JCT Environmental Infrastracture

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 46

JCT(LIR) Mahayag-Katipunan Road (Alicia side)

ENVIRONMENTAL MANAGEMENT FOR INFRASTRUCTURES AND ROADS (EMIR) Province of Bohol,


PHILIPPINES

PROJECT ENVIRONMENTAL ASSESSMENT REPORT

Project Provincial Road Maintenance Facility (PRMF) Implementing Partner Provincial Government of
Bohol

(Hon. Edgar M. Chatto, Governor) Project Name Rehabilitation of Jct. (LIR) Mahayag-Katipunan Rd (Alicia
Side) Location Alicia, Bohol Duration Approximately two (2) months Project Description & Cost

Gravelling of 5.725 km earth section of existing earth Provincial Road with an estimated cost of Four
Million Pesos (PhP4M). A detailed description of project activities is provided as Attachment A.

Certification: I, the undersigned, certify that:

1. The information in this form is correct and complete.

2. The following actions have been and will be taken to assure that the project complies with
environmental requirements established under the Government of the Philippines.

Prepared by: Environmental Management for Infrastructure and Roads (EMIR) Team

Name Agency Signature Date 1. Jeffrey A. Bernasor 2. Jovencia B. Ganub 3. Moises P. Cañete Jr. 4. Vilma
B. Baguhin 5. Zosimo Mejias 6. Einstein Gonzales 7. Judith Sumatra

DILG BEMO BEMO PEO PEO PEO

PPDO
_______________________ _______________________ _______________________
_______________________ _______________________ _______________________
_______________________

__________ __________ __________ __________ __________ __________ __________

Reviewed & Endorsed by Leonilo C. Lafuente BEMO-OIC ______________________ __________


Endorsed by: Ms. Ma. Loisella E. Lucino

DILG Provincial Director

______________________ __________

Rosalinda B. Yu Provincial Engineer ______________________ __________ Approved: Atty. Edgar M.


Chatto Provincial Governor ______________________ __________

JCT(LIR) Mahayag-Katipunan Road (Alicia side)

ATTACHMENT A

Project Environmental Assessment Report

Road Rehabilitation of Jct. (LIR) Mahayg – Katipunan Road (Alicia Side) Project Re-gravelling, Raise Up
and Widening

1.0 BASIC PROJECT INFORMATION


The proposed road rehabilitation project is located in Barangays Katipunan, Mahayag, San Isidro and
Babag in the Municipalities of Alicia, San Miguel, Pilar and Dagohoy, respectively Province of Bohol. The
existing 5.725 km length and 5.0 lm width of earth road ends Katipunan, Alicia. This road serves as a the
main route of transport of local agricultural products of the Barangays of Katipunan, Mahayag, San
Isidro and Babag and other influenced barangays in Boyles (Ubay), La Suerte and Estaca (Pilar) and
provides access to goods and services available in the towns of Alicia, Pilar, Dagohoy, San Miguel and
Ubay. Presently, the condition of the road section is poor and deteriorated with no proper drainage and
during heavy rain, the road section is flooded, becomes muddy and slippery that pose risks to motorists
and pedestrian. It has an average annual daily traffic of two hundred ninety one (291). The rehabilitation
of the deteriorated earth road which is under the core road network of Management Unit II of the
Provincial Engineer’s Office (PEO) is urgently needed. Refer to Annex A Location/Vicinity Map including
Vegetative Cover.

1.2 Rationale

The purpose of the project is to upgrade the deteriorated earth road section along existing route to an
all-weather gravel road. The rehabilitation work will include embankment fill in selected sections, re-
graveling, raise-up, widening and drainage structures without altering the existing hydrology of the
surrounding area. The Provincial Government of Bohol will fund and implement the road upgrading. The
PLGU will carry out regular road repair and maintenance, and implement recommended environmental
measures when operational.

