Environmental Impact Assessment of The Fabrication of Pipe Rehabilitation Materials
Environmental Impact Assessment of The Fabrication of Pipe Rehabilitation Materials
Abstract: With the consistent increase in the global population, sustainable construction has become a trend that will need to be practiced in
perpetuity. The three main factors of sustainable construction that should be considered during planning and design of new projects are direct
Downloaded from ascelibrary.org by Universidad de los Andes on 03/10/20. Copyright ASCE. For personal use only; all rights reserved.
cost, social costs, and environmental impacts. Direct costs are regularly evaluated, and social costs are coming under more scrutiny, but the
environmental sustainability of construction is a big issue due to increasing concerns about global climate change and carbon emissions.
If reducing carbon emissions is a target, it is first essential to quantify the environmental impacts of any potential project to set the target to
achieve. In the pipeline industry, carbon footprint analyses for the construction phase have been performed regularly to identify less-carbon-
intensive methods. The pipeline industry, however, has yet to evaluate the environmental sustainability of its construction materials during the
fabrication stages. The objective of this study is to calculate and analyze the environmental sustainability, as determined by carbon footprint
and embodied energy, of 30 m (100 ft) of pipeline during the fabrication stages (material extraction, material production, and pipe manu-
facturing). This study focuses on three commonly used types of pipe/pipeline: prestressed concrete cylinder pipe (PCCP), PVC, and cured-in-
place pipe (CIPP). This paper focuses on a large-diameter 90-cm (36-in.) sewer pressure pipe operating at 689 kPa (100 psi) internal pressure.
Results show the environmental sustainability of PCCP to be lower than PVC and CIPP. The second phase of this project will focus on the
environmental impacts for each material during construction and operation to determine the overall environmental footprint of each material.
DOI: 10.1061/(ASCE)PS.1949-1204.0000395. © 2019 American Society of Civil Engineers.
Author keywords: Life cycle analysis; Carbon footprint; Embodied energy; Fabrication stage; Trenchless technology.
Fig. 1. Life cycle analysis and life phases of a pipeline. (Adapted from Filion et al. 2004, © ASCE.)
This would include all phases of fabrication, as seen in the life to 61 cm (24 in.), and the DIP was largest among the other pipes.
stages in Fig. 1. The emissions and generation resource integrated For pipe diameters larger than or equal to 76 cm (30 in.), PVC had
database (eGRID214) was used for this study. The eGRID is a the highest CO2 emissions. For all pipe sizes, the concrete pipe had
general source of data on the environmental aspects of almost all the lowest CO2 emissions (Du et al. 2013).
electric power generated in the United States. The eGRID is based For this study, three pipe materials were used, namely PCCP,
on available plant-specific data for all U.S. electricity generating CIPP, and PVC. These materials are briefly described in the sub-
plants that produce energy to the electric grid and report data to sequent sections.
the U.S. government. The eGRID is developed from a variety of
data collected by the U.S. Environmental Protection Agency (EPA),
and the Energy Information Administration (EIA). Texas regional Prestressed Concrete Cylinder Pipe
entity (TRE) = 1.2038 lb CO2 emission/kWh for electricity usage
(EPA 2014) PCCP has been manufactured and in use since 1942 for pressure
Most previous carbon emission studies have been about build- pipeline applications. PCCP can be designed for operating pressures
ings and not about water or sewer pipelines. There are a few studies greater than 2,758 kPa (400 psi) and underground covers of 30-m
on pipeline carbon emissions, but none of these compare CIPP liners (100-ft) [AWWA C301 (AWWA 2014b)]. There are two types of
with other pipe materials such as PCCP, PVC, or high-density poly- PCCP: line cylinder pipe (LCP) and embedded cylinder pipe (ECP).
