100% found this document useful (2 votes)
818 views8 pages

Statement For First Fixed Electrical Work

This document outlines the requirements and procedures for installing first fixed electrical work. It specifies the scope, objectives, required plant, equipment, materials, storage and protection measures, installation and fixation process, responsibilities of roles like the project manager and safety engineer, required manpower, equipment, waste management, and special control measures. The key steps are measuring, cutting, bending, drilling, and fixing conduits and boxes to walls and ceilings while following safety standards and taking measures to prevent corrosion.

Uploaded by

Hytham El-Nouby
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
818 views8 pages

Statement For First Fixed Electrical Work

This document outlines the requirements and procedures for installing first fixed electrical work. It specifies the scope, objectives, required plant, equipment, materials, storage and protection measures, installation and fixation process, responsibilities of roles like the project manager and safety engineer, required manpower, equipment, waste management, and special control measures. The key steps are measuring, cutting, bending, drilling, and fixing conduits and boxes to walls and ceilings while following safety standards and taking measures to prevent corrosion.

Uploaded by

Hytham El-Nouby
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

Rev.

: 00
Method of Statement for first
fixed electrical work Date : 16-9-2021 Page: 2 of 3

Method of Statement for


first fixed electrical work

Issue Date Prepared Checked Approved

00 Hytham El-Nouby
Rev.: 00
Method of Statement for first
fixed electrical work Date : 16-9-2021 Page: 2 of 3

Amendment Since Last Issue

Issue Clause Changes Made

05

04

03

02

01

00 - Original Issue
1- Scope:
his method of statement specifies the detailed requirements and procedures for first
fixed electrical work

2- Objective:

The objective of this method of statement is to define construction for first fixed
electrical work

3- Plant and Equipment:

- Measuring tape
- Cutting plier
- Box spanner set
- Bending spring
- Pipe Wrench
- Drilling Machine
- Pulling spring
- Hammer
- Common tools

4- Material

 Material used will be as approved by the Engineer.

 The sizes and routes routing will be as per the approved Shop Drawings.

5- Storage and Protection:

 Deliver components parts to site, completely identified in accordance with


shop and certified CAD Drawings prepared for this work.

 Store in accordance with the manufacturer’s instructions, above ground,


properly protected from the weather and construction activities.
6- Installation and fixation

Pre-Installation:

6-1 All materials and documentation relevant to this particular section


of works will be checked and verified ensuring that these are
correct and approved type.

6-2 Prior to the commencement of works, ensure that the areas for
permanent installation are ready, accessible and in suitable
condition.
Installation:

- Slit and cracking in the walls drop the pipes from the ceiling joints and install
them using a concrete dots Pull the tube tensioner to ensure the wire path
Electricity boxes shall be installed free of charge or installed higher than
buildings at a distance of 2 cm

 During the course of the installation of the conduit system, procedures for
working and dressing the installation as recommended shall be employed.

 All bends and sets shall be in accordance with IEE regulation 522-08 formed
with the aid of a helical spring fitted internally, with if necessary, the conduit
warmed sufficiently for it to move without avoidable wall thinning of the
outside of the bend.

 Conduit system shall be installed so as to ensure compliance with the


requirements of Specified Standard and Regulation.

 Joints between PVC conduit + fittings shall be made with suitable adhesive,
but expansion couplings shall be installed where any length of conduit,
inclusive of draw in boxes etc., exceeds five meters in length.

 The minimum and maximum sizes of conduit to be employed shall be 20mm


and 32mm diameter respectively, unless otherwise stated in subsequent
sections of the Specification.

 Conduits in floors shall be routed and installed so as to avoid the fixings of


floor standing equipment to be installed on the floor.
Commissioning:

 Where conduits are left "open ended" prior to wiring they shall be protected by
caps or plugs to prevent the ingress of building material.

 All conduits runs must be designed to permit wiring to be readily installed after
the complete erection of the conduits through the available draw-in, accessory
and luminary suspension boxes.

 Where surface mounted equipment (other than luminaries) is specified, all


concealed conduits shall be terminated and an adaptable box installed
recessed into the wall at every surface mounted equipment position.

 Where conduits pass through an external wall/roof the conduit box shall be
fitted on the side and after wiring filled with an inert, permanently plastic
compound having a high insulation value.

