a. Maximin
b. Maximax
c. Laplace
d. Minimax Regret
A. MAXIMIN
Alternative Low
Hire $0
Subcontract $175 000
Do Nothing $75 000
The best of these worst numbers is $175000, so the pessimist would develop
subcontracts with other home improvement contractors.
Decision: Sub-contract
B. MAXIMAX
Alternative High
Hire 850 000
Subcontract 625 000
Do Nothing 400 000
The best of these best numbers is $850000, so the optimist would hire more
employees.
Decision: Hire
C. LAPLACE
The best of these is $338250, so the realist would develop subcontracts with other
home improvement contractors.
Decision: Subcontract
D. MINIMAX REGRET
REGRET
alternative Moderate Maximum
Low Demand High Demand
Demand Regret
225000-150000= 850000-850000=
Hire 175000-0= 175000 250000
75000 0
Sub- 225000-225000= 850000-625000=
175000-175000= 0 225000
contract 0 225000
175000-75000= 225000-120000= 850000- 400000=
Do Nothing 655000
100000 105000 450000
To minimize the maximum regret, choose to develop subcontract with other home
improvement contractors. The biggest regret is associated with doing nothing while
having high demand.
Decision: Subcontract