Pressure Technical Manual: For PVC and Polyethylene Pipe Systems
Pressure Technical Manual: For PVC and Polyethylene Pipe Systems
Pressure Technical Manual: For PVC and Polyethylene Pipe Systems
3. PVC
4. Polyethylene
5. Design
6. Installation
7. Jointing Systems
11. Disclaimer
12. Calculator
1. PLASTIC PIPELINES
- GENERAL RETURN TO
CONTENTS
• PVC
• Medium Density PE
• Strength
• Elevated Temperatures
• Toughness
• Hydraulic Properties
• Fire Rating
• Permeability
STRENGTH
The “strength” of a pipe may be considered as its
ability to withstand (hoop) stress in the pipe mater-
ial under internal pressure over a prolonged period
of time. The design stress for local authorities is
chosen to ensure a life in excess of 50 years.
The strength of plastics pipes is known to be
time/temperature dependent. This characteristic is
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 1
General
THE STRESS For specification purposes the design points adopt-
ed for PVC-u pipes is the 50 year line with an ulti-
REGRESSION LINE FOR mate stress of 23.6 MPa (26.0 MPa for pipes
175mm and above) giving a safety factor of 2.1. It
HOOP STRESS can be seen that the safety factor at 100 years is
The traditional method for portraying the tensile only slightly lower. For PVC-m the ultimate stress is
strength of plastics pipe is through a graph of log 17.5 MPa.
stress vs log time to failure. For polyethylene pipes the method of classifying the
This is known as the stress regression line. This material is by reference to its Minimum Required
chart is a plot of circumferential stress in the pipe Strength (MRS). The MRS is determined by using
wall against time to failure. the value of the predicted hoop stress (97.5% lower
Practical tests are done subjecting pipe samples to confidence limit) at the 50 year point.
different hoop stresses and the results of the times The hydrostatic design stress (HDS) is obtained by
to failure are plotted over a range of times up to the application of a factor, not less than 1.25, to the
10,000 hours. A linear regression line (log log) is MRS value.
established and extrapolated to the longer term. The wall thickness of Marley MDPE manufactured
An appropriate factor of safety is established on the to AS/NZ4130 are established by use of the Barlow
long term ultimate stress to give a working stress formula as follows:
for design purposes. PD
The confidence of extrapolated data such as this T= and S = MRS/C
2S + P
depends on a number of factors:
1. The linearity of the data
T = minimum wall thickness (mm)
2. The scatter of the data (data fit)
P = working pressure (MPa)
3. Data available concerning closely allied materials
D = minimum mean OD (mm)
With MDPE which exhibits a knee in the regression
S = design hoop stress (MPa)
line testing is also done at elevated to determine the
MRS = Minimum Required Strength
position of the knee. This stress regression which is
C = Safety Factor Typically 1.25 for water
used to define the knee is used only as a design
basis and does not predict the system life which has
been shown to be significantly greater than the con-
servative predictions.
MPa
20
15
10
20°C
Hoop Stress
5
4
80°C
3
1
0.10 1.0 10 102 103 104 105 106 hours
1 month 1 year 10 years 50years
PE 100
Time to Failure
PE 80B
PE 80C
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 2
General
TYPICAL STRESS REGRESSION CURVES FOR PVC
WEATHERABILITY AND Marley PVC pipes are stabilised with Ti02 to pro-
vide suitable protection for up to 50 years expo-
TEMPERATURE CHANGES sure.
UV degradation will result in micro crazing of the
Black PE material has generally excellent prolonged surface which results in a reduction of impact
weatherability properties and can readily withstand strength. Tests have shown however that the
wide variations of weather without degradation. hoop stress of the pipe is not compromised when
Black PE pipes contain carbon black pigments such degradation occurs. Marley recommend
which act both as a pigment and as an ultra violet that pipes that are to be installed in situations
radiation stabiliser and these pipes require no where they are directly exposed to UV should be
additional protection for external storage, or pro- protected by painting with a light coloured acrylic
longed use in natural conditions. paint or covered.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 3
General
ELEVATED TEMPERATURE PRESSURE DE-RATING
uPVC Pipes
Temp PN6 PN9 PN12 PN15
°C
20 0.60 0.90 1.20 1.50
30 0.48 0.72 0.96 1.20
40 0.36 0.54 0.72 0.90
50 0.24 0.36 0.48 0.60
60 0.12 0.18 0.24 0.30
PE80B Material
Maximum Working Pressure (Metres Head)
Temp PN4 PN6.3 PN8 PN10 PN12.5 PN16
°C
20 40 63 80 100 125 160
25 39 61 78 97 122 156
30 37 59 75 94 112 156
35 35 55 70 87 109 140
40 32 51 65 81 102 130
45 30 47 60 75 94 120
50 26 41 52 65 81 104
PE100 Material
Maximum Working Pressure (Metres Head)
Temp PN4 PN6.3 PN8 PN10 PN12.5 PN16
ºC
20 40 63 80 100 125 160
25 37 59 75 94 112 156
30 35 55 70 87 109 140
35 32 51 74 80 100 128
40 29 46 58 73 91 117
45 26 42 53 66 83 106
50 24 37 47 59 74 94
The above tables are based on the relationship: the operating temperature may be taken as the
(70 - T) mean of the internal and external pipe surface
PT = P20 temperatures.
50
It should be noted that the pressure condition
where: where flow is stopped for prolonged periods should
PT = maximum working pressure at T°C also be checked. In this event, water temperature
P20 = maximum working pressure at 20°C and outside temperature may equalise.
T = material temperature °C
2. With respect to time:
This is equivalent to a reduction in working pressure The average temperature may be considered to
of 2% per 1°C rise in temperature above 20°C. be the weighted average of temperatures in
Pressure ratings for pipes of other classes may be accordance with the percentage of time spent at
computed from these relationships. each temperature under operational pressures:
The material temperature in question here is the
Tm = T1L1 + T2L2 + ... + TnLn
average temperature of the pipe wall under
operational conditions. where Ln = proportion of life spent at temperature Tn
Temperature is averaged in two ways:
1. Across the wall of the pipe: This approximation is reasonable provided the
Where a temperature differential exists between temperature variations from the mean do not
the fluid in the pipe and the external environment, exceed ±10°C which is generally the case for pipes
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 4
General
buried below 300 mm. tion of thermal movement is during installation in
For most underground water supply systems, the high ambient temperatures.
overall mean temperature from meteorological Under these conditions the black PE pipe will be at
records is appropriate for class selection purposes, its maximum surface temperature and when placed
since this represents the mean of the annual and into a shaded trench and backfilled, will undergo
diurnal sinusoidal temperature patterns. the maximum temperature change and hence ther-
For systems subjected to lager variations, the mal movement.
temperature for rating purposes should be taken as in these cases the effects of thermal movement
the maximum less 10°C. However the peak can be minimised by some minor snaking of the
temperature should not exceed 60°C. pipe in the trench for small diameter sizes (up to
110mm).
Example
For large diameter pipe the final connection
A reticulation system is to be installed in a town
shouldbe left until the pipe temperature has sta-
with a mean ground temperature at pipe depth
bilised to that of the surrounding soil.
20°C. The December-February average is 25°C.
Above ground pipes require no expansion/contrac-
Although diurnal variations occur with air temperatures
tion considerations for free ended pipe or where
up to 40°C during heatwave period, water temperatures
lateral movement is of no concern on site.
and ground temperatures at pipe depth do not
Alternatively, pipes may be anchored at intervals to
exceed the mean of 27°C. A 50 year life is required
allow lateral movement to be spread evenly along
at basic factor of safety 2.145.
the length of the pipeline.
Weighted average temperature: Where rubber ring jointed (Z joint) pipe is used for
Tm = 25(3/12) + 20.5(6/12) + 15(3/12) buried urban water supply, the thermal movement
= 6.25 + 10.25 + 3.75 = 20.25°C caused by seasonal changes in temperature can
Therefore use rating for 20°C. This is the same be absorbed by the rubber ring rocking in the
result as taking the mean. recess. The joint is not able to absorb the gross
movement caused on occasions by the severe
EXPANSION AND temperature drop at the time of laying.
A pipeline should be allowed to expand and con-
CONTRACTION tract freely.
Wherever possible, expansion and contraction
All materials expand and contract with changes in should be taken up by changes in direction.
temperature and uPVC has a relatively high rate of Careful positioning of fixed points will enable the
change. direction of expansion and contraction to be con-
The coefficient of thermal expansion for PVC is trolled.
7 x 10-5/°C. Expansion bellows and O-ring slip joints should be
A handy rule is 7 mm change in length for every 10 used only as a last resort; the pipes must then be
metres for every 10°C change in temperature. suitably protected against separation.
The coefficient of thermal expansion for MDPE is Care must be taken in the positioning of loose
2.0 x 10-4/°C. brackets, as these can sometimes create condi-
A handy rule is 14mm change in length for every 10 tions in which there may be a risk of shearing.
metres for every 10°C change in temperature. Values and heavy components must be indepen-
Therefore this characteristic must be considered dently supported so that no stresses are imposed
carefully in the design of the pipeline and during on the pipeline.
installation. In buried pipelines the main considera-
PVC
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 5
General
TOUGHNESS COMPARATIVE ABRASION RATES OF
PIPE MATERIALS
General
In practice it is recognised that plastics is a tough,
resilient material capable of withstanding the normal
rigours of pipelaying and service conditions. The
many years of successful installation and service of
PVC and MDPE pipe in the water industry confirms
this confidence.
Abrasion
Plastics pipes have high resistance to abra-
sion by suspended particles being carried in the
water, however the external surface can be
scratched and gouged by sharp objects. Careful
handling is therefore required but provided the
depth of any surface notch is no greater than 10%
of the wall thickness, there is no significant loss in
the stress rupture performance of the pipe.
The properties of plastics pipes including flexibil-
ity, ease of handling and robustness have led to
their widespread use for abrasive applications
such as mine tailings and slurry transportation.
Abrasion occurs as a result of friction between the
pipe wall and the transported particles.
The actual amount and rate of abrasion of the pipe
wall is determined by a combination of:
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 6
General
FIRE RATING the chemical. Examples of this type of attack on
uPVC are aqua regia at 200C and wet chlorine
PE pipe systems will support combustion and as gas.
such are not suitable for use in fire rated zones in
buildings without protection. FACTORS AFFECTING
In multi-storey buildings PE systems penetrating
floor cavities must be enclosed in fire rated service CHEMICAL RESISTANCE
ducts.
PVC pipe systems may support combustion but are A number of factors can affect the rate and type of
self-extinguishing when the source of ignition is chemical attack that may occur. These are:
removed.
Concentration: In general, the rate of attack
CHEMICAL RESISTANCE increases with concentration, but in many cases
there are threshold levels below which no
AND STABILITY significant chemical effect will be noted.
Corrosion Resistance Temperature: As with all processes, rate of attack
For all practical purposes, plastics pipes are chem- increases as temperature rises. Again, threshold
ically inert within their normal temperature range of temperatures may exist.
use. They do not rot, rust, pit, corrode or lose wall Period of Contact: In many cases rates of attack
thickness through chemical or electrical reaction are slow and of significance only with sustained
with the surrounding soil. They do not normally contact.
support the growth of, nor is it affected by algae,
bacteria or fungi. Stress: Some plastics under stress can undergo
higher rates of attack. In general uPVC is
Chemical Effects considered relatively insensitive to “stress
Plastics pipes have a good resistance to a wide corrosion”.
range of chemicals. In the water supply context,
the main concern is the effect of certain chemicals
Considerations for Plastics Pipe
existing in contaminated ground, some of which For normal water supply work, plastics pipes are
can have harmful effect upon the pipe material or totally unaffected by soil and water chemicals. The
may cause taste problems in extreme cases due to question of chemical resistance is likely to arise
permeation through the material wall. In broad only if they are used in unusual environments or if
terms the most common harmful chemicals are oxi- they are used to convey chemical substances.
disers, cracking agents and certain solvents as Table 2 gives guidance in this context.
shown in the Chemical Resistance Table. For applications characterised as food conveyance
or storage, health regulations should be observed.
Where pipelines are to be laid in environments Specific advice should be obtained on the use of
where significant concentrations of such chemicals plastics pipes.
may prevail (e.g. garage forecourts, within certain
processing works, etc) the use of PVC or PERMEABILITY
MDPE is NOT recommended unless suitability
sleeved, although it is noted leakage of this nature Plastics pipes can be shown to be permeable to
is not acceptable under the Environment Act. certain gases and liquids under extreme condi-
tions, the rate of permeation being mainly depen-
For the effects of specific chemicals on plastics pipes dent upon the thickness of the pipe, the concentra-
see chemical resistance table. tion, time and temperature.
Chemical Attack Permeation of natural gas into the water supply
Chemicals that attack plastics do so at differing pipe causing taste problems should be of no con-
rates and in differing ways. There are two general cern provided reasonable separation distances are
types of chemical attack on plastic: maintained.
1. Swelling of the plastic occurs but the plastic
returns to its original condition if the chemical
is removed. However, if the plastic has a
compounding ingredient that is soluble in the
chemical, the plastic may be changed because
of the removal of this ingredient and the chemical
itself will be contaminated.
2. The base resin or polymer molecules are
changed by crosslinking, oxidation, substitution
reactions or chain scission. In these situations
the plastic cannot be restored by the removal of
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 7
General
Chemicals Potentially Harmful to Plastics Pipes
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 8
2. PVC & PE
- Consideration before Design
RETURN TO
• PVC
CONTENTS
• PE
PVC
Mainlaying Design and Installation Considerations
Design Considerations Laying Considerations
1. PVC pipes are usually joined using the push- 1. Gradual changes of direction of PVC pipelines
fit elastomeric jointing ring or solvent cement can be accommodated by pipe deflection but
techniques. The push-fit technique has advan- every effort should be made to keep the pipe as
tages as it is less dependent on weather condi- central as possible within the trench to enable
tions and provides allowances for pipe move- correct side-fill compaction.
ment. The solvent cement technique is usually
restricted to smaller diameter pipes. 2. PVC should generally be installed in straight runs
in order to reduce the stresses induced when the
2. The sub surface material to be excavated should pipe is bent. It is possible in some circumstances
be assessed for its suitability as backfill material, however to bend the pipe in a radius no less than
i.e. free from large sharp stones, heavy clay, etc. 200 times the pipe diameter. Elastomeric ring
If the material is unsuitable for bedding and joints will provide for some deflection of the pipe
surround to the pipe then imported material in the vicinity of 3° but it is unacceptable for the
should be utilised and the surplus spoil removed trailing joint to have an angular deflection greater
from site. than 1°C.
3. The properties of PVC make it suitable for areas 2. During the pipelaying of continuous fusion joint
subject to minor ground movements due to systems, allowance should be made for the
seismic forces, mining subsidence, com- movement likely to occur due to the thermal
paction of filled sites or the disturbance caused expansion/contraction of the material. This effect
by the activities of other utilities in the vicinity. In is most pronounced at the end connections to
larger sizes greater than DN 160 special atten- fixed positions and at branch connections.
tion to the flexibility of the joints is necessary.
3. In cold conditions allowance should be made for
4. Where PVC is to be used in environments with expansion with push-fit joints to accommodate
temperatures greater than 20°C for prolonged subsequent thermal expansion. Once a pipeline
periods, the allowable operating pressure should is installed the temperature variation is usually
be reduced in accordance our recommendations, very small and is not likely to induce any signif-
to maintain the expected life of the pipe. icant stress or movement in the pipe system.
5. Corrosive ground (e.g. ground with low pH or 4. Whenever possible, a minimum distance of
high sulphate characteristics) has no known 300mm from obstructions should be maintained.
effect on PVC but all metal fittings, ancillary This distance is often possible when laying par-
equipment, bolts etc should be carefully protected allel to other services but not always practicable
against corrosion in the normal way. when crossing other services. A separation dis-
tance of 75mm may be allowed for a square
6. Contaminated ground, however, must be considered crossing but suitable protection should be pro-
carefully. PVC is resistant to most chemicals, but vided from possible joint loading, interference,
is vulnerable to petroleum products and certain damage or contamination.
solvents. Where concentrations of such
contaminants exist, PVC should NOT be used 5. PVC is not a conductor of electricity and no
unless suitably protected. Where any doubt attempt should be made to use PVC pipework as
exists, soil sampling should be undertaken and a means of earthing electrical equipment.
specialist advice sought. Similarly, because of its high electrical resistivity,
caution is required in the use of the material
7. Where the natural ground water table is high, or where the avoidance of static electricity may be
the construction trench is liable to flooding, special an important consideration.
consideration should be given to the possibility of 6. PVC is a poor conductor of heat but can burn
flotation of the pipe when empty. This particularly when subjected to a naked flame. Upon removal
applies to the larger diameters where special of the source of ignition burning ceases.
anchoring or weighting may be necessary prior
to backfilling. 7. The installation of flanged fittings such as sluice
valves, hydrant tees, end caps etc. usually
8. Direct connection of PVC to sources of high fre- requires the use of stub flanges complete with
quency should be avoided and a flexible joint backing rings and gaskets. Care should be taken
should be used to isolated such vibration. when tightening these flanges to provide even
and balanced torque. Provision should be made
where heavy fittings are installed for concrete
support both for the weight and to resist the turn-
ing moments associated with valves and
hydrants.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 1
PVC
8. Where there are large diameter fabricated fit-
tings installed in the main, similar concrete sup-
port may be necessary to counteract the imbal-
ance of forces under working conditions.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 2
Polyethylene
Mainlaying Design and Installation Considerations
Design Considerations Laying Considerations
1. PE pipes are normally joined using fusion 1. Gradual changes in direction of PE pipelines can
techniques. Butt fusion jointing is usually carried be accommodated by pipe deflection but every
out above ground and after cooling, long lengths effort should be made to keep the pipe as central
of pipe are snaked into the trench. This procedure as possible within the trench to enable correct
requires consideration of appropriate storage side-fill compaction. Similar care should be
areas, jointing canopies and working space at taken when any distortion of coiled pipe has
the trench side away from the spoil areas. occurred.
Attention must be given to the additional
inconvenience caused to both pedestrian and 2. During the pipelaying of continuous fusion joint
vehicular traffic. Extra signs and protection systems, allowance should be made for the
barriers will be required. movement likely to occur due to the thermal
expansion/contraction of the material. This effect
2. The sub surface material to be excavated should is most pronounced at the end connections to
be assessed for its suitability as backfill material, fixed positions and at branch connections.
i.e. free from large sharp stones, heavy clay, etc.
If the material is unsuitable for bedding and 3. For summertime installations, with two fixed
surround to the pipe then imported material connection points, a slightly longer length of
should be utilised and the surplus spoil removed polyethylene may be required to compensate for
from site. contraction of the pipe in the cooler trench bottom.
The snaking of the pipe in the trench which
3. The properties of MDPE make such pipelines naturally occurs with pipe sized 90mm and
particularly suitable for areas subject to ground below, is normally sufficient to compensate for
movement due to seismic forces, mining this anticipated thermal contraction.
subsidence, compaction of filled sites or the
disturbance caused by the activities of other 4. During a winter installation, the exact length of
utilities in the vicinity. pipe should be used. Pipe which is too short or
not aligned must not be drawn up by the bolts
4. Where PE is to be used in environments with of a flanged connection because of potential
temperatures greater than 20°C for prolonged overstressing of the stub end, flanged adapter
periods, the allowable operating pressure should and ultimately the valve or fixture to which it is
be reduced in accordance our recommendations, connected.
to maintain the expected life of the pipe.
5. It is advisable to defer the final tie-in connections
5. Corrosive ground (e.g. ground with low pH or until thermal stabilisation of the pipeline has
high sulphate characteristics) has no known occurred. Once a pipeline is installed and in service,
effect upon PE but all metal fittings, ancillary the temperature variation is usually small, occurring
equipment, bolts etc should be carefully protected over an extended period of time and is not likely
against corrosion in the normal way. to induce any significant stress or movement in
the pipe system.
6. Contaminated ground, however, must be considered
carefully. PE is resistant to most chemicals, but 6. Whenever possible, a minimum distance of
is vulnerable to petroleum products and certain 300mm from obstructions and other services
solvents. Where concentrations of such should be maintained. This distance is often
contaminants exist, PE should NOT be used possible when laying parallel to other services
unless suitably protected. Where any doubt but not always practicable when crossing other
exists, soil sampling should be undertaken and services. A separation distance of 75mm may be
specialist advice sought. allowed for a square crossing but suitable
protection should be provided from possible joint
7. Where the natural ground water table is high, or loading, interference, damage or contamination.
the construction trench is liable to flooding, special
consideration should be given to the possibility of 7. Polyethylene is not a conductor of electricity and
flotation of the pipe. This particularly applies to no attempt should be made to use PE pipework
the larger diameters where special anchoring or as a means of earthing electrical equipment.
weighting may be necessary prior to the backfill Similarly, because of its high electrical resistivity,
being installed. caution is required in the use of the material
where the avoidance of static electricity may be
8. Direct connection of MDPE PE80 and PE100 to an important consideration.
sources of high frequency such as pump outlet
flanges should be avoided and a flexible joint
should be used to isolate such vibration.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 3
Polyethylene
... Laying Considerations
8. The bending of polyethylene is permissible and 15. The degree to which the trench is backfilled
the properties of fusion jointed systems enable prior to testing will be influenced by:
changes of direction without recourse to the
• the prevailing site and/or traffic conditions;
provision of special bends or anchor blocks.
