Piping Knowledge
Piping Knowledge
OBJECTIVES
II. RESPONSIBILITIES
III. APPLICABLE CODES & STANDARDS FOR MANIFA
PROJECT
IV. MATERIALS (RECEIVING, STORAGE & HANDLING)
V. PIPE FIT-UP TOLERANCES
VI. FABRICATION AND INSTALLATION REQUIREMENTS
VII. PIPE SUPPORTS AND HANGERS
VIII.PRESSURE TESTING (OTHER SET OF PRESENTATION)
a. Pneumatic Testing (EMS)
b. Hydrostatic Testing (RFP / RAD)
IX. REINSTATEMENT
a. Bolt Torquing & Tensioning (RGP)
b. Lay-up (RAD)
➢ TO PROVIDE A MINIMUM GUIDELINES TO CARRY PIPING
FABRICATION AND ERECTION TO ENSURE THAT THE WORK
IS CARRIED OUT WITH PROJECT DRAWINGS AND SAUDI
ARAMCO PROJECT SPECIFICATIONS.
A. INTERNATIONAL
STANDARDS
B. SAUDI ARAMCO
STANDARDS
C. JAL PROJECT
SPECIFICATIONS
D. ARCC PROJECT
PROCEDURES
III. APPLICABLE CODES & STANDARDS FOR
ARAMCO PROJECTS
A. INTERNATIONAL
STANDARDS
a. ASME B31.1 for
power plant piping
b. ASME B31.3 for
chemical process
plant piping
c. ASME IIC for welding rods,
electrodes, and filler metals
d. ASME V for nondestructive
examination
e. ASME IX for welding
qualifications
III. APPLICABLE CODES & STANDARDS FOR
ARAMCO PROJECTS
B. SAUDI ARAMCO
STANDARDS
C. JAL PROJECT
SPECIFICATIONS
SCOPE OF WORK
SCOPE OF WORK
1. The aboveground piping installation works shall mean the erection of the piping
including reviewing of the prefabricated spools prepared by the other party,
components and raw materials to be installed in exposed conditions, not buried
under the ground. This scope includes transportation of raw/prefabricated
piping materials, hoisting, assembling, cutting, beveling, fitting, pre-heating,
welding, bolting, installation of piping components such as all valves, strainers,
blind/orifice plates, flow/level/pressure/temperature instruments, spring
hangers, counter-weights, sliding plates, expansion joints, emergency showers,
locking devices, all non-destructive examination except for RT which is to be
measured under FWBS 6700.
III. APPLICABLE CODES & STANDARDS FOR
ARAMCO PROJECTS
C. JAL PROJECT SPECIFICATIONS
a. FWBS Code FUNCTIONAL WORK BREAKDOWN STRUCTURE
FWBS Code Work Description
6200 ABOVEGROUND INSTALLATION
SCOPE OF WORK
2. Installation of the following local instruments shall be handled in this category:
➢ pressure gauge (directly mounted on piping)
➢ thermocouple, resistance bulb, thermometer and well
➢ displacement type level instrument, level switch, and level gauge
➢ in-line flow instrument, e.g. PD meter, turbine meter, magnetic meter,
area meter, vortex meter, etc.
3. Spool drawings preparation and prefabrication of the small bore piping shall be
included under this work category, in addition to the installation of the piping
at the Site.
