Risk Assessment/Management Form: Risk Assessment-Erection of Column, Stair Case and Bracing
Risk Assessment/Management Form: Risk Assessment-Erection of Column, Stair Case and Bracing
Risk Assessment/Management Form: Risk Assessment-Erection of Column, Stair Case and Bracing
Ref:
Section / Dept: Preheater / civil Risk Assessment-
Activity:
ERECTION OF COLUMN,STAIR
CASE AND BRACING
Sl Basic Job Potential Hazard Consequence Current control measure
Probability
Probability
N. Steps Risk rating Risk rating
Residual
Additional
Initial control
risk
P E A R Risk measure P E A R
Use guide rope during shifting of
materials and always keep away
Get Injury/ from swing area.Daily tool box talk
Fall of materials
Fatality before starting of job by crew
supervisor.
Failure of wire rope Get Injury All the wire rope sling & D-shackle
sling/D-shackle must be visually checked . Tested
sling must
Skilled be colour
workmen shallcoaded by a
be engaged
specific colour
for hooking .aily tool box talk
of material.Hook of hydra
before
must bestarting of job
provided byhook
with crewlatchaily
Hooking of material Get injury supervisor.
tool box talk before starting of job by
crew supervisor.
Probability
Probability
N. Steps Risk rating Risk rating
Residual
Additional
Initial control
risk
P E A R Risk measure P E A R
Leackage of hose Get Injury due to Proper hose clamp shall be provided
pipe fire at both cylinder side and torch side.
Binding wire shall never be used or
allowed inplace of hose clamp
Probability
Probability
N. Steps Risk rating Risk rating
pipe fire
Residual
Additional
Initial control
risk
P E A R Risk measure P E A R
Colour code for separate hose pipe
(Red for DA and blue for Oxygen)
Gas cutting shall be maintained and never be
8 2 1 0 0 2 4
activity mixed
Only striking lighter shall be used to
light the torch and torch shall be
checked for any kind of damages
prio to start the job