6 Ed - Smaple Qa
6 Ed - Smaple Qa
Sam is the project manager recently appointed to the IntelX project. While she was creating her project
management plan, she found that the project business case contains some wrong information and should be
updated. She decided to change this document and inform her sponsor and concerned stakeholders about the
change. What is your advice to Sam?
1. I will advise her to execute the required change to the business case and inform the concerned
management
2. I will advise her to review the change with the project sponsor before she communicates the change to
the other concerned stakeholders
3. I will advise her not to change the business case document as it is not one of the project documents
that she is authorized to change
4. I will advise her to review the change with the PMO before she communicates the change to the other
concerned stakeholders
Question 2/10
James started to execute the Manage Quality process and he was looking for the acceptable level of project and
product quality and how to ensure this level of quality in its deliverables and processes. Which document
should James review?
1. Project documents
2. The project management plan
3. Organizational process assets
4. Enterprise environmental factors
Question 3/10
Which of the following documents is created as a result of market demand?
1. Business Case
2. Project Charter
3. Benefits management plan
4. Project information document
Question 4/10
As a project manager, you have this network diagram for a simple project and you are requested to identify the
activity with the highest total float. Which of the following statements will be correct?
Network diagram
Question 5/10
Which of the following team can help in managing your project quality?
1. Project team
2. The customer
3. The project sponsor
4. All the above
1. The sponsor
2. The public community groups
3. The traffic police officers and representatives
4. All the above
Question 8/10
Adam is about to close his project after 13 months of hard work. He started to review the project management
plan to:
1. Ensure that the accepted deliverables have its associated sign-off sheets
2. Ensure that the project management plan complies with the organization standards
3. Ensure that all project work is completed and that the project has met its objectives
4. All the above
Question 9/10
Amy starts to get acceptance of the completed project deliverables. Which process does Amy start to work
with?
1. Control quality
2. Control Scope
3. Validate Scope
4. Accept Scope
Question 10/10
Which of the following Project Documents can be considered input to the Validate Scope process?
1. Project communications
2. Requirements documentation
3. Team charter
4. All the above
1. 1. Question
Your stakeholder approaches you to follow up on a concern or problem about the
project that she brought up a few weeks ago. On which document will you the detail
information about this problem, who responsible for resolution, and detail information
about the resolution?
o Change requests
o Issue log
o Control Quality
o Plan quality
o Quality audit
o Quality inspection
o Gold plating
4. 4. Question
You are trying to establish your cost baseline but you haven’t included cost of quality
into your budget. Which is part of cost of non-conformance for your project?
o Liabilities payment
o Internal inspections
5. 5. Question
On managing a project, you have asked one of your project staff to collect data on start
and finish of scheduled activities, actual durations, works completed, actual costs, and
number of defects. These data will later be reviewed, analyzed, and processed into:
o Before any deliverables can be validated they need to be verified first by Control
Quality process
o Any approved change request will be executed by this process and the
results will be validated afterwards
o Projectized organization
o Written informal
o Verbal informal
o Written formal
o Verbal formal
CORRECT
Written formal is best to use to avoid any misunderstanding.
10. 10. Question
While reviewing your project financial documents you have discover that payment for
one of your sub-contractor has not been executed. You have already accepted the sub-
contractor works 6 months ago and the payment was due 2 months ago yet you haven’t
received any complaints from them regarding the payment. What is the best course of
action that you should take?
o Organizational chart
o Verified Deliverables
o Accepted Deliverables
o Since all the scope have been defined then this project will not require any project
life cycles
o Project charter
o Analyze the impact of the defect and reports to your client about the defect
and its impact.
o Analyze the impact of the defect and reports to your sponsor about the defect
and its impact.
o Fix the defect right away, it’s important to deliver a zero defect deliverables.
19. 19. Question
You have developed your project schedule and now you need to establish your project
cost baseline. In order to estimate the cost, you refer to your past similar project cost
estimation data. What kind of estimating technique that you are using?
o Three-point estimating
o Parametric estimating
o Analogous estimating
o Bottom-up estimating
CORRECT
Analogous estimating uses value and data from a previous, similar project. Ref PMBOK
p. 204
20. 20. Question
You have just calculated that your project TCPI is 1.2. What does this mean?
o The project requires to utilize resources and achieve schedule efficiency index at
1.2
o The project requires to utilize resources and achieve cost efficiency index at
1.2
o The project will over budget 1.2 times from the schedule baseline
o The project will under budget 1.2 times from the schedule baseline
21. 21. Question
You are managing a project that builds a customized hospital management system for
your client, which is a big hospital chain. Once completed, this new system will be
implemented in all 75 hospitals across the nation. Close to project completion, your
client requests some changes on how the medical workers will be authorized to look at
patient’s data. The hospital claims that this is a small change and expects you to
implement it right away. What would you do?
o You check with your lawyer first since this concerns patient’s data. Once the lawyer
agrees, you will implement the change.
o Issue a change request and bring this to your change control boards.
o Reject your client request since the project is already close to completion.
CORRECT
Every change that was requested by your stakeholder needs to be reviewed by a
change control board or processed by a Perform Integrated Change Control process.
