Ep Wells Daily Operation Report

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

EP WELLS DAILY OPERATION REPORT Report 36 20/08/2021

Company BOC - IFMS


Well Type Producer Well Slim
Well MJ-113
Wellbore M_25
WBS No/ API No G18-1 WellPad/ S02

Event Summary
Event Type Drilling & Suspension Event Start Date 16/07/2021 Days on Location 96.00
Objective Drilling Original Spud Date 16/07/2021 Days since Spud 36.00
Est. Days 24.03 Contractor SCHLUMBERGER
Work Unit SLB-ZPEC-29 Days to Release -11.97
Rig Phone/ Fax No AOS DSV-07809186481 /

Well Status
Supervisor Bahaa Rashid / Haider Kadhum Measured Depth (m) 3,197.00
Engineer Ahmed Al Jandeel / Danish Khan TVD (m) 2,920.39
Other Supervisor Ali Saleh / Samer Mehdi 24 Hr Progress (m)
Depth Ref/ Grd Elev/ Water Depth (m) 11.92/ 1.00 Hole Size (in) 8.500
THF Datum
Cum NPT (hr/%) 174.75 / 20.34% Last Casing MD 7.000 (in) @ 3,193.00 (m)
Daily NPT (hr/%) 24.00 / 100.00% Next Casing MD
Days Ahd(-) Bhnd(+)(50/50) 12.20 Current Fluid Density (ppg) 10.70
Formation Ahmadi Fm Top LOT/FIT EMW (ppg) 18.19
Lithology Limestone
Formation Top MD (m) 3,047.80

HSE Summary
Last Incident Date Days Last Incident Date Days KPI's
LWC 0 PSI 0 TRCF
RWC 0 NII 0 LWCF
MTC 0 HPI 0 Safety Cards - Safe 11
FAC 0 Goal Zero Days 17-Jun-2021 64 Safety Cards - Unsafe 32
Last Casing Pressure Test 03/08/2021 17 SSE%
Last Casing Pressure (psi) 4,000.00
Safety Comments
Dropping objects
Noticed a safety pin was missing in one of the shackles while rigging down third-party
equipment,SWA called, inserted the safety pin and then start to work.

HSE Drill
Drills/Tests Date Days Since Last
Last Derrick Inspection 0 JSA's/Toolbox Talks 7
Last BOP Function Test 17/08/2021 3 Days Since Last Drill
Last BOP Test 17/08/2021 3
Next BOP Test 07/09/2021 21

Operations Summary
24 Hour Summary
Waiting on decision while Well Secured (RIH 10 Stands 5" DP kill string and VBR's closed/FOSV closed). POOH kill string and rack back to derrick, closed
BSR's. L/D 3-1/2" DP (18 Std. of 35 Std.) and 2 Stand 3-1/2" HWDP from derrick. Run back 10 stands 5" DP as a kill string to 289 m. Continue waiting on
decision while Well Secured.
Update Since Report Time
Continued change 3-1/2" DP handling equipment to 5" DP handling equipment. Opened BSR's, RIH 10 Stands 5" DP as a kill string. Secured the well.
Waiting on decision while Well Secured.
24 Hour Forecast
Option#1 : RIH 3-1/2" TBG (+/- 1000 m), Land 13-5/8" Cameron tubing hanger into THS and Install 3-1/2" BPV (H Type).
N/D 13-5/8" 15K BOP stack, N/U 3-1/8" 5K XMT. Cavity test XMT against Tubing hanger twin seal.
Option#2 : Perform balance CMT plug into 7"

20/08/2021 22:43:36 Generated from data in EDM/OpenWells/PROFILE 1


EP WELLS DAILY OPERATION REPORT Report 36 20/08/2021
Company BOC - IFMS
Well Type Producer Well Slim
Well MJ-113
Wellbore M_25
WBS No/ API No G18-1 WellPad/ S02

