OPGW Spec
OPGW Spec
OPGW Spec
This section describes the functional & technical specifications of OPGW cabling and associated
hardware & fittings.
This section defines the requirements for G.652D & G655 Dual-window Single mode (DWSM)
telecommunication grade fibre optic. Bidders shall furnish with their bids, detailed descriptions
of the fibres & cable (s) proposed.
All optical fibre cabling including fibre itself and all associated installation hardware shall have a
minimum guaranteed design life span of 25 years. Documentary evidence in support of
guaranteed life span of cable & fibre shall be submitted by the Contractor during detailed
engineering.
This section describes the characteristics of optical fibre to be provided under this specification.
Dual-Window Single mode (DWSM), G.652D optical fibres shall be provided in the fibre optic
cables. DWSM optical fibres shall meet the requirements defined in Table 2-1 (a).
1.1.1.2 Attenuation
The attenuation coefficient for wavelengths between 1525 nm and 1575 nm shall not exceed the
attenuation coefficient at 1550 nm by more than 0.05 dB. The attenuation coefficient between
1285 nm and 1330 nm shall not exceed the attenuation coefficient at 1310 nm by more than 0.05
dB. The attenuation of the fibre shall be distributed uniformly throughout its length such that
there are no point discontinuities in excess of 0.10 dB. The fibre attenuation characteristics
specified in table 2-1 (a) shall be “guaranteed” fibre attenuation of any & every fibre reel.
The overall optical fibre path attenuation shall not be more than calculated below:
Maximum attenuation @ 1550nm: 0.21 dB/km x total km + 0.05dB/splice x no. of splices + 0.5
dB/connector x no. of connectors.
Maximum attenuation @ 1310nm: 0.35 dB/km x total km + 0.05 dB/splice x no. of splices + 0.5
dB/connector x no. of connectors.
Table 1-1 (a)
DWSM OPTICAL Fibre Characteristics
1300 to 1324 nm
Zero Dispersion Wavelength: 0.092 ps/(nm²xkm) maximum
Zero Dispersion Slope:
Overhead Fibre Optic Cables shall be OPGW (Optical Ground Wire). The OPGW cable is
proposed to be installed on transmission lines. The design of cable shall account for the varying
operating and environmental conditions that the cable shall experience while in service.
Typical details of transmission lines are indicated in the Appendices. Any other details, as
required for cable design etc, shall be collected by the Contractor during survey.
The Contractor shall supply & install the optical fibre cable as required based on detailed site
survey to be carried out by the Contractor during the project execution. The Contract price shall
be adjusted accordingly.
For the purpose of payment, the optical fibre link lengths are defined as transmission line route
lengths from Gantry at one terminating station to the Gantry in the other terminating station. The
actual cable lengths to be delivered shall take into account various factors such as sag, service
loops, splicing, working lengths & wastage etc, and no additional payment shall be payable in
this regard. The unit rate for FO cable quoted in the Bid price Schedules shall take into account
all such factors.
Individual optical fibres within a fibre unit and fibre units shall be identificable in accordance
with EIA/TIA 598 OR IEC 60304 or Bellcore GR-20 colour-coding scheme.
Colouring utilized for colour coding optical fibres shall be integrated into the fibre coating and
shall be homogenous. The colour shall not bleed from one fibre to another and shall not fade
during fibre preparation for termination or splicing.
Each cable shall have traceability of each fibre back to the original fibre manufacturer’s fibre
number and parameters of the fibre. If more than the specified number of fibres are included in
any cable, the spare fibres shall be tested by the cable manufacturer and any defective fibres shall
be suitably bundled, tagged and identified at the factory by the vendor.
Loose tube construction shall be implemented. The individually coated optical fibre(s) shall be
surrounded by a buffer for protection from physical damage during fabrication, installation and
operation of the cable. The fibre coating and buffer shall be strippable for splicing and
termination. Each fibre unit shall be individually identificable utilizing colour coding. Buffer
tubes shall be filled with a water-blocking gel.
The fibre optic cable shall be designed and installed such that the optical fibres experience no
strain under all loading conditions defined in IS 802. Zero fibre strain condition shall apply even
after a 25 year cable creep.
For the purpose of this specification, the following definitions shall apply;
Maximum Working Tension (MWT) is defined as the maximum cable tension at which
there is no fibre strain.
The no fibre strain condition is defined as fibre strain of less than or equal to 0.05%, as
determined by direct measurements through IEC/ETSI(FOTP) specified optical
reflectometry techniques.
The Cable strain margin is defined as the maximum cable strain at which there is no fibre
strain.
The cable Maximum Allowable Tension (MAT) is defined as the maximum tension
experienced by the Cable under the worst case loading condition.
The cable max strain is defined as the maximum strain experienced by the Cable under
the worst case loading condition
The cable Every Day Tension (EDT) is defined as the maximum cable tension on any
span under normal conditions.
The Ultimate / Rated Tensile Strength (UTS/RTS/breaking strength) is defined as the
maximum tensile load applied and held constant for one minute at which the specimen
shall not break.
While preparing the Sag-tension charts for the OPGW cable the following conditions shall be
met:
The Max Allowable Tension (MAT) / max strain shall be less than or equal to the
MWT/Strain margin of the cable
The Sag shall not exceed the earth wire sag in all conditions.
The Max Allowable Tension shall also be less than or equal to 0.4 times the UTS.
The 25 years creep at 25% of UTS (creep test as per IEEE 1138) shall be such that the 25
years creep plus the cable strain at Max Allowable Tension (MAT) is less than or equal to
the cable strain margin.
The everyday tension (EDT) shall not exceed 20% of the UTS for the OPGW cable.
The Sag-tension chart of OPGW cable indicating the maximum tension, cable strain and sag
shall be calculated and submitted along with the bid under various conditions mentioned below:
The above cases shall be considered for the spans from 100 m to 600 m or higher span length in
the range of 50 m spans. Max. vertical sag, max. tension and max sag at 0º C & no wind shall be
considered for in line with the design parameter of transmission line. The typical details are
indicated in the appendices. The full wind load shall be considered as the design wind load for all
the specified transmission lines as per relevant IS 802 version and the sag-tension chart shall be
submitted considering the transmission lines. The contractor shall submit the stringing chart for
review of Employer.
