The Director Steel Authority of Vs Ispat Khadan Janta Mazdoor Union On 5 July 2019
The Director Steel Authority of Vs Ispat Khadan Janta Mazdoor Union On 5 July 2019
The Director Steel Authority of Vs Ispat Khadan Janta Mazdoor Union On 5 July 2019
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO(s). 80818082 OF 2011
THE DIRECTOR
STEEL AUTHORITY OF INDIA LTD. …..Appellant(s)
VERSUS
ISPAT KHANDAN JANTA MAZDOOR UNION …..Respondent(s)
WITH
CIVIL APPEAL NO(s). 8084 OF 2011
J U D G M E N T
Rastogi, J.
1. These appeals arise from the judgment dated 6 th September,
2010 passed by the Division Bench of the High Court of Madhya
Pradesh in Writ Petition No. 10963 of 2009 and 12485 of 2009
Digitally signed by
SATISH KUMAR YADAV
Date: 2019.07.05
16:50:05 IST
Reason:
Industrial Tribunal(CGIT), Jabalpur dated 16th September, 2009
answering the reference in the affirmative form and directing the
1
contract labourers who were in the employment of SAIL from
1993 till 1996(17th March, 1993 to April 1996) to be reinstated,
with Para 125 of the Judgment of this Court in Steel Authority
Workers and Others 1 declining to grant them back wages.
2. The case involves a chequered history and almost after four
rounds of litigation, the matter has reached at a stage where the
Section 10(1) of the Industrial Disputes Act, 1947 to decide the
Janta Mazdoor Union vide notification dated 27th January, 2003
followed with 22nd February, 2005.
present purpose are that the appellant Steel Authority of India
Limited (hereinafter being referred to as “SAIL”) is a Government
of India undertaking and is a State within the meaning of Article
12 of the Constitution of India and has steel plants in different
1 2001(7) SCC 1
2
parts of India. SAIL has one of the captive lime stone and
dolomite mines in Kuteshwar in the District of Katni of Madhya
Pradesh. Limestone and Dolomite are necessary ingredients for
manufacture of steel. The SAIL did blasting work as this work
the contractors at Kuteshwar Lime Stone Mines were doing the
Notification No. S.O. 707 dated 17th March, 1993 issued under
Section 10(1) of the Contract Labour(Regulation & Abolition) Act,
1970(hereinafter referred to as “CLRA Act”).
Section 7 of the CLRA Act and the contractors through whom the
under Section 12 of the CLRA Act and the workmen engaged as
partite agreement entered into from time to time not less than the
3
rates so prescribed by the authority under the Minimum Wages
Act, 1948.
prohibition notification of employment of contract labour for the
establishment wherein their services hired by the appellant SAIL
under Section 10(1) of the CLRA Act dated 17 th March, 1993, the
extract of which is referred to hereunder:
SCHEDULE
appropriate Government under Section 10(1) of the CLRA Act, the
relationship of contractor and contract labour stands ceased and
by legal fiction, contract comes to extinct and the indisputed fact
4
which has come on record is that no fresh agreement, in the
interregnum period, was executed and the existing agreement to
extended from time to time by the competent authority and the
contract labour was allowed to continue on the same terms and
conditions till their services were terminated by the contractor in
the month of April, 1996.
employment of contract labour, it was held that on abolition of
contract labour system from any establishment under Section 10
contract labourer covered by the sweep of such abolition for the
2 1997(9) SCC 377
5
employee of the employer on whose establishment they were
system in the establishment for the work which they were doing
gets abolished.
8. The effect of the prohibition notification under Section 10(1)
later stage, came to be examined by the Constitution Bench of
this Court in Steel Authority of India Ltd. and Others (supra)
wherein it was held that there is no provision under CLRA Act
notification by the appropriate Government under Section 10(1),
operation or other work in any other establishment and overruled
the judgment in Air India Statutory Corporation and Others
provision in the CLRA Act provides for automatic absorption of
contact labour on issuance of a notification by the appropriate
later stage.