Time Summary
Start Hours PH OPN WS OPN Drilled NPT Rig Rate Description
Depth Level
(m)
00:00 6.00 CO9 WOD 3,197.00 1.00 Waiting on decision.
- Well Secured (VBR's closed/FOSV closed).
- Monitoring well thru choke manifold (HCR Open).
- Well Stable, No losses/No gain.
NPT Vendor:IWC
06:00 6.00 CO9 WOD 3,197.00 1.00 Waiting on decision.
- Well Secured (VBR's closed/FOSV closed).
- Monitoring well thru choke manifold (HCR Open).
- Well Stable, No losses/No gain.
- Meanwhile maintained cellar pump.
NPT Vendor:IWC
12:00 5.00 CO9 WOD 3,197.00 1.00 Waiting on decision.
- Well Secured (VBR's closed/FOSV closed).
- Monitoring well thru choke manifold (HCR Open).
- Well Stable, No losses/No gain.
NPT Vendor:IWC
17:00 0.75 CO9 DRT 3,197.00 1.00 .POOH 10 Stand '5' DP and rack back to derrick and secured the well (close
BSR').
-Monitoring the well via trip tank.
-Well stable, No losses /No gain.
NPT Vendor:IWC
17:45 0.25 CO9 DRT 3,197.00 1.00 Changed 5" DP handling equipment to 3-1/2" DP handling equipment.
- Closed BOP & Secured the well.
- Monitoring well thru choke manifold (HCR Open).
- Well Stable, No losses/No gain.
NPT Vendor IWC
18:00 1.75 CO9 MND 3,197.00 1.00 L/D 3-1/2 DP (9 Std. of 35 Std.) from derrick in single.
- Monitoring the well via Choke manifold (HCR open).
- Well stable, No losses/No gain.
19:45 1.50 CO9 SAF 3,197.00 1.00 HPJSM with all rig crew and explain to them current operation, all personal
understand well situation.
NPT Vendor:IWC
21:15 1.75 CO9 MND 3,197.00 1.00 Continued L/D of 3-1/2'' 'DP from derrick in single (total L/D 18 std. of 35 std)
-Monitoring the we; via choke manifold (HCR open).
-Well stable,No losses/ No gain.
NPT Vendor:IWC
23:00 0.25 CO9 MND 3,197.00 1.00 L/D 2 Std of 3-1/2'' 'HWDP from derrick in single.
-Monitoring the we; via choke manifold (HCR open).
-Well stable,No losses/ No gain.
NPT Vendor:IWC
23:15 0.75 CO9 MND 3,197.00 1.00 Changed 3-1/2" DP handling equipment to 5" DP handling equipment.
- Closed BOP & Secured the well.
- Monitoring well thru choke manifold (HCR Open).
- Well Stable, No losses/No gain.
Offline Activities:
** Preparing 80 Joints 3-1/2" TBG (VAM TOP, 9.2#, L-80), clean, drift and
measured it.
** Physically checked 13-3/8" 5K Cameron Tubing Hanger (thread-1/4"
plugsseal),
OK.
** Physically checked 3-1/2" BPV/TWCV (H-Type), OK.
** 3-1/2" VAM Top Pup Jt. below Tubing hanger in good condition.
Total section down hole losses: 0 bbls.
Surface losses day: 0 bbls.
Total section surface losses: 534 bbls.
Dump Mud: 0 bbl.
Total section losses: 534 bbl
NPT Vendor :IWC
Total 24.00

20/08/2021 22:43:36 Generated from data in EDM/OpenWells/PROFILE 2


EP WELLS DAILY OPERATION REPORT Report 36 20/08/2021
Company BOC - IFMS
Well Type Producer Well Slim
Well MJ-113
Wellbore M_25
WBS No/ API No G18-1 WellPad/ S02

06:00 Update
Start Hours PH OPN WS OPN Drilled NPT Rig Rate Description
Depth Level
(m)
00:00 0.25 CO9 MNR 3,197.00 1.00 Continued change 3-1/2" DP handling equipment to 5" DP handling equipment
NPT Vendor:IWC
00:15 0.75 CO9 DRT 3,197.00 1.00 Opened BSR's, RIH 10 Stands 5" DP as a kill string. Secured the well.
- Installed FOSV & Closed BSR's.
NPT Vendor:IWC
01:00 4.00 CO9 WOD 3,197.00 1.00 Waiting on decision.
- Well Secured (VBR's closed/FOSV closed).
- Monitoring well thru choke manifold (HCR Open).
- Well Stable, No losses/No gain.
NPT Vendor:IWC
Total 5.00