• the potential risk of flotation;
However, the pipe should not normally be cold
• the unbalanced forces due to configuration and
bent to a radius smaller than 20 times the
imposed test pressure.
diameter. For push-fit or mechanical non
end-load resistant jointing systems, anchor
Where practical it is advisable to consider leaving
blocks to withstand the resultant thrusts must
at least the mechanical joints exposed throughout
be provided in the traditional manner.
the test.
9. Although the hot bending of PE pipe is possible
16. As part of the preparation for the hydrostatic
under carefully controlled conditions, under no
pressure test, all anchorages and struts should
circumstances should hot bending be attempted
be checked to ensure they are adequate to
on site.
withstand the excess pressure and it is advisable
to retighten all bolted flanged joints and to
10. Polyethylene is a poor conductor of heat but is
check that all intermediate control valves are
flammable and should not be exposed to naked
open.
flame.
17. Complete and accurate records should be
11. The installation of flanged fittings such as sluice
taken of the installation. It is useful for records
valves, hydrant tees, end caps etc usually
to be taken before the pipes are buried whilst
requires the use of polyethylene stub flanges
memories are fresh and key elements are still
complete with backing rings and gaskets. Care
visible. Photographic records of important or
should be taken when tightening these flanges
complex features should be considered.
to provide even and balanced torque. Provision
should be made where heavy fittings are
18. The marker tape should be laid along the line of
installed for concrete support both for the
the main and connected at each end to either a
weight and to resist the turning moments
sluice valve or hydrant. The recommended
associated with valves and hydrants.
position of the tape is 350mm below the surface
directly above the crown of the pipe.
12. Where there are large diameter fabricated
fittings installed in the main, similar concrete
support may be necessary to counteract the
inbalance of forces under working conditions.
Consideration should be given to introducing a
flanged connection on the branch outlet of the
tee so that the branch main joint can be made
in a separate operation.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 4
3. PVC
RETURN TO
CONTENTS
• Material Properties
• Pipe Dimensions
• Flow Charts
-Series 1 (PN 6, PN 9, PN 12, PN 15, PN 18)
-Series 2 (PN 4.5 to 20)
• Fitting Dimensions
Material Properties
MATERIAL PROPERTIES . . .. . .. . . . .. . .
PROPERTIES OF uPVC
PHYSICAL PROPERTIES
Molecular weight 14,000
Relative density 1.42 cf: 1.48
Water absorption 0.12% 23˚C, 24 hours
Hardness 80 Shore D Durometer, Brinell 15, Rockwell R 114
Impact strength: 20˚C 20kJ/m2 Charpy 250 µm notch tip radius
Impact strength: 0˚C 8kJ/m2 Charpy 250 µm notch tip radius
Coefficient of friction 0.4 uPVC to uPVC cf: PE 0.25
MECHANICAL PROPERTIES
Ultimate tensile strength 52 MPa AS 1175 Tensometer at constant strain rate
Elongation at break 50 - 80% AS 1175 Tensometer at constant strain rate
Short term creep rupture 44 MPa Constant load 1 hour value cf: PE 10 - 16
Long term creep rupture 28 MPa Constant load extrapolated 50 year value
Elastic tensile modulus 3.0 - 3.3 GPa 1% strain at 100 seconds cf: PE 0.6 - 0.8
Elastic flexural modulus 2.7 - 3.0 GPa 1% strain at 100 seconds cf: PE 0.6 - 0.8
Long term creep modulus 0.9 - 1.2 GPa Constant load extrapolated 50 year secant value
Shear modulus 1.0 GPa 1% strain at 100 seconds
Bulk modulus 4.7 GPa 1% strain at 100 seconds
Poissons ratio 0.4 Increases marginally with time under load
ELECTRICAL PROPERTIES
Dielectric strength (breakdown) 14 - 20 kV/mm Short term, 3mm specimen
Volume resistivity 2 x 1014 Ωm AS 1255.1
Surface resistivity 1013 - 1014 Ω AS 1255.1
Dielectric constant (permittivity) 3.9 (3.3) 50 Hz (106Hz) AS 1255.4
Dissipation factor (power factor) 0.01 (0.02) 50 Hz (106Hz) AS 1255.4
THERMAL PROPERTIES
Softening point 80 - 840C Vicat method 120B BS 2782
Max. continuous service temp. 600C
Coefficient of thermal expansion 7 x 10-5/K 7mm per 10m per 100C cf: PE 18-20 x 10-5
Thermal conductivity 0.16 W/[m.K] 0-500C
Specific heat 1,000 J/[kg.K] 0-500C
Thermal diffusivity 1.1 x 10-7 m2/s 0-500C
FIRE PERFORMANCE
Flammability 45% ASTM D2683 Fennimore Martin test, cf: PE 17.5
Ignitability test 10 - 12 (/20) cf: 9 - 10 when tested as pipe )
Smoke produced test 6 - 8 (/10) cf: 4 - 6 when tested as pipe ) AS 1530
Heat evolved test 0 ) Early Fire
Spread of flame index 0 Will not support combustion ) Hazard Test
General properties of uPVC compounds used in pipe manufacture are given. Properties of thermoplastics
are subject to significant changes with temperature, and the applicable range is noted where appropriate.
Mechanical properties are subject to duration of stress application, and are more properly defined by creep
functions. More detailed data pertinent to pipe applications are given in the design section of this manual.
For data outside of the range of conditions listed, users are advised to contact our Technical Department.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 1
UPVC PRESSURE PIPE
PN12 PN18
Nominal Mean OD T Min T Max Mean Mass T Min T Max Mean Mass
Size mm mm mm Bore kg/m mm mm Bore kg/m
mm mm
100 121.9 6.3 7.1 108.5 3.467 9.2 10.3 9.8 4.912
Pipe Dimensions
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. .
150 177.4 9.2 10.3 157.9 7.341 13.4 14.9 14.2 10.374
200 232.3 10.8 12.1 209.4 11.358 15.9 17.7 16.8 16.261
2
H
HYDRAULIC GRADIENT L (meter/100 meters)
1.6
1.2
1.0
0.9 0
0.8
0.7 0
0.6 0
0.5
0.4
0.3
0.2
0.1
0.1
0.1
0.0
0.0 0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
00
00
0
00
0
0
00
00
00
00
00
60
20
00
9
80
70
60
50
40
30
20
16
12
10
09
08
07
06
700
0
2000
180 650
0
160
0
140 500
2 0 0
1
0 450
1000
90
400
800
700
375
350
600
500 300
300
400
250
300 250
250
200
200 200
180 180
160
140 160
120 150
140
100
90
80 120
70
60 100
100
50
90
40
80
30
70
25
20 60
18
16
50
14
12 45
10
9 40
8
7 35
6
30
5
4
25
3
2.5 20
2 18
1.8
1.6 16
1.4
1.2 14
1
0.9 12
0.8
0.7
10
6.0
5.0
4.5
4.0
3.5
3.0
2.5
2.0
1.8
1.6
1.4
1.2
1.0
0.9
0.8
0.7
0.6
0.50
0.45
0.40
0.35
0.30
0.25
0.20
VELOCITY V, m/s
Hydraulic design of pipes k = 0.003mm based on Colebrook-White formula for pipes flowing full with water at 20˚c
700
650
500
450
400
350
300
250
200
180
160
140
120
100
90
80
70
60
50
45
40
35
30
25
20
18
16
14
12
10
700
650
575
500
450 450
400
375
350
300
300
250
250
225
200
200
180
160
150
140
125
120
100
100
90
80 80
70
66
60
60
50
40 45
40
32
35
25 30
25
20
18
16
14
12
10
700
650
500
450
400
350
300
250
200
180
160
140
120
100
90
80
70
60
50
45
40
35
30
25
20
18
16
14
12
10
700
650
500
450
400
350
300
250
200
180
160
140
120
100
90
80
70
60
50
45
40
35
30
25
20
18
16
14
12
10
700
650
500
450
400
350
300
250
200
180
160
140
120
100
90
80
70
60
50
45
40
35
30
25
20
18
16
14
12
10
Fitting Dimensions
DESCRIPTION CODE NOMINAL A O.D. DESCRIPTION CODE NOMINAL A O.D.
SIZE SIZE
PLAIN 90 ° ELBOW REDUCING VALVE
801-15-90 15 49 28 ADAPTOR 817-20-15 20x15 45 31
801-20-90 20 59 32 817-25-20 25x20 49 37
801-25-90 25 65 41 817-32-15 32x15 54 42
801-32-90 32 94 51 817-32-25 32x25 58 47
801-40-90 40 112 57 817-40-32 40x32 63 57
801-50-90 50 101 69 817-50-32 50x32 69 60
801-65-90 65 135 84
801-80-90 80 145 102
801-100-90 100 202 135
DESCRIPTION CODE NOMINAL A B O.D.@
G1361 801-125-90 125 234 163
SIZE socket
801-150-90 150 271 178
M & F RRJ
G106 801-175-90 175 FORMED BEND Z803-50D-90 50
801-200-90 200 357 248 90° Z803-65D-90 65 440 400 75
Not on list 801-225-90 225 Z803-80D-90 80 523 476 89
Not on list 801-300-90 300 Z803-100D-90 100 475
Z803-125D-90 125
Z803-150D-90 150
Z803-175D-90 175 989 985 246
PLAIN 45 ° ELBOW
801-15-45 15 57 25 Z803-200D-90 200 1013 976 282
801-20-45 20 52 33 Z803-225C-90 225
801-25-45 25 49 41 Z803-300C-90 300
801-32-45 32 78 50
801-40-45 40 77 51 45° 803-50D-45 50
801-50-45 50 83 69 803-65D-45 65 565 281 102
801-65-45 65 117 88 803-80D-45 80
801-80-45 80 145 104 803-100D-45 100
801-100-45 100 165 135 803-125D-45 125
G0082 801-125-45 125 803-150D-45 150
G0102 801-150-45 150 231 179 803-175D-45 175
801-175-45 175 287 230 803-200D-45 200
801-200-45 200 300 260 803-225D-45 225
Not on list 801-225-45 225 803-300D-45 300
Not on list 801-300-45 300
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 10
Fitting Dimensions
DESCRIPTION CODE NOMINAL A B O.D. DESCRIPTION CODE NOMINAL A B O.D.
SIZE SIZE
PLAIN 90° FAUCET REDUCING
REDUCING TEE 805-20-15 20x15 86 43 31 ELBOW 90° 808-25-15-90 25X15 66 47 39
805-25-15 25x15 60 35 41 808-25-20-90 25X20 66 46 39
805-25-20 25x20 93 47 39
805-32-20 32x20 96 46 53
805-32-25 32x25 96 46 53
805-40-15 40x15 118 50 58
805-40-25 40x25 102 49 60
805-40-32 40x32 111 57 58
805-50-15 50x15 98 52 71
805-50-20 50x20 114 55 75
DESCRIPTION CODE NOMINAL A O.D.
805-50-25 50x25 111 60 71
SIZE
805-50-32 50x32 119 64 71
EXPANSION
805-50-40 50x40 125 65 71 COUPLER
809-15 15 126 47
805-80-25 80x25 134 68 103 809-20 20 138 153
805-80-32 80x53 161 72 102 809-25 25 141 61
805-80-40 80x40 199 81 104 809-32 32 149 73
805-80-50 80x50 200 88 104 809-40 40 175 80
805-100-50 100x50 189 99 132 809-50 50 185 93
805-100-80 100x80 222 127 132 809-100 100 313 162
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 11
Fitting Dimensions
DESCRIPTION CODE NOMINAL A O.D. DESCRIPTION CODE NOMINAL A O.D.
SIZE SIZE
SOCKET UNION PLAIN CROSS
811-15 15 67 56 (Rated PN9 Only) 820-15 15 64 28
811-20 20 67 63 820-20 20 84 34
811-25 25 74 70 820-25 25 98 41
811-32 32 81 83 820-32 32 114 52
811-40 40 91 96 820-40 40 124 59
811-50 50 98 111 820-50 50 139 71
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 12
Fitting Dimensions
DESCRIPTION CODE NOMINAL A B O.D. DESCRIPTION CODE NOMINAL A B O.D.
SIZE SIZE
FULL FACE FLANGE THREADED END
825-15 15 28 13 96 PLUG 837-15 15 25.1 7 30
825-20 20 30 13 102 837-20 20 30 7 36
825-25 25 33 30 115 837-25 25 30 8 45
825-32 32 121 13 33 837-32 32 32.2 8 58
825-40 40 42 13 132 837-40 40 33.2 9 63
825-50 50 46 13 153 837-50 50 37.3 9 80
825-65 65 67 13 169 837-80 80 53.4 20 113
825-80 80 57 13 184 837-100 100 58 20 144
825-100 100 68 16 216
825-125 125 99 19 253
825-150 150 98 20 280
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 13
4. POLYETHYLENE
RETURN TO
CONTENTS
• Material Properties
• Pipe Dimensions
• Flow Charts
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 1
3.3.0 PE80 Pipe Dimensions
Standard AS/NZS 4130
20 20.2 16.7 1.6 1.9 0.096 16.1 1.9 2.2 0.110 15.2 2.3 2.7 0.132
25 25.2 21.1 1.9 2.2 0.142 20.2 2.3 2.7 0.168 19.2 2.8 3.2 0.199
32 32.2 27.0 2.4 2.8 0.230 26.0 2.9 3.3 0.266 24.5 3.6 4.1 0.326
40 40.2 33.8 3.0 3.4 0.353 32.3 3.7 4.2 0.423 30.6 4.5 5.1 0.507
PE80: SDR 13.6 - SDR 9
50 50.3 42.4 3.7 4.2 0.546 40.4 4.6 5.2 0.657 38.4 5.6 6.3 0.788
63 63.3 53.3 4.7 5.3 0.870 51.0 5.8 6.5 1.038 48.2 7.1 8.0 1.256
75 75.4 63.7 5.5 6.2 1.214 61.0 6.8 7.6 1.450 57.6 8.4 9.4 1.766
90 90.5 76.5 6.6 7.4 1.744 73.1 8.2 9.2 2.102 69.1 10.1 11.3 2.548
110 110.5 93.3 8.1 9.1 2.615 89.4 10.0 11.1 3.114 84.5 12.3 13.7 3.783
125 125.6 106.1 9.2 10.3 3.371 101.5 11.4 12.7 4.041 96.1 14.0 15.5 4.880
140 140.7 118.9 10.3 11.5 4.223 113.9 12.7 14.1 5.037 107.6 15.7 17.4 6.132
160 160.8 135.9 11.8 13.1 5.512 130.0 14.6 16.2 6.612 123.1 17.9 19.8 7.986
180 180.9 152.8 13.3 14.8 6.996 146.3 16.4 18.2 8.358 138.5 20.1 22.3 10.104
200 200.9 169.9 14.7 16.3 8.577 162.5 18.2 20.2 10.302 153.7 22.4 24.8 12.488
225 226.1 191.1 16.6 18.4 10.895 182.9 20.5 22.7 13.044 173.2 25.1 27.8 15.760
250 251.2 212.4 18.4 20.4 13.421 203.4 22.7 25.1 16.043 192.5 27.9 30.8 19.433
280 281.3 237.9 20.6 22.8 16.813 227.8 25.4 28.1 20.108 215.4 31.3 34.6 24.423
315 316.5 267.6 23.2 25.7 21.311 256.3 28.6 31.6 25.458 242.4 35.2 38.9 30.901
355 356.6 301.6 26.1 28.9 27.011 288.8 32.2 35.6 32.305 273.3 39.6 43.7 39.150
400 401.8 339.9 29.4 32.5 34.256 325.4 36.3 40.1 41.017 307.8 44.7 49.3 49.769
450 452.1 382.4 33.1 36.6 43.398 366.1 40.9 45.1 51.949 346.5 50.2 55.4 62.923
500 502.3 424.9 36.8 40.6 53.546 406.8 45.4 50.1 64.096 385.0 55.8 61.5 77.657
560 562.5 475.9 41.2 45.5 67.167 455.8 50.8 56.0 80.283
630 632.9 535.5 46.3 51.1 84.911 512.6 57.2 63.1 101.737
710 713.2 603.4 52.2 57.6 107.862
800 803.6 680.0 58.8 64.8 136.820
1000 1004.5
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. .
2
33.0 PE80B Pipe Dimensions
Standard AS/NZS 4130
32 32.2 28.7 1.6 1.9 0.159 28.7 1.6 1.9 0.159 28.7 1.6 1.9 0.159 28.1 1.9 2.2 0.184
40 40.2 36.7 1.6 1.9 0.201 36.7 1.6 1.9 0.201 36.1 1.9 2.2 0.233 35.0 2.4 2.8 0.292
50 50.3 46.8 1.6 1.9 0.254 46.0 2.0 2.3 0.309 45.1 2.4 2.8 0.370 43.9 3.0 3.4 0.450
63 63.3 59.0 2.0 2.3 0.392 58.1 2.4 2.8 0.471 56.9 3.0 3.4 0.574 55.2 3.8 4.3 0.716
75 75.4 70.4 2.3 2.7 0.544 69.2 2.9 3.3 0.669 67.7 3.6 4.1 0.822 65.8 4.5 5.1 1.011
90 90.5 84.5 2.8 3.2 0.783 83.0 3.5 4.0 0.971 81.3 4.3 4.9 1.179 79.0 5.4 6.1 1.454
110 110.5 103.2 3.4 3.9 1.164 101.9 4.3 4.9 1.454 99.2 5.3 6.0 1.768 96.5 6.6 7.4 2.162
125 125.6 117.3 3.9 4.4 1.504 115.4 4.8 5.4 1.834 112.9 6.0 6.7 2.260 109.9 7.4 8.3 2.759
140 140.7 131.5 4.3 4.9 1.868 129.2 5.4 6.1 2.316 126.5 6.7 7.5 2.831 123.1 8.3 9.3 3.464
160 160.8 150.4 4.9 5.5 2.415 147.6 6.2 7.0 3.037 144.5 7.7 8.6 3.713 140.7 9.5 10.6 4.522
180 180.9 169.2 5.5 6.2 3.056 166.3 6.9 7.7 3.782 162.7 8.6 9.6 4.666 158.3 10.7 11.9 5.720
200 200.9 187.7 6.2 7.0 3.827 184.6 7.7 8.6 4.688 180.6 9.6 10.7 5.778 175.8 11.9 13.2 7.055
225 226.1 211.5 6.9 7.7 4.767 207.9 8.6 9.6 5.894 203.3 10.8 12.0 7.305 197.8 13.4 14.9 8.951
250 251.2 234.9 7.7 8.6 5.912 230.9 9.6 10.7 7.302 226.1 11.9 13.2 8.939 220.0 14.8 16.4 10.969
280 281.3 263.1 8.6 9.6 7.393 258.7 10.7 11.9 9.106 253.0 13.4 14.9 11.282 246.3 16.6 18.4 13.778
315 316.5 296.0 9.7 10.8 9.369 290.9 12.1 13.5 11.602 284.9 15.0 16.6 14.180 277.1 18.7 20.7 17.450
355 356.6 333.6 10.9 12.1 11.844 327.9 13.6 15.1 14.658 321.0 16.9 18.7 17.999 311.1 21.1 23.4 22.203
400 401.8 375.8 12.3 13.7 15.085 369.5 15.3 17.0 18.588 361.5 19.1 21.2 22.952 351.9 23.7 26.2 28.062
450 452.1 423.0 13.8 15.3 19.000 415.8 17.2 19.1 23.507 406.8 21.5 23.8 29.030 395.9 26.7 29.5 35.559
500 502.3 470.0 15.3 17.0 23.432 462.0 19.1 21.2 28.996 452.0 23.9 26.4 35.815 440.0 29.6 32.7 43.802
560 562.5 526.3 17.2 19.1 29.487 517.4 21.4 23.7 36.339 506.4 26.7 29.5 44.817 492.7 33.2 36.7 55.028
630 632.9 592.2 19.3 21.4 37.203 582.1 24.1 26.7 46.053 569.8 30.0 33.1 56.624 554.4 37.3 41.2 69.541
710 713.2 667.3 21.8 24.1 47.278 655.9 27.2 30.1 58.533 641.9 33.9 37.4 72.090 624.6 42.1 46.5 88.438
800 803.6 752.0 24.5 27.1 59.891 739.2 30.6 33.8 74.133 723.4 38.1 42.1 91.375 703.9 47.4 52.3 112.141
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. .