9. It reveals from the record that after the Constitution Bench
Judgment of this Court, the matter was agitated by the workers
union before the appropriate Government and after failure of the
conciliation proceedings, the case of 3404 workmen was referred
Tribunal(CGIT) is reproduced hereunder:
1. “The Government of India, Ministry of Labour vide its
Notification No.L29011/97/2002IR(M) dated 271
2003 has referred the following dispute for
adjudication by this tribunal:
7
II. Whether the action of the Mines manager,
Koteshwar Lime Stone Mines of Steel Authority of India
ltd. in denying terminal benefits of gratuity
retrenchment compensation and exgratia applicable to
VRS seeking employees is fair and justified. If not, to
what relief these workers/heirs are entitled to?
III. Whether the action of the management of the Mines
Manager, Koteshwar Lime Stone Mines of Steel
Authority of India Ltd. in disregarding Clause8 of
Memorandum of Agreement signed between the Steel
Authority of India, New Delhi and their Unions
including HMS and employing workers through
contractors on jobs of permanent and perennial nature
in Mines between 520 years even without ensuring
statutory wages and service conditions was legal, fair
and justified? If not, to what relief concerned
workmen/heirs are entitled?”
CORRIGENDUM
issues:
“I. Whether the reference R/40/03 is maintainable?
8
III.Whether the action of the Mines Manager,
Kuteshwar Lime Stone Mines of the Steel Authority of
India Ltd. in terminating the services of 3404(3380+24)
as per list attached mine workers in April 1996 who
ceased to be contract labour after prohibition of
employment of contract labour in lime stone vide
Notification No.S.O.707 dated 170393 was legal, fair
and justified?
IV.Whether the said contact workers/heirs are entitled
the terminal Benefits of gratuity, retrenchment
compensation and exgratia applicable to VRS from
SAIL?
V. Whether Lime Stone Mines violated the provision of
Clause8 of the memorandum of agreement signed
between the SAIL, New Delhi and their Unions and
employing workers through contractors on jobs of
permanent and perennial nature was justified, legal
and fair?
11. The parties to the reference were called upon to lay evidence
in support of their respective claim and after taking note of the
evidence(oral & documentary), the Tribunal recorded the facts in
seriatim emerging from the records as under:
9
(2) Wage slips, wagesheets and the evidence of the
witnesses clearly show that the contractors were
paying wages to the contract labours.
(3) Exhibit M/8 filed in R721/05 and the evidence of the
witnesses show that the contractor dismissed the
employee and also transferred some of the employees
from the place of work and had disciplinary authority.
(5) The contract papers and the evidence show that the
contractors had full control over the skilled and
professional work.
(7) The contract agreements further show that there was
penal clause, if there was any breach of contract.
12. The Tribunal taking note of the evidence including oral and
documentary adduced in support of the reference held that the
contract between the Management(SAIL) and the contractors was
genuine and not sham and bogus and the contract workers were
allowed to continue even after the prohibition notification under
Section 10(1) dated 17th March, 1993 under the CLRA Act on the
10
same terms and conditions and the services of the contract
labourer were terminated by the Contractor in April, 1996.
13. It may be noted that status of the workers after the issuance
of notification dated 17th March, 1993 has also been examined by
the Tribunal and held as follows:
(3) The contract between the Principal Employer and the
contractors after publication of the notification ceases
to exist and became not genuine.
(4) The wages were being paid to the contract labour by
the so called contractors in the same way as from
before.
(5) The principal Employer was in need of the workers for
the specified works even after the publication of the
notification as same workers were continuing in work
till April, 1996.
(6) There is no evidence on the record to show that the
principal employer adopted the procedure of
regularization and had intended to employ regular
workers as has been directed by the Hon’ble Apex
Court at Para 125 subpara6 in the Constitution
Bench Judgment in the case of SAIL versus National
Union Water Front Workers (Supra) after the contract
was found genuine before the notification.
