KEYPLAN
A B C D E F G H J K L M
VACANT PLOT
9 M SET BACK
24 M. WIDE ROAD
45 M. WIDE ROAD
15 M SET BACK
9 M SET BACK
20 M GREEN BELT
PLOT NO. 05
9 M SET BACK
KEY PLAN
GENERAL NOTES
COLUMN SCHEDULE
R10
SIZE
10 COLUMN TYPE
X Y
R8 R9 C16,C17,C18,C46,C45
600 300
9 C53,C54,C55,C56
300 600
R6 C69 800 800 C70 800 800 C71 800 800 C72 800 800 C73 800 800 R7
8.1 C30,C31,C32,C33,C34,C35,C37,C38,C39,C40,C41,C42,C43,C44 1000 1400
C48,C49,C50,C51,C58,C59,C64,C65
C1,C2,C3,C4,C5,C6,C7,C8,C9,C10,C11,C12,C13,C14,C15,C19,
800 800
C20,C21,C22,C23,C24,C5,C26,C27,C28,C29,C36,C47,C52,C57,
C60,C61,C62,C63,C66,C67,C68,C69,C70,C71
S20 6330 450 S21 4950 450 S22 4950 450 S23 6330 450 7.3 S7 2400 600
C55 300 600 C56 300 600
7.2 S14,S15,S18,S19 450 2900
S16 450 2000 S18 450 2900 S19 450 2900 S17 450 2000
S14 450 2900 S15 450 2900 7.1 S20,S23 6330 450
7
C49 800 800 C50 1000 1400 C51 1000 1400 C52 1000 1400 C53 1000 1400 C48 600 300 C54 800 800 S10,S13,S21,S22 4950 450
S10 4950 450 S11 2800 450 S12 2800 450 S13 4950 450 6.5
S11,S12,S24,S25 2800 450
C47 600 300
6.4 S14,S16,S17 450 2000
S8 450 5025
6.3
S7 2400 600
S9 600 5100 6.2
R5 6.1
6
C38 1000 1400 C39 1000 1400 C40 1000 1400 C41 1000 1400 C42 1000 1400 C43 1000 1400 C44 1000 1400 C45 1000 1400
R1 C37 800 800 C46 800 800
5
C30 1000 1400 C31 1000 1400 C32 1000 1400 C33 1000 1400 C34 1000 1400 C35 1000 1400
C29 800 800 C36 800 800
S3 450 3000 S4 450 3000
3.1
C16 600 300 C17 600 300
3
C6 800 800 C7 800 800 C8 800 800 C9 800 800 C10 800 800 C11 800 800 C12 800 800 C13 800 800 C14 800 800 C15 800 800
2.1
R4 2
C1 800 800 C2 800 800 C3 800 800 C4 800 800 C5 800 800
R3
R2
1
B.TECH SEMESTER 7
DRAWING BY: NORTH
AJAY KUSHWAHA
DATE:31.10.2020
3A