1.3 Expected Results

When completed, the rehabilitated road is expected to provide safe year-round access and enable local
residents to transport produce and avail of goods and services in the town proper of Alicia and its
neighboring municipalities. It is anticipated that the road improvement will generate substantial savings
in transport costs and vehicle operating costs, increase net value added of farm produce, and create
incentives for local economic activities. In the long-term, the project is envisioned to help improve the
living and economic conditions in Barangays Katipunan, Mahayag, San Isidro, Babag and Boyles.

JCT(LIR) Mahayag-Katipunan Road (Alicia side)

2.0 PROJECT ACTIVITY DESCRIPTION Project Components The road rehabilitation project will be
implemented according to the DPWH Standard Specifications for Highways and Bridges (2004), and
Special Provisions and Supplementary Specifications for the project. The project is the Rehabilitation of
Junction Loay-Interior- Road at Mahayag to Katipunan Road situated on Alicia side. It is classified as a
Core Road. Embankment materials, surfacing materials and other road accessories are the needed
materials for the project. The scope of work has specific activities namely: pre- construction,
construction and post-construction phases. The project component activities are described in Table 1.
Table 1. Project Component Activities

Project Phases Activity Description and Assigned Responsibilities Responsible Parties Pre- Construction
Phase

Technical and engineering, social and environmental data are available for the preparation of Site
Development Plan for the road rehabilitation project. Refer to Annex B for the SDP and Site Photos.
Conducted public consultation with local residents, officials, and including representative from women’s
group (Annex C- Attendance Sheet and Photos). Confirm ROW prior to the start of construction (Annex D
– Certification). Take responsibility for security, information dissemination, and securing of necessary
government permits prior to the start of construction.

BEMO PEO PLGU PLGU

Construction Phase

Supervise the contractor and monitor construction work to ensure compliance with contractual
obligations. Carry out the scope of work for the road upgrading consisting of: • Widening of narrow road
sections to more than 5.0 lm width

carriageway prior to graveling or laying of sub-base materials; • Embankment fill to raise the road
elevation above the existing

ground level, as deemed necessary; • Installation of canals, cross-drain and side slope protection on

identified locations along the roadway, if applicable. Carry out any clean up and restoration works at the
construction area prior to demobilization.

PEO PEO Contractor Contractor


Operation and Maintenance

Operate the facility properly, provide necessary repair and maintenance works, and allocate adequate
funds and personnel for implementation.

PEO

JCT(LIR) Mahayag-Katipunan Road (Alicia side)

Implementation Schedule and Funding

The construction work will be approximately completed within two (2) months from mobilization with
an estimated total cost of Four Million Pesos (P4M) to be funded under the Provincial Roads
Management Facility. Skilled and unskilled workers, local hired labor, including women will be utilized
during the pre- during and post construction works.

PEO Contractor

3.0 ENVIRONMENTAL BASELINE INFORMATION Table 3 presents baseline environmental information to


characterize the existing condition at the general location of the project site prior to implementation.
Table 3. Baseline Environmental Information

Site Location Characteristics

Environmental Parameters Recorded and Reported Information

Geographic Location
Latitude 124ο 22.683’ E Longitude 9 ο 52.647.6’ N

Local Topography

Terrain/Slope The road section below the rice-field is of flat terrain and partly rolling

Elevation 131.8 to 144.1 m AMSL Local Geology

Soil Type Alicia has four (4) known soil types, namely: Ubay clay,

Faraon clay, Candijay Clay and rough stone land. The most dominant type is Ubay clay which occupies
7,802.03 hectares or about 68.14% of the total land areas. Faraon clay constitutes 2,158.32 hectares or
18.85%; Candijay clay occupies 1,095.76 hectares or 9.57% and Rough stone land occupies 393.88
hectares or 3.44% of the total land area. (CLUP-Alicia, p. 7)

JCT(LIR) Mahayag-Katipunan Road (Alicia side)

