APEGBC Legislated Dam Safety Reviews
APEGBC Legislated Dam Safety Reviews
APEGBC Legislated Dam Safety Reviews
V2.0
table of contents
Preface 1
Definitions 2
1.0 Introduction 4
Introduction to the Guidelines
1.1 Purpose of these Guidelines 5
1.2 Role of APEGBC 5
1.3 Introduction of Terms 6
1.4 Scope of the Guidelines 6
1.5 Applicability of the Guidelines 6
1.6 Acknowledgments 7
2.0 Project Organization and Responsibilities 8
2.1 Common Forms of Project Organization 8
2.2 Responsibilities 10
2.2.1 The Client/Dam Owner 10
2.2.2 The Qualified Professional Engineer 12
2.2.3 The regulatory authority 14
2.2.4 External Review of Dam Safety Review Reports 15
3.0 Guidelines for Professional Practice 17
3.1 General Principles 17
3.2 Dam Safety Review Phases 17
3.3 Background Information 22
3.4 Field Work 23
3.5. Dam Safety Analysis (Hazards, Failure Modes, 23
and Consequences Analyses)
3.5.1 General 23
3.5.2 Context and Hierarchy of Principles for
Dam Safety Reviews 24
3.5.3 Implementation Principles 25
3.5.4 Elements of Dam Safety Analysis: Hazards, 26
Failure Modes, Failure Effects and Consequences
3.5.5 Methods of Dam Safety Review 27
3.5.6 Consideration of Safety and Risk 29
3.6 Considerations of Changed Conditions 34
3.7 Dam Safety Review Report 34
3.8 Limitations and Qualifications in Dam Safety Reviews 35
3.9 Follow-Up to Dam Safety Review Reports 36
1
APEGBC’s Code of Ethics is at https://www.apeg.bc.ca/APEGBC/media/APEGBC/Governance/APEGBC-Code-of-Ethics.pdf. The Code of Ethics, along with
accompanying Guidelines and Commentary, are published in the current (1994) edition of APEGBC’s Guidelines for Professional Excellence.
Required content and format for report May need to gather more
structures for Owner’s use information including field
investigations
3b. Review information provided
Decision by Owner
5. Review report,
prioritize deficiencies and
make plans to address Fix or
Documentation by Qualified deficiencies Next steps? decommission
Professional Engineer
• Regulatory
Start / End of process • Legal Regulatory
• Financial acceptance of risk
• Risk
The above actions must be taken if a Dams subject to the Mines Act require that
hazardous condition at the dam could dam safety reviews for dams with significant,
possibly result in loss of life and/or other high, very high and extreme classifications
significant negative consequence occurring, be carried out in accordance with the CDA
or if workplace safety or the environment Dam Safety Guidelines.
is potentially jeopardized by the hazardous Before the dam safety review is initiated, the
condition at the dam. regulatory authority will:
2.2.3 The Regulatory Authority • Inform the client of the current
classification of the dam if the client is not
The regulatory authority is the department
aware of the classification;
within the Ministries that is tasked with
assigning the regulatory requirements of • Inform the client by when the dam safety
dam safety. For water reservoir dams this review must completed and dam safety
would be the department within the British review report submitted to the regulatory
Columbia government responsible for the authority; and
status and regulations of the Water Act (e.g., • Provide the client with guidelines, if they
British Columbia Dam Safety Regulation). exist, of the dam owner’s responsibilities
Details of the regulatory requirements for the safe management of dams, as
for water reservoir dams are presented in defined in the relevant legislation.
Appendix A. For mining dams this would
be the department within the British After the dam safety review, the regulatory
Columbia’s government responsible for authority will:
the status and regulations of the Mines Act. • Review the dam safety review report and
Details of the regulatory requirements for Dam Safety Review Assurance Statement;
mining dams are presented in Appendix B. • Accept the dam safety review report or,
In accordance with the British Columbia if the dam safety review report does not
Dam Safety Regulation, the regulatory comply with the requirements of the
authority assigns the classifications to relevant legislation reject the dam safety
dams. Currently only dams with high, very review report; and
high and extreme classifications require • If necessary, discuss the conclusions and
legislated dam safety reviews. Dams with recommendations of the dam safety review
low and significant classifications are not report and Dam Safety Review Assurance
required by the British Columbia Dam Safety Statement with the client and qualified
Regulation to undergo legislated dam safety professional engineer.