ethylene pipe (HDPE). Chilana (2011) and Chilana et al. (2016) LCP is designed with a steel cylinder core lined with concrete and
researched and analyzed the carbon footprints for 241 km (150 mi) subsequently wrapped with a prestressing wire directly on the steel
of pipeline of different large diameters (66, 72, 84, and 108 in.). cylinder and coated with mortar. The diameter range of LCP is be-
The pipe materials were PCCP and steel. Chilana (2011) found that tween 41 and 152 cm (16 and 60 in.) ECP is designed with a core
PCCP pipes are better in terms of ecological impacts because they composed of a steel cylinder encased in concrete and subsequently
have a smaller carbon footprint than steel pipes. Khan and Tee wire-wrapped with prestressing wire over the concrete core and
(2015) analyzed the life cycle assessment between steel pipe, ductile coated with cement mortar. The pipe diameter is manufactured
mostly in a size range of 122 cm (48 in.) and larger. For both types
iron pipe (DIP), and PVC pipe, for a 1,524-m (5,000-ft)-long, 40-cm
of PCCP, the lengths in general are between 5 and 7.3 m (16 and
(15.7-in.)-diameter pipe. The results indicated that PVC emitted
24 ft) [AWWA M9 (AWWA 2008); AWWA C304-14 (AWWA
less carbon compared with steel and ductile iron pipe. Kyung et al.
2014a)]. Key differences are highlighted in Table 1 and Fig. 2.
(2017) estimated the total greenhouse gas (GHG) emissions for
whole life cycle stages of a sewer pipeline system for various
pipeline materials including PVC, polyethylene (PE), concrete, and
cast-iron pipe (CIP). The results show that concrete pipe generated a Table 1. Differences between lined cylinder pipe and embedded cylinder
pipe
lower amount of GHG than pipes made from other materials (Kyung
et al. 2017). Lined cylinder pipe Embedded cylinder pipe
Du et al. (2013) carried out a life cycle analysis (LCA) study Parameter (LCP) (ECP)
for six different pipe materials: PVC, CIP, HDPE, DIP, concrete, Diameter 400–1,500 mm (16–60 in.) 750–6,500 mm (30–256 in.)
and reinforced concrete. The objectives were to compare the six Design Steel cylinder lined with Steel cylinder embedded in a
pipe materials regarding global warming potential through the four a cast concrete core concrete core
life cycle phases. The pipe diameters ranged from 10 to 122 cm Prestressing Wrapped over steel Wrapped over concrete core
(4 to 48 in.) for that study. The results for CO2 emissions in the wire cylinder
fabrication phase shows that pipe diameters were less than or equal Source: Data from Romer et al. (2007).
Fig. 2. Schematic showing the different in wall cross sections between LCP and ECP pipe. (Reprinted with permission from AWWA C304-14 Design
of Prestressed Concrete Cylinder Pipe Copyright © AWWA 2014. All rights reserved.)
To determine the carbon emissions involved with the manufac- described subsequently. Assumptions for the design of all three
ture of PCCP, the steps of manufacture must be understood. There pipe materials in this study include an outside diameter of 90-cm
are eight steps to manufacture PCCP (AWWA M9) (Manda 2014): (36-in.), internal operating pressure of 689 kPa (100 psi), and a total