1000 1004.5 940.1 30.6 33.8 93.439 924.1 38.2 42.2 115.694 904.2 47.7 52.6 142.841 879.8 59.3 65.4 175.319
3
PE100 Pipe Dimensions
Standard AS/NZS 4130
Nominal Mean OD Mean T Min T Max Mass Mean T Min T Max Mass Mean T Min T Max Mass
Size Bore kg/m Bore kg/m Bore kg/m
20 20.2 16.7 1.6 1.9 0.096 16.7 1.6 1.9 0.096 16.7 1.6 1.9 0.096
25 25.2 21.7 1.6 1.9 0.122 21.7 1.6 1.9 0.122 21.7 1.6 1.9 0.122
PE100: SDR 41 - SDR 21
32 32.2 28.7 1.6 1.9 0.159 28.7 1.6 1.9 0.159 28.7 1.6 1.9 0.159
40 40.2 36.7 1.6 1.9 0.201 36.7 1.6 1.9 0.201 36.1 1.9 2.2 0.233
50 50.3 46.8 1.6 1.9 0.254 46.0 2.0 2.3 0.309 45.1 2.4 2.8 0.370
63 63.3 59.0 2.0 2.3 0.392 58.1 2.4 2.8 0.471 56.9 3.0 3.4 0.574
75 75.4 70.4 2.3 2.7 0.544 69.2 2.9 3.3 0.669 67.7 3.6 4.1 0.822
90 90.5 85.5 2.3 2.7 0.783 83.0 3.5 4.0 0.971 81.3 4.3 4.9 1.179
110 110.5 104.7 2.7 3.1 1.164 101.3 4.3 4.9 1.454 99.2 5.3 6.0 1.768
125 125.6 118.9 3.1 3.6 1.504 115.4 4.8 5.4 1.834 112.9 6.0 6.7 2.260
140 140.7 133.2 3.5 4.0 1.868 129.2 5.4 6.1 2.316 126.5 6.7 7.5 2.831
160 160.8 152.3 4.0 4.5 2.415 147.6 6.2 7.0 3.037 144.5 7.7 8.6 3.713
180 180.9 171.5 4.4 5.0 3.056 166.3 6.9 7.7 3.782 162.7 8.6 9.6 4.666
200 200.9 190.5 4.9 5.5 3.827 184.6 7.7 8.6 4.688 180.6 9.6 10.7 5.778
225 226.1 214.4 5.5 6.2 4.767 207.9 8.6 9.6 5.894 203.3 10.8 12.0 7.305
250 251.2 238.0 6.2 7.0 5.912 230.9 9.6 10.7 7.302 226.1 11.9 13.2 8.939
280 281.3 266.7 6.9 7.7 7.393 258.7 10.7 11.9 9.106 253.0 13.4 14.9 11.282
315 316.5 300.2 7.7 8.6 9.369 290.9 12.1 13.5 11.602 284.9 15.0 16.6 14.180
355 356.6 338.2 8.7 9.7 11.844 327.9 13.6 15.1 14.658 321.0 16.9 18.7 17.999
400 401.8 381.1 9.8 10.9 15.085 369.5 15.3 17.0 18.588 361.5 19.1 21.2 22.952
450 452.1 428.9 11.0 12.2 19.000 415.8 17.2 19.1 23.507 406.8 21.5 23.8 29.030
500 502.3 476.3 12.3 13.7 23.432 462.0 19.1 21.2 28.996 452.0 23.9 26.4 35.815
560 562.5 533.6 13.7 15.2 29.487 517.4 21.4 23.7 36.339 506.4 26.7 29.5 44.817
630 632.9 600.4 15.4 17.1 37.203 582.1 24.1 26.7 46.053 569.8 30.0 33.1 56.624
710 713.2 676.5 17.4 19.3 47.278 656.2 27.2 30.1 58.533 641.9 33.9 37.4 72.090
800 803.6 762.3 19.6 21.7 59.891 739.2 30.6 33.8 74.133 723.4 38.1 42.1 91.375
1000 1004.5 952.9 24.5 27.1 93.439 924.1 38.2 42.2 115.694 904.2 47.7 52.6 142.841
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. .
4
PE100 Pipe Dimensions
Standard AS/NZS 4130
20 20.2 16.7 1.6 1.9 0.096 16.7 1.6 1.9 0.096 16.1 1.9 2.2 0.110
25 25.2 21.7 1.6 1.9 0.122 21.1 1.9 2.2 0.142 20.2 2.3 2.7 0.168
PE100: SDR 17 - SDR 11
32 32.2 28.1 1.9 2.2 0.184 27.0 2.4 2.8 0.230 26.0 2.9 3.3 0.266
40 40.2 35.0 2.4 2.8 0.292 33.8 3.0 3.4 0.353 32.3 3.7 4.2 0.423
50 50.3 43.9 3.0 3.4 0.450 42.4 3.7 4.2 0.546 40.4 4.6 5.2 0.657
63 63.3 55.2 3.8 4.3 0.716 53.3 4.7 5.3 0.870 51.0 5.8 6.5 1.038
75 75.4 65.8 4.5 5.1 1.011 63.7 5.5 6.2 1.214 61.0 6.8 7.6 1.450
90 90.5 79.0 5.4 6.1 1.454 76.5 6.6 7.4 1.744 73.1 8.2 9.2 2.102
110 110.5 96.5 6.6 7.4 2.162 93.3 8.1 9.1 2.615 89.4 10.0 11.1 3.114
125 125.6 109.9 7.4 8.3 2.759 106.1 9.2 10.3 3.371 101.5 11.4 12.7 4.041
140 140.7 123.1 8.3 9.3 3.464 118.9 10.3 11.5 4.223 113.9 12.7 14.1 5.037
160 160.8 140.7 9.5 10.6 4.522 135.9 11.8 13.1 5.512 130.0 14.6 16.2 6.612
180 180.9 158.3 10.7 11.9 5.720 152.8 13.3 14.8 6.996 146.3 16.4 18.2 8.358
200 200.9 175.8 11.9 13.2 7.055 169.9 14.7 16.3 8.577 162.5 18.2 20.2 10.302
225 226.1 197.8 13.4 14.9 8.951 191.1 16.6 18.4 10.895 182.9 20.5 22.7 13.044
250 251.2 220.0 14.8 16.4 10.969 212.4 18.4 20.4 13.421 203.4 22.7 25.1 16.043
280 281.3 246.3 16.6 18.4 13.778 237.9 20.6 22.8 16.813 227.8 25.4 28.1 20.108
315 316.5 277.1 18.7 20.7 17.450 267.6 23.2 25.7 21.311 256.3 28.6 31.6 25.458
355 356.6 311.1 21.1 23.4 22.203 301.6 26.1 28.9 27.011 288.8 32.2 35.6 32.305
400 401.8 351.9 23.7 26.2 28.062 339.9 29.4 32.5 34.256 325.4 36.3 40.1 41.017
450 452.1 395.9 26.7 29.5 35.559 382.4 33.1 36.6 43.398 366.1 40.9 45.1 51.949
500 502.3 440.0 29.6 32.7 43.802 424.9 36.8 40.6 53.546 406.8 45.4 50.1 64.096
560 562.5 492.7 33.2 36.7 55.028 475.9 41.2 45.5 67.167 455.8 50.8 56.0 80.283
630 632.9 554.4 37.3 41.2 69.541 535.5 46.3 51.1 84.911 512.6 57.2 63.1 101.737
710 713.2 624.6 42.1 46.5 88.438 603.4 52.2 57.6 107.862
800 803.6 703.9 47.4 52.3 112.141 680.0 58.8 64.8 136.820
1000 1004.5 879.8 59.3 65.4 175.319
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. .
5
5 5
4 4
3 3
2 2
1 1
.9 .9
.8 .8
.7 .7
.6 .6
.5 .5
.4 .4
.3 .3
.2 .2
.1 .1
.09 .09
.08 .08
.07 .07
.06 .06
.05 .05
.04 .04
.03 .03
.02 .02
.01 .01
.009 .009
.008 .008
.007 .007
.006 .006
.005 .005
Flow Chart
(PE80: PN3.2 & PE100: PN4)
Polyethylene Pipe - SDR 41
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. .
7
5 5
4 4
3 3
2 2
1 1
.9 .9
.8 .8
.7 .7
.6 .6
.5 .5
.4 .4
.3 .3
.2 .2
.1 .1
.09 .09
.08 .08
.07 .07
.06 .06
.05 .05
.04 .04
.03 .03
.02 .02
.01 .01
.009 .009
.008 .008
.007 .007
.006 .006
.005 .005
1 2 4 6 8 10 20 40 60 80 100 200 400 600 800 1000 2000 3000
Polyethylene Pipe - SDR 33
(PE80: PN4)
Flow Chart
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. .
8
5 5
4 4
3 3
2 2
1 1
.9 .9
.8 .8
.7 .7
.6 .6
.5 .5
.4 .4
.3 .3
.2 .2
.1 .1
.09 .09
.08 .08
.07 .07
.06 .06
.05 .05
.04 .04
.03 .03
.02 .02
.01 .01
.009 .009
.008 .008
.007 .007
.006 .006
.005 .005
1 2 4 6 8 10 20 40 60 80 100 200 400 600 800 1000 2000 3000
Polyethylene Pipe - SDR 26
(PE 100: PN6.3)
Flow Chart
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. .
9
5 5
4 4
3 3
2 2
1 1
.9 .9
.8 .8
.7 .7
.6 .6
.5 .5
.4 .4
.3 .3
.2 .2
.1 .1
.09 .09
.08 .08
.07 .07
.06 .06
.05 .05
.04 .04
.03 .03
.02 .02
.01 .01
.009 .009
.008 .008
.007 .007
.006 .006
.005 .005
Flow Chart
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. .
10
5 5
4 4
3 3
2 2
1 1
.9 .9
.8 .8
.7 .7
.6 .6
.5 .5
.4 .4
.3 .3
.2 .2
.1 .1
.09 .09
.08 .08
.07 .07
.06 .06
.05 .05
.04 .04
.03 .03
.02 .02
.01 .01
.009 .009
.008 .008
.007 .007
.006 .006
.005 .005
1 2 4 6 8 10 20 40 60 80 100 200 400 600 800 1000 2000 3000
(PE 80: PN8 & PE100: PN10)
Polyethylene Pipe - SDR 17
Flow Chart
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. .
11
5 5
4 4
3 3
2 2
1 1
.9 .9
.8 .8
.7 .7
.6 .6
.5 .5
.4 .4
.3 .3
.2 .2
.1 .1
.09 .09
.08 .08
.07 .07
.06 .06
.05 .05
.04 .04
.03 .03
.02 .02
.01 .01
.009 .009
.008 .008
.007 .007
.006 .006
.005 .005
1 2 4 6 8 10 20 40 60 80 100 200 400 600 800 1000 2000 3000
(PE 80: PN10 & PE100: PN12.5)
Polyethylene Pipe - SDR 13.6
Flow Chart
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. .
12
10 10
9 9
8 8
7 7
6 6
5 5
4 4
3 3
2 2
1 1
.9 .9
.8 .8
.7 .7
.6 .6
.5 .5
.4 .4
.3 .3
.2 .2
.1 .1
.09 .09
.08 .08
.07 .07
.06 .06
.05 .05
.04 .04
.03 .03
.02 .02
.01 .01
(PE80: PN 12.5 & PE100: PN16)
Polyethylene Pipe - SDR 11
Flow Chart
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. .
13
5. DESIGN
RETURN TO
• Pipe Selection CONTENTS
• Fatigue Response
• Effect of Surges
• Water Hammer
• Design Hints
• Effect of Temperature
• Safety Factors
• Fittings
• Celerity
• Surge Celerity
• Hydraulic Flow
• Air Valves
Time to Failure
104
105 106h
50 Years
and Minimum Required Principal stress/time curves for PE80 and PE100
Strength Values pipes at 20°C and 80°C. The standard curve for
HDPE Type 2 at 80°C (acc. to DIN 8075) is shown
- for MDPE for comparison. The minimum required strength
(MRS) at 20°C and 50 years is 10 MPa for PE100
Material Minimum Required Hydrostatic and 8 MPa for PE80 giving the design stress 8
Designation Strength DesignStress MPa and 6.3 MPa, respectively.
(MRS)MPa (S) MPa
PE63 5.0 6.3 Burst Stress MPa
50
PE80 6.3 8.0
30
PE100 8.0 10.0 20°C
20 40°C
- for PVC
10
60°C
Material Minimum
Designation Required Strength 5
(MRS)MPa 3
up to 20mm nominal size - 9.8 MPa 2
25 to 150 nominal size - 11.0 MPa 1
175 nominal size and larger - 12.3 MPa 0.5
10-1 1 10 102 103 104 105 106h
50 Years
Time to Failure
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 1
Design
FATIGUE RESPONSE SURGE PRESSURE
Studies of fatigue response have shown that a
ENVELOPES - PVC
fatigue crack initiates from some dislocation in the
material matrix, usually towards the inside surface 9 Bar PVC-U pipe
of the pipe where stress levels are highest, and
propagates or grows with each stress cycle at a Recommended limitation.
rate dependent on the magnitude of the stress. Maximum sustained
1 million cycles or
9 bar 500,000 events
Ultimately the crack will penetrate the pipe wall, working pressure
tres long in the axial direction and will produce a 7 bar Maximum surge
pressure
leak. On occasion, particularly with larger pipes 6 bar
containing air entrained in the line, a large surge
5 bar
may cause unstable crack propagation and the 4.5 bar
pipe will burst. 4 bar
3 bar
It is important to appreciate that the growth of a
2 bar
fatigue crack is primarily dependent on the stress
Minimum
cycle amplitude, i.e. the maximum pressure minus 1 bar surge pressure
the minimum pressure. Therefore a pipe subjected 0 bar
0 bar
Negative
to a pressure cycle of zero to half working pressure -1 bar pressure
is as much in danger of fatigue as one subjected to
a pressure cycle of half to full working pressure.
Thus pipe fatigue failures occur just as frequently
at high points in the system as at low points where
the total pressure is greater.
3 bar
The DYNAMIC loads normaly considered during Minimum
surge pressure
operation are:
0 bar 0 bar
Negative
• internal cyclic loading e.g. surge associated with -1 bar pressure
pumping regimes or the rapid closure of valves;
• external cyclic loadings due to traffic conditions.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 2
Design
SURGE PRESSURE DEFINITION OF CYCLE
ENVELOPES - PE AMPLITUDE
In the simplest terms the pressure cycle amplitude
PE100, SDR 11 is defined as the maximum pressure, minus the
minimum pressure experienced by the system,
16 Maximum sustained working pressure
including all transients, both positive and negative.
15 For purposes of fatigue design, transient pressures
14 (a)
13 due to accidental events such as power failure may
Operating Pressure Range (bar)
8
7 (b)
Maximum surge pressure
6 WATER HAMMER
5
Water hammer is a temporary change in pressure
4 in a pipeline due to a change in the velocity of flow
(c)
3 in a pipe with respect to time, e.g. a valve opens or
2 (d) closes or a pump starts or stops. Accidental events
1 such as a pipe blockage can also be a cause. The
Minimum surge pressure effects are exacerbated by:
0
• Fast closing/stopping valves/pumps
-1
• High water velocities
Negative pressure
• Air in the line
• Poor layout of the pipe network, positioning of
The vertical lines a, b, c, d illustrate that the pumps
permissable range of fluctuation in pressure should • Pump start method
not exceed 5 bar and may be, for example, Note that water hammer pressure may be positive
between the following limits; or negative. Both can be detrimental to pipe
(a) from 5-10 bar, systems; not only pipes, but pumps, valves and
(b) from 3-8 bar, thrust supports can be damaged. Negative pressures
(c) from 0-5 bar, can cause “separation” (vacuum formation), with
(d) from 1-4 bar (possible vacuum conditions). very high positive pressures on “rejoinder” (collapse
This applies to 10 bar PE pipe, eg. PE100 pipes at of the vacuum). For these reasons, water hammer
SDR 17.6 and PE80 pipes at SDR 11. should be eliminated as far as possible.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 3
Design
Water hammer pressures can be reduced by: under hydraulic thrust when improperly supported,
• Controlling and slowing valve and pump operations or vibration induced fatigue caused by direct
• Reducing velocities by using larger diameter pipes connection of pipe work to pumps, e.g. flanged
• Using pipe material with lower elastic modulus connections. Isolation from vibration should always
• Astute layout of network, valves, pumps and air valves be provided in the design. Injection moulded fittings
• Fast-acting pressure relief valves. up to and including 50 mm diam. should be rated
It is beyond the scope of this manual to give a PN15. Larger sizes are rated PN12. In large pipe
complete description of water hammer analysis and installations, where high pressures are expect-
mitigation. ed, cast iron fittings are preferred. With PVC full
faced flanges should be fitted with backing rings
DESIGN HINTS behind both bolt head and nut when used at pres-
To reduce the effect of dynamic fatigue in an sures above 240kPa. Stub flanges are recom-
installation, the designer can: mended.
1. Limit the number of cycles by:
(a)Increasing well capacity for a pumping station. WAVE SPEED
(b)Matching pump performance to tank size
eliminate short demand cycles for an automatic TRANSMISSION
pressure unit. In applications where surgepressures may occur,
(c)Using double-acting float valves or limiting the relatively low shock wave transmission speed
starts on the pump by the use of a time clock in polymer pipes (compared with that of a pipe of
when filling a reservoir. a more rigid material), can be particularly benefi-
2. Reduce the dynamic range by: cial.
(a)Eliminating excessive water hammer. The range of wave transmissions speeds in water
(b)Using a larger bore pipe to reduce friction loss. for various pipematerials and wall thicknesses.
Wave speed is approximately related to pressure
EFFECT OF TEMPERATURE change by the Joukowski formula:
Research to date (ref.[2]) suggests that crack
growth rates in uPVC is not greatly affected by ∆p = p.a. ∆V
temperature change.
where
Therefore while temperature rating principles must
be applied in pressure rating selection for static ∆p = pressure change (N/m2)
pressures, (ductile burst), no adjustment need be p = fluid density (kg/m3)
applied for dynamic design. Select the highest a = wave speed (m/s)
according to: ∆C = velocity change (m/s)
(a) static design including temperature derating
Therefore for a given density and change in velocity,
or
the surge pressure is approximately proportional to
(b) dynamic design as discussed in this section.
wave speed. This illustrates how, for a given surge
SAFETY FACTORS ‘event’, the surge pressures generated in Marley
Pressure pipes will be considerably less than the
The analysis and design method adopted by
magnitude of surge developed in other pipe mate-
Joseph can be considered conservative. Given
rials.
reasonable confidence in prediction of pressure
cycle amplitude, no additional factor of safety need For external dynamic loading conditions the use of
be applied for selection of pipe class. PE pressure mains under major carriageways is
The more likely area of deficiency is in the dependent on the type of trench bedding conditions
frequency of number of cycles. Lack of confidence used.
in this parameter may warrant application of an PE 80 and PE 100 pressure mains should be laid
appropriate factor of safety. This judgement is in under major roads with the correct installation
the hands of the designer. It is recommended that techniques.
systems that are of concern to the designer should
be monitored on commissioning to ensure that
operation is in accordance with design criteria.
Pressure cycling outside acceptable limits can be
mitigated by a number of techniques, as outlined
above.
FITTINGS
Complex stress patterns in fittings can “amplify” the
stress cycling in the fitting. This factor is particularly
prevalent in branch fittings such as tees, where
amplification factors of up to four times have been
observed. The condition can be aggravated by the
existence of stress cycling from other sources. For
example, bending stresses induced by flexing
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 4
Design
10000
1000
Steel
Ductile Iron
Grey cast
iron
GRP
Asbestos cement
PVC-U
100 PE 80
10 100 1000
Wave speeds for water in various pipes of diameter (D) and wall thickness (e)
The time taken for the pressure wave to travel the SURGE CELERITY
length of the pipeline and return is
The surge celerity in a pipeline filled with liquid can
be determined by:
t = 2L
C
[ ( )]
-0.5
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 5
Design
MDPE Surge Celerity HYDRAULIC FLOW
Celerity m/s The velocity of flow in Marley pipes should not nor-
SDR MDPE (PE 80B) HDPE (PE 100) mally exceed 1-2 metres per second in distribution
mains. Where higher velocities are expected,
41 160 190 consideration should be given to the effects of
33 170 210 surge.
26 190 240
21 220 260 The hydraulically smooth bore of a Marley pipe
17 240 290 gives excellent flow characteristics which are usu-
13.6 270 320 ally retained through its operational life. The
11 300 360 hydraulic frictional coefficients normally used in the
9 330 390 design of continuous straight PE pipes working
7.4 360 430 under pressure are:
• Colebrook-White Ks = 0.003mm
PVC Surge Celerity • Hazen Williams C = 144
SIZE UP TO AND SIZES DN 175 The metric Colebrook- White formula for the velocity
of water in a smooth bore pipe under laminar
PN INCL. DN 150 AND LARGER
conditions takes the form:
Class SDR a(m/s) SDR a(m/s)
6 36.7 281 39.3 272
9
12
24.4
18.3
341
390
26.2
19.7
330
377
V = -2 2gDi. • log. [ Ks
3.7D
+
2.51v
D 2gDi
15 14.7 432 15.7 419
18 13.8 444 14.8 430 Depending on the nature of the surface of a pipe
and the velocity of fluid that it is carrying, the flow
Dimension Ratio (SDR) and Celerity (a) in a pipe will either be rough turbulent, smooth
turbulent or most probably somewhere in between.
For buried pipes increase the wave celerity (a) by 7%.
