Chapter 5 Quiz Project Scope Management

This document contains a 10 question quiz on project scope management concepts from Chapter 5. The questions cover topics like developing a work breakdown structure (WBS), scope validation and verification, common scope management problems, and inputs used to create a WBS.

Uploaded by

Seol Han Min
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
248 views5 pages

Chapter 5 Quiz Project Scope Management

This document contains a 10 question quiz on project scope management concepts from Chapter 5. The questions cover topics like developing a work breakdown structure (WBS), scope validation and verification, common scope management problems, and inputs used to create a WBS.

Uploaded by

Seol Han Min
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

Subject: SPM-Chapter 5 Quiz - Project Scope Management (Time: 10’)

Number of question: 13

QN=1 Which tool or technique for collecting requirements is often the most
expensive and time consuming?
a. surveys
b. focus group
c. interview
d. observation
e.
f.

m
er as
ANS: c

co
PTS: 1

eH w
CHAPTER: 5

o.
MIX NO
CHOICES:
rs e
ou urc
QN=2 A__________________ is a deliverable-oriented grouping of the work
involved in a project that defined the total scope of the project
o

a. WBS
aC s

b. scope statement
vi y re

c. WBS dictionary
d. work package
e.
ed d

f.
ar stu

ANS: a
PTS: 1
CHAPTER: 5
is

MIX NO
Th

CHOICES:

QN=3 What approach to developing a WBS involves writing down or


drawing ideas in a nonlinear format?
sh

a. top-down
b. mind mapping
c. bottom-up
d. Analogy

This study source was downloaded by 100000808797969 from CourseHero.com on 09-09-2021 12:16:19 GMT -05:00

https://www.coursehero.com/file/8060219/Chapter-5-Quiz-Project-Scope-Management/
e.
f.
ANS: B
PTS: 1
CHAPTER: 5
MIX NO
CHOICES:

QN=4 Assume you have a project with major categories called planning,
analysis, design, and testing. What level of the WBS would these items
fall under?
a. 1
b. 2

m
er as
c. 3

co
d. 4

eH w
e.

o.
f.
ANS: 2 rs e
ou urc
PTS: 1
CHAPTER: 5
MIX NO
o

CHOICES:
aC s
vi y re

QN=5 Which of the following is not a best practice that can help in avoiding
scope problems on information technology project?
a. Keep the realistic scope
ed d

b. Don't involve too many users in scope management


ar stu

c. Follow good project management processes


d. Use off-the-shelf hardware and software whenever possible
e.
is

f.
Th

ANS: b
PTS: 1
CHAPTER: 5
sh

MIX NO
CHOICES:

This study source was downloaded by 100000808797969 from CourseHero.com on 09-09-2021 12:16:19 GMT -05:00

https://www.coursehero.com/file/8060219/Chapter-5-Quiz-Project-Scope-Management/
QN=6 What major restaurant chain terminated a large project after spending
$170 millions on it, primarily because they realized the project scope
was too much to handle?
a. Burger King
b. McDonald's
c. Taco Bell
d. Pizza Hut
e.
f.
ANS: B
PTS: 1
CHAPTER: 5

m
MIX NO

er as
CHOICES:

co
eH w
QN=7 Scope________ is often achieved by a customer inspection and then

o.
sign-off on key deliverables.
rs e
ou urc
a. validation
b. completion
c. close-out
o

d. verification
aC s

e.
vi y re

f.
ANS: d
PTS: 1
ed d

CHAPTER: 5
ar stu

MIX NO
CHOICES:
is

QN=8 Which of the following is not a suggestion for improving user input?
a. Only have meetings as needed, not on a regular basis
Th

b. Have users on the project team


c. Co-locate users with developers
d. Develop a good project selection process for IT projects
sh

e.
f.
ANS: a
PTS: 1

This study source was downloaded by 100000808797969 from CourseHero.com on 09-09-2021 12:16:19 GMT -05:00

https://www.coursehero.com/file/8060219/Chapter-5-Quiz-Project-Scope-Management/
CHAPTER: 5
MIX NO
CHOICES:

QN=9 Project management software helps you develop a __________, which


serves as basis for creating Gantt charts, assigning resources, and
allocating costs.
a. project plan
b. WBS
c. schedule
d. deliverables and WBS Dictionary
e.

m
f.

er as
ANS: b

co
eH w
PTS: 1
CHAPTER: 5

o.
MIX NO
CHOICES: rs e
ou urc
QN=10 The project scope statement, __________, and organizational process
o

assets are primary inputs for creating a WBS.


aC s

a. Project management plan


vi y re

b. Requirements documents
c. Stakeholder register
d. Requirements traceability
ed d

e.
ar stu

f.
ANS: b
PTS: 1
is

CHAPTER: 5
MIX NO
Th

CHOICES:

QN=11 ________________ refer(s) to all the project work involved in creating


sh

the products of the project and processes used to create them.


a. Deliverables
b. Scope
c. Milestones

This study source was downloaded by 100000808797969 from CourseHero.com on 09-09-2021 12:16:19 GMT -05:00

https://www.coursehero.com/file/8060219/Chapter-5-Quiz-Project-Scope-Management/
d. Product development
e.
f.
ANS: b
PTS: 1
CHAPTER: 5
MIX NO
CHOICES:

QN=12 Which of the following items is not a primary output of Create WBS
process?
a. WBS

m
b. WBS Dictionary

er as
c. Project documents updates

co
d. Project Charter

eH w
e.

o.
f.
ANS: d rs e
ou urc
PTS: 1
CHAPTER: 5
o

MIX NO
aC s

CHOICES:
vi y re

QN=13 Which of the following items is not a primary input for Scope
Verification process?
ed d

a. PM Plan
ar stu

b. Requirements document
c. Validated deliverables
d. Requirement traceability matrix
is

e. Project reports
f.
Th

ANS: e
PTS: 1
CHAPTER: 5
sh

MIX NO
CHOICES:

This study source was downloaded by 100000808797969 from CourseHero.com on 09-09-2021 12:16:19 GMT -05:00