 Make provision in conduit and trunking, installation where building expansion


joints are crossed or settlement is likely

 Ensure conduits are not concealed until works has been inspected and
approved. Ensure that conduit and fittings buried in concrete or behind plaster
are protected against corrosion or electrolytic action prior to rendering.

7. RESPONSIBILITIES

 PROJECT MANAGER
1. To ensure that all the preparation and application works are carried out
according to the Contract Specification and with the approved drawings.

2. To ensure that the progressing of works is carried out according to the


planned program and as per the approved method of statement.

3. To ensure that all the equipment and material required executing the work
are available according to the planned construction program.

4. To co-ordinate with the Main contractor, MEP coordinator, Safety Officer for
a safe and proper execution of the works.

 SITE ENGINEER
1. To ensure that the works are carried out according to the Contract
Specification, approved method statement and the shop drawings.

2. To provide all necessary information and distribute responsibilities to his


construction.

3. To monitor the progress of work in relation with the work program and to
report to the Project Manager.
4. To co-ordinate with the safety officer and to ensure that the works are
carried out in safe practicing method.

 FOREMAN
1. The foreman will carry out his duties by maintaining continuous coordination
with the site engineer on daily basis, and ensure proper distribution of the
work force on the required and planned locations.

2. To ensure that his assistant foreman/ charge hand are aware of the job
requirements and they have enough information to carry out their duties
properly.

3. To ensure that the daily work is progressing as planned and advice the site
engineer of any requirement for additional resources.

4. To ensure in consultation with the site engineer that the manpower involved
in the works are moving as agreed and planned for the work.

5. To control disposal of waste materials according to the instructions received


from the site engineer.

6. To ensure full coordination with the safety officer to maintain safe working
and proper house keeping of the site, following the proved safety measures
and further ensure that all his working team are aware of the same to
prevent accident and losses.

7. To inform the site engineer regarding areas ready for inspection.

8. Foreman and the storekeeper are responsible for the distribution and control
of materials.

 SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in accordance with
the HSE plan and everybody aware of it for it’s proper implementation.

2. Ensure all the implemented safety measures are adequate to maintain safe
working on the site.

3. Inspect all the site activities and train the person to prevent accidents and
it’s proper implementation.

4. Ensure that the site is maintained clean and tidy.

 TECHNICIAN FROM SUPPILER


1. The carrying-out of work and the proper distribution of all the available
resources in coordination with the sub-contractor Site Engineer on a daily
basis.
2. Daily reports of the works are achieved and coordinated for the future
planning with the Site Engineer.
3. Complying with the sub-contractor basic design practices, particularly
those related to safety and engineering
4. Meeting with any type of unforeseen incident or requirement and reporting
the same to the Site Engineer immediately.

 STORE KEEPER
1. Responsible for overall Store operations in making sure to store the
material delivery to the site and keep it in suitable area that will keep the
material in safe from rusty and damage.
2. One who will acknowledge the receiving of materials at site in coordination
with QA/QC and concerned Engineer.

8. MANPOWER REQUIRED
 Charge hand and Experienced Technicians

9. MATERIALS REQUIREMENTS
 Electrical PVC Conduits Components and Accessories

10. EQUIPMENTS REQUIREMENTS


 The Equipment that will be engaged for Electrical PVC Conduits Installation will be as
follows:

1. Hack saw
2. Measuring tape
3. Cutting plier
4. Knipex (End cutter)
5. Bending spring
6. Drilling Machine

11. WASTE MANAGEMENT

 The Rubbish which would be created from our scope of works will be disposed to the
designated dumping ground.

12. SPECIAL CONTROL MEASURES


 The following general control measures against Safety, Environment and Quality shall
be required for our scope of work and special control measures are not applicable for
us :

 Proper PPE must be worn at all time


 Permit to work at height > 2m where applicable
 Lifting operation permit (using crane) where applicable.
 Confined space permit where applicable.
 Approved work method statement and risk assessment will be made available to
site.
 All workers doing the work shall be briefed on this method statement and risk
assessment.

13. SUPPORTING DOCUMENTATION


 This method Statement should be read in conjunction with the below referenced
documentations:

 ITP for Anti – termite Treatment.

 Insulation Resistance and continuity Test Report.

14. DISTRIBUTION
 Copy of this method statement shall be issued to the following for information / action /
comments:

1. Project Manager

2. Site Engineer

3. Foremen

4. Safety Engineer

5. Technician From Supplier

6. Store Keeper

You might also like