The Colebrook-White transition equation incorporates
Complex Cycle Patterns the smooth turbulent and rough turbulent conditions.
For smooth pipe the first term in the brackets tends
In general, a similar technique may be applied to to zero and the second term predominates. For a
any situation where smaller cycles exist in addition rough pipe the first term in the brackets predominates,
to the primary cycle. Empirically, crack growth is particularly at flows with a high Reynolds Number.
related to stress cycle amplitude according to ( This equation is therefore an almost universal
∆S)3.2. Thus n secondary cycles of magnitude ∆P1, application to virtually any surface roughness, pipe
may be deemed equivalent in effect to one primary size, fluid or velocity of flow in the turbulent range.
cycle, ∆P0.
Substituting for f in the Darcy equation note that:
( )
∆ P1 Q = flow velocity x pipe internal area.
3.2
where n =
∆ P0 Where Q = discharge (m3/s)
Q = πD • 2gD H • log 10 D
2
()
2 3.2
n= = 9.2 4 L k + 2.51v
1
3.7 2gD H
L
so it would require nine secondary cycles to
produce the same effect as one primary cycle. If Where
these are occurring at the same frequency, the
V = velocity in metres per second
effective frequency of primary cycling is increased
g = gravitational acceleration (a valve of 9.807
by 1.1 for the purpose of design.
ms-2 maybe assumed)
i = hydraulic gradient
v = kinetic viscosity (a value of 1.141 x 10-6
may be assumed).
Ks = linear measure of roughness in mm = 0.003
D = mean internal diameter of pipe in metres
Q = discharge (litres/second)
H = head of loss (meters/100 metres of pipe)
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 6
Design
However, it is conceivable that a pipe could be
Flowcharts for pipe systems using this formula manufactured with a maximum OD and a minimum
have been in operation in New Zealand for over 20 wall thickness within approved tolerances. In this
years for transmission of water and have been case the discharge will be more than that indicated
proven in practical installations. by the charts. Similarly a pipe with a minimum OD
and a maximum wall thickness will have a lower
discharge than indicated.
Other Pipe Flow Formulas For a given discharge the variation in friction head
loss or hydraulic gradient due to this effect can be
a) The Manning formula of the order of 2% to 10% depending on the pipe
size and class. For pipe sizes greater than 100mm,
V = 1 R2/3
()
H 1/2
this variation is usually limited to 6% for a PN18
n L pipe.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 7
Design
Percentage increase in Hydraulic AIR VALVES
Gradient for Values of k Higher than All water contains dissolved air. Normally this
0.003 mm. would be about 2% but it can vary largely depending
on temperature and pressure. Air trapped in the
SIZE FLOW VELOCITY k = 0.006 k = 0.015 line in pockets is continually moving in and out of
(m/s) (mm) (mm) solution.
50 0.5 0.6% 2.3% Air in the line not only reduces the flow by causing
1.0 1.0% 3.8% a restriction but amplifies the effects of pressure
2.0 1.6% 6.2% surges. Air valves should be placed in the line at
4.0 2.7% 9.8% sufficient intervals so that air can be evacuated, or,
100 0.5 0.5% 2.0% if the line is drained, air can enter the line.
1.0 0.9% 3.3% Air valves should be placed along the pipe line at
2.0 1.5% 5.5% all high points or significant changes in grade. On
4.0 2.4% 8.8% long rising grades or flat runs where there are no
200 0.5 0.4% 1.8% significant high points or grade changes, air valves
1.0 0.8% 2.9% should be placed at least every 500-1,000 metres
2.0 1.3% 4.9% at the engineer’s discretion.
4.0 2.2% 7.9%
300 0.5 0.4% 1.6% Recommended Air Valve Size
1.0 0.7% 2.8%
2.0 1.2% 4.6% Size Air Valve Size
4.0 2.0% 7.4% Up to 100 25 single
450 0.5 0.4% 1.5% 100-200 50 double
1.0 0.6% 2.5%
200-450 80 double
2.0 1.1% 4.3%
4.0 1.9% 6.9%
HEAD LOSS DUE TO
Relating Roughness Coefficients
Knowing k the equivalent roughness coefficients n FRICTION IN PIPE
and C for the other two formulas can be compared
as follows:
Lv2
1 = 5.04 D D H = f
-1/6
√2g log10 D2g
n k 2.51v
+
3.7 2gD H
L Where
f = Darcy friction factor
H = head loss due to friction (m)
C = 5.64 D-0.13 H D
-0.04
D = pipe internal diameter (m)
L √2g log k 2.51v L = pipe length (metres)
+
2gD H
10
3.7 v = flow velocity (m/s)
L g = gravitational acceleration (9.8 m/s2)
R = Reynolds Number
EQUIVALENT ROUGHNESS COEFFICIENTS This is valid for the laminar flow region. However,
as most pipes are likely to operate in the transition
ID k v H/L n C zone between smooth and full turbulence, the
(m) (m) (m2/s) (mm) transition function developed by Colebrook-White
0.20 0.003 x 10-3 1 x 10-6 0.01 0.0082 154 is necessary to establish the relationship between
0.015 x 10-3 1 x 10-6 0.01 0.0084 154 f and R.
0.45 0.003 x 10-3 1 x 10-6 0.01 0.0084 156
[
0.015 x 10-3 1 x 10-6 0.01 0.0086 152 1 K 2.51
= -2 Log10 +
f 3.7D R f
Where
K = Colebrook-White roughness coefficient (m)
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 8
Design
Head Loss Through Actual headloss characteristics for a range of
service pipe sizes and appropriate fittings to
Fittings determine overall headloss for PE 80 pipes service
The frictional losses occasioned by flow through installations.
valves and fittings are approximately proportional
to the square of the liquid velocity, The effect of the frictional resistance created by
the internal beads in butt welded joints is hardly
Kv2 significant in normal distribution installations in
H = smaller diameters or where the joints are frequent
2g
(e.g. for a joint once every 2 metres, an increase in
the frictional resistance of about 2% should be
where
allowed).
H = loss of head
v = liquid velocity For practical purposes, designers of water mains
g = acceleration due to gravity for normal housing layouts may consider alternative
K = coefficient dependent on type of fitting methods to take account of all secondary and minor
Perhaps a more convenient way of allowing for the losses for small and medium sized developments.
frictional resistance of valves, fittings, obstruction,
etc is to consider an equivalent straight length of
pipe which would create the same frictional
resistance.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 9
Design
RESISTANCE COEFFICIENTS FOR VALVES, FITTINGS AND CHANGES IN PIPE CROSS-SECTION.
SUDDEN ENLARGEMENTS
Ratio d/D Reflux Valve 2.50
0.9 0.04
0.8 0.13
0.7 0.26
0.6 0.41 Globe Valve 10.00
0.5 0.56
0.4 0.71
0.3 0.83
0.2 0.92 Butterfly Valve 0.20
(fully open)
<0.2 1.00
SUDDEN CONTRACTIONS
Ratio d/D Angle Valve 5.00
0.9 0.10
0.8 0.18
0.7 0.26
0.6 0.32 Foot Valve with strainer
hinged disc valve 15.00
0.5 0.38 unhinged (poppet) 10.00
0.4 0.42 disc valve
0.3 0.46
0.2 0.48
<0.2 0.50
Air Valves zero
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 10
Design
NEGATIVE PRESSURE EXPANSION AND CONTRACTION
EFFECTS Expansion and contraction of Marley pipes occurs
with changes in the pipe material service tempera-
The buckling performance limit may govern the
ture.
design of a flexible pipe under conditions of internal
This is in common with all pipe material and in
vacuum or underwater installations.
order to determine the actual amount of expansion
Reduced pressures can be generated in pumped
or contraction, the actual temperature change, and
mains due to sudden change in system operation.
the degree of restraint of the installed pipeline need
In some instances these transients can generate
to be known.
sub-atmospheric pressures in the pipeline. The
For design purposes, an average value of
magnitude of negative pressure conditions is limit-
ed by the vapour pressure of the fluid conveyed. 2.0 x 10-4/°C for Marley PE pipes
For water at 20°C the vapour pressure is 2.34 kPa. 8.0 x 10-5/°C for Marley PVC pipes
As atmospheric pressure is nominally 101.3 kPa, may be used.
full negative head can not exceed 99 kPa or 10 The relationship between temperature change and
metres head. In practise, negative head is only a length change for different materials.
transient phenomenon and is also mitigated by Where pipes are buried, the changes in tempera-
leakage past valves and control devices. ture are small and slow acting, and the amount of
PVC rubber ring jointed pressure pipes are capable expansion/contraction of the pipe is relatively
of performing under the most severe conditions of small. In addition, the frictional support of the back-
negative pressure. Both AS1477 and AS2977 fill against the outside of the pipe restrains the
specify that joints must withstand a minimum vacu- movement and any thermal effects are translated
um of 90 kPa for 2 hours without leakage. into stress in the wall of the pipe.
For a circular ring subjected to a uniform external Accordingly, in buried pipelines the main consider-
pressure (or internal vacuum) the critical buckling ation of thermal movement is during installation in
pressure PCR is defined by Timoshenko as: high ambient temperatures.
Above ground PE pipes require no expansion/con-
2.E traction considerations for free ended pipe or
PCR = where lateral movement is of no concern on site.
( )
D-t
t
3
Alternatively, pipes may be anchored at intervals to
allow lateral movement to be spread evenly along
the length of the pipeline. But with PVC pipes
where allowance must be made for expansion and con-
E = Young’s Modulus (MPa) traction.
D = outside diameter (mm)
t = wall thickness (mm)
Thermal Expansion and
For long tubes such as pipelines under combined Contraction
stress, Poissons effect must be taken into account, - for MDPE
and the equation becomes: 20.0
17.5
Expansion and Contraction (mm/m)
15.0
2.E
( )
t 3 12.5
PCR = x
1-υ 2
D-t 10.0
7.5
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 11
Design
THERMAL EXPANSION OR CONTRACTION
Maximum Expansion or Contraction of
Unplasticised uPVC Pipe
Example: For a pipe with expansion of 10mm and an external diameter (de) of 50mm, the length of the arm (a)
shall be at least 750mm.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 12
6. INSTALLATION
RETURN TO
• Design Consideration CONTENTS
• Loads on Pipes
• External Pressure
• Deflection
• Thrust Support
• Pipeline Buoyancy
• Expansion Joints
• Pipeline Detection
• Concrete Encasement
• Pneumatic Design
• Trenchless Installation
6 Installation
6.1 DESIGN Standards 2566 plastics pipelaying design) sets
out procedures to be adopted.
CONSIDERATION Special construction techniques can involve backfill
stabilisation, load bearing overlay or slab protection.
1. Where Marley Pressure Pipes are selected the It should be noted that cover of less than 1.5
designer must consider: diameters may result in flotation of empty pipes
• the use of straight or coiled pipes under wet conditions. Low covers may also result
• the jointing method in pipe “jacking” (lifting at vertically deflected joints)
• the trench width (standard or narrow) when pressurised.
• directional drilling – no trench installation
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 1
Installation
The value of Pc calculated requires a factor of U
h=
safety to be applied and a factor of 1.5 may be w
applied for those conditions where the negative
pressure conditions can be accurately assessed. 4) Traffic Loads
Where soil support is taken into account then a
factor of 3 is more appropriate. MαΩ
W = Cp
In general terms a Class 9 pipe should be used as I
a minimum for pump suction lines or when negative
pressure will be generated due to gradient the pipe The symbols expressed in these formulate for
is laid. evaluating the loads acting on the pipes are
Where the individual installation conditions result in contained in AS/NZ2566 and are as follows:
negative pressure conditions that are not present in
W = load on pipe (kN/m)
operation, then regard must be paid to construction
C = load coefficient
techniques. For example pipes may need to be
Ω = impact factor
filled with water during concrete encasement when
l = length of pipe over which concentrated
being used as vertical or horizontal ducting.
load acts (m)
In operation, fluid may be removed from the
M = concentrated load (kN)
pipeline faster than it is supplied from the source.
D = mean pipe outside diameter (m)
This can arise from valve operation, draining of the
B = trench width (m)
line or rupture of the line in service. Air valves must
U = uniformity distributed load (kPa)
be provided at high points in the line and
w = density of fill (t/m3)
downstream from control valves to allow the entry
of air into the line and prevent the creation of
vacuum conditions. Generally, in long pipelines air 6.5 DEFLECTION
valves should be provided each 250 metres along Flexible pipes resist external loading by a combi-
the line. nation of ring stiffness of the pipe and the soil sup-
port developed as a result of deflection of the pipe
6.4 EXTERNAL LOADING under loading.
This deflection invokes passive support and
Underground pipes behave as structural elements provides the major portion of the total installed pipe
and as such are required to withstand external strength.
loads from various sources. The amount of passive support is determined by
The actual loading on the pipe may be caused by the type of soil and the amount of compaction in
one of more of the following: the soil at the side of the pipe.
The determination of this support is contained in
1) Earth loads in either trench or embankment
the various sections of AS2566 and is specific to
installations.
each installation.
2) Imposed loading either concentrated point
For flexible pipes the maximum load bearing
loading or uniformly distributed loading such as
capacity is determined by the deflection of the pipe
in footings or foundations.
from the original diameter.
3) Traffic loads from aircraft, railway and motor
Traditionally, in New Zealand the maximum allowable
vehicles.
deflection has been 5% of the pipe outside the
AS/NZS2555 – Plastics Pipelaying Design provides diameter and this value has been adopted in AS1477
a methodology of calculating these loads operating on & AS/NZS4130. This value originally related to the
buried pipes under various installation conditions. limit applied to cement lined steel pipe as being the
The basis of the AS/NZ2566.1 and 2566.2 is that limit before the lining cracked under loading.
developed by Marston in the USA and for each of In the case of homogeneous flexible pipes this limit
the load sources listed in 1,2 and 3 is as follows: has not engineering basis and may be exceeded
without structural damage. For such pipes deflection
4) Earth Loads of 20% O.D may be tolerated without structural
distress.
Trench In several overseas countries deflection values of 7
a) Embankment and 12.5% O.D. are used for design purposes.
b) W = CewD2 The actual maximum design value adopted may be
selected by the designer taking into account the
1) Imposed Loads particular requirements of the installation, such as
the need to pass mechanical cleaning equipment
Uniformly distributed load down the bore of the pipe.
For the pipe deflected at 5% O.D. the hydraulic
2) Trench capacity of the pipe is 99.9% of the capacity of the
W = CuBU same pipe as a perfect circle.
3) Embankment The calculation of the deflection of the pipe caused
The load U is expressed as an equivalent height by the external loading is performed in AS2566
of fill and added to the embankment height. using the approach developed by Spangler in the
USA at Iowa State College.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 2
aaa
aaaa Where
∆
D
T
Ec
E`
W
=
=
=
=
=
=
∆x =
compaction techniques.
b) Type 2
The level of compaction
attained by thorough
hand tamping methods
normally used in trench
and
c) Type 3
embankment
conditions for sewer
and drain applications.
a) Type 1
The highest level of
compaction as used in
the highway and road
pavements
requires
and
mechanical
H
D
B
D + 150mm
D + 150mm
D + 150mm
D + 150mm
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. .
150m
75m
150m
75m
150m
75m
150m
Installation
6.6 BELOW GROUND
INSTALLATION
6.6.1 Preparing the Pipes
Before installation, each pipe and fitting should
be inspected to see that its bore is free from for-
eign matter and that its outside surface has no
large scores or any other damage. Pipe ends
should be checked to ensure that the spigots and
sockets are free from damage.
Pipes of the required diameter and pressure rat-
ing should be identified and matched with their
respective fittings and placed ready for installa-
tion.
3
aaa
a a aaa
aa
Trench Widths
In general, the width of trenches should be kept to
the minimum that enable construction to readily
proceed.
100mm
min
100mm
min
D 100mm
min
100mm
min
Bedding
75mm min
Bedding
75mm min
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. .
crown.
Installation
6.6.5 Minimum Cover
Trenches should be excavated to allow for the
specified depth of bedding, the pipe diameter and
the minimum recommend cover, overlay plus
backfill, above the pipes. Table below provides
recommendations for minimum cover to pipe
Minimum Cover
Loading
Roads and streets
Driveways and similar areas
subject to traffic
Footpaths, gardens
Construction traffic
crushed gravel or
road base.
• Use a higher class
of pipe
considerations.
than
required for normal
pressure or other
struction loads.
steel
plates may be used
in the case of con-
500
750
listed
75
mm
in
4
a
a aa
Variations in the hard bed should never exceed
20% of the bedding depth. Absolute minimum
underlay should be 50 mm.
6.6.8 Backfill
Unless otherwise specified, excavated material
from the site should constitute the back fill.
Gravel and sand can be compacted by vibratory
methods and clays by tamping. This is best
achieved when the soils are wet. If water flooding
is used and extra soil has to be added to the original
backfill, this should be done only when the flooded
backfill is firm enough to walk on.
When flooding the trench, care should be taken not
to float the pipe, or wash fines into rear joints.
All ground should be compacted back to 91-
Flexible or Composite
Wearing Course
Base Course
Road Base
Sub-base
Back fill
Surround to
apparatus
(fine fill)
Bedding
Running Surface
Surfacing
Road Structure
250mm
Maximun
Overlay
Base Course
Concrete slab or
bedded module
Sub-base
Back fill
Surround to
apparatus
(fine fill)
Bedding
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. .
Installation
6.7 THRUST SUPPORT
An imbalanced thrust is developed by a pipeline at:
• Direction changes (>10°), e.g. tees and bends.
• Changes in pipeline size at reducers.
• Pipeline terminations, e.g. at blank ends and
valves.
The support system or soil must be capable of
sustaining such thrusts.
Pressure thrust results from internal pressure in the
line acting on fittings. Velocity thrust results from
inertial forces developed by a change in direction
or flow. The latter is usually insignificant compared
to the former.
Pressure Thrust
The pressure thrust developed for various types of
fittings can be calculated as follows:
5
a
a
aa Tee -
aa
aa
THRUST SUPPORT DETAIL
elevation
Reducer - Plan
Tee - Plan
Valve -
Elevation
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. .
Blank End -
Elevation
Vertical Bend -
Elevation
Hydrant at end
of line -
Elevation
6
Installation
Pressure Thrust at Fittings in kN for pipes, these can be placed at such support points
Each 10 Metres Head of Water as flange locations. Additional supports, such as
sand bags, may be required to prevent scouring of
bedding and backfill materials down the trench
SIZE AREA BENDS TEES
floor.
DN (mm2) 11 Qr ° 22 Qw ° 45° 90° ENDS
15 363 .01 .01 .03 .05 .04 Calculating Thrust Block Size.
20 568 .01 .02 .04 .08 .06
25 892 .02 .03 .07 .12 .09 1) Establish the maximum working or test pres-
32 1410 .03 .05 .11 .20 .14 sure to be applied to the line.
40 1840 .04 .07 .14 .26 .18 2) Calculate the thrust developed at the fitting
50 2870 .06 .11 .22 .40 .28 being considered.
65 4480 .09 .17 .34 .62 .44 3) Divide 2) above by the safe bearing capacity
80 6240 .12 .24 .47 .87 .61 per square metre for the soil type against
100 6240 .20 .39 .77 1.43 1.01 which the thrust block must bear.
125 10300 .30 .59 1.16 2.15 1.52
150 20200 .39 .77 1.52 2.80 1.98
200 40000 .77 1.53 3.00 5.55 3.92 Example
225 49400 .95 1.89 3.71 6.85 4.84 What bearing area of thrust block is required for a
150mm Class 12 90º. Bend in hard dry clay.
250 61900 1.19 2.37 4.65 8.58 6.07
i) Maximum working pressure of Class 12 pipe is
300 78400 1.51 3.00 5.88 10.87 7.69
1.2 MPa. Test pressure is 1.5 times working
375 126000 2.42 4.82 9.46 17.47 12.36 pressure = 1.0 MPa.
ii) A 150mm x 90º bend develops a thrust of
6.7.4 Construction of Thrust Blocks 24.9 x 10-3 newtons for each pascal of pressure
applied.
Concrete should be placed around the fitting in a Therefore thrust =
wedge shape with its widest part against the solid (24.9 x 10-3) x (1.8 x 106) = 4.4 x 104 newtons.
trench wall. Some forming may be necessary to iii) Bearing capacity of hard dry clay is 15 x 104
achieve an adequate bearing area with a minimum newtons per square metre. Therefore bearing
of concrete. The concrete mix should be allowed to area of thrust block =
cure for seven days before pressurisation.
A thrust block should bear firmly against the side of
the trench and to achieve this, it may be necessary
to hand trim the trench side or hand excavate the Velocity Thrust
trench wall to form a recess. The thrust acts Applies only at changes in direction of flow:
through the centre line of the fitting and the thrust
block should be constructed symmetrically about F = W a V2 • 2 sin(0/2) • 10-9 (kN)
this centre line.