III. APPLICABLE CODES & STANDARDS FOR
ARAMCO PROJECTS
C. JAL PROJECT SPECIFICATIONS
a. FWBS Code FUNCTIONAL WORK BREAKDOWN STRUCTURE
FWBS Code Work Description
6200 ABOVEGROUND INSTALLATION
APPLICABLE STANDARDS
SAUDI ARAMCO TYPICAL INSPECTION PLAN
SATIP-L-350-01
SAUDI ARAMCO INSPECTION CHECKLISTS
SAIC-A-2001 SAIC-A-2007 SAIC-A-2013 SAIC-A-2019
SAIC-A-2002 SAIC-A-2008 SAIC-A-2014 SAIC-A-2020
SAIC-A-2003 SAIC-A-2009 SAIC-A-2015 SAIC-A-2021
SAIC-A-2004 SAIC-A-2010 SAIC-A-2016 SAIC-A-2022
SAIC-A-2005 SAIC-A-2011 SAIC-A-2017
SAIC-A-2006 SAIC-A-2012 SAIC-A-2018
SAUDI ARAMCO TEST REPORTS
SATR-A-2007 SATR-A-2011
SATR-A-2008 SATR-L-2001
SATR-A-2009
III. APPLICABLE CODES & STANDARDS FOR
ARAMCO PROJECTS
C. JAL PROJECT
SPECIFICATIONS
a. FWBS Code FUNCTIONAL WORK BREAKDOWN STRUCTURE
FWBS Code Work Description
6300 UNDERGROUND INSTALLATION
SCOPE OF WORK
1. The underground piping installation works shall mean the erection of the piping
to be buried under the ground up to and including the first bend when such
underground piping stubs up above the ground level or connected to the
aboveground piping. This scope includes transportation of raw/prefabricated
piping materials, hoisting, assembling, cutting, beveling, fitting, pre-heating,
welding, bolting, installation of piping components such as valves, strainers,
blind and orifice plates, flow/level/pressure/temperature instruments, fire
hydrants, fire monitors, hose reels, laying sand bags underneath the piping,
additional excavation of trench for working spaces, non-destructive
examination except for RT which is to be measured under FWBS 6700, etc.
III. APPLICABLE CODES & STANDARDS FOR
ARAMCO PROJECTS
C. JAL PROJECT
SPECIFICATIONS
a. FWBS Code FUNCTIONAL WORK BREAKDOWN STRUCTURE
FWBS Code Work Description
6300 UNDERGROUND INSTALLATION
APPLICABLE STANDARDS
SAUDI ARAMCO TYPICAL INSPECTION PLAN
SATIP-S-070-03
SCOPE OF WORK
1. This category shall cover the fabrication and installation of piping supports
including support pads. This scope includes purchasing of the materials as
per the Exhibit B of this Annex, transportation of raw/prefabricated
support materials, hoisting, assembling, fitting, cutting, pre-heating,
welding, bolting, necessary inspection, etc. Supports for the heat
tracing piping/tubing are excluded herefrom.
III. APPLICABLE CODES & STANDARDS FOR
ARAMCO PROJECTS
C. JAL PROJECT SPECIFICATIONS
a. FWBS Code FUNCTIONAL WORK BREAKDOWN STRUCTURE
FWBS Code Work Description
6400 SUPPORT FOR PIPING
SCOPE OF WORK
The work under this category is broken down into FWBS Code 6410 and 6420:
FWBS Code 6410 FABRICATION
• The work under this FWBS Code covers the fabrication of
piping supports at shop in field or other place.
FWBS Code 6420 INSTALLATION
• The work under this FWBS Code covers the installation of
fabricated supports on the piping.
• Pre-cast concrete foundation installation shall be included in this
category.
• Special supports such as spring supports, sliding plates, counter
weights, etc., which are fabricated by manufactures and supplied
in prefabricated or pre-assembled condition are not included in
this category. They shall be deemed to be a part of the installation
of piping components under FWBS 6200 and 6300.