reviews. However, dam owners are required
In general, the following phases or steps • The qualified professional engineer must
should be carried out to complete a dam request from the client all available
safety review. The following information documentation and data for compilation
is intended to assist with defining the and review, such that all relevant
scope and requirements of the dam safety background information on the dam,
review. However, it is not exhaustive, and the river system (if relevant) and the
professional judgment is required when dam management system is considered
adding or subtracting specific steps. (Section 3.3). If there is uncertainty
whether any documentation is relevant,
Phase 1 (Review of available
it is the qualified professional engineer who
information and data):
must make that determination;
• I t is strongly recommended that a written • The qualified professional engineer must
agreement between the client and the understand the current dam classification
qualified professional engineer be put in as determined by the regulatory authority
place before any work is initiated. This and identify performance expectations
agreement should address, scope of work, based on current guidelines, regulations,
objectives, expectations, responsibilities, generally accepted practices, and
level of service, schedule and anticipated consideration of changed conditions
extent of the study area, as noted in (Section 3.6);
Section 2 of these guidelines;
Upstream Rip-Rap
Upstream
Filter
Upstream Cofferdam
Downstream Shell
Upstream Shell Core
Foundation
Grout Curtain
Immediate
Water Controlled Generation
Reservoir Downstream
Retention Discharge and Control
Area
For each element of the dam determine its
principal functions:
• Water retention or
• Flow control Water Retaining Subsystem
Categorize issues into “safety concern types” DAM SAFETY OVERSIGHT ACTIVITIES
Q/A Review
The dam safety review should state the extent The dam safety analysis process involves
of the understanding gained during the consideration of the various relevant
course of the dam safety review and the degree engineered and operational safety control
to which the scope of the dam safety review measures:
permitted the analysis of failure modes and • Prevention of loss of performance
the identification of safety measures. capacity or loss of functional capability;
3.5.3 Implementation Principles • Control of the deviations from designed
performance characteristics; and
The implementation of this principles
based approach as provided above • Mitigation of the effects of loss of control
comes from the principles for dam safety of the containment and conveyance
management that are commonly adopted functions.
in dam safety assessment in Canada, as Since dam safety management involves
described in the CDA Dam Safety Guidelines. implementing preventative, control and
ICOLD provides a complementary set of mitigation measures to various degrees to
principles that serve as a basis for the ensure the functional safety of the dam,
managerial aspects of the dam safety review. the dam safety analysis should reveal the
The dam safety review can be carried out in balance across and between these measures
terms of these principles, or some other and the extent to which functional
suitable set of principles. If another set of performance is assured.
suitable principles are to be followed, they
must be clearly referenced and the basis of There are a number of engineering
their suitability documented. principles that the qualified professional
engineer may use to guide the dam safety
Dams are designed to perform certain analysis as follows:
functions, and dam safety analysis involves 1. R
edundancy: More than one way to
two fundamentally different dimensions of achieve the desired performance;
the safe performance of a dam:
2. D
iversity: Different ways to achieve the
•T
he physical capacity of the dam to same function for a dam system;
withstand applied loads associated
with the hazards of the environment at 3. S
egregation: Function served from
the dam’s location (limit of the design different locations and directions;
envelope); and 4. D
efense in depth: Large margins of
•T
he functional capacity of the dam to capacity over demand (in all systems –
safely perform its functions (containment including redundant systems);
and conveyance). 5. F
ault tolerance (include human fault
tolerance): A single fault will not cause
The engineering principles involved in
loss of dam system function; and
dam safety analysis, and in setting the
engineering dimensions of the framework 6. F
ail to a safe condition: If a part of the
for a dam safety review, can be set in terms dam system does fail, it will render the
of the management concept of “Loss dam to a safe condition.