11
(7) There was no automatic absorption of contract labour
on issuing the notification prohibiting the employment
of contract labours.
employer(SAIL) was prohibited to employ any contract labour in
any process, operation or other work in the establishment and
been allowed to continue in the establishment by operation of law
Award is as under:
12
1993 becomes not genuine. The Principal employer
was prohibited to employ any contract labour in any
process, operation or other work in the establishment
in any process, operation or other work in the
establishment to which the notification relates at any
time thereafter. It is evident that when the contract of
the contractors after notification became itself void and
not genuine, the extension of the period of contract of
the respective contractors would be abinitio void and
sham and bogus. Thus it is established that the
contract of Principal employer with contractors in
regard to the contract labours became subsequently
sham and bogus after the notification No. S.O. 707
dated 1731993 coming into the effect from the date of
its publication.”
contract labourer through contractors was not sham and bogus
before notification dated 17th March, 1993, but after publication
of the said notification, by operation of law, the contract through
void and sham as the contract labour was allowed to continue in
the establishment till April 1996. It was further observed that
the Union is at liberty to take recourse of the penal consequences
as mandated under Section 23 to 25 of the CLRA Act. Rest of the
issues framed by the Tribunal(Issue nos. 3,4, 5 & 6) have been
dated 16th September, 2009.
13
16. The appellant(SAIL) and the workers Union both filed writ
observed in Para 85 to that extent in the writ petition.
evidence(oral/documentary) reversed the finding of fact recorded
by the Tribunal and observed that the contract to be sham and
bogus and observed as under:
14
be considered for regularization in accordance with the
directions issued by the Apex Court in para 125 of
Steel Authority of India Ltd. and others vs. National
Union Waterfront Workers and others (supra).”
18. The judgment of the High Court dated 6th September, 2010
is a subject matter of challenge before us in these appeals.
19. Sh. Ranjit Kumar and Sh. Parag P. Tripathi, learned senior
counsel for the appellant submit that the CGIT in its award dated
16th September, 2009 has not only extensively considered the oral
and documentary evidence placed on record but also took note of
appropriate industrial adjudicator, after going into merits and the
management SAIL and contractors, arrived to the conclusion that
the contract was genuine and not sham and bogus under its
approach of the Tribunal was wholly perverse in the sense that
the Tribunal has acted on no evidence, it was not justified for the
15
adjudicator sitting as a Court of First Appeal to reappreciate the
evidence and even if on the basis of the material on record, two
views are possible and one view has been expressed by the
Tribunal it was not open for the High Court to substitute its view
under the limited scope of judicial review under Sections 226 and
227 of the Constitution of India. In the given circumstances, the
finding of fact which has been reversed by the High Court under
its impugned judgment holding the contract is not genuine but a
interfered by this Court.
extensive discussion based on the material available on record, it
between the appellant and respondent workmen and, therefore,
the question of compliance of Section 25(n) of the Act does not
arise and it was the contractor who had terminated their services
in April 1996 and it was the contractor who had full control and
supervision over the work of the labourers. It has also concluded
16
evidence on record that the wage slips and identity cards were
contractors who paid wages to the contract labour and few of the
witnesses have also supported payment through contractors.
over the contract labours and tools and equipment were supplied
by the contractors as per the terms of the contract and payment
was made by respective contractors to the contract labourers and
proceeded on illegal strike in April 1996 and all the agreements
between the management and the contractors entered into are of
extended by the competent authority from time to time until the
disciplinary powers against the contract labour being supported
by the cogent evidence on record was not open for the High Court
17
to sit as a Court of Appeal and reappraised the evidence under its
impugned judgment.
Court in Dena Nath and Others Vs. National Fertilisers Ltd.
and Others 3 and submits that mere violation of the prohibition
notification under Section 10(1) of the CLRA Act would not entail
considered as further continuation to be illegal resulting in penal
consequences envisaged under Section 23 to 25 of the Act.
23. Per contra, Sh. Colin Gonsalves, learned senior counsel for
the respondent, on the other hand, while supporting the finding
submits that the Tribunal has committed a manifest error in not
appreciating the documentary/oral evidence on record and thus
that the finding of fact recorded by the Tribunal under its award
evidence, has rightly interfered and recorded a finding that the
3 1992(1) SCC 695
18
contract was sham and bogus and in consequence thereof in
the instant case and entitled for the wages payable to the regular
regularisation of service.
entitled for the back wages which has been wrongly denied by the
terminated, the delay in fact has caused because of 34 rounds
of litigation and was also due to the fact that earlier it was held
by this Court in Air India Statutory Corporation and Others
case (supra) that immediately on the issuance of a prohibition
notification under Section 10(1) of the CLRA Act, which has been
19
Steel Authority of India Ltd. and Others(supra) at a later point
employees and they are entitled for wages for the period they
have worked and discharged their duties in the establishment of
SAIL and denial of their actual wages by the High Court in the
impugned judgment is legally not sustainable.