The materials used for optical fibre cable construction, shall meet the following requirements:
The interstices of the fibre optic unit and cable shall be filled with a suitable compound to
prohibit any moisture ingress or any water longitudinal migration within the fibre optic unit or
along the fibre optic cable. The water tightness of the cable shall meet or exceed the test
performance criteria as per IEC-794-1-F-5.
The filling compound used shall be a non-toxic homogenous waterproofing compound that is
free of dirt and foreign matter, nonhygroscopic, electrically nonconductive and non-nutritive to
fungus. The compound shall also be fully compatible with all cable components it may come in
contact with and shall inhibit the generation of hydrogen within the cable.
The waterproofing filling materials shall not affect fibre coating, colour coding, or encapsulant
commonly used in splice enclosures, shall be dermatologically safe, non-staining and easily
removable with a non-toxic cleaning solvent.
When the fibre optic cable design incorporates metallic elements in its construction, all metallic
elements shall be electrically continuous.
This section describes the requirements for marking, packaging and shipping the overhead fibre
optic cable.
(a) Drum Markings: Each side of every reel of cable shall be permanently marked in
white lettering with the vendors’ address, the Purchaser’s destination address, cable
part number and specification as to the type of cable, length, number of fibres, a
unique drum number including the name of the transmission line & segment no.,
factory inspection stamp and date.
(b) Cable Drums: All optical fibre cabling shall be supplied on strong drums provided
with lagging of adequate strength, constructed to protect the cabling against all
damage and displacement during transit, storage and subsequent handling during
installation. Both ends of the cable shall be sealed as to prevent the escape of filling
compounds and dust & moisture ingress during shipment and handling. Spare cable
caps shall be provided with each drum as required.
The spare cable shall be supplied on sturdy, corrosion resistant, steel drums sutiable
for long periods of storage and re-transport & handling.
There shall be no factory splices allowed within a continuous length of cable. Only one
continuous cable length shall be provided on each drum. The lengths of cable to be supplied on
each drum shall be determined by a “schedule’ prepared by the Contractor.
OPGW cables shall be installed in off-line conditions. The tentative bill of quantities for both
live- line as well as off-line OPGW cable system installations have been specified in the
appendices and the actual quantities for both types shall be finalized during project execution
after detailed survey.
Supervision of Installation – The Contractor shall supervise the stringing at site as per the
approved stringing procedure. Site visit for supervision shall be carried out as per instruction of
Employer. However, the contract price shall be adjusted as per the actual requirement. The
Supervision/Inspection work in Contractor’s scope shall mainly include inspection as per
stringing procedure, proper location of drum site, installation of stringing blocks/pulleys, proper
sagging, proper installation of hardware, proper tension as per Sag-Tension chart, provision of
service loops of OPGW in jointing locations etc.
OPGW cable construction shall comply with IEEE-1138, 1994. The cable provided shall meet
both the construction and performance requirements such that the ground wire function, the
optical fibre integrity and optical transmission characteristics are suitable for the intended
purpose. The cable shall consist of optical fibre units as defined in this specification. There shall
be no factory splices within the cable structure of a continuous cable length.
The composite fibre optic overhead ground wire shall be made up of buffered optical fibre units
(fibres in the buffer tube) embedded in a water tight aluminimum / aluminium alloy / stainless
steel protective central fibre optic unit surrounded by concentric-lay stranded metallic wires in
single or multiple layers. The dual purpose of the composite cable is to provide the electrical and
physical characteristics of conventional overhead ground wire while providing the optical
transmission properties of optical fibre.
The central fibre optic unit shall be designed to house and protect multiple buffered optical fibres
units from damage due to forces such as crushing, bending, twisting, tensile stress and moisture.
The central fibre optic unit and the outer stranded metallic conductors shall serve together as an
integral unit to protect the optical fibres from degradation due to vibration and galloping, wind
and ice loadings, wide temperature variations, lightning an fault current, as well as
environmental effects which may produce hydrogen.
Central fibre optic unit may be of aluminium or stainless steel tube with aluminium protective
coating. In case of aluminium protective coating, the coating must completely cover the tubes
leaving no exposed areas of tubing that can make electrical contact either directly or indirectly
through moisture, contamination, protrusions, etc with the surrounding stranded wires. The tube
may be fabricated as a seamless tube, seam welded, or a tube without a welded seam.
The rated breaking strength shall not include the strength of the optical unit. The fibre optic unit
shall not be considered a load bearing tension member when determining the total rated breaking
strength of the composite conductor.
Table 2-2(a) provides OPGW Electrical and Mechanical Requirements for the minimum
performance characteristics. Additionally, the OPGW mechanical & electrical characteristics
shall be similar to that of the earthwire being replaced such that there is no or minimal
consequential increase in stresses on towers. For the purpose of determining the appropriate Max
Working Tension limit for the OPGW cable IS 802:1995 and is 875:1987 shall be applied.
However the OPGW installation sag & tension charts shall be based on IS 802 version to which
the line is originally designed. For the OPGW cable design selection and preparation of sag
tension charts, the limits specified in this section shall also be satisfied. The Bidder shall submit
sag-tension charts for the above cases with their bids.
Table 1.2(a)
OPGW Electrical and Mechanical Requirements
Since OPGW shall be located at the top of the EHV transmission line support structure, it will be
subjected to Aeolian vibration, Galloping and Lightning strikes. It will also carry ground fault
currents. Therefore, is electrical and mechanical properties shall be same as those required of
conventional ground conductors.
1.1.2.7.5 Installation
OPGW installed under off line condition, shall be generally in accordance with the IEEE Guide
to the Installation of Overhead Transmission Line Conductors (IEEE STD. 524 with latest
revisions), with additional instructions and precautions for fibre optic cable handling. The
stringing procedure shall be submitted by the Contractor prior to stringing for Employer’s
approval.