Pipes and fittings should be covered with a protec- Where:
tive membrane of PVC, polyethylene or felt when a = cross sectional area of pipe take at the
adjacent to concrete so that they can move without inside diameter (mm2)
being damaged. W = density of fluid (water = 1,000) (kg/m3)
The designer should consider all aspects of the V = velocity of flow (m/s)
system, including the unbalanced loads imposed
by testing procedures, unusual configurations,
large temperature variations, etc and where exces-
sive load on the pipe system is envisaged, addi-
tional anchorage should be considered. To estab-
lish thrust block size establish the pressure to be
applied to the line, calculate thrust developed con-
sider the safe bearing capacity of the soil type
using one 3 x safety factor.
In shallow (<600mm) cover, installations or in
unstable conditions of fill, the soil support may be
considerably reduced and a complete soil analysis
may be needed.
The velocity thrust is generally small in comparison to
the pressure thrust.
The pressure used in the calculations should be
the maximum working or test pressure applied to
the line.
Where pipes are installed on steep slopes (greater
than 1:5) then bulkheads may need to be placed
along the pipeline to prevent movement of the
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 7
a a
6.7.5 Bearing Loads of Soils
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. .
Installation
The indicative capacities of various soil types are tabulated below:
Soil Type
8
Installation
6.12 BENDS AND BENDING Angular deflection of a single pipe
joint (shown exaggerated for clarity).
6.12.1 Bending MDPE Pipes
1. The bending of PE pipe is permissible and the
properties of fusion jointed systems enable 2°
changes of direction without recourse to the
provision of special bends or anchor blocks.
However, for PE materials the pipe should not
normally be cold bent to a radius less than 20 Flexural Stress
times the outside diameter of the pipe. No joints One critical limit to the bending of PVC pipe is long
or tappings should occur on the bend. term flexural stress. Axial bending causes only a
small amount of ovalisation or diametric deflection
of the pipe, which indicates some change in
circumferential stress. PVC pipe has short term
strengths of 48 - 55 MPa in tension and 75 - 100
MPa in flexure. The long term strength of PVC pipe
in tension, compression or flexure can conser-
vatively be assumed to equal the ultimate hydro-
static design stress of 23.6 MPa. The recom-
mended design stress of 11.0 MPa for PVC pipe at
2. A full range of standard preformed bends are 20°C be used for the allowable long term flexural
available and are preferable for the larger sizes. stress in rubber ring pipe that is free of longitudi-
Special configurations are similarly available nal stress from longitudinal pressure thrust.
upon request. However, when the joints are restrained as they are
when solvent cemented, and the pipe is not snaked
6.12.1 Bending PVC Pipes in the trench, then the end thrust from internal pres-
sure imposes a longitudinal tensile stress equal to
When installing PVC pipes on a curve, the pipe one half of the hoop stress.
should be jointed straight and then laid to the
curve.
Significant bending moments should not be exerted
on the joints, since this introduces undesirable
stresses in the spigot and socket that may be
detrimental to long term performance. To avoid
this, the joints in curved lines must be thoroughly
supported by compacted soil, with the bending
occurring primarily at the centre of each pipe.
Some changes in the alignment of the pipe may be
achieved without the use of direction-change fit-
tings such as elbows and sweeps. PVC pipe is
capable of controlled longitudinal bending within
acceptable limits. A combination of axial flexure
and joint deflection can achieve further longitudinal
deviation of the pipeline. As a guide, PVC pipe can
be bent to a radius equal to 130 times the diame-
ter. However, Marley recommends that pipe under
pressure should be bent to a radius not less than
300 times the diameter, e.g. a 100 mm pipe should
have a minimum radius of curvature of 30 metres.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 9
aa
a
aa
aa
aa
6.13 CONCRETE ENCASEMENT
6.13.1 Pipe Entry Into Structures
1. Wherever pipework meets or passes through
rigid structures, careful consideration should be
given to:
Reinforced
support pad
Puddle flange
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. .
Installation
...........
2.Alternatively, flexi-
ble (rubber ring)
joints should be
provided at entry to
and exit from the
concrete as shown.
This procedure
also allows for pos-
sible
between
differential
m o v e m e n t
It must be borne in
mind, however, that
without a compress-
ible membrane,
stress transfer to
a
4. These points of detail are important since these
connections are often deep and sometimes
associated with underdrainage, (e.g.outlets to
reservoirs). This usually means any subsequent
defect is difficult to identify, expensive to locate
and very costly to remedy.
10
Installation
6.14.1 Support Spacing 6.14.2 Vertical Installation
The spacing of supports for a uPVC pipeline Generally, vertical runs are supported by spring
depends on factors such as the diameter of the hangers and guided with rings or long U-bolts
pipe, the density of the fluid being conveyed and which restrict movement of the rise to one plane. It
the maximum temperature likely to be reached by is sometimes helpful to support a long riser with a
the pipe material. saddle at the bottom.
Table 8 below, shows the support spacing in
metres for uPVC pipe carrying water at 20°C. 6.14.3 Brackets and Clips
These spacings do not allow for additional extra-
neous loading. For either free or fixed pipelines supports using
brackets or clips, the bearing surface should
Recommended Support provide continuous support for at least 120° of the
circumference.
Spacing
Straps
- for PVC pipes
Metal straps used as supports should be at least
MAXIMUM SUPPORT SPACING 25mm wide, either plastic coated or wrapped in a
SIZE HORIZONTAL VERTICAL protective material such as nylon, PE, PVC or rub-
(m) (m) ber sheet. If a strap is fastened around a pipe, it
15 0.60 1.20 should not distort the pipe in any way.
20 0.70 1.40
25 0.75 1.50
Location and type of support must
32 0.85 1.70 take into account provision for thermal
40 0.90 1.80 movement, if required. If the supports
50 1.05 2.10 are to resist thermal movement, an
65 1.20 2.40 assessment of the stress induced in
80 1.35 2.70 pipes, fittings and supports may need
100 1.50 3.00 to be made.
125 1.70 3.40
150 2.00 4.00
175 2.20 4.40
200 2.30 4.60
225 2.50 5.00
300 3.00 6.00
25 0.35
32 0.38 Free Support
40 0.43
50 0.45 A fee support allows the pipe to move without
restraint along its axis while still being supported.
63 0.50
To prevent the support from scuffing or damaging
75 0.60 the pipe as it expands and contracts, a 6mm thick
90 0.67 layer of felt or lagging material is wrapped around
125 0.75 the support. Alternatively, a swinging type of support
140 0.85 can be used and the support strap, protected with
160 1.00 felt or lagging, must be securely fixed to the pipe.
200 1.10
225 1.15
Fixed Supports
250 1.25 A fixed support rigidly connects the pipeline to a
280 1.30 structure totally restricting movement in a least two
355 1.50 planes of direction. Such a support can be used to
absorb moments and thrusts.
If temperatures are in excess of 20°C the horizontal
spacing should be reduced by 25% for every 10°C.
At 60°C , continuous horizontal support is required.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 11
Installation
Placement of Support the roof sheeting in order to prevent temperature
build up.
Careful consideration should be given to the layout
of piping and its support system. Even for non 6.15.3 Vibration
pressure lines the effects of thermal expansion and
contraction have to be taken into account. In Direct connection to sources of high frequency
particular, the layout should ensure that thermal such as pump outlet falnges should be avoided.
and other movements do not induce significant Allfabricated fittings manufactured by cutting and
bending moments at rigid connections to fixed welding techniques must be isolated from vibration.
equipment or at bends or tees. Where high frequency vibration sources exist in the
For solvent cement jointed pipe any expansion pipeline, the sections should be connected using a
coupling must be securely clamped with a fixed flexible joint such as a repair coupling, expansion
support. Other pipe clamps should allow for joint, or wire reinforced rubber bellows joint. When
movement due to expansion and contraction. used above ground such joints may need to be
Rubber ring jointed pipe should have fixed supports restrained to prevent pipe end pullout.
behind each pipe socket.
6.15.4 Conductivity
6.15 INSTALLATION Marley pipes are non-conductive and cannot be
CONSIDERATIONS used for electrical earthing purposes or dissipating
static electricity charges.
6.15.1 Expansion and Contraction When pipes are used to replace existing metal
water pipes, the designer must consider any exist-
Pipe will expand or contract if it is installed during ing systems used for earthing. In these cases the
very hot or very cold weather, so it is recommended appropriate electrician must be consulted to deter-
that the final pipe connections be made when the mine the requirements.
temperature of the pipe is stabilized at a temperature
close to that of the backfilled trench. 6.15.5 Fire Rating
Will MDPE lines laid directly on the natural surface
by snaking the pipe during installation and allowing Marley MDPE pipe systems will support combus-
the pipe to move freely in service. Where the final tion and as such are not suitable for use in fire
joint connections are made in high ambient tem- rated zones in buildings without suitable protection.
perature, sufficient pipe length must be allowed to
permit the pipe to cool, and hence contract, without 6.15.6 Ploughing In
pulling out of non end load bearing joints. MDPE pipe may be ploughed directly into the
For solvent cemented systems, the lines should be ground.
free to move until a strong bond has been developed The pipe must be stationary in relation to the
(see solvent cement jointing procedures) and surrounding soil and care must be taken to ensure
installation procedure should ensure that contraction that the pipe is not excessively tensioned during
does not impose strain on newly made joints. the ploughing activities.
For rubber ring jointed pipes, if contraction Ploughing should not be attempted where the soil
accumulates over several lengths, pull out of a joint contains rock or sharp stones or shale outcrops.
can occur. To avoid this possibility the preferred
technique is to back fill each length, at least 6.16 PNEUMATIC DESIGN
partially, as laying proceeds. (It may be required to
leave joints exposed for test and inspection.) 6.16.1 Pneumatic Flow
It should be noted that rubber ring joint design Marley MDPE pipe systems are ideal for the
allows for contraction to occur. Provided joints are transmission of gases both in the high and low
made to the witness mark in the first instance, and pressure range.
contraction is taken up approx. evenly at each joint, The use of compressible fluids in PE pipes requires
there is no danger of loss of seal. A gap between a number of specific design considerations as
witness mark and socket of up to 10 mm after distinct from the techniques adopted for fluids such
contraction is quite acceptable. as water.
Further contraction may be observed on pressurisation In particular:
of the line (so-called Poisson contraction due to Safety factor for different gases should be considered
circumferential strain). Again this is anticipated in in any design.
joint design and quite in order. Natural gas 2.0
Compressed air 2.0.
6.15.2 Heat sources
I. Compressed air may be at a higher temperature
Pipes and fittings should be protected from exter-
than the ambient air and PE pipes require
nal heat sources which would bring the continuous
temperature re-rating accordingly.
pipe material service temperature above 60°C.
For air cooled compressors the air temperature
Where the pipes are installed above ground, the
averages 15ºC above the surrounding air
protection system used must be resistant to ultra
temperature.
violet radiation and the effects of weathering, pipes
For water cooled compressors the air temperature
running across roofing should be supported above
averages 10ºC above the cooling water temperature.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 12
Installation
II. For underground applications the surrounding properties should be available from testing.
temperature may reach 30ºC and the pipe It is not permitted under the New Zealand Health
properties require adjustment accordingly. and Safety Act to use PVC for compressed air
lines.
III. High pressure lines must be protected from
damage, especially in exposed installations.
6.17 TRENCHLESS
IV. Valve closing sped must be reduced to prevent
a build up of pressure waves in the compressible
INSTALLATION
gas flow. Marley’s plastic pipes are a versatile material and
V. Where gaseous fuels such as propane, natural particularly through their toughness and flexibility,
gas or mixtures are carried the gas must be dry they are able to be used with a range of cost effec-
and free from liquid contamination which may tive “no dig” methods for the pressure pipelines
cause stress cracking in the PE pipe walls. installation.
dV1.85
450.l.
5 dt
di=
∆p.p
Where
∆p = pressure decrease (bar)
p = working pressure (bar)
V = volumetric flowrate (l/s)
dV/dt = atmosphere (l/s)
l = pipe length (m)
od = outside diameter (mm)
The values are specific to each fluid type and the
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 13
7. JOINTING SYSTEMS
RETURN TO
CONTENTS
• PVC Pipe Jointing
• PE Pipe Jointing
- PE Electrofusion
- Butt Welding
• Mechanical Jointing
- Mechanical Joints
- Tapping Systems
PVC Pipe Jointing
. . . . . . . . .. PVC PIPE JOINTING SYSTEMS
3. A fine tooth hand saw and mitre box
PVC pipes employ two jointing This saw produces a square cut but requires more
systems: deburring. It takes comparatively more time and
effort and requires a stand.
1. Rubber Ring Joint (“Z” Joint) The use of roller cutters is not recommended
A rubber ring joint system providing a flexible joint because of the large burr resulting.
with capability of axial and angular movement.
Simple, error free installation makes this joint suited
7.1.3 Rubber Ring Joints
to larger diameter underground work. Sizes 50 and Jointing rings are supplied with the pipe. We
larger. recommend the use of a lubricant approved for use
with potable water supply lines. Other lubricants
2. Solvent Cement Joint may not be suitable for potable water contact and
A chemically “welded” joint with capability of may affect the ring. They should not be substituted
supporting axial thrust. Available in sizes to 300 but without specific knowledge of these effects.
especially suited to smaller diameter systems. The ring provides a fluid seal in the socket of a pipe
or fitting and is compressed when the spigot is
7.1 RUBBER RING passed into the socket. Rings from other manufacturers
cannot be interchanged.
JOINTING
One end of the PVC pipe is accurately pressure 7.1.4 Chamfering
formed to provide a purpose designed socket and If the pipe is to be used for making a rubber ring
groove into which is fitted a purpose made rubber joint, a chamfer is required. Special chamfering
sealing ring. The socket is strengthened by tools are available for this purpose, but in the
increasing its wall thickness in both socket and absence of this equipment a flat file can be used
groove zone, to accommodate the increased Hoop provided it does not leave any sharp edges which
Stress. may cut the rubber ring. Do not make an
excessively sharp edge at the rim or the bore and
7.1.2 Specification do not chip or break this edge. As a guide, cut the
The “Z” joint socket and ring seal are designed to chamfer to 15° to the pipe surface to approx. half
conform with the requirements of AS/NZS 1477. the wall thickness at the pipe end.
The performance test in AS/NZS 1477 requires that When a pipe is cut, a witness mark should be
the spigot side of a completed joint be flattened by pencilled in and care should be taken to mark the
7.5% of the pipe diameter. While distorted the joint correct position in accordance with Table 6.
must withstand a negative pressure of 25 kPa for
one hour without leaking. Rubber Ring Spigot Dimensions
Performance tests not required by the Standard
Size Approx length Witness mark
show that the undistorted joint will not leak when a
DN of chamfer L
negative pressure of 100 kPa is applied.
(mm) (mm)
These tests ensure that a Marley PVC water sup-
ply system, even under extreme conditions will nei- 50 6 103
ther leak nor admit contaminated ground water. 65 8 110
80 10 116
Cutting
100 13 126
PVC is notch sensitive and care should be taken 125 13 137
when cutting. 150 14 145
During manufacture pipes are cut to standard by cut
200 20 162
off saws. These saws have carbide-tipped circular
blades which produce a neat cut without burrs. 225 22 174
However, pipes may be cut on site with a variety of 300 28 213
cutting tools. These are:
1. Proprietry cutting tools witness mark L
These tools can cut, deburr and chamfer the pipe
in one operation. They are the best tools for cutting
pipe. chamfer
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 1
a a
7.1.5 Procedure
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. .
Bar to
provide
thrust
NOTE: If excessive force is required to make a
joint, this may mean the rubber ring has been dis-
placed. To check placement of the ring without hav-
ing to dismantle the joint, a feeler gauge can be
inserted between the socket and the pipe to check
even placement of the ring, or use a torch to check
the pipe joint.
Details of the construction of a pipe puller are available.
Clean Socket
Clean socket and ring
groove of dirt and
loose gravel.
Align Pipes
Align pipes horizontal-
ly and vertically. Do
not try to insert pipe
at an angle to socket.
Lubricate Spigot
Clean of dust and dirt
and apply jointing
lubricant to chamfer.
Keep end free from
dirt.
Insert Pipe
Insert spigot into socket to the marked distance.
Do not use undue force. If force is required, check
ring seating, using a torch to look up the pipe.
2
PVC Pipe Jointing
This lubricant dries after a short period of time and pipe or fitting socket.
the joint cannot be easily dismantled. For situations Once the joint is made, do not disturb it for five
where it may be necessary to dismantle the rubber minutes or rough handle it for at least one hour.
ring joint after assembly, the use of silicone based Do not pressurise the line for at least 24 hours.
jointing lubricant is recommended. Where it is
necessary to joint in wet conditions, it may also
be advantageous to use silicone lubricant. If
7.2.2 Health
dismantled, joints should be fitted with new rings. Marley Solvent Cement has been specially
formulated for jointing Marley PVC pipe. It releases
7.2 SOLVENT CEMENT flammable and toxic vapours. Forced ventilation
should be used in confined spaces. Do not bring a
JOINTING naked flame within the vicinity of solvent cement
operations.
Solvent cement pressure pipe joints require an After using solvent cement wash the hands
interference fit between the spigot and socket
thoroughly before eating or smoking. Do not eat or
in pipes and fittings. Solvent cement jointing is
smoke while using solvent cement.
a welding and not a glueing process. It is very
important that the spigot achieve an interference Spillage onto the skin should be washed off
fit in the socket. Do not attempt to make a joint that immediately with soap and water. Should the
does not achieve an interference fit when dry. The solvent cement affect the eyes, wash them in clean
actual area of contact between the spigot and the water for at least 15 minutes. If solvent cement is
socket may only be a few millimetres. The ends accidentally swallowed induce vomiting and seek
must therefore be square to make a good joint. medical advice immediately.
Before proceeding make sure that the spigots and
sockets are not cracked or damaged. A pipe with 7.2.3 Precautions
minor damage to the spigot end may be cut back
and used as a shorter pipe. Make sure that the end of each pipe is square in its
socket and in the same alignment and grade as the
7.2.1 Procedure (NZS 2032) preceding pipes or fittings.
While applying solvent cement, support the
Before jointing, check that the spigot has been spigot and socket clear of the ground to avoid
cut square and all burrs removed from the inside contaminating joint with sand or soil.
and outside pipe edge. Remove all dirt, swarf,
Take care not to spill solvent cement onto pipes
and moisture from spigot and socket. Chamfer the
or fittings. Accidental spillage should be wiped off
spigot end on pipes over 80 mm diameter.
immediately.
Mark the pipe spigot with a pencil line at a distance
equal to the internal depth of the socket. Other The process of curing is a function of temperature,
marking methods may be used provided that they humidity and time. Joints cure faster when the
do not damage or score the pipe. humidity is low and the temperature is high. The
Dry fit the spigot into the socket. The spigot should higher the temperature the faster the joints will
interfere in the socket before it is fully inserted to cure. Avoid making solvent cement joints when the
the pencil line. temperature is more than 35°C and provide some
Dry and degrease each spigot and socket with a form of protection when jointing in windy and dusty
cloth dampened with Methylated Spirits. Prepare conditions.
the pipe spigot and socket with Marley primer fluid. When jointing under wet and very cold conditions,
Wipe the surfaces firmly, to remove all dirt and the make sure that the mating surfaces are dry and
glossy surface on both the spigot and socket. (Do free from ice, as moisture may prevent the solvent
not paint surfaces with primer. Primed areas will cement from obtaining its maximum strength.
be slightly tacky.) Prime the surface just before At temperatures over 16°C, joints will require 24
applying the solvent. hours to cure. When the temperature is between
Using a suitably sized brush, apply a thin, even 0°C and 15°C 48 hours should be allowed. See
coat of solvent cement to the internal surface of the also the precautions in NZS 2032.
socket first. Then apply a thin, even coat of solvent Do not fill the pipe with water for at least one hour
cement up to the mark on the spigot. after making the last joint.
Do not use excess solvent cement, and do not Keep the containers of solvent cement tightly
dilute or add anything to the solvent cement.
sealed when not in use to prevent evaporation of
As a guide, the brush should be approximately the solvent and consequent loss of bond strength.
one third to one half the pipe diameter and large
enough to apply the solvent cement to the joint in Do not use solvent cement that has gone cloudy or
about thirty seconds. has started to gel in the can.
Make the joint immediately. In one movement When applying solvent cement to a pipe or fitting
insert and twist the spigot into the socket so that socket take special care to prevent excessive
it rotates to about a 1/4 turn. The spigot should be solvent cement from entering the joint as this can
fully homed in the socket. Mechanical force will be cause future “solvent cracking” of the joint. Wipe
required for larger joints, over 100 mm. Pipe pullers excess solvent cement from the outside and where
are commercially available for this purpose. Hold possible, from the inside of the joint.
for a minimum of 30 seconds. An unsatisfactory solvent cement joint cannot be
With a clean rag, wipe off any excess solvent re-executed, nor can previously solvented spigots
cement which may have built up externally on a and sockets be re-used. To effect repairs, cut off the
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 3
PVC Pipe Jointing
spigot and socket and use a solvent cement cou- Solvent which has thickened in the can through
pling, or use mechanical fittings. evaporation of the solvents should not be used as
it will not soften the pipe surface sufficiently.
7.2.4 How to make a Solvent Cement The solvents attack the natural oils in human skin
Joint eventually causing serious dermatitis.
Clean Off
Remove surplus solvent
cement.