25. Learned counsel further submits that High Court has taken
note of various tests for determining nature of contract which has
been laid down from time to time by the judicial pronouncements
disciplinary action, payment of wages etc., the primary tests as
the determining factor in arriving to a conclusion as to whether
any contract entered in contradistinction to the tests laid down,
indeed is sham and bogus. The High Court on appraisal of the
and the contractor was sham and bogus and once the finding has
been recorded under the impugned judgment, the consequence is
20
contract labour as an employer and employee and this makes the
who were regular in employment of the appellant establishment
which indeed could not have been denied to the respondent. In
the given facts and circumstances, no error has been committed
by the High Court in the impugned judgment which may call for
any interference.
judgment in Dena Nath and Others (supra) is not applicable for
the reason that it was of much prior to the Constitution Bench
Judgment of this Court and it has no application for the further
reason that it was a case where the effect of failure of compliance
of Section 7 and 12 of the CLRA Act was a question and there
was no such prohibition notification under Section 10(1) of the
CLRA Act which came into consideration. Thus, what has been
appellant.
21
27. We have considered the rival submissions made by the
parties and with their assistance perused the materials available
on record.
instant appeals any further, it may be apposite to take note of the
indisputed facts which has come on record and take a note of the
facts recorded by the High Court in the impugned judgment.
29. It is not disputed that the appellant SAIL is a Government of
India undertaking and a State within the meaning of Article 12 of
the Constitution of India and has its steel plants in the different
parts of India. SAIL has one of the captive lime stone and
dolomite mines in Kuteshwar in the District of Katni of Madhya
Pradesh. Limestone and Dolomite are necessary ingredients for
manufacture of steel. The SAIL did blasting work as this work
were executed between the principal employer(SAIL), contractor
and contract labour and from time to time wages to which the
contract labour was entitled for in terms of tripartite agreement
22
which indisputedly was higher in comparison to the minimum
wages notified by the appropriate Government from time to time
under the Minimum Wages Act, 1948 was paid to each of the
appellant.
30. It is also not disputed that the contract labour which is
which has been prohibited by the appropriate Government under
its notification issued under Section 10(1) of the CLRA Act, dated
proceedings.
31. After 34 rounds of litigation, a reference was made by the
wherein respective claims with supporting oral and documentary
evidence were placed by the contesting parties. CGIT under its
holding that the contract was not sham and bogus and if, at all,
23
there was any violation in continuation of the contract labour
review under Article 226 & 227 of the Constitution of India under
the impugned judgment dated 6th September, 2010.
32. Before we may advert to examine the question in the instant
appeals any further, it will be apposite to take note of the legal
Government in exercise of power under Section 10(1) of the CLRA
Act and its exposition by the Constitution Bench of this Court in
Steel Authority of India Ltd. and Others (supra) overruling the
(supra). The legal consequence of Section 10(1) of the CLRA Act,
has been noticed in paragraph 68, 88, 105 and 125 as follows:
24
“68. We have extracted above Section 10 of the CLRA
Act which empowers the appropriate Government to
prohibit employment of contract labour in any process,
operation or other work in any establishment, lays
down the procedure and specifies the relevant factors
which shall be taken into consideration for issuing
notification under subsection (1) of Section 10. It is a
common ground that the consequence of prohibition
notification under Section 10(1) of the CLRA Act,
prohibiting employment of contract labour, is neither
spelt out in Section 10 nor indicated anywhere in the
Act. In our view, the following consequences follow on
issuing a notification under Section 10(1) of the CLRA
Act:
(2) the contract of principal employer with the
contractor in regard to the contract labour
comes to an end;
(5) the contractor can utilise the services of
the contract labour in any other
establishment in respect of which no
notification under Section 10(1) has been
issued where all the benefits under the CLRA
Act which were being enjoyed by it, will be
available;
25
(6) if a contractor intends to retrench his
contract labour, he can do so only in
conformity with the provisions of the ID Act.