III. APPLICABLE CODES & STANDARDS FOR
ARAMCO PROJECTS
THIS WILL BE SEPARATELY
C. JAL PROJECT DISCUSSED BY WELDING
SPECIFICATIONS PRESENTOR
SCOPE OF WORK
SCOPE OF WORK
APPLICABLE STANDARDS
SAUDI ARAMCO TYPICAL INSPECTION PLAN
SATIP-A-004-01 PNEUMATIC PRESSURE TESTING
SA INSPECTION CHECKLISTS SA TEST REPORTS
SAIC-A-2001 SAIC-A-2011 SATR-A-2001 SATR-A-2007
SAIC-A-2003 SAIC-A-2020 SATR-A-2002 SATR-A-2008
SAIC-A-2004 SAIC-A-2021 SATR-A-2003 SATR-A-2010
SAIC-A-2005 SAIC-A-2022 SATR-A-2006 SATR-A-2011
SAIC-A-2006 SAIC-A-2023
SAIC-A-2009 SAIC-L-2001
SAIC-A-2010 SAIC-L-2017
III. APPLICABLE CODES & STANDARDS FOR
ARAMCO PROJECTS
C. JAL PROJECT
SPECIFICATIONS
a. FWBS Code FUNCTIONAL WORK BREAKDOWN STRUCTURE
FWBS Code Work Description
6800 PRESSURE TEST, FLUSHING & LAY-UP
APPLICABLE STANDARDS
SAUDI ARAMCO TYPICAL INSPECTION PLAN
SATIP-A-004-02 PRESSURE TESTING-HYDROSTATIC TEST OF PLANT PIPING
SA INSPECTION CHECKLISTS SA TEST REPORTS
SAIC-A-2001 SAIC-A-2015 SATR-A-2001 SATR-A-2009
SAIC-A-2003 SAIC-A-2016 SATR-A-2001V SATR-A-2010
SAIC-A-2006 SAIC-A-2017 SATR-A-2002 SATR-A-2011
SAIC-A-2007 SAIC-A-2018 SATR-A-2003 SATR-A-6133
SAIC-A-2008 SAIC-A-2021 SATR-A-2004
SAIC-A-2009 SAIC-A-2023 SATR-A-2005
SAIC-A-2010 SAIC-L-2001 SATR-A-2006
SAIC-A-2011 SAIC-L-2041 SATR-A-2007
SAIC-A-2013 SAIC-L-2042 SATR-A-2008
III. APPLICABLE CODES & STANDARDS FOR
ARAMCO PROJECTS
C. JAL PROJECT
SPECIFICATIONS
a. FWBS Code FUNCTIONAL WORK BREAKDOWN STRUCTURE
FWBS Code Work Description
6800 PRESSURE TEST, FLUSHING & LAY-UP
APPLICABLE STANDARDS
SAUDI ARAMCO TYPICAL INSPECTION PLAN
SATIP-A-004-03 PRESSURE TESTING-HYDROSTATIC TEST OF PIPELINES
SA INSPECTION CHECKLISTS SA TEST REPORTS
SAIC-A-2001 SAIC-A-2016 SATR-A-2001 SATR-A-2009
SAIC-A-2003 SAIC-A-2017 SATR-A-2001V SATR-A-2010
SAIC-A-2006 SAIC-A-2018 SATR-A-2002 SATR-A-2014
SAIC-A-2007 SAIC-L-2001 SATR-A-2003 SATR-A-2021
SAIC-A-2008 SAIC-L-2017 SATR-A-2004 SATR-A-2023
SAIC-A-2009 SAIC-L-2041 SATR-A-2005
SAIC-A-2011 SAIC-L-2042 SATR-A-2006
SAIC-A-2013 SAIC-L-2139 SATR-A-2007
SAIC-A-2015 SAIC-L-2042 SATR-A-2008
III. APPLICABLE CODES & STANDARDS FOR
ARAMCO PROJECTS
C. JAL PROJECT
SPECIFICATIONS
a. FWBS Code FUNCTIONAL WORK BREAKDOWN STRUCTURE
APPLICABLE STANDARDS
JAL PROJECT SPECIFICATIONS
S-000-3160-015 FLANGE BOLT TENSIONING PROCEDURE FOR PIPING
FOR SPECIFICATION 6
S-000-1360-003
FOR VENDOR DOCUMENT
6
V-216B-144C-A-201
III. APPLICABLE CODES & STANDARDS FOR
ARAMCO PROJECTS
D. ARCC PROJECT
PROCEDURES
b. MS METHOD STATEMENTS
• PIPES • FITTINGS
PIPING REFERS TO
THE OVERALL NETWORK
OF PIPES, FITTINGS,
PIPES FITTINGS
VALVES, FLANGES,
PIPING SUPPORTS, AND
OTHER COMPONENTS
• FLANGE FLANGES
& VALVES • VALVE
THAT COMPRISE A GASKETS
COMPLETE SYSTEM • GASKET
USED TO CONVEY FLUIDS
(LIQUIDS, VAPORS, OR
GAS)
IV. MATERIALS
IV. MATERIALS
A FITTINGS INCLUDE
ELBOWS, TEES,
REDUCERS, BRANCH
CONNECTIONS AND
INTEGRALLY REINFORCED
CONNECTIONS.