1. Manufacture and fabricate the steel cylinder. length of 30 m (100 ft).
2. Attach the joint rings to the steel cylinder pipe. After acquiring In this study LCP was used, which is more common for 90-cm
the desired shape and sizes of the steel cylinder, the joints are (36-in.)-diameter pipes. The minimum design thickness of the core
attached and welded to the steel cylinder. including the thickness of the steel cylinder should be 1=16 of
3. Perform hydrostatic test for steel cylinder. There are two ways to the design pipe diameter based on AWWA C301. So, the core
do the test: horizontally or vertically. thickness is
4. Place the concrete core around the steel cylinder. The main com- 36
ponents of concrete are cement, coarse aggregate, fine aggregate, ¼ 57 mm ð2.25 in:Þ
water, and admixtures. 16
5. Cure the concrete core. Curing is a process of maintaining sa- where the thickness of the steel cylinder is 16 gauge (0.0598 in.);
tisfactory moisture content at a certain temperature for a certain the size of prestressing wire is 6 gauge [0.5 cm (0.192 in.)]; and the
period. design spacing between pre-stressing wire is 2.75× wire diameter
6. Wrap the prestressing wire around the concrete core to give it a per AWWA C301. Therefore, the space between wire centers is
high tensile strength. 2.75 × 0.192 ¼ 1.34 mm ð0.528 in:Þ The mortar coating thickness
7. Apply the external mortar coating. After the concrete has been is 19 mm (0.75 in.) per AWWA C301. The materials densities per
wrapped with prestressed wire, an exterior mortar coating should AWWA C301 are as follows:
be applied. The mortar coating minimum thickness is 19 mm • concrete: 0.0839 lb=cu in. (2,322.61 kg=m3 ),
(3/4 in.), and the mortar coating should cover the wire. • prestressing wire: 0.2829 lb=cu in. (7,832.80 kg=m3 ),
8. Cure the mortar coating. • steel cylinder: 0.2829 lb=cu in. (7,832.80 kg=m3 ), and
From the steps of manufacture, one can determine the types • mortar coating: 0.0423 lb=cu in. (1,170 kg=m3 ).
and order of materials used when making the pipe. To determine The total energy consumption for each pipe of PCCP is calcu-
the amount of each material, the pipe design method is used as lated using the following equation:
Total energyPCCP PVC resin with heat stabilizers, lubrication materials, and fillers.
The purpose of adding heat stabilizers to the PVC resin mix is to
¼ Embodied energyConcrete × WeightConcrete delay heat degradation so the mix can be formed into a product
þ Embodied energySteel Cylider × WeightSteel cylinder before it degrades. Lubrication materials control the melting point
in the extruder to achieve the best processing and physical proper-
þ Embodied energyMortar coating × WeightMortar coating
ties. The filler is added to the PVC resin mix to lower material cost
þ Embodied energyPrestressing wire × WeightPrestressing wire and provide coloring (AWWA M23). Fig. 3 details the flow of PVC
pipe production.
Total CO2 emissions equal total energy consumption multiplied Assumptions for the design of the PVC in this study remain
by the CO2 emission rate. The inputs for the PCCP calculation are the same as they were for the other materials, i.e., diameter of
given in Table 2. 90-cm (36 in.), internal pressure of 689 kPa (100 psi), and length
of 30 m (100 ft). The pipe wall thickness is 2.4 cm (0.934 in.)
per AWWA C900 (AWWA 2016). The schematic cross section for
PVC Pipe CIPP shown in Fig. 4, and the standard pipe length is 51 cm (20 ft)
per ASTM D2665 (ASTM 2012). The PVC pipe embodied
PVC was found in the late nineteenth century, and in the 1920s, energy is 67.5 Mj=kg per ICE version 2.0. The total energy con-
scientists brought PVC to public attention again. In the 1930s, sumption for each pipe of PVC is calculated using the following
scientists in Germany developed and produced limited quantities equation:
of PVC pipe. PVC pipe has been installed regularly in Europe
since the early 1970s, and since the early 1990s in North America Total energyPVC ¼ Embodied energyPVC × WeightPVC
[AWWA M23 (AWWA 2002)]. The fundamental raw materials
of PVC pipe resin are derived from ethylene (mostly natural Total CO2 emissions are equal to the total energy consumption
gas–based or petroleum-based), and chlorine (mostly salt-based) multiplied by the CO2 emission rate. The inputs for the PVC cal-
(Krock and Middleton 2013). PVC pipe is manufactured by mixing culation are given in Table 3.
Fig. 3. Cradle to resin flow diagram of PVC production. (Adapted from Krock and Middleton 2013.)