88. If we may say so, the eloquence of the CLRA Act in
not spelling out the consequence of abolition of
contract labour system, discerned in the light of
various reports of the Commissions and the
Committees and the Statement of Objects and Reasons
of the Act, appears to be that Parliament intended to
create a bar on engaging contract labour in the
establishment covered by the prohibition notification,
by a principal employer so as to leave no option with
him except to employ the workers as regular employees
directly. Section 10 is intended to work as a permanent
solution to the problem rather than to provide a one
time measure by departmentalizing the existing
contract labour who may, by a fortuitous circumstance
be in a given establishment for a very short time as on
the date of the prohibition notification. It could as well
be that a contractor and his contract labour who were
with an establishment for a number of years were
changed just before the issuance of prohibition
notification. In such a case there could be no
justification to prefer the contract labour engaged on
the relevant date over the contract labour employed for
a longer period earlier. These may be some of the
reasons as to why no specific provision is made for
automatic absorption of contract labour in the CLRA
Act.
105. The principle that a beneficial legislation needs to
be construed liberally in favour of the class for whose
benefit it is intended, does not extend to reading in the
provisions of the Act what the legislature has not
provided whether expressly or by necessary
implication, or substituting remedy or benefits for that
provided by the legislature. We have already noticed
above the intendment of the CLRA Act that it regulates
the conditions of service of the contract labour and
26
authorizes in Section 10(1) prohibition of contract
labour system by the appropriate Government on
consideration of factors enumerated in subsection (2)
of Section 10 of the Act among other relevant factors.
But, the presence of some or all those factors, in our
view, provides no ground for absorption of contract
labour on issuing notification under subsection (1) of
Section 10. Admittedly, when the concept of automatic
absorption of contract labour as a consequence of
issuing notification under Section 10(1) by the
appropriate Government, is not alluded to either in
Section 10 or at any other place in the Act and the
consequence of violation of Sections 7 and 12 of the
CLRA Act is explicitly provided in Sections 23 and 25
of the CLRA Act, it is not for the High Courts or this
Court to read in some unspecified remedy in Section
10 or substitute for penal consequences specified in
Sections 23 and 25 a different sequel, be it absorption
of contract labour in the establishment of principal
employer or a lesser or a harsher punishment. Such an
interpretation of the provisions of the statute will be far
beyond the principle of ironing out the creases and the
scope of interpretative legislation and as such, clearly
impermissible. We have already held above, on
consideration of various aspects, that it is difficult to
accept that Parliament intended absorption of contract
labour on issue of abolition notification under Section
10(1) of the CLRA Act.
125.The upshot of the above discussion is outlined thus:
27
the establishment was situated, would be the
appropriate Government;
(b) After the said date in view of the new definition of
that expression, the answer to the question referred to
above, has to be found in clause (a) of Section 2 of the
Industrial Disputes Act; if (i) the Central Government
company/undertaking concerned or any undertaking
concerned is included therein eo nomine, or (ii) any
industry is carried on (a) by or under the authority of
the Central Government, or (b) by a railway company;
or
(c) by a specified controlled industry, then the Central
Government will be the appropriate Government;
otherwise in relation to any other establishment, the
Government of the State in which that other
establishment is situated, will be the appropriate
Government.
(1) after consulting with the Central Advisory
Board or the State Advisory Board, as the
case may be, and
(2) having regard to
28
the date of this judgment, shall be called in question in
any tribunal or court including a High Court if it has
otherwise attained finality and/or it has been
implemented.
(3) Neither Section 10 of the CLRA Act nor any other
provision in the Act, whether expressly or by necessary
implication, provides for automatic absorption of
contract labour on issuing a notification by the
appropriate Government under subsection (1) of
Section 10, prohibiting employment of contract labour,
in any process, operation or other work in any
establishment. Consequently the principal employer
cannot be required to order absorption of the contract
labour working in the establishment concerned.
(4) We overrule the judgment of this Court in Air India
case [(1997) 9 SCC 377] prospectively and declare that
any direction issued by any industrial adjudicator/any
court including the High Court, for absorption of
contract labour following the judgment in Air India
case [(1997) 9 SCC 377] shall hold good and that the
same shall not be set aside, altered or modified on the
basis of this judgment in cases where such a direction
has been given effect to and it has become final.