Solvent Cement
Marley Solvent Cement is designed for solvent
welding uPVC pipe joints. IT IS NOT AN ADHESIVE.
It is a blend of three aggressive solvents and sufficient
resin to provide a brushing consistency.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 4
PE Pipe Jointing
7.4 PE ELECTROFUSION . . . . . . . . .. . . .
7.4.1 Preparation All jointing faces must be dry before being assembled.
Mark the end of the pipe at a distance equal to half
All electrofusion processes must be carried out the length of the coupling and scrape the outside
inside a suitable shelter to prevent dirt and dust diameter of the pipe over this distance to remove
contamination of the pipes, couplings and power all oxidation layers on the pipe surface. This should
leads. be in the order of a layer of 0.3mm and removed
with a sharp scraper.
The pipes must be aligned so the same centreline All rough edges and swarf from the pipe ends must
height of the coupling clamps and supported evenly be removed.
support the pipe on both sides of the joint. The
pipes should be leveled to prevent pulling away 7.4.4 Fusion Welding Fusion Cycle
from the coupling joint during welding, or allowing
water or dirt inside the pipe to contaminate the Only the recommended fusion and cooling times
weld zone. recommended by the manufacture of the fitting
An inbuilt resistor is contained within the terminal must be used. Where any doubt exists that the
pin. The resistor pins are colour coded and require proper cycle has taken place, the coupling should
the correct colour coded lead to be connected to be cut out of the line and discarded.
the resistor. No attempt must be made to rerun the fusion cycle
as this will lead to overheating of the PE and degra-
7.4.2 Fusion Welding Equipment dation.
The full cooling times must be allowed. No attempt
Preparation, Control Systems must be made to accelerate the rate of cooling.
Ensure that the generator is operating correctly See cooling time in Butt welding section before
and that the power output conforms to the control allowing pressure testing
box requirements. Excessive fluctuations in the
power source, outside +10%, -10% from a nominal 7.4.5 Fusion Welding Coupling Storage
240 volt, may cause control box to shut down using a Couplings, saddles and electrofusion fittings must
safety cut out device. be stored in the original containers until actual use.
Both the fusion and cooling times are entered Where fittings are sealed in plastic bags, the bags
manually or entered by a bar code reader into the must not be perforated before the couplings are
control box by the operator. used.
Care needs to be taken to ensure that the pins are Saddles may be protected with a cardboard insert
compatible with the control box being used. wrapped around the heating element and fitted
Position the welding cables so as to prevent there over the terminal posts. These should not be
weight from twisting the welding socket. removed before use.
During the welding process including the total cooling Terminals may have a plastic cap fitted over the
time the clamps should remain in place terminal post and these should be left in place until
connecting the control box leads.
7.4.3 Fusion Welding Pipe Spigot Ends Couplings should be stored under cover to prevent
Successful electrofusion jointing depends correct any oxidation of the fitting materials in the element
gap alignment between the end of the pipe spigot zone.
and the coupling. Pipes which are oval must be The fusion surfaces must not be handled after they
rerounded and clamped. Pipes should not be are cleaned and prepared for welding.
forced into the coupling as this can damage the
coupling and misplace the heating element wires. Fusion Welding Minimum Cooling Times
Where pipe ends have a “toe in” or diameter reduction
at the end, or flats from storage this can affect the Size (mm) Cooling Time (minutes)
strength of the joint and lead to peel strength OD20-63 6
reduction. The Spigot ends must be recut square OD75-110 11
to remove the imperfections. OD 125-160 16
The pipe ends must be aligned evenly along the
OD180-225 20
centreline of the coupling and pipes, especially
OD250-355 30
coiled pipe, must be held in clamps to prevent
movement and stressing during the fusion process.
All jointing surfaces must be clean and free from all
contamination.
This includes dirt, dust and oil films. Surfaces must
not be handled after cleaning. If the sections are
contaminated they must be cleaned with a clean
cloth and a non depositing alcohol.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 5
PE Jointing
Power connection
Automatic fusion sensor
Cold zone
Fusion zone
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 6
PE PipeJointing
7.5 BUTT WELDING . . . . . . . . . .. . . . . .
7.5.3 Butt Weld Detail Heater Plates
BUTT WELDING The heater plate surface temperature should be set at
7.5.1 Introduction Thermal Welding 230°C with an evenly distributed tolerance of plus/
minus 10°C.
All thermal welding joint systems require the PE materials Temperatures above this will lead to possible failure
to be heated and raised well above the crystalline melt due to thermal degradation.
temperature of nominally 130°C, creating a melt pool Temperatures below this may be adopted, as it may be
of the PE material, placing that melt pool under steady necessary to adopt these values for thick wall pipes to
pressure, and then allowing the PE melt zones to cool prevent overheating, or for PE materials with a high Melt
down to ambient temperature. Flow Index.
After the heat source is removed, the temperature Only plates in good order should be used and they need
will drop and as the cooling continues, the crystalline to be kept scrupulously clean.
structure of the MDPE will gradually develop. PE is a
poor conductor of heat and the internal pipe sections Butt Weld Detail Interface Pressure
will remain considerably hotter than the outer surfaces. The gauge pressure adopted must have drag pressures
Accelerated cooling of the melt zone must not be
added to any calculated values.
attempted in any type of thermally welded joint. This
will lead to smaller crystalline structures and decrease
impact strength of the joint. 7.5.4 Butt Weld Detail Pipe Alignment
Any misalignment between pipe outside diameter and
the ends will reduce the strength of the completed
Temperature Distribution Through Pipe weld. Pipe and fitting must be accurately aligned
Wall At Final Weld Stage in the welding machine before the ends are faced.
The alignment of the welding machine also needs to
Hottest Material be checked after the trimming procedure has been
Cooler Material
completed.
Misalignment arises from:
• Ovality of pipes
• Eccentric wall thickness around the circumference
of the pipe.
Boundary Layer • Pipes not being properly aligned in support rollers
Skin Remnants on either side of the welding machine.
Surface Cooling • Pipe spigot end diameter reduction due to in built
stresses in the pipes.
• Bent, or misaligned, welding machine frames.
Pipes should be supported on free running rollers on
either side of the welding machine and the height and
Introduction Butt Welding alignment of these rollers should be adjusted to ensure
Butt welding is normally only used in pipe size from that the pipe centrelines are level with the welding
90mm to 1000mm for jointing pipe and fittings. Butt machine.
fusion brings the molten surfaces together under The alignment should be checked after the pipe
precise temperature pressure and time to provide a ends are trimmed and brought together. The outside
homogeneous material which has the same properties diameters should be even around the circumference of
as the original pipe. Butt Fusion is a precise operation the pipes and any offsets adjusted using the adjusting
and must be carried out with equipment which is well clamps in the welding machine (when fitted).
maintained and calibrated by qualified staff in an
appropriate working environment. Clean, dry working The maximum offsets at the outside diameter between
conditions are imperative as is consistency in the abutting pipe ends should not exceed 5 – 10% of the pipe
procedure and process. wall thickness when measured at any cross-section.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 7
PE Jointing
7.5.5 Butt Weld Welding Times Recording for both Butt and Fusion Weld
The times adopted for each section of the weld process Conditions
must be adhered to and care needs to be taken to recognize The welding conditions actually applied must be
the units in seconds or minutes as appropriate. recorded for each weld joint made.
When the welding process has been completed, the Each joint needs to be numbered and the identifiable
pipe joint must be held under compression for the full records as shown in the pipe weld record sheets must be
period of the cooling time. The interface pressure can completed and signed by the welding operator. A copy
be backed off from the welding pressure, however, the of the records should be held by the contractor and an
pressure must be above the drag pressure. additional copy submitted to the client as part of the
Any attempt to shorten the cooling times will damage Quality Assurance program for each installation.
the final joint.
Each joint needs to be numbered and the identifiable
records as shown in the pipe weld record sheets must
be completed and signed by the welding operator. A copy
of the records should be held by the contractor and an Butt Weld Detail Welding Parameters
additional copy submitted to the client as part of the
Quality Assurance program for each installation.
P1 P3
iii) T3 Changeover
= (160 x 0.01) + 3 = 4.6 seconds (maximum)
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 8
PE Jointing
Butt Fusion Parameter Units Value
Heater plate temperature °C 220 ± 15
Pressure value: Bead up P1 kPa 175 ± 25
Approx. bead width after bead up mm 0.5 + 0.1t
Bead up time T1 second Approx. 6t
Pressure value: Heat soak P2 kPa Drag only
Heat soak time T2 second 15t
Max changeover time T3 second 3 + 0.01D
Maximum time to achieve welding pressure T4 second 3 + 0.03D
Pressure value: Welding & Cooling P3 kPa 175 ± 25
Welding & cooling time:
SDRt<15mm
11 T5 minute SDR +110.5t
10
Welding & cooling time: t>15mm T5 minute 1.5t
Min bead width after cooling mm 3 + 0.5t
Max bead width after cooling mm 5 + 0.75t
* Drag Pressure measured for each joint must be added to give the final applied pressure, eg. P = Pi + Pd.
P = Pinterface + Pdrag
SDR 11
7.5.6 Polyethylene Fusion Jointing Compatibility
CORRECT WRONG
SDR 11
PE 100 PE 80
(a) Dissimilar materials and dissimilar wall thicknesses (d) Dissimilar wall thicknesses must not be jointed
can be jointed by electrofusion coupler by butt fusion
SDR 11 SDR 11
PE 100 PE 100
SDR 11 SDR 11
PE 100 PE 80
(c) Dissimilar materials may be jointed by butt
fusion. However, care is required to ensure a
ductile weld is produced.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 9
PE Jointing
7.5.7 Pipe Misalignment
Pipe misalignment, combined with high fusion pressure, creates an excessively sharp weld bead notch. This
can cause premature stress crack failure and reduced impact resistance. Bead removal will reveal the offset.
Re-crystallisation of melt surface, due to excess cooling before fusion gives a low bond strength brittle
region at the interface. The weld bead interface can be good, but the weld bead may be small. this causes
a joint with poor impact strength and brittleness in bending. stress crack resistance may be adequate.
FAILS ON
Interface contamination TEST
In an otherwise well-made joint, contamination (eg. from a dusty hotplate) may be retained at the interface.
Butt fusion is not fully self-cleaning. Weld bead removal will reveal a slit defect. The weld bead interface is
weak. This causes very poor properties in bending or impact when the very sharp slit crack can grow.
Pressure tests may fail to detect poor stress crack resistance.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 10
PE Jointing
Butt Weld Bead Appearance Current research shows that none of these methods
alone will fully evaluate a joint and that they need
The size, shape and surface appearance of the to be used in combination. The requirements for a
completed weld bead is good first order guide to joint will depend on the end application of the
the quality of the weld. pipeline.
The weld beads should be evenly formed around
the circumference of the pipe and be even sized on The strength of a butt weld will be less than that of
both sides of the weld line. a plain pipe section due to the interruption of the
The weld bead must project above the outside wall section due to differences in wall thickness,
diameter of the pipe at all times and be smooth and slight misalignment of the diameters and the effect
free from all voids and pitting. on the pipe material structure due to the welding
Where pitting or bubbling is observed on the weld process.
bead surfaces, the welding procedure must be
immediately stopped. This appearance is due to For pipe to pipe welding with equal wall sections, a
moisture or volatiles being present in the weld face minimum weld strength factor of 90% can be
due to moisture in the pipe materials or the heater assumed (Dedrich and Dempe Kunststoffe 1980).
plate surfaces.
a) Hydrostatic Pressure Testing
B Pressure testing the completed pipeline is routinely
adopted to detect leaks at assemblies or joints.
For PE Pressure pipelines, this is commonly
performed at a nominal test pressure of 1.3 times
the maximum working pressure in the line, for a
period of 15 minutes.
A hydrostatic pressure test of 1.3WP will only
B = 0.5 + 0.1t detect a weld with a strength of less than 70%. A
pipe tested to the maximum pressure class rating
As a general guide the minimum set-up bead will pass a weld with a strength of 50% of the
width should be a 1mm with a maximum set-up pipe strength.
bead width of 5mm. Welds of these strength levels are regarded as reject.
Hydrostatic pressure testing is not adequately
evaluate of weld strength.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 11
PE Jointing
Short term tensile testing using crosshead speeds
around 10mm per minute, are useful to detect
extremely low strength welds.
weld strength
%=
pipe strength
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 12
a
a
Mechanical Jointing
7.6 MECHANICAL JOINTS
nut or a self wedging lock onto the pipe. They are
available in pipe diameters from 20mm to 110mm.
The fittings are all demountable.
The elastomeric seal ring material requires
consideration. In addition, the temperature of the
fluids and the environment must be taken into
account. Sealing rings supplied are produced in
nitrile rubber.
Compression fittings may be assembled by directly
pushing the PE pipes into the coupling ends. When
using fittings with a compression nut care needs to
aa
a Mechanical jointing utilises compression of
elastomeric seals with the pipe being restrained with
a gripper ring, either locked by a mechanical locking
MS back-up
plates
(polyethylene
standard)
drilled table D
Stub Flanges and Backup Plates
(a) Polyethylene to Polyethylene
be taken to ensure that the nuts are not damaged
in installation. The fitting should not be disassem-
bled, loosen and insert the chamfered pipe fully
home before tightening. Only tightening by hand,
strap wrench or specialised assembly spanner.
Serrated teeth spanners, or wrenches must not be
used.
MS back-up
plate
Gasket if required
(polyethylene
standard)
drilled table D
MS flange
Table D
galvanised or specification
a
galvanised or painted
painted
Gasket
Polyethylene Stub Polyethylene Polyethylene Stub Steel pipe
flanges flange
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 13
7.7 TAPPING SYSTEMS 7.7.3 Mechanical Jointing and Service
Connections
7.7.1 General Considerations
PVC/PE pipelines may be tapped using specialist
7.7.4 Tapping Saddles
tapping saddles or tees connected to the PE main Only tapping saddles designed for use with PVC
by either thermal welding methods or compressed /PEpipe should be used. These saddles should:
rubber seals. • Be contoured to fit around the pipe and not have
Tapping systems are limited to the size of the off lugs or sharp edges that dig in.
take pipe diameter compared to the main line pipe • Have a positive stop to avoid overtightening of the
diameter and the pressure classes of the PVC/PE saddle around the pipe.
pipes used in both the service and main lines.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 14
7.7.5 Live Tapping
Various tools are available to allow live tapping of a
line using a specially adapted tapping band.
The tapping band should be fitted to the pipe and
correctly tightened. A specially adapted main cock
for live tapping should be fitted to the tapping saddle
using PTFE tape and a drilling machine fitted with
a “shell” cutter or hole saw only. The hole is drilled
and the tapping flushed. The hole saw is then with-
drawn and the main cock sealed. The tapping
machine is removed along with the hole cut out and
the main cock plunger or cap is then fitted.
Swivel Ferrule/Strap
7.7.7 Direct Tapping
Marley does not recommend direct tapping (thread-
ing of the pipe wall) for PVC/PE pressure lines.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 15
8. HANDLING & STORAGE
RETURN TO
CONTENTS
• General Principles
• Handling
• Storage
• Transport
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 1
Handling and Storage
Full colour pipes must be covered when stored in Where flanges, or other end fittings are pre assembled
direct sunlight for any extended period ( 12 months ). on the pipe ends, these must not be allowed to
Where covers are used, these should allow free air bear directly on each other, the pipe barrels, or
movement between pipe stacks to prevent directly on the ground as a point load.
temperature build up. Black pipes may be stored
for extended periods without covers. Pipe Strings
Stack sites should be selected to allow ready Where pipes are strung out along the proposed
access around, and between any stacks by pipeline alignment, they should be located at a
handling equipment and staff. Care must be taken distance to allow free access to excavation
to ensure security and site safety of any stack equipment. The pipes should be restrained to
sites. prevent any possibility of the pipes rolling.
In principle, stack heights should be kept to a
minimum. Fittings
Different grades of PE and different pressure class-
es should be segregated to prevent confusion in Fittings should be stored in original packaging until
selection at the time of installation. required for actual installation. The containers
Coiled pipes should be store flat to prevent distortion should be stored under cover at all times.
and where coils are stacked on top of each other, Large diameter fittings should be stored on an even
the maximum number of stacked coils should be base, and not subject to other loads. Fittings
limited to 5 for pipe diameters up to 32mm. 4 for should not be stacked on top of each other.
pipe diameters 50mm and 63mm and 2 for pipe End fittings, and gasket sealing surfaces must be
diameters 90mm and 110mm. protected at all times to prevent distortion, or gouging
Crated pipes may be stacked on top of each other, of the surfaces.
if the timber frames bear on each other. The All sealing gaskets and rings must be stored in light
maximum stack height under these circumstances proof containers, and kept away from heat sources
should be limited to 2 metres. and contaminants such as petrol and oils.
8.4 TRANSPORT
0.7m 2.25m 2.25m 0.8m
Where pipes are transported by road, or rail, they
Strapped timber
must be evenly supported at all times.
battens
Coiled pipes should be transported laid flat on the
bed of the tray.
For transporting, vehicles should be provided with
a clean flat bed, free from nails or other projections
which may cause damage. If high sided lorries are
used, special care must be taken to prevent
2m slippage or excessive bowing of the pipes and
max extra protection given at all sharp edges.
Coils may be stacked on top of each other, provided
that they are evenly placed on top of each other
and firmly secured to prevent movement. If coils
are transported vertically, then they must be
secured to prevent movement, and any distortion
at the bottom of the coils. Other materials must
not be placed on top of the coils.
Care should be taken to avoid positioning pipes
and fittings near or adjacent to exhaust systems or
Additional support battens other head sources and to avoid possible
contamination from materials such as diesel oil.
Straight length pipes must be stacked evenly along
Individual straight pipes may be stored in either the length of the truck trays, and evenly supported
pyramid shape stacks, or side supported stacks. using timber spacers 75mm wide, and spaced at
For pyramid stacks, the bottom pipes must be gaps of 3 metres. All end fittings must be protected
securely supported to prevent any movement. The and raised up above the tray floors, and not
pipes can then be stacked neatly on the lower layer allowed to bear directly on any pipes, or other
up to a maximum stack height of 1.5 metres. surfaces. Large diameter, or low pressure class,
Pipes should be supported with timber spacers pipes can be subject to localised distortion and
75mm wide, located at 1.5 metre gaps along the should have internal supports placed in the ends of
length of the pipes. Care must be taken to ensure the pipes.
localised distortion does not take place. The All pipes should be covered by tarpaulins during
maximum stack heights should not exceed 2 transport to prevent road film contamination, and
metres. the pipes must be kept away from all heat sources
Large diameter pipes should not be stacked on top and other sources of contamination.
of each other.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 2
a
a aaOnly webbed slings of polyethylene or nylon are
recommended. Straight pipes should be fully
supported and bound together. Pipes must not rest
on the integral socket, if one is incorporated.
When transporting fabricated fittings, these should
not be loaded in a way that could distort the end, or
left exposed to direct sunlight.
Both vertical and horizontal deliveries of coiled
pipes are permissible, although in the case of
horizontal transportation special notification may
be required for highway authorities in respect of
wide load regulations.
No other cargo, or loads, should be placed on top
of PE pipes during transport.
On-site transport
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. .
if suitably padded to protect the pipe from damage.
Care should be taken that the pipes are firmly tied
so that the sockets cannot rub together.
Pipes may be unloaded from vehicles by rolling
them gently down timbers, care being taken to
ensure that the pipes do not fall onto one another
or onto any hard or uneven surface.
8.5.3 Storage of PVC Pipes
Pipes should be given adequate support at all
times. Pipes should be stacked in layers with sockets
placed at alternate ends of the stack and with the
sockets protruding.
Horizontal support of about 75 mm wide should be
spaced not more than 1.0m centre-to-centre
beneath the pipes to provide even support. Vertical
side supports should also be provided at intervals
of 2m along rectangular pipe stacks.
For long term storage (longer than 3 months) the
maximum free height should not exceed 1.0m. The
heaviest pipes should be on the bottom. The crates
used for delivery are adequate for long term storage
provided additional bearers (approx. 75mm wide)
are placed under the pipes between the crate
frames.
If it is planned to store pipes in direct sunlight for a
period in excess of one year, then the pipes should
be covered with a material such as hessian.
Coverings such as black plastics must not be used
as these can greatly increase the temperatures
within the stack (see Weathering).
DO NOT DRAG
x 1m
3
8.6 ABOVE GROUND
INSTALLATION
(refer to AS/NZ 2566.1,
AS/NZ 2032, AS/NZ 2033)
8.6.1 General Conditions
In above ground installation, pipes should be laid on
broad, smooth bearing surfaces wherever possible
to minimise stress concentration and to prevent
physical damage e.g. cable trays.
PVC pipe should not be laid near steam lines or in
proximity to other high temperature surfaces.
Where PVC pressure pipeline is used to supply
cold water to a hot water cylinder, the last two
metres of pipe should be made of copper and a
non return valve fitted between the PVC and
copper line to prevent pipe failure.
If a pipeline is subjected to continuous vibration
such as the connection with a pump, it should be
connected by a flexible joint or, if possible, the
system should be redesigned to eliminate the
vibration.