The OPGW cable sections shall normally be terminated & spliced only on tension towers. In
exceptional circumstances, and on Employer specific approval, cable may be terminated on
Suspension towers, but in this case tower strength shall be examined to ensure that tower loads
are within safe limits and if required, necessary tower strengthening shall be carried out by the
Contractor.
The scope of supply of the optical cable includes the assessment, supply and installation of all
required fittings and hardware such as Tension assembly, Suspension assembly, Vibration
dampers, Reinforcing rods, Earthing clamps, Downlead clamps, splice enclosure etc. The Bidder
shall provide documentation justifying the adequacy and suitability of the hardware supplied.
The Contractor shall determine the exact requirements of all accessories required to install and
secure the OPGW.
The OPGW hardware fittings and accessories shall follow the general requirements regarding
design, materials, dimensions & tolerances, protection against corrosion and markings as
specified in clause 4.0 of EN 61284:1997 (IEC 61284). The shear strength of all bolts shall be at
least 1.5 times the maximum installation torque. The OPGW hardware & accessories drawing &
Data Requirement Sheets (DRS) document shall consist of three parts: (1) A technical particulars
sheet (2) An assembly drawing i.e. level 1 drawing and (3) Component level drawings i.e. level 2
& lower drawings. All component reference numbers, dimensions and tolerances, bolt tightening
torques & shear strength and ratings such as UTS, slip strength etc shall be marked on the
drawings.
The fittings and accessories described herein are indicative of installation hardware typically
used for OPGW installations and shall not necessarily be limited to the following:
The Contractor shall supply all the components of the suspension assembly
including shackles, bolts, nuts, washers, split pins, etc. The total drop of the
suspension assembly shall not exceed 150 mm (measured from the center point of
attachment to the center point of the OPGW). The design of the assembly shall be
such that the direction of run of the OPGW shall be the same as that of the
conductor.
(b) Dead End Clamp Assemblies: All dead end clamp assemblies shall preferably be
of performed armoured grip type and shall include all necessary hardware for
attaching the assembly to the tower strain plates. Dead end clamps shall allow the
OPGW to pass through continuously without cable cutting. The slip strength shall
be rated not less than 95% of the rated tensile strength of the OPGW.
(c) Clamp Assembly Earthing Wire: Earthing wire consisting of a 1500 mm length of
aluminium or aluminium alloy conductor equivalent in size to the OPGW shall be
used to earth suspension and dead end clamp assemblies to the tower structure.
The earthing wire shall be permanently fitted with lugs at each end. The lugs shall
be attached to the clamp assembly at one end and the tower structure at the other.
(d) Structure Attachment Clamp Assemblies: Clamp assemblies used to attach the
OPGW to the structures, shall have two parallel grooves for the OPGW, one on
either side of the connecting bolt. The clamps shall be such that clamping
characteristics do not alter adversely when only one OPGW is installed. The
tower attachment plates shall locate the OPGW on the inside of the tower and
shall be attached directly to the tower legs/cross – members without drilling or
any other structural modifications.
(e) Vibration Dampers: Vibration dampers type 4R Stockbridge or equivalent, having
four (4) different frequencies spread within the Aeolian frequency bandwidth,
shall be used for suspension and tension points in each span. The Contractor shall
determine the exact numbers and placement(s) of vibration dampers through a
detailed vibration analysis as specified in technical specifications. Vibration
damper clamps shall be made of aluminium or aluminium alloy, shall support the
dampers during installation and shall maintain the dampers in position without
damage to the OPGW and without causing fatigue. Armour or patch rods made of
aluminium or aluminium alloy shall be provided as required to reduce clamping
stress on the OPGW. The vibration damper body shall be hot-dip galvanized mild
steel/cast iron or shall be permanent mould cast zinc alloy.
All splices shall be encased in Fibre Optic Splice Enclosures. Suitable splice enclosures shall be
provided to encase the optical cable splices in protective, moisture and dust free environment.
Splice enclosures shall comply to ingress protection class IP 66 or better. The splice enclosures
shall be designed for the storage and protection of required number of optical fibre splices and
equipped with sufficient number of splice trays for splice trays for splicing all fibres in the cable.
No more than 6 fibres shall be terminated in a single splice tray. They shall be filled with
suitable encapsulate that is easily removable should re-entry be required into the enclosures.
Splice enclosures shall be suitable for outdoor use with each of the cable types provided under
this contract. Splice enclosures shall be appropriate for mounting on transmission line towers
above anti-climb guard levels at about 10 metres from top of the tower and shall accommodate
pass-through splicing. The actual mounting height and location shall be finalized after Survey.
Contractor shall be responsible for splicing of fibres and installation of splice enclosures.
Splicing of the optical fibre cabling shall be minimized through careful contractor planning.
There shall be no mid-span splices allowed. All required splices shall be planned to occur on
tower structures. All optical fibre splicing shall comply with the following:
For purposes of this specification, a fibre optic approach cable is defined as the Armoured
underground fibre optic cable required to connect Overhead Fibre Optic Cable (OPGW) between
the final in line splice enclosure on the gantry / tower forming the termination of the fibre cable
on the power line and the Fibre Optic Distribution Panel (FODP) installed within the building.
The estimated fibre optic approach cabling length requirements are indicated in the appendices.
However, the Contractor shall supply & install the optical fibre approach cable as required based
on detailed site survey to be carried out by the Contractor during the project execution and the
Contract price shall be adjusted accordingly.
The cable shall be suitable for direct burial, laying in trenches & PVC/Hume ducts, laying under
false flooring and on indoor or outdoor cable raceways.
The approach cable shall be a UV resistant, rodent proof, armoured cable with metallic type of
armoring. The outer cable jacket for approach cable shall consist of carbon black polyethylene
resin to prevent damage from exposure to ultra-violet light, weathering and high levels of
pollution. The jacket shall confirm to ASTM D1248 for density.
