Power System Dynamics and Control: Test 1 Date: 16 December 2020 Time: 04:00 - 06:00 PM
Power System Dynamics and Control: Test 1 Date: 16 December 2020 Time: 04:00 - 06:00 PM
Power System Dynamics and Control: Test 1 Date: 16 December 2020 Time: 04:00 - 06:00 PM
1
Dept. of EE, IISc E4:231 PSDC, 2020
2
Dept. of EE, IISc E4:231 PSDC, 2020
The load connected at bus 3 and 13 is a ZIP load model as given in the following
expression.
𝑃 (𝑉 ) = 𝑃 (0.4 + 0.3 ∗ 𝑉 + 0.3 ∗ 𝑉 )
𝑄 (𝑉 ) = 𝑄 (0.4 + 0.3 ∗ 𝑉 + 0.3 ∗ 𝑉 )
| |
where, 𝑉 = and 𝑃 , 𝑉 are the initial values of power and voltage at the
| |
bus as given in load flow data.
a. Compute all initial conditions of all generators considering 1.1
model of generator.
b. Compute the diagonal elements of augmented Y-bus for the given
power system network. The diagonal elements for generator and
load buses only need to be calculated.
c. Consider, a certain disturbance occurs in the network and the voltage
at load buses (3 and 13) changes to 0.99∠ − 16.12 and 1.02∠ −
24.65 respectively. Compute the current injections at both load
buses.
3
Dept. of EE, IISc E4:231 PSDC, 2020