PVC pipe must not be used to reticulate
compressed air.
The pipe must be adequately supported in order to
prevent sagging and excessive distortion. Clamp,
saddle, angle, spring or other standard types of
supports and hangers may be used where necessary.
Pipe hangers should not be over tightened. Metal
surfaces should be insulated from the pipe by plastic
coating, wrapping or other means.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 4
9. TESTING
& COMMISSIONING
RETURN TO
• PVC Pipeline Testing CONTENTS
Flushing
Following successful testing, the line should be
thoroughly flushed and dosed with a sterilising
agent such as chlorine. Local authority requirements
should be followed.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 1
Testing and Commissioning
Polyethylene Pipeline Testing . . .. . .. . . . .. . .
9.1 INTRODUCTION 9.2 PRE TESTING
All completed PE pipelines should be tested to CONSIDERATIONS
ensure that all joints, fittings, anchorage blocks are
installed correctly and that there are no defects in Prior to carrying out any testing activities, a number
the pipes causing leakage or loss of fluid. of precautions need to be observed.
The actual testing procedures to be adopted will • All facilities must be available and sufficient
vary on the actual application of each pipeline and notice given to relevant Local Authority to allow
the specific requirements laid down by the relevant compliance inspection prior to any testing being
Local Authority in tender contract documents. carried out.
The local authority specifications must be
followed at all times. • All residential construction materials must be
removed from the trench or embankment,
No air
alignments so that no additional materials are in
B Increasing volume of air direct contact with the PE pipes or fittings.
P There should be no point loading on fittings.
C D
eg 5% eg 10%
E • PE pipelines must be supported by either back-
eg 15% filling with soil or loaded with sandbags to pre-
Pressur(bar)
vent movement and possible mechanical seal
joint displacement. Where PE pipes are partially
backfilled over the entire length, leaving open
only the joints at the start and end of the pipe run.
• Where cast insitu concrete thrust blocks are
used, a minimum period of 7 days should be
A allowed before testing. Where timber or moulded
V
Water volume (litres)
blocks are used then testing can start as soon as
(directly related to time for constant rate pumping) required. All blanked off ends, including valves,
must be fully supported.
Typical Pressure/volume characteristic
during pressurisation • All intermediate valves should be opened to
allow full venting of entrapped air form the PE
pipeline.
The introduction of the PE63, PE80 and PE100 rating
systems in AS/SNZ 4130 and the modification to • Where water is used as the test fluid, then PE
the applied design factor applied to calculate each pipeline testing should not be performed in wet
of the pressure class wall thicknesses, has resulted weather, unless any potential leakage can be
in reduced pipe wall section thicknesses, when readily observed on site.
compared to the previous AS1159. This means
that the hydrostatic test pressure applied for • Where thermal fusion joints are used in the PE
pressure pipes must also be reduced from the pipeline, no testing should proceed until the last
previous values applied to AS 1159 pipes. joint made has completely cooled to ambient
All PE materials listed in AS/NZS 4130 behave in temperature.
an elastic manner when internally pressure tested
and this shows up as an apparent pressure loss, or
lead on the test recording gauge due to the
9.3 PE PRESSURE
increase in pipe volume as the pipeline expands. PIPELINE TESTING
This means that, as distinct from rigid pipeline
PE pipelines may be tested as a single section for
materials, a makeup volume of water may be needed
lengths up to 800 metres, depending on the size of
to be added to the pipeline during the test period to
the pipe and the availability of test water. Beyond
maintain a constant pressure reading. PE
this length, the pipeline should be progressively
pipelines subjected to extended periods of high test
tested in sections.
pressure may also creep over the test period
The test section must be swabbed and flushed
and this may show up as a drop in the pressure
clean before introducing test water. The test water
readings.
should be introduced at the lowest available point
Neither of these observations means that a leak is
to assist air venting and all air vent valves opened.
present in the pipeline.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 2
Testing and Commissioning
As PE pipes are subject to thermal expansion until a test pressure of 50 KPa is reached on a
and contraction the testing should take place at recording gauge fitted to the pipeline. The test
ambient temperature and the water should be pressure of 50 KPa must be maintained for a minimum
introduced and the pipeline kept full of water (but time of 3 minutes and if no leaks are detected or
not under pressure) for 12 hours where elevated pressure loss is observed on the gauge, then the
temperatures are encountered. Where pipes are at air supply control valve should be turned off.
ambient temperature testing may commence as The pressure should be held for a minimum time of
soon as required. 1 minute and if the gauge pressure reading has not
Pressure test gauges or recording devices should fallen below 35 KPa after this time then the test
be placed at the lowest elevation point accessible pressure should be released.
in the pipeline. When the test pressure drops below 35 KPa after
The test water should be fed into the pipeline evenly 1 minute, then the pressure should be returned to
and without pulsation up to the nominated test 50 KPa and this pressure maintained until a full
pressure value. The actual test pressures adopted inspection of the PE pipeline has been completed.
may vary depending on the Local Authority All joints and connections need to be individually
requirements and these must be adhered to at all inspected for leakage and a solution of water and
times. detergent should be poured over any suspect joint.
For small diameter PE pipelines (up to 110mm If a leak is present, it will cause the detergent
diameter) a test pressure of a maximum of 1.2 WP solution to bubble and foam.
(working pressure) may be applied for a period of The test must be accepted by the relevant Local
15 minutes or for sufficient time to allow the Authority representative before completing the
pipeline to be inspected for leakage at all joints. testing.
The same procedures may be adopted for small
length additions to existing pipelines. The pressure 9.3.2 Deflection Testing
gauge reading should not drop once the pressure PE drainage pipelines are designed to support
has stabilised. external loading within the acceptable limits of
For PE pipe property service connections using diameter deflection (or ovality) for hydraulic or
PN16 class PE pipe, a standard test pressure of structural reasons.
1.5 MPa may be applied uniformly for all applications. Where this is a critical feature of the installation,
For large diameter PE pipelines and for pipeline then the effectiveness of the backfill compaction
lengths up to 800 metres, the volume change in the may require testing.
pipes under the action of the test pressure needs to In these cases a presized plug, or proving tool can
be evaluated. Pipes should be brought up to test be pulled through the pipeline between manholes
pressure and the pressure stabilised by introducing or other entry points.
make up water. For flanged, electrofusion or mechanically jointed
A test pressure of a maximum of 1.25 times WP PE pipelines without any protrusions into the pipe
(working pressure) may be applied for a period of bore due to the joints, the plug can be sized to the
up to 8 hours, or for sufficient time to inspect all maximum diameter reduction allowed in the
joints and connections for signs of leakage. design.
Pressure gauge readings should be taken at regular For butt welded PE pipes, unless the internal
time intervals during the test period to ensure that beads are removed, the plug needs to be sized to
leakage does not take place. account for the weld bead presence.
High pressure testing using air must not be In either case, the plug should be able to be pulled
carried out. completely through the PE pipeline.
The following are identified as contributing factors 9.4 GAS PIPE TESTING
to variations in the pressure test results: For gas pipe installations, testing should not proceed
until the last completed fusion joint has had
• length of the test section adequate time to fully cool to ambient temperature.
• diameter of the pipe Hydrostatic pressure testing may be carried out
• temperature changes using inert liquid (such as water), air or an inert gas
• range of test pressure imposed approved by the utility.
• rate of pressure loading Test pressure such as TP = 1.10 x WP may be
• presence of air in the pipeline applied for pipelines provided that the test pressure
• relative movement of ‘mechanical’ fittings is not less than 100 KPa and does not exceed 1.5
• efficiency of the bedding and compacted times the design pressure of the pipeline system.
surround to resist pipe movement. For larger diameter or longer pipelines, progressive
• accuracy and efficiency of testing apparatus. testing may be applied such that:
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 3
Testing and Commissioning
Final testing may be applied or required by the utility 9.6.1
after progressive test in the form of:
Take a first reading of pressure P1 at t1, where t1 is
Test Device Test Pressure Test Duration equal to the pressure loading time (tL).
Dial gauge 700 KPa 24 hours, no drop 9.6.2
Recorder 700 KPa 24 hours, no drop
Take a second reading of Pressure P2, at a time
approximately 7tL; Let this be t2.
9.5 PRESSURE TEST
To allow for the stress relaxation behavior of PE
9.5.1 Large Bore Commissioning pipelines, calculate the corrected values of t1 and t2.
On reaching the test pressure and satisfying the
condition for minimal air entrapment, the pipeline is • calculate corrected t1
isolated and the pressure allowed to decay. The t1c = t1 + 0.4tL
pressure decay readings (tL) to achieve test pres-
sure is used as a reference. The natural pressure • calculate corrected t2
decay readings at predetermined times are then t2c = t2 + 0.4tL
recorded in minutes from the movement of valve
closure. 9.6.3
The analysis will be more comprehensive with larg- The measure of the slope of the pressure decay
er numbers of readings being taken throughout the curve between t1 and t2 is then calculated as the
test. ratio n1.
Since the pipeline begins to relax within the period
of pressurisation, a correction factor has to be log P1 - log P2
Calculate n1
applied to allow for this. Experience suggests that log t2c - log t1c
this correction should be 0.4tL.
A typical sequence of readings is illustrated below. For a sound main, experience suggests that the
ratio n1 should be;
Test pressure reached.
Valve closed.
Recording starts.
a) 0.08 – 0.10 for pipes without constraint
(eg sliplined or not backfilled).
P1
P2
b) 0.04 – 0.05 for pipes with compacted backfill.
Peak test
pressure P3
Logarithmic decay curve Bearing in mind the identified compaction , if the
values are significantly less than the minimum
identified, then there is too great a volume of air in
Pressure
(bar) the main. This air will have to be removed before
a satisfactory test can be performed.
9.6.4
Starting t
1
t
2
t
3 Take a further reading of pressure P3 at a decay
pressure
Time (not to scale)
time not less than 15tL. Let this be t3. Again to
Reading 1
tL tL
approx. 7tL
allow for the stress relaxation behavior of PE
Pressure Reading 2 pipelines, calculate the correct value for t3.
loading time
At least 15tL
Reading 3
T3c = t3 + 0.4tL
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 4
Testing and Commissioning
The figure below shows the results of test (using 9.7.2
graphical analysis with multiple results from a data
logger) on mains without leaks in unconstrained The predicted pressure can be calculated from
and constrained situations respectively.
[ ( ) ]
The sensitivity of the test can be increased by t -n
P = PL 2.5 +1
extending the value of t3 ie extending the test duration. tL
9.6.6 Where
P = predicted pressure at time t
The procedure detailed above identifies the principle.
PL = test pressure (at start of test when the
However it is strongly advised that the slopes n1
test pressure is first reached)
and n2 are obtained from more than three points.
t = time (from reaching the test pressure)
tL = loading time
PRESSURE REGRESSION
From experience it has been shown that:
- Unrestrained
For pipes installed in compacted soil n = 0.04
10.0 For pipes installed without support n = 0.10
9.5 9.7.3
9.0 Slope = 0.084 (i.e. no leakage
If the actual pressure recorded was found to differ
Pressure (bar)
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 5
Testing and Commissioning
9.8 COMMISSIONING
PE pipelines should be commissioned following the
standard practices adopted by the relevant Local
Authority.
This applies for both pressure and non pressure
applications.
In the case of potable water applications, the
standard flushing and disinfection procedures
must be followed. PE pipes made to AS/NZ 4130
do not impart additional water quality flushing or
disinfection requirements due to corrosion
products, heavy metal update, or pH change, and
where these aspects have been included in standard
commissioning procedures, then consideration
should be given to the need for these elements.
Trace Wires
Pipes deeper than 600mm may be detected by the
use of tracer wires placed underneath the pipeline.
Application of a suppressed current allows the
detection of pipes up to 3 metres depth. However,
both ends of the wire must be accessible and a
complete circuit must be available without breakage
of the wire over the length of the pipeline.
Audio Detection
Several types of acoustic detectors are available
using either the sound of turbulence from flow in
the line or by the introduction of an outside sound
source.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . 6
10. CHEMICAL RESISTANCE
RETURN TO
CONTENTS
Chemical Resistance
S E C T I O N 1 1 : C H E M I C A L R E S I S TA N C E
. . .. . .. . . . .. . .. . . . .. . .. . . .
Three different classes of chemical resistance degree are conventionally used in this guide ie:
Class 1: HIGH RESISTANCE (corrosion-proof) - all materials belonging to this
class are completely or almost completely corrosion-proof against the
conveyed fluid, according to the specified operating conditions.
Class 2: LIMITED RESISTANCE - the materials belonging to this class are partially
attacked by the conveyed chemical compound. The average life of the
material is therefore shorter, and it is advisable to use a higher safety factor
by selecting a higher SN rating pipe.
Class 3: NO RESISTANCE - all material belonging to this class are subject to
corrosion by the conveyed fluid and they should therefore not be used.
The absence of any class indication means that no data are available concerning the
chemical resistance of the material in respect of the conveyed fluid.
ABBREVIATIONS
sat = saturated solution at 20oC, nd = undefined concentration,
deb = weak concentration, comm = commercial solution. dil = diluted solution
FORMULA CONC % TEMP (oC) PVC PE FORMULA CONC % TEMP (oC) PVC PE
ACETALDEHYDE CH3CHO 100 25 3 1 - FLUORIDE NH4F 25 25 1 1
60 3 60 2 1
- AQUEOUS SOLUTION 40 25 3 1 - HYDROXIDE NH4OH 28 25 - 1
60 3 2 60 2 1
ACETIC ACID CH3COOH ≤ 25 25 1 1 - NITRATE NH4NO3 sat 25 1 1
60 2 1 60 1 1
30 25 1 1
60 2 1 - PHOSPHATE DIBASIC NH4(HPO4)2 all 25 1 1
60 25 1 1 60 1 1
60 2 1 - PHOSPHAT META (NH4)4P4O12 all 25 1
80 25 1 1 60 1
60 2
- PHOSPHATE TRI (NH4)2HPO4 all 25 1
- GLACIAL 100 25 2 1 60 1
60 3 2
- PERSULFATE (NH4)2S2O8 all 25 1
ACETIC ANHYDRIDE (CH3CO)2O 100 25 3 2 60 1
60 3 2
- SULFIDE (NH4)2S deb 25 1 1
ACETONE CH3COCH3 10 25 3 1
60 2 1
(DIMETHYL KETONE) 60 3
sat 25 1 1
100 25 3 2
60 1 1
60 3 2
ACETOPHENONE CH3COC6H5 nd 25 - SULFHYDRATE NH4OHSO4 dil 25 1 1
(ACETYLBENZENE OR 60 60 2 1
sat 25 1 1
PHENYL METHYL KETONE)
60 1 1
ACRYLONITRILE CH2CHCN technically 25 1
AMYLACETATE CH3CO2CH2(CH2)3CH3 100 25 3 1
(ACRYLONITRILE pure 60 3 1
(PENTYL ACETATE) 60 3 2
OR VINYL CYANIDE)
AMYLALCOHOL CH3(CH2)3CH2OH nd 25 1 1
ADIPIC ACID (CH2CH2CO2H)2 sat. 25 1 1 60 2 1
AQUEOUS SOLUTION 60 2 1
ALNILINE C6H5HN2 all 25 3 2
ALLYL ALCOHOL CH2CHCH2OH 96 25 2 1 (PHENYLAMINE 60 3 2
60 3 2
OR AMINOBENZENE)
ALUM AI2(SO4)3K2SO4nH2O dil 25 1 1
- CHLORHYDRATE CH6H5NH2HCI nd 25 2 2
AQUEOUS SOLUTION dil 60 2 1
(ANILINE HYDROCHLORIDE) 60 3 2
(POTASH ALUM.SOL.) sat. 60 2 1
ANTIMONY SbCI3 100 25 1 1
ALUMINIUM AICI3 all 25 1 1
- TRICHLORIDE 60 1 1
- CHLORIDE 60 1 1
ANTHRAQUINONE suspension 25 1 1
- FLORIDE AIF3 100 25 1 1 (SULFONIC ACID) 60 2 -
60 1 1
AQUA REGIA HCI+HNO3 100 25 2 3
- HYDROXIDE AI(OH)3 all 25 1 60 2 3
60 1 -
ARSENIC ACID H3ASO4 deb 25 1 1
NITRATE AI(NO2)3 nd 25 1
60 2 1
60 1 -
80 25 1 1
SULFATE AI(SO4)3 deb 25 1
60 1 1 60 2 1
sat 25 1 1 BARIUM BACO3 all 25 1 1
60 1 1 CARBONATE 60 1 1
AMMONIA NH3 deb 25 1 1 - CHLORIDE BaCI2 10 25 1 1
- AQUEOUS SOLUTION 60 2 1 60 1 1
sat 25 1 - HYDROXIDE Ba(OH)2 all 25 1 1
60 2 60 1 1
- DRY GAS 100 25 1 1
- SULFATE BaSO4 nb 25 1 1
60 1 1
60 1 1
- LIQUID 100 25 2 1
60 3 1 - SULFIDE BaS sat 25 1
AMMONIUM CH3COONH4 sat 25 - 1 60 1
- ACETATE 60 2 1 BEER comm 25 1 1
- CARBONATE (NH4)2CO3 all 25 1 1 60 1
60 2 1
BENZALDEHYDE C6H5CHO nd 25 3 2
60 3 2
.48. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Chemical Resistance
FORMULA CONC % TEMP (oC) PVC PE FORMULA CONC % TEMP (oC) PVC PE
BENZENE (BENZOL) C6H6 100 25 3 3 CHLORAMINE NH2Cl dil 25 1 1
60 3 60
- + LIGROIN 20/80 25 3 CHLORIC ACID HCIO3 20 25 1 1
60 3 60 2 3
- MONOCHLORINE C6H3CI technically 25 3 2 CHLORINE CI2 sat 25 2
pure 60 60 3
BENZOIC ACID C6H5COOH sat 25 1 1 - DRY GAS 10 25 1
60 2 1 60 2
100 25 2
BENZYL ALCOHOL C6H5CH2OH 100 25 1 60 3
60 2
- WET GAS 5 g/m3 25 1
BORIC ACID H3BO3 deb 25 1 1 60 3
(BORACIC ACID) 60 2 1 10 g/m3 25 2 2
sat 25 1 1 60 2
60 2 1 66 g/m3 25 2 2
BRINE comm 25 1 60 2
60 1
- LIQUID 100 25 3 3
BROMIC ACID HBrO3 10 25 1 1 60
60 1 1
CHLOROACETIC CICH2COH 85 25 1 2
BROMINE Br2 100 25 3 3 ACID 60 2 3
- LIQUID 60 3 3 100 25 1 3
- VAPOURS low 25 2 3 60 2 3
60 3
CHLOROBENZENE C6H5CI all 25 3
BUTADIENE C4H6 100 25 1 60 3
60 1 3
CHLOROFORM CHCI3 all 25 3 2
BUTANEDIOL CH3CH2CHOHCH2OH 10 25 1 60 3
AQUEOUS 60 3
concentrated 25 2 2 CHLOROSULPHONIC CIHSO3 100 25 2 3
60 3 3 ACID 60 3 3
BUTANE C4H10 10 25 1 1 CHROME ALUM KCr(SO4)2 nd 25 1 1
GAS 60 1 60 2 1
BUTYL CH3CO2CH2CH2CH2 CH3 100 25 3 3 CHROMIC ACID CrO3+H2O 10 25 1 2
- ACETATE (BUTANATE) 60 3 3 60 2 3
30 25 1 2
- ALCOHOL (BUTANOL) C4H9OH 25 1 1 60 2 3
60 2 1 50 25 1 2
- PHENOL C4H9C6H4OH 100 25 2 3 60 2 3
60 2 3 CHROMIC SOLUTION CrO3+H2O+H2SO4 50/35/15 25 1 3
BUTYLENE C4H6(OH)2 100 25 1 60 2 3
GLYCOL 60 2 1 CITRIC ACID C3H4(OH)(CO2H)3 50 25 1 1
BUTYRIC ACID C2H5CH2COOH 20 25 1 1 AQ.SOL.min. 60 1 1
(BUTANOIC ACID) 60 2 2 COPPER CuCI2 sat 25 1 1
concentrated 25 3 3 - CHLORIDE 60 1 1
60 3 3 - CYANIDE CuCN2 all 25 3
CALCIUM Ca(HSO3)2 nd 25 1 1 60 3
- BISULFITE 60 1 1 - FLUORIDE CuF2 all 25 1 1
- CARBONATE CaCO3 all 25 1 1 60 1 1
60 1 1 - NITRATE Cu(NO3)2 nd 25 1 1
-CHLORATE CaHCI nd 25 1 1 60 2 1
60 1 1 - SULFATE CuSO4 dil 25 1 1
- CHLORIDE CaCl2 all 25 1 1 60 1 1
60 2 1 sat 25 1 1
- HYDROXIDE Ca(OH)2 all 25 1 60 1 1
60 1 COTTONSEED OIL comm 25 1
60 1
- HYPOCHLORITE Ca(OHI)2 sat 25 1
60 2 1 CRESOL CH3C6H4OH ≤90 25 2 1
(HYDROXY TOLUENE) 60 3
- NITRATE Ca(NO3)2 50 25 1 1 ≥90 25 3
60 1 60 3
- SULFATE CaSO4 nd 25 1 1 CRESYLIC ACID CH3CH6H4COOH 50 25 2
60 1 1 60 3
- SULFIDE CaS sat 25 1 2 CYCLOHEXANE C6H12 all 25 3 1
60 1 2 60 3
CAMPHOR OIL nd 25 1 3 CYCLOHEXANONE C6H10O all 25 3 1
60 3 60 3
CARBON CO2 - 25 1 1 DECAHYDRONAFTALENE C10H18 nd 25 1 1
- DIOXIDE AQUEOUS SOLUTION 60 2 1 60 1 2
- GAS 100 25 1 1 DEMINERALIZED 100 25 1 1
60 1 1 WATER 60 1 1
- DISULFIDE CS2 100 25 2 2 DIBUTYPATHALATE C6H4(CO2C4H9)2 100 25 3 3
60 3 60 3
DICHLORO- Cl2CHCOOH 100 25 1 1
- MONOXIDE CO 100 25 1 1 ACETIC ACID 60 2 2
60 1 1
DICHLOROETHANE CH2CICH2CI 100 25 3 3
- TETRACHLORIDE CCI4 100 25 2 2 (ETHYLENE DICHLORIDE) 60 3 3
60 3 3 DICHLOROETHYLENE CI(CH)2CI 100 25 3 3
CARBONIC ACID H2CO3 sat 25 1 60 3 3
- AQUEOUS SOLUTION 60 1
DIETHYL ETHER C2H5OC2H5 100 25 3 3
- DRY 100 25 1 60 3 3
60 1 DIGLYCOLIC ACID (CH2)2O(CO2H)2 18 25 1 1
- WET all 25 1 60 2 1
60 2 DIMETHYLAMINE (CH3)2NH 100 25 2
CARBON OIL comm 25 1 60 3 2
60 1
2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49. .