ASTM Equation
D 36
t¼ ¼ ¼ 14.7 mm ð0.58 in.Þ
DR 62
t ¼ 14.7 mm ð0.58 in.Þ
D Thickness of fiberglass reinforced 2.25 mm (0.088 in.) 0.088 Three layers of fiberglass with
thickness 0.75 mm per layer
E Liner and exterior layer thickness 0.20 m (0.010 in.) 0.010 Each layer 0.005 in. (0.10 mm)
ASTM D3567 standard
F Thickness of felt 12.25 mm (0.502 in.) 0.502 F ¼ C–ðD þ E)
Two layers of felt each with
6.125 mm per layer
G Weight of fiberglass reinforced lb 1,096.13 Weight = volume × density
Density 158.6 lb=cu ft
H Weight of felt lb 1,080.24 Weight = volume × density
Density 27.4 lb=cu ft
I Weight of resin lb 3,706.13 Weight = volume × density
Density of epoxy 94 lb=cu ft
J Weight of tube liner and exterior layer lb 4.71 Weight = volume × density
Density of polyurethane 6 lb=cu ft
K Embodied energy for felt MJ=kg 36 ICE version 2.0
kWh=lb 4.54 1 MJ=kg ¼ 0.126 kWh=lb
L Embodied energy for resin MJ=kg 137 ICE version 2.0
kWh=lb 17.26 1 MJ=kg ¼ 0.126 kWh=lb
M Embodied energy for fiberglass reinforcement MJ=kg 100 ICE version 2.0
kWh=lb 12.6 1 MJ=kg ¼ 0.126 kWh=lb
N Embodied energy for tube liner MJ=kg 80.10 ICE version 2.0
kWh=lb 10.1 1 MJ=kg ¼ 0.126kWh=lb
O Total energy consumption kWh 82,730.9 O¼G×MþH×KþI×LþJ×N
P CO2 emission rate lb=kWh 1.2038 eGRID2014
Q Total CO2 emissions lb 99,592 Q¼O×P
AWWA.
Fig. 6. CO2 emissions during fabrication phase.
AWWA (American Water Works Association). 2016. Polyvinyl chloride
(PVC) pressure pipe and fabricated fittings, 14 in. through 48 in.
ANSI/AWWA C900. Denver: AWWA.
diameter, and material by scaling up the material qualities using Chilana, L. 2011. “Carbon footprint analysis of a large diameter water
proper design procedures. transmission pipeline installation.” M.S. thesis, Dept. of Civil Engineer-
The limitations of this study include the embodied energy data- ing, Univ. of Texas at Arlington.
base used, which represents the UK average and may vary from Chilana, L., A. Bhatt, M. Najafi, and M. Sattler. 2016. “Comparison of
location to location. Also, the boundary conditions for fabrication carbon footprints of steel versus concrete pipelines for water transmis-
phase are assumed to be from cradle to the factory gate. The waste sion.” J. Air Waste Manage. Assoc. 66 (5): 518–527. https://doi.org/10
materials during fabrication were assumed to be negligible and .1080/10962247.2016.1154487.
are not accounted for. Also, the PCCP joint used in this study is Du, F., G. J. Woods, D. Kang, K. E. Lansey, and R. G. Arnold. 2013. “Life
assumed to be a rubber O-ring bell and spigot joint. cycle analysis for water and wastewater pipe materials.” J. Environ.
Eng. 139 (5): 703–711. https://doi.org/10.1061/(ASCE)EE.1943-7870
.0000638.
Conclusion EPA (Environmental Protection Agency). 2014. Emissions & Generation
Resource Integrated Database (eGRID2014). Washington, DC: EPA.