Approach cable shall contain fibres with identical optical/physical characteristics a those in the
OPGW cables. The cable core shall comprise of tensile strength member(s), fibre
support/bedding structure, core wrap/bedding, and an overall impervious jacket.
The existing cable trenches/cable raceways proposed to be used shall be identified in the survey
report. The Contractor shall make its best effort to route the cable through the existing available
cable trenches. Where suitable existing cable trenches are not available, suitable alternatives
shall be provided after Employer approval. However, the approach cable shall be laid in the
HDPE pipe in all condition.
Suitable provisions shall be made by the contractor to ensure adequate safety earthing and
insulated protection for the approach cable.
All required fittings, supports, accessories, ducts, inner ducts, conduits, risers and any item not
specially mentioned but required for laying and installtion of approach cables shall be supplied
and installed by the Contractor.
Optical fibre terminations shall be installed in Fibre Optical Distribution Panels (FODP)
designed to provide protection for fibre splicing of preconnectorized pigtails and to
accommodate connectorized termination and coupling of the fibre cables. The contractor shall
provide rack/wall mounted fibre optic distribution panels (FODPs) sized as indicated in the
appendices and shall terminate the fibre optic cabling up to the FODPs. The location of FODP
rack shall be fixed by the Contractor, with the Employer’s approval.
At each location requiring the termination of at least one fibre within a cable, all fibres within
that cable shall be connectorized and terminated in Fibre Optic Distribution Panels in a manner
consistent with the following:
a) All fibre optic terminations shall be housed using FODPs provisioned with splice
organizers and splice trays. All fibres within a cable shall be fusion spliced to
preconnectorized pigtails and fitted to the “Back – side” of the provided fibre optic
couplings.
b) FODPs shall be suitable for use with each of the cable types provided as part of this
contract. FODPs shall accommodate pass-through splicing and fibre terminations.
d) ALL FODPs shall be of corrosion resistant, robust construction and shall allow both top
or bottom entry for access to the splice trays, Ground lugs shall be provided on all
FODPs and the Contractor shall ensure that all FODPs are properly grounded. The FODP
shall meet or exceed ingress protection class IP55 specifications.
e) Flexible protection shall be provided to the patch cord bunches going out from FODP to
other equipment.
Optical fibres shall be connectorised with FC-PC type connectors preferably. Alternatively
connector with matching patch cord shall also be acceptable. Fibre optic couplings supplied with
FODPs shall be appropriate for the fibre connectors to be supported. There shall be no adapters.
For purposes of this specification, cable and fibre service loops are defined as slack (extra) cable
and fibre provided for facilitating the installation, maintenance and repair of the optical fibre
cable plant.
(a) Outdoor Cable Service Loops: In – line splice enclosures installed outdoors and mounted
on the utility towers, shall be installed with sufficient fibre optic cable service loops such
that the recommended minimum bend radius is maintained while allowing for installation
or maintenance of the cable to be performed in a controlled environment at ground level.
(b) Indoor Cable Service Loops: FODPs shall provide at least three (3) metres of
cable service loop. Service loops shall be neatly secured and stored, coiled
such that the minimum recommended bend radius’ are maintained.
(c) Fibre Units Service Loops: For all fibre optic cable splicing, the cable shall be
stripped back a sufficient length such that the fan-out of fibre units shall
provide for at least one (1) metre of fibre unit service loop between the stripped
cable and the bare fibre fan-out.
(d) Pigtail Service Loops: Connectorised pigtails spliced to bare fibres shall provide at least 1
metre of service loop installed in the FODP fibre organizer and at least one (1) metre of
service loop to the couplings neatly stored behind the FODP coupling panels.
(e) Fibre Service Loops: At least 0.5 metre of bare fibre service loop shall be provided on
each side of all fibre splices. The bare fibre service loops shall be neatly and safely
installed inside covered splice trays.
All optical fibre cable termination, installation, stringing and handling plans, guides and
procedures, and engineering analysis (e.g. tension, sag, vibration etc.) shall be submitted to the
Employer for review and approval in the engineering/design phase of the project, prior to
establishing the final cable lengths for manufacture. Installation procedures including details of
personnel and time required shall be documented in detail and submitted to Employer for
approval. All installation practices shall be field proven and ISO accredited.
All cable segments shall include service loops as specified in this specification. The maximum
allowable stringing tension, maximum allowable torsional shear stress, crush strength and other
physical parameters of the cable shall not be exceeded. The preventative measures to be taken
shall be documented in details and submitted to Employer in advance of installation.
Optical fibre attenuation shall be measured after installation and before splicing. Any increase in
attenuation or step discontinuity in attenuation shall not be acceptable and shall constitute a cable
segment failure. In the event of cable damage or any fibre damage, the complete section (tension
location to tension location) shall be replaced as mid-span joints are not acceptable.
Any or all additional steel work or modifications require to attach the fibre cabling to the
overhead transmission/distribution line towers shall also be carried out by the contractor. It shall
be the Contractors responsibility to provide adequate communications among all crew members
and support staff to ensure safe and successful installations.
To the extent possible, existing cable raceways shall be utilized. The Contractor is required to
provide and install any additional indoor cable raceways which maybe required for proper
implementation of and communication system. This requirement shall be finalized during
survey. The cable raceways shall conform to the following:
(a) All cable raceways shall be sized to support full loading requirements plus at least a
200% safety loading factor
(b) Indoor cable raceways shall be fabricated from construction grade aluminium,
galvanized iron or anodized sheet metal or any other suitable material approved by
the Employer. Suitable anticorrosion measures shall be provided. Steel fabricated
raceways shall be finished inside and out, treated to resist rust and to form a metal-to-
paint bond.
(c) Mechanical construction drawings of the cable raceways shall be submitted for
Employer’s information & review.