Chemical Resistance
FORMULA CONC % TEMP (oC) PVC PE FORMULA CONC % TEMP (oC) PVC PE
DIOCTYLPHTHALATE all 25 3 1 HYDROCHLORIC ACID HCI ≤25 25 1 1
60 3 2 (MURIATIC ACID) 60 2 1
DISTILLED WATER 100 25 1 1 ≤ 37 25 1 1
60 1 1 60 1 2
DRINKING WATER 100 25 1 1 HYDROCYANIC ACID HCN deb 25 1 1
60 1 1 (PRUSSIC ACID OR 60 1 1
ETHERS all 25 3 HYDROGEN CYANIDE)
60 3 HYDROFLUORIC ACID HF 10 25 1 1
ETHYL CH3CO2C2H5 100 25 3 1 60 2 1
- ACETATE (ACETIC ETHER) 60 3 3 HYDROGEN H2 all 25
- ALCOHOL CH3CH2OH nd 25 1 1 60
60 2 2 HYDROGEN H2O2 30 25 1 1
- PEROXIDE (BLEACH) 60 1 1
(ETHANOL) CH3CH2CI all 25 3 2 50 25 1 2
- CHLORIDE 60 3 60 1 -
- ETHER CH3CH2OCH2CH3 all 25 3 - SULFIDE DRY sat 25 1 1
60 3 60 2 1
ETHYLENE CICH2CH2OH 100 25 3
- CHLOROHYDRIN 60 3 - SULFIDE WET sat 25 1 1
60 2 1
- GLYCOL HOCH2CH2OH comm 25 1 1 HYDROSUPHITE ≤10 25 1
(ETHANEDIOL OR GLYCOL) 60 1 3 60 2
FATTY ACIDS nd 25 1 HYDROXYLAMINE (H2NOH)2H2SO4 12 25 1 1
60 1 SULPHATE 60 1
FERRIC FeCI3 10 25 1 ILLUMINATING 100 25 1 1
- CHLORIDE 60 2 GAS 60
sat 25 1 1 IODINE I2 3 25 2
60 1 1 - DRY AND WET 60 3
- NITRATE Fe(NO3)3 nd 25 1 1 - TINCTURE ≤3 25 2 2
60 1 1 60 3 3
- DEXTRINE (BRITISH GUM C6H12OCH2O nd 25 1 1 ISOCTANE C8H18 100 25 1 2
OR STARCH GUM) 60 2 1 60
- SULFATE Fe(SO4)3 nd 25 1 1 ISO-OCTANE (CH3)3CCH2(CH3)2
60 1 1 ISOPROPYL (CH3)2CHOCH(CH3)2 100 25 2 2
FERROUS FeCI2 sat 25 1 1 -ETHER 60 3 3
- CHLORIDE 60 1 1 - ALCOHOL (CH3)2CHOH 100 25
- SULFATE FeSO4 nd 25 1 1 (ISOPROPANOL) 60 2
60 1 1 LACTIC ACID CH3COHCOOH ≤28 25 1 1
FERTILIZER ≤ 10 25 1 1 60 2 1
60 1 1 LANOLINE nd 25 1
sat 25 1 1 60 2 1
60 1 1 LEAD ACETATE Pb(CH3COO)2 sat 25 1 1
FLUORINE GAS F2 100 25 2 2 60 1 -
DRY 60 3 3 LINSEED OIL comm 25 1
FLUROSILICIC ACID H2SiF6 32 25 1 1 60 2 2
60 1 1 LUBRICATING OILS comm 25 1 3
FORMALDEHYDE HCOH - 25 1 1 60 1
60 2 1 MAGNESIUM MgCO3 all 25 1
FORMIC ACID HCOOH 50 25 1 1 - CARBONATE 60 1
60 2 1
100 25 1 1 - CHLORIDE MgCI2 sat 25 1 1
60 3 1 60 1 1
FRUIT PULP AND JUICE comm 25 1 1 - HYDROXIDE Mg(OH)2 all 25 1
60 1 60 1
FUEL OIL 100 25 1 -NITRATE MgNO3 nd 25 1 1
60 1 60 1 1
comm 25 1 - - SULFATE MgSO4 dil 25 1 1
60 1 2 60 1 1
FURFUROLE C5H3OCH2OH nd 25 3 2 sat 25 1 1
ALCOHOL 60 3 2 60 1 1
GAS EXHAUST all 25 1 MALEIC ACID COOHCHCHCOOH nd 25 1 1
- ACID 60 1 60 1 1
- WITH NITROUS traces 25 1 1 MALIC ACID CH2CHOH(COOH)2 nd 25 1 1
- VAPOURS 60 1 1 (HYDROXYSUCCINIC ACID) 60 - -
GAS PHOSGENE CICOCI 100 25 1 2 MERCURIC HgCI2 sat 25 1 1
60 2 2 - CHLORIDE 60 1 1
GELATINE 100 25 1 1 - CYANIDE HgCN2 all 25 1
60 1 - 60 1
GLUCOSE C6H12O6 all 25 1 1 MERCUROUS HgNO3 nd 25 1 1
(DEXTROSE) 60 2 1 NITRATE 60 1 1
GLYCERINE HOCH2CHOHCH2OH all 25 1 1 MERCURY Hg 100 25 1 1
AQ.SOL(GLYCEROL) 60 1 1 60 2 1
GLYCOGLUE 10 25 1 1 METHYL CH3COOCH3 100 25 - -
AQUEOUS 60 1 1 - ACETATE 60 - -
GLYCOLIC ACID HOCH2COOH 37 25 1 1 - ALCOHOL (METHANOL CH3OH nd 25 1
60 1 1 OR WOODSPIRIT) 60 1 1
HEPTANE C7H16 100 25 1 1
60 2 3 - BROMIDE CH3Br 100 25 3 3
(BROMOMETHANE) 60
HEXANE C6H14 100 25 1 1
60 2 2 - CHORIDE CH3CI 100 25 3 1
(CHLOROMETHANE) 60 3
HYDROBROMIC ACID HBr ≤10 25 1 1
60 2 1 - ETHYLKETONE CH3COCH2CH3 all 25 3 1
48 25 1 1 60 3 2
60 2 1 METHYLAMINE CH3NH2 32 25 2 1
60 3 2
.50. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Chemical Resistance
FORMULA CONC % TEMP (oC) PVC PE FORMULA CONC % TEMP (oC) PVC PE
METHYLENE CHLORIDE CH2CI2 100 25 3 3 ≤85 25 1 1
(DICHLOROMETHANE) 60 3 60 1 2
METHYL SULPHORIC ACID CH3COOSO4 50 25 1 2 - ANHYDRIDE P2O5 nd 25 1 1
60 2 2 60 2 1
100 25 1 3 PHOSPHORUS PCI3 100 25 3 1
60 2 3 TRICHLORIDE 60 3
MILK 100 25 1 1 PHOTOGRAPHIC comm 25 1
60 1 - DEVELOPER 60 1
MINERAL ACIDOULOUS nd 25 1 1 - EMULSION comm 25 1 1
WATER 60 1 1 60 1
MOLASSES comm 25 1 1 PHTHALIC ACID C6H4(CO2H)2 50 25 - 1
60 2 2 60 3 1
NAPHTA 100 25 2 2 PICRIC ACID HOC6H2(NO2)3 1 25 1 1
60 3 3 60 1 -
NAPHTALINE 100 25 1 1
60 2 (2,4,6 TRINITROPENOL) ≥1 25 3 1
60 3
NICKEL NiCI3 all 25 1 1
- CHLORIDE 60 1 1 POTASSIUM K2Cr2O7 40 25 1 1
- BICHROMATE (POTASSIUM 60 1
- NITRATE Ni(NO3)2 nd 25 1 1 HYDROGENCARBONATE)
60 1 1
- BORATE K3BO3 sat 25 1
- SULFATE NiSO4 dil 25 1 1 60 2
60 1 2
sat 25 1 1 - BROMATE KBrO3 nd 25 1
60 1 1 60 2
NITRIC ACID HNO3 anhydrous 25 3 - BROMIDEKBr sat 25 1 1
60 3 60 1
20 25 1 1 - CARBONATE (POTASH) K2CO3 sat 25 1 1
60 2 2 60 1 1
40 25 1 -
60 1 2 - CHROLIDE KCI sat 25 1 1
60 25 1 3 (POTASSIUM MURIATE) 60 1 1
60 2 3 - CHROMATE K2CrO4 40 25 1 1
98 25 3 3 60 1 1
60 3 3 - CYANIDE KCN sat 25 1 1
NITROBENZENE C6H5NO2 all 25 3
60 3 2 60 1 1
OLEIC ACID C8H17CHCH(CH2)7CO2H comm 25 1 - - FERROCYANIDE K4Fe(CN)63H2O 100 25 1 1
60 1 2 60 1 1
OLEUM (FUMING SULPHURIC) H2S2O7 nd 25 3 - FLUORIDE KF sat 25 1
ACID OR PYROSULPHURIC ACID) 60 3 3 60 1
- VAPOURS low 25 3 - HYDROXIDE KOH ≤60 25 1 1
60 3 (CAUSTIC POTASH) 60 2 1
high 25 3
- NITRATE KNO3 sat 25 1 1
60 3
(NITRE, SALTPETRE) 60 1 1
OLIVE OIL comm 25
- PERBORATE KBO3 all 25 1
60 2 3
60 1
OXALIC ACID HO2CCO2H 10 25 1 1
60 2 1 - PERBORATE KBO3 all 25 1
sat 25 1 1 60
60 1 1 - PERMANGANATE KMnO4 10 25 1 1
OXYGEN O2 all 25 1 1 (PERMANGANATE OF POTASH) 60 1 1
60 1 2 - PERSULFATE K2S2O8 nd 25 1 1
OZONE O3 nd 25 1 2 60 2 1
60 2 3
- SULFATE K2SO4 sat 25 1 1
PALMITIC ACID CH3(CH2)14COOH 10 25 1 - 60 2 1
60 1
PROPANE C3H8 100 25 1 1
70 25 1 -
- GAS 60
60 1
PARAFFIN (ALKANE) nd 25 - LIQUID 100 25 1 2
60 2 2 60
PROPYL ALCOHOL C3H7OH 100 25 1 1
- EMULSION comm 25 1 2
(PROPANOL) 60 2 1
60 1 2
PYRIDINE CH(CHCH)2N nd 25 3 1
- OIL (KEROSENE) nd 25 1 60 3 2
60 1
RAIN WATER 100 25 1 1
PERCHLORIC HCIO4 100 25 1 1 60 1 1
ACID 60 2 1
SEA WATER 100 25 1 1
70 25 1 1
60 1 1
60 2 2
SILICIC ACID H2SiO3 all 25 1 1
PETROL 100 25 1
60 1 1
- REFINED 60 1
SILICONE OIL nd 25 1 1
- UNREFINED 100 25 1 60 3 2
60 1
SILVER AgCN all 25 1
PHENOL C6H5OH 1 25 1 1 - CYANIDE 60 1
- AQUEOUS SOLUTION 60
- NITRATE AgNO3 nd 25 1 1
(CARBOLIC ACID) ≤90 25 2 1 60 2 1
60 3
- PLATING SOLUTION comm 25 1
PHENYL HYDRAZINE C6H5NHNH2 all 25 3 2 60 1
60 3 2
SOAP high 25 1
- CHLORHYDRATE C6H5NHNH3CI sat 25 1 1 - AQUEOUS SOLUTION 60 2
60 3 3 SODIC LYE ≤60 25 1
PHOSPHORIC H3PO4 ≤ 25 25 1 1 60 1
- ACID 60 2 1 SODIUM CH3COONa 100 25 1 1
≤50 25 1 1 - ACETATE 60 1 1
60
4 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51. .
Chemical Resistance
FORMULA CONC % TEMP (oC) PVC PE FORMULA CONC % TEMP (oC) PVC PE
- BICARBONATE (SODIUM NaHCO3 nd 25 1 1 60 3 2
HYDROGEN CARBONATE) 60 1 1
- FUMING (OLEUM) all 25 2
- BISULFITE NaHSO3 100 25 1 1 60 3
60 1 1
- NITRIC H2SO4+HNO3+H2O 48/49/3 25 1 3
- BROMIDE NaBr sat 25 1
AQUEOUS SOLUTION 60 2 3
60 1
50/50/0 25 2 3
- CARBONATE Na2CO3 sat 25 1 1 60 3 3
60 1 1 10/20/70 25 1 2
- CHLORATE NaCIO3 nd 25 1 1 60 1 2
60 2 1 TALLOW EMULSION comm 25 1 1
60 1 2
- CHLORIDE NaCI dil 25 1 1
60 2 1 TANNIC ACID C14H10O9 10 25 1 1
sat 25 1 1 60 1 1
60 1 1 TARTARIC ACID HOOC(CHOH)2COOH all 25 1 1
60 2 1
- CYANIDE NaCN all 25 1
60 1 TETRACHLORO CHCI2CHCI2 nd 25 3 2
- ETHANE 60 3 3
- FERROCYANIDE Na4Fe(CN)6 sat 25 1 1
60 1 1 - ETHYLENE CCI2CCI2 nd 25 3 2
(PERCHLOROETHYLENE) 60 3 3
- FLUORIDE NaF all 25 1 1 TETRAETHYLLEAD Pb(C2H5)4 100 25 1 1
60 1 1 60 2
- HYDROXIDE NaOH 60 25 1 1 TETRAHYDROFURAN C4H8O all 25 3 2
60 1 1 60 3 3
- HYPOCHLORITE NaOCI deb 25 1 1 THIONYL CHLORIDE SOCI3 - 25 3 3
60 2 60
- HYPOSULFITE Na2S3O3 nd 25 1 THIOPHENE C4H4S 100 25 3 2
60 1 60 3 2
- NITRATE NaNO3 nd 25 1 1 TOLUENE C6H5CH3 100 25 3 2
60 1 1 60 3 3
- PERBORATE NaBO3H2O all 25 1 TRANSFORMER OIL nd 25 1 1
60 1 60 2 2
TRICHLORO- CCI3COOH ≤50 25 1 1
- PHOSPHATE di Na2HPO4 all 25 1 ACETIC ACID 60 3 2
60 1
TRICHLOROETHYLENE CI2CCHCI 100 25 3 2
- PHOSPHATE tri Na3PO4 all 25 1 1 60 3 2
60 1 1 TRIETHANOLAMINE N(CH2CH2OH)2 100 25 2 1
- SULPHATE Na2SO4 dil 25 1 60 3
60 1 TURPENTINE 100 25 2 2
sat 25 1 1 60 2 3
60 1 1 UREA CO(NH2)2 ≤ 10 25 1 1
- SULFIDE Na2S dil 25 1 1 AQUEOUS SOLUTION 60 2 1
60 2 1 33 25 1 1
sat 25 1 1 60 2 1
60 1 1 URINE nd 25 1 1
60 2 1
- SULFITE NaSO3 sat 25 1
60 1 URIC ACID C5H4N4O3 10 25 1
60 2
STANNIC CHLORIDE SnCI4 sat 25 1 1
60 1 1 VASELINE OIL 100 25 1 1
60 3 2
STANNOUS CHLORIDE SnCI2 dil 25 1 1
60 1 1 VINYL ACETATE CH3CO2CHCH2 100 25 3
60 3
STEARIC ACID CH3(CH2)16CO2H 100 25 1
60 1 2 WHISKEY comm 25 1
60 1
SUGAR SYRUP high 25 1 1
60 2 1 WINES comm 25 1 1
60 1
SULPHUR S 100 25 1
60 2 WINE VINEGAR comm 25 1 1
60 2 1
- DIOXIDE AQUEOUS SO2 sat 25 1 1 ZINC ZnCI2 dil 25 1 1
60 2 - CHLORIDE 60 1 1
- DIOXIDE DRY all 25 1 1 sat 25 1 1
60 1 1 60
- DIOXIDE LIQUID 100 25 2 1 - CHROMATE ZnCrO4 all 25 1
60 3 2 60 1
- TRIOXIDE SO3 100 25 2 3 - CYANIDE Zn(CN)2 all 25 1
60 2 3 60
SULPHURIC ACID H2SO4 ≤ 10 25 1 1
60 1 1 - NITRATE Zn(NO3)2 nd 25 1
≤75 25 1 1 60 1
60 2 2 - SULFATE ZnSO4 dil 25 1 1
≤90 25 1 2 60 1 1
60 2 2 sat 25 1 1
≤96 25 2 2 60 1 1
.52. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
11. DISCLAIMER
RETURN TO
CONTENTS
Disclaimer
DISCLAIMER . .. . .. . . .. . .. . . . .. . .. .
The Marley Guarantee of Quality and Performance
This manual has been compiled by Marley New Zealand Limited (“the Company”) to promote better under-
standing of the technical aspects of the Company’s products, to assist users in obtaining from them the best
possible performance.
The manual is supplied subject to acknowledgement of the following conditions:
• The manual is protected by Copyright and may not be copied or reproduced in any form or by any
means inwhole or in part without prior consent in writing by the Company.
• Product specifications, usage data and advisory information may change from time to time with advances
in research and field experience. The Company reserves the right to make such changes at any time
without notice.
• Correct usage of the Company’s products involves engineering judgments which cannot be properly
made without full knowledge of all the conditions pertaining to each specific installation. The Company
expressly disclaims all and any liability to any person, whether supplied with this publication or not, in
respect of any thing and of the consequences of anything done or omitted to be done by any such person
in reliance whether in whole or partially upon the whole or any part of the contents of this manual.
• This manual is and shall remain the property of the Company, and shall be surrendered on demand to the
Company.
• Information supplied in this manual does not override a job specification. Where conflict arises, consult
the authority supervising the job.
• Whilst all care has been taken to ensure that the information in this manual is accurate, the company
will not accept any responsibility for any errors.
.. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. . .. .
DISCLAIMER AUCKLAND
This technical manual has been compiled by Marley New Zealand Limited (“The Company”) to promote better understanding of the
technical aspects of the Company’s products to assist users in obtaining from them the best possible performance. Mahia Road, Manurewa, Private Bag 802 Manurewa
The technical manual is supplied subject to acknowledgment of the following conditions: Sales Department: Telephone 09 279 2777
The technical manual is protected by Copyright and may not be copied or reproduced in any form or by any means in whole or in
part without prior consent in writing by the Company. Direct Fax 09 279 2778 Freefax 0800 652 621
Product specifications, usage data and advisory information may change from time to time with advances in research and field
experience. The Company reserves the right to make such changes at any time without notice.
Head Office: Telephone 09 279 2799 Fax 09 279 2798
Correct usage of the Company’s products involve engineering judgements which cannot be properly made without full knowledge of
all the conditions pertaining to each specific installation. The Company expressly disclaims all and any liability to any person
whether supplied with this publication or not in respect of anything and of the consequences of anything done or omitted to be CHRISTCHURCH
done by any such person in reliance whether whole or partial upon the whole or any part of the contents of this publication. Shands Road, Hornby, PO Box 16233 Christchurch
No offer to trade, nor any conditions of trading, are expressed or implied by the issue or content of this manual.
Nothing herein shall override the Company’s Conditions of Sale, which may be obtained from the Registered Office or any Sales Office
205331
of the Company.
For more information call free
This technical manual is and shall remain the property of the Company, and shall be surrendered on demand
to the Company. FREEPHONE 0800 222 922