Avoidance”. In the context of dams,
Further detail on the considerations which The types of dam safety review can be
need to be addressed when carrying out broadly considered to cover a spectrum
a dam safety analysis so the intent of the ranging from an audit-type review to
above referenced concepts are met, is a comprehensive and detailed design
provided in Appendix G. and performance review. The qualified
professional engineer should recommend
3.5.4.1 External Hazards of Particular an approach to the dam safety review that
Importance in British Columbia will cause the result of the dam safety
The natural environment and climate review to be appropriate for its intended
of British Columbia, and its associated purpose. Secondary considerations will
natural hazards require that the dam safety involve factors such as being appropriate
review pays particular attention to possible for the dam safety management needs
meteorological; geological; environmental; and the existing dam safety management
and seismological events. These are arrangements. It may be necessary for the
generally considered in terms of floods, qualified professional engineer to recommend
landslides and seismic events, although a phased approach to the dam safety review.
such simple categorization masks the This would be appropriate in instances
complexity of these hazards, which can act where the actual end use of the dam safety
in combination. review is to inform a debate in the public
domain concerning a matter of significant
The dam safety review should take societal importance, but where the existing
appropriate account of the nature and dam safety management arrangements
complexity of these hazards and should may be insufficient to support a dam safety
explain how they have been addressed in review that would be suitable to inform a
the dam safety review. public debate.
Refer to Appendix H for information on In many cases an iterative approach may
how loadings from natural hazards can be appropriate beginning with an audit-
be included in a dam safety review both type review with recommendations for
individually or in combination. subsequent reviews of increasing detail
3.5.5 Methods of Dam Safety Review and rigour as considered necessary to meet
the end-use objective which includes the
Since there is no standardized and relevant regulatory requirements.
generally accepted method of dam safety
review, the qualified professional engineer The following is a summary of the most
should recommend a suitable level of important concepts for implementing an
service based on several factors including appropriate methodology when carrying
but not restricted to: out a dam safety review:
• Current classification of the dam. • All aspects of the dam safety review
should conform to the current APEGBC
• Age of the dam. guidelines on quality management of
• Use of the dam. engineering services.
Claim
(dam is reasonably safe)
Inference rule
Inference rule
Argument Structure
Sub-claim Evidence Evidence
Evidence Evidence
A conclusion that a dam is not reasonably In some cases, the minimum level of
safe would be explained in a similar way safety of a dam can be achieved by means
whereby the evidence could be shown to be of different configuration of containment
inadequate in terms of accepted norms and and conveyance, and different degrees
where logical inferences cannot be made of reliance on preventative, control and
to properly connect the evidence to the mitigation safety measures. The dam
conclusion. safety review should consider the different
configuration of safety arrangements that
3.5.6.4 Risk-Informed Dam-Safety
could be in place at a dam.
Decisions and Improvements
The results of the safety assessment may be
One purpose of the dam safety review
represented in various ways as illustrated
is to enable the dam owner to use the
in ICOLD Bulletin 154 and in the concepts
results of the dam safety review to initiate
of risk-informed identification of safety
development of designs and repairs to
engineering solutions. One method of
restore the level of safety of the dam as soon
illustrating the various extents to which
as it is practicable.
the fundamental principles of protection,
The following outlines the risk-informed control and mitigation are represented in
approach to selecting the most appropriate the safety arrangements for a dam is by
of the available options for improving the means of the graphical “bow-tie” safety
safety of a dam. The result of the dam safety management model (ICOLD Bulletin
review combined with the result of the dam 154). These “bow-tie” models of safety
safety improvements should then provide analysis and safety management clearly
key input to the next dam safety review. illustrate the relationship between accepted
generally considered to
be deficient
Generally conforms to minimum expectations
Typical range of dam safety
arrangements meeting functional
Tolerable only if risk reduction is impractical
requirements and safety or if its cost is grossly disproportionate to the
expectations improvements gained
(degree of)
the potential
for harm or
damage
Engineering Activities
Maintenance Activities
Operations Activities
5. Review report,
prioritize deficiencies and
make plans to address Fix or
deficiencies Next steps? decommission
• Regulatory
• Legal Regulatory
• Rinancial acceptance of risk
• Risk
** Additional requirements may need to be satisfied for facilities that are not checked under the responsibility
of the Ministry of Energy and Mines in the table above but are otherwise defined as “major dams” or “major
impoundments” as per the Health, Safety and Reclamation Code for Mines in British Columbia.