Deepest 5 Surveys
MD (m) Inc (°) Azi (°) TVD (m) N/S (m) E/W (m) V.Sec (m) DLeg (°) Tool
3,103.96 0.06 79.81 2,827.35 934.81 457.04 1,084.17 0.15 UIA MWD.SC.SAG
3,133.00 0.13 293.06 2,856.39 934.83 457.02 1,084.18 0.19 UIA MWD.SC.SAG
3,162.38 0.12 258.50 2,885.77 934.84 456.96 1,084.15 0.08 UIA MWD.SC.SAG
3,186.82 0.18 239.82 2,910.21 934.81 456.90 1,084.11 0.10 UIA MWD.SC.SAG
3,197.00 0.18 240.00 2,920.34 934.80 456.87 1,084.08 0.00 UIA MWD.SC.SAG

Fluid Details
Mud Type KCL / POLYMER / Glycol Oil/Water (%) /88.00 pH/Pm (cc) 9.60/0.60
MD (m) 3,197.00 TS/HGS/LGS (%) 12.00// Pf/Mf (cc) 0.20/0.35
Mud Density (ppg) 10.70 Sand (%) 0.10 Ca+ (ppm) 400
Viscosity (s/qt) 53.00 Cl- (ppm) 80,000
PV/YP (cp/lbf/100ft²) 13.00/24.000 MBT (lbm/bbl) 10.0
Gels 10 s/m (lbf/100ft²) 7.000/9.000 LCM (lbm/bbl)
API/HTHP WL (cc/30min) 4.0/ ECD (ppg) 10.80 R600/300 (°) 50@120°F/37@120°F
FC/HTHP FC (32nd") 1.0/ H2S (%) R200/100 (°)
FL Temp (°F) 120.00 KCI (%) 3.00 R6/3 (°) 8@120°F/6@120°F

Bulk Summary
Product Name Quantity OnBoard Unit Usage
DIESEL 94,650.00 L 2,200.00
Bit Details
Bit No. Size (in) Manufacturer Model no. Class IADC Code Serial no. Size (32nd") MD in (m) MD out (m) IADC Dull Grade

Drilstring Components
Item Description #Jts Length (m) OD (in) Max OD (in) ID (in) Connection Weight (ppf) Grade Serial No.
Name

Drilstring Details
Date/Time In Date/Time Out BHA No. BHA Length (m) Min. ID (in) Purpose

Personnel
Company Service No. of People Base Complement
AOS 3
BOC 3
Schlumberger 12
ZPEC 40
Al Safi 2
ECD 1
KDNA 1
KANCO 10
Total 72.00

20/08/2021 22:43:36 Generated from data in EDM/OpenWells/PROFILE 3


EP WELLS DAILY OPERATION REPORT Report 36 20/08/2021
Company BOC - IFMS
Well Type Producer Well Slim
Well MJ-113
Wellbore M_25
WBS No/ API No G18-1 WellPad/ S02

Remarks
Logistic:
*Need.
- Wire line unit and crew for 7" Liner cased hole.
- 16" Hole BHA for next well from Dnm & BDT.
- 24" & 16" Bits for next well.
*Received.
- 36 M3 Diesel.
*Sent.

FORMATION PROGNOSES (mMD/mTVD) ACTUAL (mMD/mTVD)


Lower Fars Fm Top 1097.72/1018.84 1089.42 / 1011.78
Ghar Fm Top 1465.71/1337.62 1450.48 / 1313.62
Dammam Fm Top 1653.51/1500.31 1641.64 / 1488.77
Umm Er Radhuma 1849.15/1669.79 1844.19 / 1664.17
Aaliji Fm Top 2249.65/2016.74 2241.24 / 2008.44
Shiranish Fm Top 2316.34/2074.52 2314.40 / 2072.09
Hartha Fm Top 2446.31/2187.11 2435.73 / 2176.68
Sa'di Fm Top 2574.13/2301.5 2565.56 / 2292.81
Tanuma Fm Top 2675.82/2399.5 2659.52 / 2383.55
Khasib Fm Top 2724.68/2447.9 2711.95 / 2435.41
Mishrif Fm Top 2779.13/2502.28 2766.21 / 2489.56
Rumaila Fm Top 3048.47/2771.61 3031.85 / 2755.2
Ahmadi Fm Top 3061.76/2784.9 3047.08 / 2770.43
WELL TD 3211.80/2934.90 3197.00 / 2920.34

20/08/2021 22:43:36 Generated from data in EDM/OpenWells/PROFILE 4