29
(6) If the contract is found to be genuine and
prohibition notification under Section 10(1) of the
CLRA Act in respect of the establishment concerned
has been issued by the appropriate Government,
prohibiting employment of contract labour in any
process, operation or other work of any establishment
and where in such process, operation or other work of
the establishment the principal employer intends to
employ regular workmen, he shall give preference to
the erstwhile contract labour, if otherwise found
suitable and, if necessary, by relaxing the condition as
to maximum age appropriately, taking into
consideration the age of the workers at the time of
their initial employment by the contractor and also
relaxing the condition as to academic qualifications
other than technical qualifications.”
33. The exposition of the judgment of the Constitution Bench of
this Court made it clear that neither Section 10 nor any other
provision in the CLRA Act provides for automatic absorption of
consequently the principal employer is not required or is under
legal obligation by operation of law to absorb the contract labour
working in the establishment.
30
industrial dispute is raised by any contract labour in regard to
condition of service, it is for the industrial adjudicator to consider
whether the contractor has been interposed either on the ground
legislations so as to deprive the workers of statutory benefits. If
the contract is found to be sham, nominal or camouflage, then
the socalled labour will have to be treated as direct employee of
that purpose in the facts and circumstances of the case.
35. On the other hand, if the contract is found to be genuine
principal employer intending to employ regular workmen for the
process, operation or other work of the establishment in regard to
which the prohibition notification has been issued, it shall give
31
preference to the erstwhile contract labour if otherwise found
suitable, if necessary by giving relaxation of age as it appears to
be in fulfilment of the mandate of Section 25(H) of the Industrial
Disputes Act, 1947.
36. It may be noted that the learned counsel for the respondent
been considered by the Constitution Bench of this Court in Steel
Authority of India Ltd. and Others(supra) of which a detailed
reference has been made by us.
37. Tests which are to be applied to find out whether the person
32
mere camouflage has been examined by this Court in
Bench of this Court. The relevant paras are as under:
“38. The tests that are applied to find out whether a
person is an employee or an independent contractor
may not automatically apply in finding out whether the
contract labour agreement is a sham, nominal and is a
mere camouflage. For example, if the contract is for
supply of labour, necessarily, the labour supplied by
the contractor will work under the directions,
supervision and control of the principal employer but
that would not make the worker a direct employee of
the principal employer, if the salary is paid by a
contractor, if the right to regulate the employment is
with the contractor, and the ultimate supervision and
control lies with the contractor.
38. These are the broad tests which have been laid down by this
Court in examining the nature and control of the employer and
7 2009 (13) SCC 374
33
whether the agreement pursuant to which contract labour has
nominal and camouflage.
39. It was not disputed in the instant case that the contract
extended from time to time by the competent authority even after
whom they were engaged after they proceeded on strike in April,
1996.
evidence placed by the respective parties on record in reference to
the fact whether the contract was sham and bogus which was a
contractors employed the contract labour on their own and they
34
(contract labourer) were examined and in their crossexamination
payment was made to them by the contractors, wage slips also
show that the wages were being paid by the contractors. Other
witnesses also in crossexamination have supported that half of
the PF amount of the workers were deposited by their respective
labours are the photocopies of the identity cards, pay slips, PF
slips etc. These pay slips and identity cards do not show that all
March, 1993 without break because number of these documents
thereafter from time to time. It goes to show that there was no
fresh contract thereafter ever entered between the parties. Exh.
M/8 filed in R721/05 and the evidence of the witnesses shows
that the contractor had terminated the services of the contract
35
labourers from the place of work and was the disciplinary
authority.
41. It was further observed that the contractors had full control
over the skilled and professional work and the SAIL had right to
reject the limestone, if it was not within the specified approved
record, CGIT recorded a finding of fact holding that the contract
was not sham and bogus at least up to the date of issuance of the
paragraph 85 of the award the Tribunal has recorded a finding
March, 1993 by operation of law, it became sham and bogus but
in our considered view, such a finding recorded in para 85 of the
Award dated 16th September, 2009 is not sustainable in law for
agreement after the prohibition notification under CLRA Act has
36
come into force, it may be illegal and continuance of service in
the absence of any contract which stands extinguished by virtue
of prohibition notification has to face the penal consequences as
embedded under the scheme of CLRA Act.