Low Note 1
Name
Address
With reference to the British Columbia Dam Safety Regulation, B.C. Reg. 44/2000 as amended.
UTM (Location):________________________________________________________________________________
Located at (Description):_________________________________________________________________________
Dam function:__________________________________________________________________________________
(the “Dam”)
Check one
Low
Significant
High
Very High
Extreme
The undersigned hereby gives assurance that he/she is a qualified professional engineer.
_ ___ 1. Collected and reviewed available and relevant background information, documentation and data.
_ ___ 2. Understood the current classification for the dam, including performance expectations.
_ ___ 4. Reviewed and assessed the dam safety management obligations and procedures.
_ ___ 5. Reviewed the condition of the dam, reservoir and relevant upstream and downstream portions of the river.
_ ___ 7. Reviewed available maintenance records, the Operations, Maintenance and Surveillance (OMS) Manual
and the Emergency Preparedness Plan.
_ ___ 9. After the above, reassess the consequence classification, including the identification of required dam
safety criteria.
_ ___ 10. Carried out a dam safety analysis based on the classification in 9. above.
_ ___ 12. Identified, characterized and determined the severity of deficiencies in the safe operation of the dam and
non-conformances in dam safety management system.
_ ___ 13. Recommended and prioritized actions to be taken in relation to deficiencies and non-conformances.
_ ___ 14. Prepared a dam safety review report for submittal to the regulatory authority by the owner and reviewed the
report with the owner.
_ ___ 15. The dam safety review report has been reviewed in meeting the intent of APEGBC Bylaw 14(b)(2).
Check one
Appropriate
Check one
Audit
Comprehensive
Check one
The dam is reasonably safe in that the dam safety review did not reveal any unsafe or unacceptable conditions in
relation to the design, construction, maintenance and operation of the dam as set out in the attached dam safety
review report.
The dam is reasonably safe but the dam safety review did reveal non-conformances with the British Columbia Dam
Safety Regulations as set out in section(s) ____ of the attached dam safety review report.
The dam is reasonably safe but the dam safety review did reveal deficiencies and non-conformances as set out in
section(s) ____ of the attached dam safety review report.
The dam is not safe in that the dam safety review did reveal deficiencies and/or non-conformances which require
urgent action as set out in section(s) ____ of the attached dam safety review report.
Name Date
Signature
Address
Name
Address
With reference to the permit conditions and the Health, Safety and Reclamation Code for Mines in British Columbia or the
British Columbia Dam Safety Regulation, B.C. Reg. 44/2000 as amended (refer to Table C-1 in Appendix C).
UTM (Location):________________________________________________________________________________
Located at (Description):_________________________________________________________________________
Dam function:__________________________________________________________________________________
(the “Dam”)
Check one
Low
Significant
High
Very High
Extreme
The undersigned hereby gives assurance that he/she is a qualified professional engineer.
____ 1. Collected and reviewed available and relevant background information, documentation and data.
____ 2. Reviewed the environmental objectives for the materials stored in the impoundment and related design
requirements.
____ 3. Understood the current classification for the dam, including performance expectations.
____ 5. Reviewed and assessed the dam safety management obligations and procedures.
____ 6. Inspected the condition of the dam, impoundment area and relevant areas upstream and downstream
of the facility.
____ 9. Reviewed available maintenance and operating records, the Operations, Maintenance and Surveillance
(OMS) Manual and the Emergency Preparedness Plan.
____ 10. Confirmed proper functioning of mine waste and water management systems and environmental
control systems.
____ 11. After the above, reassessed the consequence classification, including the identification of required dam
safety criteria.
____ 12. Carried out a dam safety analysis based on the classification in Item 11.
____ 13. Evaluated facility performance and conformance with design basis and operating criteria.
____ 14. Identified, characterized and determined the magnitude of deficiencies in the safe operation of the dam
and non-conformances in the dam safety management system.
____ 15. Recommended and prioritized actions to be taken in relation to deficiencies and non-conformances.
____ 16. Prepared a dam safety review report for submittal to the regulatory authority by the owner and reviewed the
report with the owner.