IV. MATERIALS
FITTINGS
FLANGES
MATERIAL HANDLING, & STORAGE
❖ A RESILIENT MATERIAL
➢ RUBBER
GASKETS
MATERIAL HANDLING, & STORAGE
Gaskets are visually checked during receiving in a clean area or warehouse
appropriate to ensure gaskets, especially fillers and lubricated items are not
fouled by sand and dust. Packaging is only opened as needed (due to
oxidation and rusting concerns) to allow basic checks to assure gasket quality.
Contractor has a Color Code System (Gasket Service Chart) for all gaskets to
be used on the project and the gaskets received are checked against the color
code chart. Color code chart (gaskets) is clearly posted in storage area.
GASKETS
MATERIAL STORAGE, & HANDLING
6” – FG – 123 – 1CS2P03
LINE SIZE
SERVICE CODE
LINE NUMBER
1CS2P03
5th
PROJECT SPECIFIC CLASS SYMBOL
4th
SERVICE
3rd
CORROSION ALLOWANCE
2nd
MATERIAL
1st
NOMINAL PRESSURE RATING OR CLASS
VI. FABRICATION & INSTALLATION
REQUIREMENTS
(ASME B16.5 / B16.47 Flange Class) (ASME B16.1 Cast Iron Flange Class)
1 150 12 125
3 300 13 250
9 900 80 Non-pressure
CC Carbon Steel (low carbon) FF Glass Fiber Vinyl Ester PV PVC (Polyvinyl Chloride)
CG Galvanized Carbon Steel LC Cement-lined Carbon Steel SC 304L, 304H Stainless Steel
CJ 1-1/4 Cr-1/2 Mo Alloy Steel LE Epoxy-lined Carbon Steel SD 316L Stainless Steel
CK 2-1/4 Cr-1 Mo Alloy Steel LP Polypropylene-lined Carbon Steel SJ 321 Stainless Steel
CL 5 Cr-1/2 Mo Alloy Steel NH Hastelloy C276 SV 254 SMO (UNS S31254 or equivalent)
Digit Description
0 Zero Corrosion allowance
1 1.6 mm
2 3.2 mm
3 4.8 mm
4 6.4 mm
9 Corrosion Allowance as noted. Refer to SAES-L-133
for specific corrosion protection requirements.
VI. FABRICATION & INSTALLATION
REQUIREMENTS
20mm OR 3Tὡ
VI. FABRICATION & INSTALLATION
REQUIREMENTS
4. REINFORCING PAD
IT IS A WELDED ATTACHMENT FOR WELDED TYPE BRANCH
NOTE:
a. PRESSURE TESTING FOR REINFORCING PAD SHALL BE PERFORMED
WITH THE CONDITION BELOW:
PRESSURE : 25 PSI
HOLDING TIME : UNTIL COMPLETION OF SOAP TEST
TAP SIZE : 6 mmØ
5. CIRCUMFERENTIAL OFFSET
PREFERABLY, THE DISTANCE (CIRCUMFERENTIAL OFFSET) BETWEEN
LONGITUDINAL WELDS OF ADJACENT PIPE JOINTS SHALL BE 90
DEGREES APART.