22. 22. Question
You are managing a project that will build new coal mine optimization software. There is
a heavy debate between your senior developers over what developing framework your
team will use to develop the software. To end the debate, you finally decide which
framework to use. Which conflict resolution technique that you use?
o Smooth/Accommodate
o Compromise/Reconcile
o Force/Direct
o Withdraw/Avoid
CORRECT
As the project manager you are forcing your decision to your project team, you are
using a force/direct conflict resolution technique. Ref PMBOK p. 283
23. 23. Question
Your bridge construction project is about to start and you need to identify your
stakeholders to understand their requirements. From the list below, which may not be
your stakeholder for this project?
o Concrete supplier
o Municipal government
o Project engineer
CORRECT
A competitor may or may not be a stakeholder in a project. All others are stakeholders
for this project.
24. 24. Question
Project management plan integrates and consolidates all of the subsidiary plan and
baselines from the planning process. Which document is not part of project
management plan?
o Schedule baseline
o Stakeholder register
o Control Quality
o Validate Scope
Any unique and verifiable product, result, or capability to perform a service that is required to be
produced to complete a process, phase, or project.
Fast Tracking
A schedule compression technique in which activities or phases normally done in sequence are
performed in parallel for at least a portion of their duration.
Program
A group of related projects, subprograms, and program activities managed in a coordinated way to
obtain benefits not available from managing them individually.
Includes the processes that are required to ensure timely and appropriate planning, collection, creation,
distribution, storage, retrieval, management, control, monitoring, and the ultimate disposition of project
information.
Includes the processes involved in planning, estimating, budgeting, financing, funding, managing, and
controlling costs so that the project can be completed within the approved budget.
Includes the processes that organize, manage, and lead the project team.
Project Integration Management
Includes the processes and activities needed to identify, define, combine, unify, and coordinate the
various processes and project management activities within the Project Management Process Groups.
The series of phases that a project passes through from its initiation to its closure.
Includes the processes necessary to purchase or acquire products, services, or results needed from
outside the project team.
Includes the processes and activities of the performing organization that determine quality policies,
objectives, and responsibilities so that the project will satisfy the needs for which it was undertaken.
Includes the processes of conducting risk management planning, identification, analysis, response
planning, and controlling risk on a project.
Includes the processes required to ensure that the project includes all the work required, and only the
work required, to complete the project successfully.
Includes the processes required to identify all people, or organizations impacted by the project,
analyzing stakeholder expectations and impact on the project, and developing appropriate management
strategies for effectively engaging stakeholders in project decisions and execution.
Project Stakeholders
An individual, group, or organization who may affect, be affected by, or perceive itself to be affected by
a decision, activity, or outcome of the project.
Project Time Management
Includes the processes required to manage the timely completion of the project.
Subproject
A smaller portion of the overall project created when a project is subdivided into more manageable
components or pieces.
1. Operations do not have any timelines. Projects are temporary and have finite time duration. 2.
Operations objective is usually to sustain the business. Project's objective is to achieve the target and
close the project.
Functional Organization
A hierarchical organization where each employee has one clear superior, and staff are grouped by areas
of specialization and managed by a person with expertise in that area.Functional organizations may still
have projects, but the perceived scope of the project is defined by the boundaries of the function.
Matrix Organization
Any organizational structure in which the project manager shares responsibility with the functional
managers for assigning priorities and for directing the work of persons assigned to the project. They
possess a blend of functional and projectized characteristics. Weak matrices maintain many of the
characteristics of a functional organization, and the Project Manager`s role is more that of a coordinator
or expediter than that of a manager. Similarly, strong matrices have many of the characteristics of the
projectized organization`s full-time project managers with considerable authority, full-time project
administrative staff, etc.
The conclusion of a project phase is marked by a review of both key deliverables and project
performance till date to determine if the project should continue into its next phase and detect and
correct errors cost-effectively. These phase end reviews may be referred to as phase exits, milestones,
phase gates, decision gates, stage gates, or kill points.
Project
A temporary endeavor undertaken to create a unique product, service, or result.
Project Management
Application of knowledge, skills, tools, and techniques to project activities to meet the project
requirements.
The centralized management of one or more portfolios to achieve strategic objectives. Portfolio
management ensures that the portfolios are reviewed to ascertain that resources are allocated as per
priority and the allocation is consistently in line with the organization`s strategies.
Projectized Organization
An organization where most of the organization`s resources are involved in project work, and Project
Managers have a great deal of independence and authority.
Regulation
PROJECT
1. TEMPORARY endeavor
PROGRAM
PORTFOLIO
Why PROJECTS
2. Driven by:
A) market demand
C) social need
D) environmental consideration
E) customer request
F) technological advance
G) legal requirement
PM OFFICE
3. Three types:
2. Two types:
A) INTERNAL:
- culture
- process
- HR
- risk tolerance
- politics
B) EXTERNAL:
- community
STAKEHOLDERS
1. Individuals, groups, orgs who are AFFECTED by project decisions, activities or outcomes
4. Includes:
B) sponsor
C) customers/users
D) sellers
E) biz partners
F) organizational groups
G) functional managers
GOVERNANCE
4. Includes:
A) acceptance criteria
B) resolve issues
D) decision-making process
E) communications process
A) leadership
B) team building
C) motivation
D) decision-making
E) negotiating
F) political awareness
G) conflict management
3. Influenced by OPAs
5. Can be:
A) PLAN-driven - product and scope DEFINED at START and managed closely (predictive)
B) ADAPTIVE - conditions are FAST (2-4 weeks) scope defined at START of each ITERATION And
INCREMENTAL. Called PROGRESSIVE ELABORATION
6. Characteristics:
A) start - CHARTER
B) prepare/organize - PM PLAN
ORGANIZATIONAL STRUCTURE
1. Six types:
PROCESS
2. Characterized by ITTOs
4. Are FINITE