“Type Tests” shall be defined as those tests which are to be carried out to prove the design,
process of manufacture and general conformity of the materials to this specification. Type testing
shall comply with the following:
a) All cable being supplied shall conform to type tests as per technical specification.
b) The test reports submitted shall be of the tests conducted within last seven (7)
years for OPGW cable prior to the date of bid opening. In case the test reports are
older than seven (7) years for OPGW cable on the date of bid opening, the
contractor shall repeat these tests at no extra to the purchaser.
c) The contractor shall submit, within 30 days of contract award, copies of test
reports for all of the type tests that are specified in the specifications and that have
previously (before contract award) been performed. These reports may be
accepted by the employer only if they apply to materials and equipment that are
essentially identical to those due to be delivered under the contract and only if test
procedures and parameter values are identical to those specified in this
specifications carried out at accredited labs and witnessed by third party /
customer’s representatives.
In the event of any discrepancy in the test reports or any type tests not carried out,
same shall be carried out by contractor without any additional cost implication to
the employer.
g) In case of failure during any type test, the supplier is either required to
manufacture a fresh sample lot and repeat all type tests successfully or repeat that
particular type test(s) at least three times successfully on the samples selected
from the already manufactured lot at his own expenses. In case a fresh lot is
manufactured for testing then the lot already manufactured shall be rejected.
The contractor shall supply equipment/material for sample selection only after the quality
assurance plan has been approved by the employer. The sample material shall be manufactured
strictly in accordance with the approved quality assurance plan. The contractor shall submit for
employer approval, the type test sample selection procedure. The selection process for
conducting the type tests shall ensure that samples are selected at random. At least three samples
of each of the proposed equipment / item / cable drum except FO cable installation hardware &
fittings shall be offered for selection. For FO cable installation hardware & fittings at least ten
(10) samples shall be offered for selection.
The type tests listed below in table 2.1 shall be conducted on DWSM fibres to be supplied as part
of overhead cables. The tests specific to the cable type are listed in subsequent sections.
Table 2.1
- End of table -
The type tests to be conducted on the OPGW cable are listed in Table 2.2 Type Tests for OPGW
Cables. Unless specified otherwise in the technical specifications or the referenced standards, the
optical attenuation of the specimen, measured during or after the test as applicable, shall not
increase by more than 0.05 dB/Km.
Table 2.2
5 Galloping test IEEE 1138-2009 IEEE 1138-2009 Test shall be conducted with
the tension/suspension
clamps proposed to be
supplied. The cable and
clamps shall be visually
inspected for mechanical
damage and photographed
after the test. All fibres of the
test cable sample shall be
spliced together in serial for
attenuation monitoring.
8 Crush Test IEEE 1138-2009 IEEE 1138-2009 The crush test shall be carried
(IEC 60794-1-2, out on a sample of
Method approximately one (1) metre
E3/EIA/TIA long in accordance with IEC
455-41B) 60794-1-2 E3. A load equal
to 1.3 times the weight of a
400 – metre length of fibre
optic cable shall be applied
for a period of 10 minutes. A
permanent or temporarily
increase in optical attenuation
value greater than 0.1 dB
change in sample shall
constitute failure. The load
shall be further increased in
small increments until the
measured attenuation of the
optical waveguide fibres
increases and the failure load
recorded along with results.
9 Impact Test IEEE 1138-2009 IEEE 1138- The impact test shall be
2009, (IEC carried out in accordance
60794-1-2 with IEC 60794-1-2 E4. Five
E4/EIA/TIA separate impacts of 0.1-
455-25B) 0.3kgm shall be applied. The
radius of the intermediate
piece shall be the reel drum
radius ± 10%. A permanent
or temporary increase in
optical attenuation value
greater than 0.1 dB/km
change in sample shall
constitute failure.
- End of table -
The type tests to be conducted on the OPGW cable fittings and accessories are listed below:
Suspension Assembly
The armour rods/reinforcement rods are assembled on to the approved OPGW using the
Installation Instructions to check that the assembly is correctly fitted and is the same that will be
carried out during installations.
Part 1:
The suspension assembly shall be increased at a constant rate up to a load equal to 50% of the
specified minimum failure load increased and held for one minute for the test rig to stabilize. The
load shall then be increased at a steady rate to 67% of the minimum failure load and held for five
minutes. The angle between the cable, the suspension assembly and the horizontal shall not
exceed 16º. This load shall then be removed in a controlled manner and the protection splice
disassembled. Examination of all the components shall be made and any evidence of visual
deformation shall be documented.
Part 2:
The suspension clamp shall then be placed in the testing machine. The tensile load shall
gradually be increased up to 50% of the specified Minimum failure load of the suspension
assembly and held for one minute for the test rig to stabilize and the load shall be further
increased at a steady rate until the specified minimum failure load is reached and held for one
minute. No fracture should occur during this period. The applied load shall then be increased
until the failing load is reached and the value shall be documented.
Tension Assembly
The Tension Assembly is correctly fitted and is the same that will be carried out during
installations.
Part 1:
The tension assembly (excluding tension clamp) shall be increased at a constant rate up to a load
equal to 50% of the specified of the specified minimum failure load increased at a constant rate
and held for one minute for the test rig to stabilize. The load shall then be increased at a steady
rate to 67% of the minimum failure load and held of five minutes. This load shall then remove in
a controlled manner and the tension assembly disassembled. Examination of the tension dead-
end and associated components shall be made and any evidence of visual deformation shall be
documented.
Part 2:
The Tension Dead-End and associated components shall then be reassembled and bolts tightened
as before. The tensile load shall gradually be increased up shall gradually be increased up to 50%
of the specified minimum failure load of the tension assembly and held for one minute for the
test rig to stabilize and the load shall be further increased at a steady rate until the specified
minimum failure load is reached and held for one minute. No fracture should occur during this
period. The applied load shall then be increased until the failing load is reached and the value
shall be documented.
- No evidence of fracture at the end of one minute at the minimum failure load during Part
2 of the test.
Acceptance Criteria:
The suspension clamp has passed the slip test if the following conditions are met:
* Definition of no slippage in accordance with IEC 61284, 1997:- Any relative movement
less than 2 mm is accepted. The possible couplings or elongations produced by the cable
as a result of the test itself are not regarded as slippage.