____ 17. The dam safety review report has been reviewed in meeting the intent of APEGBC Bylaw 14(b)(2).
Check one
Appropriate
Check one
Audit
Comprehensive
I hereby give my assurance that, based on the attached dam safety review report, at this point in time:
Check one
The dam is reasonably safe in that the dam safety review did not reveal any unsafe or unacceptable conditions
in relation to the design, construction, maintenance and operation of the dam as set out in the attached dam
safety review report.
The dam is reasonably safe but the dam safety review did reveal non-conformances with the regulatory
requirements as set out in section(s) ____ of the attached dam safety review report.
The dam is reasonably safe but the dam safety review did reveal deficiencies and non-conformances as set
out in section(s) ____ of the attached dam safety review report.
The dam is not safe in that the dam safety review did reveal deficiencies and/or non-conformances which
require urgent action as set out in section(s) ____ of the attached dam safety review report.
Name Date
Signature
Address
·L
arge and small scale topographic and • Additional considerations, changed
cadastral maps; conditions or increased knowledge may
include:
·M
aps that show existing and proposed
infrastructure, such as, transportation · Alteration to discharge capacity – due
routes, utilities, residential and to conversions of gates, settlement of
commercial subdivisions (information embankment or changes in available
from local approving authority); free board. Obstructions such as debris,
ice, landslides, debris flows or rockfall.
·A
irphotos of different years (historical Failure to operate due to power, control
to present) and scales; high-resolution or overtopping of gates. Inconsistencies
satellite imagery, and Light Detection and incompatibilities in procedures;
and Ranging (LiDAR) images that
can be also used for geological and · Foundation/Abutment problems –
geomorphological mapping and/or Undetected geological defects, such
topographical mapping; as, open fissures, erodible or soluble
materials, etc., have led to some notable
·T
errain maps, terrain stability maps, dam failures including Teton Dam (1976)
bedrock and surficial geology; where core fines were transported in the
·F
lood plain mapping and alluvial fan foundation. Excessive settlements can
mapping; occur due to hydrogeological changes in
·P
revious development, including the foundation or natural ground may
residential and non-residential, and be poorer than considered in design.
associated infrastructure; and Potential liquefaction should also be
considered; and
·S
eismic data including: seismic hazard
maps and reports; ground motion data,
seismic site class, and modal magnitude
values of the design earthquake.
2
ICOLD, B154 (2012)
The complexity of the model and the extent From an analysis perspective, dam breach
of the modelling endeavour will vary from consequences can be broadly considered to
one situation to the next depending on fit into two main categories:
the extent of the dam breach inundation, • Direct consequences attributable to
and the demographics and land use of contact with the flood waters; and
the area affected by the flood. The system • Indirect consequences that arise as a
boundary may be limited to the extent of result of the direct consequences.
the inundation or it might be larger if wider
environmental, social and economic issues Typically, direct consequences, which are
are considered. the focus of this chapter, are divided into
three categories:
As is the case with analysis of functional
failure, the level of the modelling effort will • Life safety;
also depend on the degree of resolution • Economic and financial; and
required by the dam safety analysis as • Environmental impact.
determined at the outset of the dam
safety review. In keeping with the iterative The following boundaries apply to this
nature of the dam safety analysis process, categorization (model):
it is generally appropriate to begin with • Public safety including life safety
a relatively coarse representation of the considerations that apply to loss of life,
downstream area, moving to more refined physical injuries and emotional trauma
modelling techniques as the need arises. caused by direct contact with flood
waters.
Typically, functional failure consequences
of interest will include: • Economic losses pertain to all third party
economic impacts whereas financial
• Threats to public safety;
losses pertain solely to the dam owner.
• Environmental degradation;
• Environmental degradation refers to
• I nfrastructure and property damage and environmental losses that occur during
losses; the flood event, with collateral losses of
•S
ocio-economic impacts, including habitat that impact migratory species
political and public perception issues; and being considered as indirect losses.
• Owner’s reputation and financial integrity.
Store
Dam “A”
Pass
Gate Demand/Response
Discharge Structure
Hydrology Reservoir shaping
FEEDBACK
Precipitation modelled as
a ‘random’ event in time
R(t)
Reservoir SPILLWAY MODEL
Inflows
Outflow control
Time (t)
Runoff Volume
3
EBA 2010/11
4
CDA07, Hydrotechnical Considerations
5
ICOLD B124 (2000)