42. The High Court has taken note of the various provisions of
statutory measures which are applicable over the establishment
of the appellant including various welfare schemes which provide
safety and security of the workers. To say so, every establishment
contract agreement entered between the parties in arriving to a
camouflage as held by the High Court in its impugned judgment.
43. The High Court appears to be primarily persuaded with the
issuance of a prohibition notification under Section 10(1) of the
37
factors including perennial nature of work, under the CLRA Act
has recommended for abolition of contract labour and accepted
employment of contract labour after issuance of the prohibition
notification under Section 10(1) of the CLRA Act in holding that
the action of the establishment was opposed to the public policy
principles enshrined under Section 23 of the Indian Contract Act
and taking work from the contract labour was in violation of the
statutory notification dated 17th March, 1993 and that appears to
be the reason which persuaded to hold that the finding recorded
by the Tribunal that contractors had full control and supervision
over the work in view of the functioning of the scheme of mines
contract was sham and bogus and also the fact that in all the
agreements executed between the parties, there was a provision
of abolition of contract labour in the matter of work of a perennial
in nature and certain other conditions of agreement in recording
its satisfaction that the contract was sham and bogus.
38
44. In our considered view, the finding recorded by the High
Court under the impugned judgment is not sustainable for the
10(1) of CLRA Act has been settled by the Constitution Bench of
this Court in Steel Authority of India Ltd. and Others (supra)
and this Court has made it clear that neither Section 10 nor any
provision in the CLRA Act provides for automatic absorption of
appropriate Government under Section 10(1) of the CLRA Act and
the Tribunal in the first place being the fact finding authority has
extensively examined the documentary and oral evidence which
came on record and also the relationship of principal employer,
proceeded on a strike in April 1996.
extenso regarding the wage slips, identity cards and the nature of
work being discharged by the contract labour subsequent to the
39
finding in return that the contract between the contractor and
the employee was not sham and bogus and the workmen were
employer.
46. To test it further, apart from the statutory compliance which
with, its noncompliance or breach may at best entail in penal
consequences which is always for the safety and security of the
nature of job in a particular establishment. The exposition of law
has been further considered in International Airport Authority
of India case(supra) where the contract was to supply of labour
and necessary labour was supplied by the contractor who worked
contract entered between the contractor and contract labour to
be sham and bogus per se.
47. Thus, in our considered view, if the scheme of the CLRA Act
taking note of the oral and documentary evidence which came on
record, the finding which has been recorded by the CGIT under
its award dated 16th September, 2009 in absence of the finding of
fact recorded being perverse or being of no evidence and even if
there are two views which could possibly be arrived at, the view
judicial review under Article 226/227 of the Constitution of India
and this exposition has been settled by this Court in its various
judicial precedents.
is in reference to failure of compliance of Section 7 and 12 and
not in reference to Section 10(1) of the CLRA Act but if we look
into the scheme of CLRA Act which is a complete code in itself,
CLRA Act, it result into penal consequences as has been referred
to in Sections 23 to 25 of the Act and there is no provision which
would entail any other consequence other than provided under
Section 23 to 25 of the Act.
41
49. In our considered view, the Tribunal under its award dated
16th September, 2009 has rightly arrived to the conclusion that
the contract was not sham and bogus and there shall be no
prohibition notification under the CLRA Act and the High Court
of Madhya Pradesh has committed a manifest error in reversing
the finding of fact in return under its impugned judgment dated
6th September, 2010 which, in our view, is not sustainable and
deserves to be set aside.
50. The appeals are accordingly disposed of and the impugned
judgment of the High Court dated 6 th September, 2010 is hereby
set aside. The respondent is at liberty to avail remedy for alleged
accordance with law. No costs.
51. Pending application(s), if any, also stand disposed of.
…………………………………J.
(A.M. KHANWILKAR)
…………………………………J.
(AJAY RASTOGI)
New Delhi
July 05, 2019
42
43