- Slippage shall occur between the specified maximum and minimum slip load of 12-
17KN.
- There shall be no slippage of the Reinforcing Rods over the cable, and no slippage of the
Armour Rods over the Reinforcing Rods.
- The relative movement (i.e. more than 2 mm between Armour Rods & Clamp body)
between minimum 12KN and maximum slip 17KN, shall be considered as slip.
- The Armour Rods shall not be displaced from their original lay or damaged**.
Tension clamps shall be fitted on a 8 m length of fibre optic cable on both ends. The assembly
shall be mounted on a tensile testing machine and anchored in a manner similar to the
arrangement to be used in service. A tensile load shall gradually be applied up to 20% of the
RTS of OPGW. Displacement transducers shall be installed to measure the relative movement
between the OPGW relative to the Reinforcing Rods and Tension Dead – End relative to
Reinforcing Rods. In addition, suitable marking shall be made on the OPGW and Dead – End to
confirm grip. The load shall be gradually increased at a constant rate up to 50% of the UTS and
the position scale of the recorder is zeroed. The load shall then gradually increased up to 95% of
the UTS and maintained for one minute. After one minute pause, the load shall be slowly
released to zero and the marking examined and measured for any relative movement.
Acceptance Criteria:
- No movement* shall occur between the OPGW and the Reinforcing Rods, or between the
Reinforcing Rods and the Dead-End assembly.
- No failure or damage or disturbance to the lay of the Tension Dead – End, Reinforcing
Rods or OPGW.
*Definition of no movement as defined in IEC 61284: Any relative movement less than 2
mm is accepted. The possible couplings or elongations produced by the conductor as a result
of the test itself are not regarded as slippage.
For structure mounting clamp, one series of test shall be conducted with two fibre optic cables
installed, one series of tests with one fibre optic cable installed in one groove, and one series of
tests with one fibre optic cable in the other groove. Each clamp shall be installed including
clamping compound as required on the fibre optic cable. The nut shall be tightened on to the bolt
by using torque wrench with a torque of 5.5 kgm or supplier’s recommended torque and the
tightened clamps shall be held for 10 minutes. After the test remove the fibre optic cable and
examine all its components for distortion, crushing or breaking. Also the fibre optic cable shall
be checked to ensure free movement within the core using dial callipers to measure the diameter
of the core tube. The material shall be defined as failed if any visible distortion, crushing,
craking or breaking of the core tube is observed or the fibre optic cable within the core tube is
not free to move, or when the diameter of the core tube as measured at any location in the
clamped area is more than 0.5 mm larger or smaller of the core diameter as measured outside the
clamped area.
The clamp and mounting assembly shall be assembled on a vertical 200 mm x 200 mm angle and
a short length of fibre optic cable installed. A vertical load of 200 kg shall be applied at the end
of the mounting clamp and held for 5 minutes. Subsequently, the load shall be increased to 400
kg and held for 30 seconds. Any visible distortion, slipping or breaking of any component of the
mounting clamp or assembly shall constitute failure.
The damper shall be mounted with its clamp tightened with torque recommended by the
manufacturer on shaker table capable of simulating sinusoidal vibrations for Critical Aeolian
Vibration frequency band ranging from 0.18/d to 1.4/d – Where d is the OPGW cable diameter in
meters. The damper assembly shall be vibrated vertically with a ± 1 mm amplitude from 5 to 15
Hz frequency and beyond 15 Hz at 0.5 mm to determine following characteristics with the held
of suitable recording instruments.
The force Vs frequency curve shall not show steep peaks at resonance frequencies and deep
troughs between the resonance frequencies. The resonance frequencies shall be suitably spread
within the Aeolian vibration frequency-band between the lower and upper dangerous frequency
limits determined by the vibration analysis of fibre optic cable without dampers.
(i) The above dynamic characteristics test on five damper shall be conducted.
(ii) The mean reactance and phase angle Vs frequency curves shall be drawn with the
criteria of best fit method.
(iii) The above mean reactance response curve should lie within following limits:
(iv) The above mean phase angle response curve shall be between 25° to 130° within
the frequency range of interest.
(v) If any above curve lies within the envelope, the damper design shall be considered
to have successfully met the requirement.
The vibration analysis of the fibre optic cable shall be done with and without damper installed on
the span. The vibration analysis shall b done on a digital computer using energy balance
approach. The following parameters shall be taken into account for the purpose of analysis.
(i) The analysis shall be done for single fibre optic cable without armour rods. The
tension shall be taken as 25% of RTS of fibre optic cable for a span ranging from
100 m to 1100 m.
(ii) The self damping factor and flexural stiffness (EI) for fibre optic cable shall be
calculated on the basis of experimental results. The details to experimental
analysis with these data shall be furnished.
(iii) The power dissipation curve obtained from damper characteristics test shall be
used for analysis with damper.
(iv) Examine the Aeolian Vibration level of the fibre optic cable with and without
vibration damper installed at the recommended location or wind velocity ranging
from 0 to 30 Km per hour, predicting amplitude, frequency and vibration energy
input.
(v) From vibration analysis of fibre optic cable without damper, antinode vibration
amplitude and dynamic strain levels at clamped span extremities as well a
antinodes shall be examined and thus lower and upper dangerous frequency limits
between which the Aeolian vibration levels exceed the specified limits shall be
determined.
(vi) From vibration analysis of fibre optic cable with damper(s) installed at the
recommended location, the dynamic strain level at the clamped span extremities,
damper attachment point and the antinodes on the fibre optic cable shall be
determined. In addition to above damper clamp vibration amplitude and antinodes
vibration amplitudes shall also be examined.
The dynamic strain levels at damper attachment point, clamped span extremities
and antinodes shall not exceed the specified limits. The damper clamp vibration
amplitude shall not be more than that of the specified fatigue limits.
