVI P.145
HK SMM 4 206
207
Roof Tiling XII P.97 Stone Copings, Curbs, Steps etc. XI P.92 Wood Balustrades XIII P.113
Roofing and Flashings, Sheet Metal XV P.123 Stone Facings to Structural Backgrounds XI P.94 Wood Block Flooring XIII P.101
Rubber Sheet Finishes XVI P.151 Stone Moon Gates XI P.93 Wood Handrails XIII P.113
S Stone Pitching to Slopes XI P.92 Wood Doors XIII P.111
Sanitary & Laboratory Fittings XVII P.155 Stone Walling XI P.91 Wood Framed Suspended Ceilings XIII P.103
Sea Water, Works Under II P.5 Structural Timber XIII P.99 Wood Frames & Linings XIII P.111
Security Systems XIX P.183 Structural Steel XV P.119 Wood Hatches XIII P.111
Security Systems, Equipment XIX P.184 Surface Finishes & Screeds, In-situ XVI P.145 Wood Stairs XIII P.113
Security Systems, Final Circuits XIX P.186 Surface Water Channels VII P.59 Wood Strip Flooring XIII P.101
Security Systems, Sundries XIX P.189 Suspended Ceiling, Metal XV P.136 Wood Trims XIII P.103
Septic Tanks IX P.83 Suspended Concrete Slabs VII P.61 Wood Ventilators XIII P.111
Service Ducts IX P.81 Switchgear & Equipment XVIII P.172 Working Space, for Excavation VI P.46
Sheet Linings & Claddings XIII P.103 Symbols and Abbreviations II P.3 Work in Compressed Air II P.5
Sheet Membrane Waterproofing X P.88 Synthetic Rubber Tiling XVI P.148 Work in Existing Buildings II P.5
Sheet Plastic Paperhanging XXI P.199 T Work outside the Site II P.5
Shelving, Wood XIII P.114 Tanks XVII P.154 Work under Reservoir, River or Sea Water II P.5
Shelving, Racks, Metal XV P.142 Temporary Roofs IV P.23 X
Shop Fronts, Metal XV P.139 Temporary Screens IV P.23 Y
Shoring IV P.23 Temporary Shoring for Bank Excavation VI P.49 Z
Shutters, Folding, Rolling, Metal XV P.124 Terrazzo Finishes XVI P.145
Sign Boards & Signage, Wood XIII P.114 Tile & Slab Finishes XVI P.148
Sign Boards & Signage, Metal XV P.142 Toilet Cubicle Partitions, Wood XIII P.110
Signwriting XXI P.199 Toilet Cubicle Partitions, Metal XV P.133
Site Clearance VI P.45 Trays & Ladders XVIII P.173
Slate Tiling XVI P.148 Trenches for Pipe Ducts IX P.81
Sliding and Folding Partitions XIII P.109 Trenches for Drain Pipes IX P.81
Spatterdash XVI P.143 Trunking & Busbar Trunking XVIII P.174
Specification, Used for BQ preparation II P.3 Turfing & Grass Seeding XXII P.201
Sprayed Concrete to Slopes VI P.51 U
Squash Court Armoured Glass Walls XX P.193 Underpinning VI P.53
Stairs, Wood XIII P.113 Uninterruptible Power Supply (UPS) XIX P.184
Stairs, Metal XV P.125 Units of Billing II P.3
Steel & Metal, Sundries XV P.129 Units of Measurement II P.3
Steel Piles V P.36 V
Steel Sheet Piling V P.25 Ventilators, Woods XIII P.111
Stone Arches XI P.93 W
Stone Beds & Sides to Water Courses XI P.92 Walling, Diaphragm V P.43
Stone Construction XI P.91 Windows & Glazed Doors, Metal XV P.138