90°
VI. FABRICATION & INSTALLATION
REQUIREMENTS
5. CIRCUMFERENTIAL OFFSET
MINIMUM REQUIREMENT
25mm or 30°
VI. FABRICATION & INSTALLATION
REQUIREMENTS
5. CIRCUMFERENTIAL OFFSET
MINIMUM REQUIREMENT
❖ PIPING DESIGNED BY 31.4 : AT LEAST 100mm APART
100 mm
CHAMFER
CHAMFER
SECTION
VI. FABRICATION & INSTALLATION
REQUIREMENTS
8. WELDING ATTACHMENTS
9. JOINTS
A. BUTT JOINT
B. SOCKET JOINT
REFER TO SAIC-W-2037
C. THREADED JOINT
REFER TO SAIC-L-2015
D. FLANGED JOINT
REFER TO SAIC-L-2014
VI. FABRICATION & INSTALLATION
REQUIREMENTS
9. JOINTS
A. BUTT JOINT – A JOINT BETWEEN TWO MEMBERS ALIGNED
APPROXIMATELY IN THE SAME PLANE.
INTERNAL MISALIGNMENT
(HI-LO) = 1.5mm max
EXCEPTION:
±
VI. FABRICATION & INSTALLATION
REQUIREMENTS
9. JOINTS
A. BUTT JOINT
PRIOR TO START WELDING, THE FOLLOWING SHALL BE CHECKED,
3. CLEANLINESS OF GROOVE
4. ALIGNMENT OF PIPING
±
VI. FABRICATION & INSTALLATION
REQUIREMENTS
9. JOINTS
ACCEPTABLE
2 mm CORRECT
±
VI. FABRICATION & INSTALLATION
REQUIREMENTS
9. JOINTS
0 mm WRONG
±
VI. FABRICATION & INSTALLATION
REQUIREMENTS
9. JOINTS
2 mm WRONG
±
VI. FABRICATION & INSTALLATION
REQUIREMENTS
9. JOINTS
WRONG
±
VI. FABRICATION & INSTALLATION
REQUIREMENTS
9. JOINTS
±
VI. FABRICATION & INSTALLATION
REQUIREMENTS
9. JOINTS
STEP 1 : CLEAN SOCKET END STEP 2 : CUT PIPE NICE AND SQUARE
±
VI. FABRICATION & INSTALLATION
REQUIREMENTS
9. JOINTS
B. SOCKET WELDING JOINT
STEP 3 : MECHANICAL MARK – A 25mm RULE
A. MARK A POINT EXACTLY 25mm FROM PIPE END
B. QC WILL WITNESS DIMENSION. (QC SHALL USE PERMANENT SHARPY PEN OR MARKER
AND CIRCLE THE 25mm VERIFICATION MARK).
25mm
13-09-10
A DVD
±
VI. FABRICATION & INSTALLATION
REQUIREMENTS
9. JOINTS
B. SOCKET WELDING JOINT
STEP 4 : INSERT THE PIPE FULLY INTO THE SOCKET UNTIL THE PIPE CONTACTS TO
THE INNER SOCKET FACE. THEN MEASURE THE DISTANCE FROM EDGE OF
FITTING TO THE MARK.
Example
X=10
x
25mm
±
VI. FABRICATION & INSTALLATION
REQUIREMENTS
9. JOINTS
B. SOCKET WELDING JOINT
STEP 5 : RETRACT PIPING 2mm ABOVE THE EDGE OF THE FITTING USING THE
MARK AS REFERENCE.
X+2 Example
X=10
x X+2=12
25mm
±
VI. FABRICATION & INSTALLATION
REQUIREMENTS
9. JOINTS
B. SOCKET WELDING JOINT
STEP 6 : TACK WELD THE JOINT.
THEN ENDORSE TO QC PRIOR SEAL 12mm min.
WELDING.
±
VI. FABRICATION & INSTALLATION
REQUIREMENTS
9. JOINTS
PREVIOUS
B. SOCKET WELDING JOINT
STEP 4 : PULL OUT CUT PIPE UNTIL MARKING IS 2mm FROM SOCKET END AS
SHOWN BELOW.