Constant tension shall be maintained within the span by means of level arm
arrangement. After the fibre optic cable has been tensioned, clamps shall be
installed to support the fibre optic cable at both ends and thus influence of
connecting hardware fittings are eliminated from the free span. The clamps shall
not be used for holding the tension on the fibre optic cable. There shall be no
loose parts, such as suspension clamps, U bolts, on the test span supported
between clamps mentioned above. The span shall be equipped with vibration
inducing equipment suitable for producing steady standing vibration. The
inducting equipment shall have facilities for step less speed control as well as step
less amplitude arrangement. Equipment shall be available for measuring the
frequency, cumulative number of cycles and amplitude of vibration at any point
along the span.
The vibration damper shall be installed on the test span with the manufacturer’s specified
tightening torque. It shall be ensured that the damper shall be kept minimum three loops away
from the shaker to eliminate stray signals influencing damper movement.
The damper shall be vibrated at the highest resonant frequency of each damper mass. For
dampers involving torsional resonant frequencies, tests shall be done at torsional modes also in
addition to the highest resonant frequencies at vertical modes. The resonance frequency shall be
identified as the frequency at which each damper mass vibrates with the maximum amplitude on
itself. The amplitude of vibration of the damper clamp shall be maintained not less than ±25/f
mm where f is the frequency in Hz.
The test shall be conducted for minimum ten million cycles at each resonant frequency
mentioned above. During the test, if resonance shift is observed, the test frequency shall be tuned
to the new resonant frequency.
The clamp slip test as mentioned herein shall be repeated after fatigue tests without retorquing or
adjusting the damper clamp, and the clamp shall withstand a minimum load equal to 80% o the
slip strength for a minimum duration of one minute.
After the above tests, the damper shall be removed from fibre optic cable and subjected to
dynamic characteristics test. There shall not be any major deterioration in the characteristics of
the damper. The damper then shall be cut open and inspected. There shall not be any broken,
loose, or damaged part. There shall not be significant deterioration or wear of the damper. The
fibre optic cable under clamp shall also be free from any damage.
(1) There shall not be any resonant frequency shift before and after the test by more
than ± 20%
(2) The power dissipation of the damper before and after test at the individual
resonant frequencies do not differ by more than ± 20%
Beside above tests, the type tests listed below in the table shall also be conducted on vibration
damper.
1 Visual examination & Dimensional and material IEC 61897 Clause 7.1 & 7.2
verification
Following type tests shall be demonstrated on the splice enclosure(s) (Splice Enclosure/Box).
For certain tests, lengths of the fibre optic cable shall be installed in the splice box, and the fibres
must be spliced and looped in order to simulate conditions of use. The attenuation of the fibres
shall be measured, during certain tests, by relevant fibre optic test procedures (EIA/TIA 455 or
IEC 60794-1 procedures).
FO cable is installed in the splice enclosure and optical fibres spliced and looped. The box must
be subjected to 5 cycles of temperature variations of -40ºC to + 65 ºC with a dwell time of at
least 2 hours on each extreme.
Fibre loop attenuation shall be measured in accordance with EIA 455-20/IEC 60794-1-C10. The
variation in attenuation shall be less than ±0.05dB. The final humidity level, inside the box, shall
not exceed the initial level, at the closing of the box.
The sealed splice enclosure, with fibres spliced and looped inside, must be subjected to a
temperature of +55 ºC ±2 ºC with a relative humidity rate of between 90% and 95% for 5 days.
The attenuation variation of the fibres during the duration of the test shall be less than ±0.05dB,
and the internal humidity rate measured, less than 2%.
The splice enclosure with optical fibres cable installed and fibres spliced fixed, shall be subjected
to 24 hours of simulated rain in accordance with IEC 60060 testing requirements. No water
seepage or moisture shall be detected in the splice enclosure. The attenuation variation of the
fibres after the test shall be less than ±0.05dB.
The splice enclosure, with fibres united inside, shall be subjected to vibrations on two axes with
a frequency scanning of 5 to 50 Hz. The amplitude of the vibrations shall be constant at
0.450mm, peak to peak, for 2 hours, for each of the vibrations’ axes. The variation in attenuation,
of the fibres, shall be less than ±0.05dB. The splice enclosure shall be examined for any defects
or deformation. There shall be no loosening or visible damage of the FO cable at the entry point.
The splice enclosure, with fibres spliced inside, shall be firmly held in place and be subjected to
the following sequence of mechanical stresses on the cable:
a) 3 torsion cycles of ±180° shall be exercised on the cable. Each cycle shall be less than
one minute.
b) 3 flexure cycles of the cable, of ±180° with one cycle less than one minute.
The variation in the attenuation, of the fibres, shall be less than ±0.05dB. The cables connection
ring shall remain securely fixed to the box with the connection maintained firmly. No
defects/fissures shall be noted on the joint ring or on the splice enclosure.
The splice enclosure with cable fixed to the boxes shall be subjected to a minimum tension of
448 N for a period of two minutes. No fissure shall be noted in the connections or on the box.
With 2 lengths of 11 metres of cable fixed to the box, it shall be dropped five times from a height
of 10 metres. There shall be no fissure, at all, of the box, and the connections shall remain tight.
The test surface shall be carried out in accordance with IEC 60068-2-32.
Factory acceptance tests shall be conducted on randomly selected final assemblies of all
equipment to be supplied. Factory acceptance testing shall be carried out on OPGW cable and
associated hardware & fittings, Joint box.
Material shall not be shipped to the employer until required factory tests are completed
satisfactorily, all variances are resolved, full test documentation has been delivered to the
employer, and the employer has issued material inspection & clearance certificate (MICC).
Successful completion of the factory tests and the employer approval to ship shall in no way
constitute final acceptance of the system or any portion thereof. These tests shall be carried out
in the presence of the employer’s authorized representatives unless waiver for witnessing by
employer’s representatives is intimated to the contractor.
Factory acceptance tests shall not proceed without the prior delivery to and approval of all test
documentation by the employer.
