And W: The Factor of Safety Determined in The Dam: For Preliminary Design
And W: The Factor of Safety Determined in The Dam: For Preliminary Design
• Graphical method of determining Wn and b • An approximate method to determine the safety of earth
Wt: The factor of safety determined in the dam: for preliminary design
above approach entirely depends on the • Overall stability: it is to be checked by considering the dam
accuracy of ϴ and areal measurements, which zi as a solid mass.
usually are difficult. Thus to avoid such in • The resisting force is taken as the shear developed at the
accuracies a the following graphical method is A base of the dam and is given by W tanφ. Where W is the
Wni
proposed. Wi effective unit weight of the dam and φ is the angle of
C internal friction angle. To determine the effective weight the
• 1. For each slices find out the heights through B
the centroid z1, z2, etc for all the slices. phreatic line has to be drawn first and then soil above the
phreatic line is considered moist or dry and the soil below
• 2. Calculate the weight of each slice as: Wi = bziϒ; where ϒ is the phreatic line is considered saturated.
the unit weight of the embankment soil depending on the • The force tending to cause sliding is the horizontal water
conditions (saturated or submerged). pressure given by 0.5ϒh2.
• 3. Extend z1, z2, etc vertically through A and draw W1, W2, etc • The factor of safety which is the ratio of the resisting force to
to the correct scale to locate B. the sliding force should not be less than 2.
• 4. Draw a tangent and normal lines through A and a parallel • Note here that the upstream water weight is not considered
line to the tangent through B. The triangle formed (ABC) is the in the analysis. Moreover the factor of safety uses the force
force polygon of Wni, Wti and Wi. rather than the momentum created by the forces
49 50
Hd 0.5 s H 2 tan 2 45 0.5 0.5h12 • As the portion of the soil above the phreatic line is small the
– Where ϒs is the unit weight of the soil at the vertical section AB entire soil mass is assumed to be saturated thus the ϒsat is
s subh1 moist H h1 H
and is given by used. The stability is analyzed for sudden drawdown.
• The resisting force against sliding is developed due to the
• The resisting force against sliding is developed due to the internal friction and cohesion (c) of the soil mass in the u/s
internal friction and cohesion (c) of the soil mass in the d/s portion. i.e. Wu tanφ + cbu; where Wu is the submerged
portion. i.e. Wd tanφ + cbd; where Wd is the effective weight weight (0.5ϒsubHbu) of the u/s portion of the soil.
(ϒsubAsub + ϒmoistAmoist) of the d/s portion of the soil. • The factor of safety is computed as the ratio of Hu and
• The factor of safety is computed as the ratio of Hd and resisting force. The factor of safety shall not be less than 2.
resisting force. The factor of safety shall not be less than 2.
51 52
1
5/2/2011
4.9 Seepage control 5. Steel sheet pile: Are driven up to the impervious stratum.
Steel sheet piles are usually expensive and are not very
• Measures to control seepage through the foundation: effective. There may be leakage through the joints between
1. Positive cutoff trench: When the foundation layer is of two sheet piles.
moderate depth (up to 25 m) a trench is excavated with 6. Upstream blanket with relief well: if the foundation material
suitable side slope and up to the hard stratum. The trench is extends to a great depth all the methods described above
then filled with impervious material. The fill materials shall be may not be viable from economic point. In such a case an
the same as the core. upstream blanket combined with a relief well is preferred.
2. Concrete diaphragm: Consists of a thin concrete cutoff wall An upstream blanket reduces the seepage gradient by
placed in a slurry trench excavated in the foundation. increasing the flow path. Impervious clay blanket of 1.5 m to
3. Grout curtain: is obtained by injecting a grout of cement, clay, 3 m thick and length up to 10 times the head of the ponded
chemicals or combination of these are injected under water are constructed; however the exact length is to be
pressure within the foundation zone. Clay grout is quite designed to keep the seepage gradient within the
effective in sand and gravel deposits. permissible limit. The relief well are provided to collect the
4. Slurry trench: A trench is excavated by a machine up to the seepage water through the foundation.
impervious stratum and the trench is filled with bentonite • For foundation having heterogeneous soil the combination
which prevents the trench from caving in. The trench is then of the above methods could be used.
backfilled with well graded impermeable material such as • For high permeable foundation (permeability greater than
mixture of sand, gravel and bentonite blended with 10 – 15 % 10-3m/s) grout curtain with diaphragm wall are generally
of natural silt. 55 economical. 56
59