In the first phase of the pipeline life cycle (fabrication phase), this Filion, Y. R., H. L. MacLean, and B. W. Karney. 2004. “Life-cycle energy
study has shown that PCCP generated a lower amount of carbon analysis of a water distribution system.” J. Infrastruct. Syst. 10 (3):
compared with PVC and CIPP for a 90-cm (36-in.), 30-m (100-ft)- 120–130. https://doi.org/10.1061/(ASCE)1076-0342(2004)10:3(119).
long pressure pipe project. PVC has higher energy consumption Hammond, G., and C. Jones. 2011. Inventory of carbon and energy (ICE),
than PCCP but lower energy consumption than CIPP. Finally, CIPP version 2.0. Bath, UK: Sustainable Energy Research Team, Dept. of
has the highest energy consumption compared with both PCCP and Mechanical Engineering, Univ. of Bath.
Khan, L. R., and K. F. Tee. 2015. “Quantification and comparison of carbon
PVC. Small savings in the quantity of material makes a big change
emissions for flexible underground pipelines.” Can. J. Civ. Eng.
in the total carbon emissions. Pipes with smaller diameters emitted
42 (10): 728–736.
less carbon than large pipes made with the same pipe material. The
Krock, R., and G. Middleton. 2013. The role of PVC resins in sustainable
second phase of this study is underway and is focused on the in- design. Washington, DC: Vinyl Institute.
stallation stage. The overall goal is to look at the entire life cycle Kyung, D., D. Kim, S. Yi, W. Choi, and W. Lee. 2017. “Estimation of
of each material, including installation, use, and disposal stages, to greenhouse gas emissions from sewer pipeline system.” Int. J. Life
determine which material is most environmentally friendly. Cycle Assess. 22 (12): 1901–1911. https://doi.org/10.1007/s11367
Of the three cost/impact factors that should be considered when -017-1288-9.
choosing pipeline material (direct cost, social cost, and environ- Manda, R. 2014. “Performance of Prestressed Concrete Cylinder Pipe
mental impact), this study is only focused on environmental impact. (PCCP) in water applications.” M.S. thesis, Dept. of Civil Engineering,
There are some studies on the direct cost, but few have been done Univ. of Texas at Arlington.
on social cost [Matthews et al. (2015) did a study on the social cost Martins, J., E. Freire, and H. Hemadipour. 2009. “Applications and market
impact evaluations for pipelines], but no study has been done re- of PVC for piping industry.” Polímeros 19 (1): 58–62. https://doi.org/10
garding the environmental impact for trenchless options over the .1590/S0104-14282009000100014.
entire life cycle. It is recommended to include all three cost/impact Matthews, J. C., E. N. Allouche, and R. L. Sterling. 2015. “Social cost
factors together, which will help the decision maker to obtain the impact assessment of pipeline infrastructure projects.” Environ. Impact
best results for selecting a pipe material and method. This study Assess. Rev. 50 (Jan): 196–202. https://doi.org/10.1016/j.eiar.2014.10
benefits pipeline industry and decision makers to monitor their car- .001.
bon footprint and to set their carbon emissions target. For future Matthews, J. C., A. Selvakumar, R. L. Sterling, and W. Condit. 2014.
research, it is recommended that field studies should be conducted “Innovative rehabilitation technology demonstration and evaluation
to obtain necessary data to overcome dependence on the assump- programs.” Tunnelling Underground Space Technol. 39: 73–81.
Moore, W., and N. N. Dig. 2011. Non-styrene options for cured in place
tions made in this study.
pipe. Cleveland: North American Society for Trenchless Technology.
Romer, A., G. Bell, and R. Ellison. 2007. “Failure of prestressed concrete
References cylinder pipe.” In Proc, ASCE Pipelines, 1–17. Reston, VA: ASCE.
Teimouri Sendesi, S. M., et al. 2017. “Worksite chemical air emissions and
ASTM. 2002. Standard practice for determining dimensions of ‘Fiber- worker exposure during sanitary sewer and stormwater pipe rehabilita-
glass’ (Glass-fiber-reinforced thermosetting resin) pipe & fittings. tion using cured-in-place-pipe (CIPP).” Environ. Sci. Technol. Lett.
ASTM D3567. West Conshohocken, PA: ASTM. 4 (8): 325–333. https://doi.org/10.1021/acs.estlett.7b00237.