The factory acceptance test shall demonstrate the technical characteristics of the equipment in
relation to this specifications and approved drawings and documents. List of factory acceptance
tests for fibre optic transmission system. Termination equipment Sub-system, NMS are given in
specified tables in this section. This list of factory acceptance tests shall be supplemented by the
contractor’s standard FAT testing program The factory acceptance tests for the other items shall
be proposed by the contractor in accordance with technical specifications and contractor’s
(including Sub-Contractor’s/supplier’s) standard FAT testing program. In general the FAT for
other items shall include at least: Physical verification, demonstration of technical
characteristics, various operational modes, functional interfaces, alarms and diagnostics etc.
For Test equipment & clock, FAT shall include supply of proper calibration certificates,
demonstration of satisfactory performance, evidence of correct equipment configuration and
manufacturer’s final inspection certificate/report.
From each batch of equipment presented by the contractor for factory acceptance testing, the
employer shall select random sample(s) to be tested for acceptance. Unless otherwise agreed, all
required FAT tests in the approved FAT procedures, shall be performed on all samples. The
sampling rate for the factory acceptance tests shall be minimum 10% of the batch size (minimum
1) for all items. The physical verification shall be carried out on 100% of the offered quantities
as per the approved FAT procedure. In case any of the selected samples fail, the failed sample is
rejected and additional 20% samples shall be selected randomly and tested. In case any sample
from the additional 20% also fails the entire batch may be rejected. In case a number of
equipments are required for demonstration of the performance of any equipment during FAT, the
sample size shall be taken as that number of equipments which are necessary to demonstrate the
performance, irrespective of the percentage.
For the OPGW cable hardware fittings & accessories, the minimum sampling rate, and batch
acceptance criteria shall be as defined in IS 2486.
The sampling rate for the factory acceptance tests shall be 10% of the batch size (minimum2)
for FO cable drums, FODPs Joint box and other similar items.
Since FAT testing provides a measure of assurance that the quality control objectives are being
met during all phases of production, the employer reserves the right to require the contractor to
investigate and report on the cause of FAT failures and to suspend further testing/approvals until
such a report is made and remedial actions taken, as applicable.
Production testing shall mean those test which are to be carried out during the process of
production by the contractor to ensure the desired quality of end product to be supplied by him.
The production tests to be carried out at each stage of production shall be based on the
contractor’s standard quality assurance procedures. The production tests to be carried out shall be
listed in the Manufacturing Quality Plan (MQP), along with information such as sampling
frequency, applicable standards, acceptance criteria etc.
The production tests would normally not be witnessed by the employer. However, the employer
reserves the right to do so or inspect the production testing records in accordance with inspection
rights specified for this contract.
The factory acceptance tests listed in table below are applicable for the Optic fibres to be
supplied. The listed tests follow testing requirements set forth in IEEE standard 1138, 1994
section 4.2.2.1 and section 5.2.2.1. The referenced sections specify the detailed test description.
The acceptance norm shall be as specified in the above mentioned IEEE standards unless
specified otherwise in the technical specifications.
Table 3.1 Factory Acceptance Tests for Optical Fibres: Optical Tests
- End of table -
The test report for the above tests for the fibers carried out by the fiber manufacturer and used in
the OPGW cables shall be shown to the inspector during OPGW cable FAT and shall be
submitted along with the OPGW cable FAT report.
The factory acceptance tests for OPGW cable specified below in table follow the requirements
set forth in IEEE standard 1138/IEC 60794. The FAT shall be carried out on 10% of offered
drums in each lot as specified in technical specifications and the optical tests shall be carried out
in all fibres of the selected sample drums. The Rated Tensile strength test shall be carried out on
one sample in each lot.
Table 3.2
The factory acceptance tests for OPGW fittings as specified below in Table 3.3. The sampling
plan shall be as per relevant standard:
Table 3.3
Suspension Assembly
5 Galvanising test
Tension Assembly
9 Galvanising test
Vibration Damper
- End of Table -
The factory acceptance tests for Splice Enclosures/FODP as specified below in Table:
Table 3.4
1. Visual check of quantities and specific component number for each component
of splice enclosure/FODP and dimensional checks against the approved
drawings
3.4 Factory Acceptance Tests on test equipment, Pigtail & other items
The contractor shall be responsible for the submission of all equipment & test equipment
supplied in this contract for site tests and inspection as required by the employer. All equipment
shall be tested on site under the conditions in which it will normally operate.
The tests shall be exhaustive and shall demonstrate that the overall performance of the contract
works satisfies every requirement specified. At a minimum Site Acceptance Testing requirement
for FO cable is outlined in following section. This testing shall be supplemented by the
contractor’s standard installation testing program, which shall be in accordance with his quality
plan(s) for FO equipment installation.
During the course of installation, the Employer shall have full access for inspection and
verification of the progress of the work and for checking workmanship and accuracy, as maybe
required. On completion of the work prior to commissioning, all equipment shall be tested to the
satisfaction of the employer to demonstrate that it is entirely suitable for commercial operation.
Prior to installation, every spooled fibre optic cable segment shall be tested for compliance with
the pre-shipment data previously received from the manufacturer. This requirement will preclude
the installation of out of specification cable segments that may have been damaged during
shipment.
SAT shall be carried out link from FODP to FODP. SAT may be performed in parts in case of
long links.
The tests, checks, adjustments etc conducted by the contractor prior to offering the equipment for
SAT shall be called Pre-SAT activities. The Pre-SAT activities shall be described in the
installation manuals and field quality plan documents.
Sag and tension of OPGW shall generally be as per approved sag-tension chart and during
installation, sag and tension of OPGW shall be documented. Upon completion of a continuous
cable patch, all fibres within the cable patch shall be demonstrated for acceptance of the cable
path. Fibre Optic cable site testing minimum requirements are provided in Table 3.5 through 3.6
below:
Table 3.5
Item Description
Table 3.6
Item Description
Table 3.7
Item Description
3 Bi-directional average splice loss by OTDR of each splice as well as for all splices
in the link (including at FODP also)
4 Proper termination and labeling of fibres & fibre optic cables at FODP as per
approved labeling plan.
- End of Table -
Chief Engineer/Telecom