2mm
MARK PIPE
2mm
HERE
TOP VIEW
±
VI. FABRICATION & INSTALLATION
REQUIREMENTS
9. JOINTS
C. THREADED JOINT
±
VI. FABRICATION & INSTALLATION
REQUIREMENTS
9. JOINTS
C. FLANGED JOINT
A JOINT IN A PIPING SYSTEM IS ACHIEVED BY 1.)
WELDING 2.) THREADING 3.) FLANGES
1. FLANGE
2. GASKET
3. BOLTING
±
VI. FABRICATION & INSTALLATION
REQUIREMENTS
9. JOINTS
C. FLANGED JOINT
➢ FOR TEMPORARY GASKET
10 O’CLOCK 2 O’CLOCK
2.5m
BELOW
VI. FABRICATION & INSTALLATION
REQUIREMENTS
9. JOINTS
C. FLANGED JOINT
➢ FOR PERMANENT GASKET
THE GASKET IDENTIFICATION HANDLE POSITION WHEN INSTALLED IN THE
FLANGE SET SHALL FOLLOW
b. WHEN THE FLANGE JOINT IS MORE THAN 2.5m HIGH, LOCATE HANDLE AT
4 O’CLOCK OR 8 O’CLOCK POSITION
ABOVE
2.5m
4 O’CLOCK
8 O’CLOCK
VI. FABRICATION & INSTALLATION
REQUIREMENTS
9. JOINTS
C. FLANGED JOINT
➢ FOR PERMANENT GASKET
12 O’CLOCK
2.5m
6 O’CLOCK
VI. FABRICATION & INSTALLATION
REQUIREMENTS
10. CLEANING
INTERNAL CLEANING FOR PLANT PIPING SYSTEM
PRIOR TO INSTALLATION & PRESSURE TESTING AS A MINIMUM & PRIOR TO INSTALLATION
AND/OR ERECTION OF PIPE SPOOLS ON PIPE RACKS & PIPE SUPPORTS, THE FOLLOWING
SHALL BE CONDUCTED:
A. ALL PIPES SHALL BE INTERNALLY CLEANED BY AIR BLOWING WITH A MINIMUM
EXIT VELOCITY OF 15m/s. ALSO, LARGE DIAMETER PIPE IS RAG CLEANED
(BRUSHED, SWEPT) AS PRACTICAL TO DO SO.
B. ALL PREFABRICATED PIPE SPOOLS SHALL BE VISUALLY INSPECTED FOR CLEANLINESS
& SHALL HAVE FOREIGN MATERIALS REMOVED FROM THE INSIDE.
C. PIPING ENDS SHALL BE COVERED AFTER INSPECTION TO PREVENT UNAUTHORIZED
REMOVAL OF END COVERS PRIOR TO MAKING THE JOINT TO THE SUCCEEDING
SECTION OF PIPING.
APPLICABLE DOCUMENTS:
SAIC- L-2017 PIPING/EQUIPMENT INTERNAL CLEANING INSPECTION
SATR-A-2008 INTERNAL CLEANLINESS REPORT (PIPING SYSTEMS AND EQUIPMENT)
VII. PIPE SUPPORTS, ANCHORS, GUIDES
PIPE SUPPORTS, ANCHORS, PIPE GUIDES, AND SHOES SHALL BE INSTALLED IN PROPER
POSITION IN ACCORDANCE WITH RELATIVE DRAWINGS SUCH AS STANDARD SUPPORT
DRAWING, ISO DRAWING, AND SPOOL DRAWING.
DURING HYDRO TESTING, SPRING SUPPORT SHALL BE LOCKED. THE LOCK SHALL BE
RELEASED AFTER HYDRO TESTING.
DUMMY SUPPORT
BASE SCREWED TRUNNION
SUPPORT
±
VII. PIPE SUPPORTS, ANCHORS, GUIDES
EXAMPLE PHOTOS
±
IX. PRESSURE TESTING
A. PNEUMATIC TESTING
B. HYDROSTATIC TESTING
1. TESTING OF PIPING SYSTEM
2. TESTING OF VALVES
±
X. REINSTATEMENT
B. LAY-UP