Statement For First Fixed Electrical Work
Statement For First Fixed Electrical Work
: 00
Method of Statement for first
fixed electrical work Date : 16-9-2021 Page: 2 of 3
00 Hytham El-Nouby
Rev.: 00
Method of Statement for first
fixed electrical work Date : 16-9-2021 Page: 2 of 3
05
04
03
02
01
00 - Original Issue
1- Scope:
his method of statement specifies the detailed requirements and procedures for first
fixed electrical work
2- Objective:
The objective of this method of statement is to define construction for first fixed
electrical work
- Measuring tape
- Cutting plier
- Box spanner set
- Bending spring
- Pipe Wrench
- Drilling Machine
- Pulling spring
- Hammer
- Common tools
4- Material
The sizes and routes routing will be as per the approved Shop Drawings.
Pre-Installation:
6-2 Prior to the commencement of works, ensure that the areas for
permanent installation are ready, accessible and in suitable
condition.
Installation:
- Slit and cracking in the walls drop the pipes from the ceiling joints and install
them using a concrete dots Pull the tube tensioner to ensure the wire path
Electricity boxes shall be installed free of charge or installed higher than
buildings at a distance of 2 cm
During the course of the installation of the conduit system, procedures for
working and dressing the installation as recommended shall be employed.
All bends and sets shall be in accordance with IEE regulation 522-08 formed
with the aid of a helical spring fitted internally, with if necessary, the conduit
warmed sufficiently for it to move without avoidable wall thinning of the
outside of the bend.
Joints between PVC conduit + fittings shall be made with suitable adhesive,
but expansion couplings shall be installed where any length of conduit,
inclusive of draw in boxes etc., exceeds five meters in length.
Where conduits are left "open ended" prior to wiring they shall be protected by
caps or plugs to prevent the ingress of building material.
All conduits runs must be designed to permit wiring to be readily installed after
the complete erection of the conduits through the available draw-in, accessory
and luminary suspension boxes.
Where conduits pass through an external wall/roof the conduit box shall be
fitted on the side and after wiring filled with an inert, permanently plastic
compound having a high insulation value.
Ensure conduits are not concealed until works has been inspected and
approved. Ensure that conduit and fittings buried in concrete or behind plaster
are protected against corrosion or electrolytic action prior to rendering.
7. RESPONSIBILITIES
PROJECT MANAGER
1. To ensure that all the preparation and application works are carried out
according to the Contract Specification and with the approved drawings.
3. To ensure that all the equipment and material required executing the work
are available according to the planned construction program.
4. To co-ordinate with the Main contractor, MEP coordinator, Safety Officer for
a safe and proper execution of the works.
SITE ENGINEER
1. To ensure that the works are carried out according to the Contract
Specification, approved method statement and the shop drawings.
3. To monitor the progress of work in relation with the work program and to
report to the Project Manager.
4. To co-ordinate with the safety officer and to ensure that the works are
carried out in safe practicing method.
FOREMAN
1. The foreman will carry out his duties by maintaining continuous coordination
with the site engineer on daily basis, and ensure proper distribution of the
work force on the required and planned locations.
2. To ensure that his assistant foreman/ charge hand are aware of the job
requirements and they have enough information to carry out their duties
properly.
3. To ensure that the daily work is progressing as planned and advice the site
engineer of any requirement for additional resources.
4. To ensure in consultation with the site engineer that the manpower involved
in the works are moving as agreed and planned for the work.
6. To ensure full coordination with the safety officer to maintain safe working
and proper house keeping of the site, following the proved safety measures
and further ensure that all his working team are aware of the same to
prevent accident and losses.
8. Foreman and the storekeeper are responsible for the distribution and control
of materials.
SAFETY ENGINEER
1. Ensure the implementation of all the safety measures in accordance with
the HSE plan and everybody aware of it for it’s proper implementation.
2. Ensure all the implemented safety measures are adequate to maintain safe
working on the site.
3. Inspect all the site activities and train the person to prevent accidents and
it’s proper implementation.
STORE KEEPER
1. Responsible for overall Store operations in making sure to store the
material delivery to the site and keep it in suitable area that will keep the
material in safe from rusty and damage.
2. One who will acknowledge the receiving of materials at site in coordination
with QA/QC and concerned Engineer.
8. MANPOWER REQUIRED
Charge hand and Experienced Technicians
9. MATERIALS REQUIREMENTS
Electrical PVC Conduits Components and Accessories
1. Hack saw
2. Measuring tape
3. Cutting plier
4. Knipex (End cutter)
5. Bending spring
6. Drilling Machine
The Rubbish which would be created from our scope of works will be disposed to the
designated dumping ground.
14. DISTRIBUTION
Copy of this method statement shall be issued to the following for information / action /
comments:
1. Project Manager
2. Site Engineer
3. Foremen
4. Safety Engineer
6. Store Keeper