Minerals The municipality is covered by five (5) rock formations, namely: Carmen Rock Formation (Mc),
Alicia Schist (Pta), Sierra Bullunoes Limestone (Msb), Boctol Serpentine (Ptb) and Ubay Volcanics (Ptu).
Carmen formation covers 5,288.56 hectares or 55.11% of the total and area. the name of the formation
nis derived form Carmen town in the central part of Bohol where the type section is best exposed. It is
essentially composed of shale, sandstone, slabby to elastic limestone beds, conglomerare, siltstone,
mudstone and marl. Generally the sedimentary beds are low dipping and inter-bedded with each other
and assume a highly tuffacious nature. The base of the Carmen formation is a thin, medium-grained
particles of feldspars, glass shards, sharply angular glass and fragments of hexaltic horn bleeds. In
between shale beds are thin sandy tuffaceous stringers of volcanic ash and other pyroclastics. A period
of erogeny during the early Carmen time may have affected the complex structural behavior of the base
of the formation. The thickness of the exposure is difficult to determine. (CLUP-Alicia p. 5)

Local Hydrology Rivers/ Creeks The municipality is traversed by 4 major rivers, namely: Malitbog River,
Bagasiko River, Napo River and Cabatang River divides the boundary between Pilar and Alicia and
stretches a total length of 1.75 kilometers from its origin starting from the southwestern portion
between Barangays Cagongcagong and Katipunan ending at the western portion boundary between
Katipunan and Alicia. Bagasiko River starting from La Hacienda traverses Untaga Poblacion and Progreso
converging with the Cabatang River stretching to about 2.25 kilometers. This is known o be the longer
river in Alicia. Both Cabatang and Napo Rivers stretches to about 2 kilometers. The Tugasan Creek
originates at the northwestern portion of La Hacienda towards the northern end portion of Cabatang
stretching to a total length of 1.75 kilometers. This serves as the boundary between Alicia and Ubay.
There are 8 known springs located in Putlongcam, Mahayag, La Hacienda, Progreso, Cabatang, Cayacay,
Sudlon ang Napo. (CLUP Alicia, p. 7)

JCT(LIR) Mahayag-Katipunan Road (Alicia side)

Present Use Agriculture including inland fisheries and Domestic Use Safe and potable water is an
essential requirement for a healthy population and therefore ranks high in the priority of infrastructure
needs of the municipality. The Level II water supply in the Poblacion and partly in Del Monte, Sudlon and
Putlongcam is supplied from a spring in sitio Puti that is brought to the service area by gravity. (CLUP
Alicia, p. 41)

Sensitive habitats/species

None within 6 km radius from the project site

Local Climate Climate type Like the rest of Bohol, the climate of the municipality of Alicia is classified as
Type IV under the Corona Classification which is characterized by evenly distributed rainfall throughout
the year. Alicia is generally out of the typhoon belt and seldom experiences severe weather
disturbances. The municipality as well as the entire island of Bohol is generally sheltered from the
effects of most air masses from adjacent islands. (CLUP Alicia, p. 4)

Annual Rainfall The average annual rainfall as transposed from the neighboring stations is about 2,074
mm/year per sqm. The average annual municipal rainfall is the sum of the average annual rainfall from
their respective river basin multiplied by the percentage of the municipal area within the river basin.
Monthly rainfall within the year differs in varying degrees. The months from July to December a re
usually rainy months, while the months of January to June are the dry months. The prevailing winds
come from the north. (CLUP Alicia, p. 4)
Natural Earthquakes/Volcanic No reported of past occurrences

JCT(LIR) Mahayag-Katipunan Road (Alicia side)

Physical Hazards

Landslide/Erosion The areas that are not susceptible to erosion dominate the entire municipality. These
areas are characterized by the slopes which are level to nearly level wherein the drainage capacity of the
soil offsets the erosion potential. this occupies a land area of 6,330.71 hectares or 55.29% of the total
land area. Areas which are highly susceptible to erosion could be well observed on the northeastern and
southwestern portion of the municipality. This constitutes about 4,544.51 hectares or 39.69% of the
total land area of Alicia. These areas are characterized by an abrupt rise in elevation with slopes of over
8%. Areas moderately susceptible to erosion most likely occur in areas where slopes are characterized to
be nearly elevated which also depends on the type of soil present. This can be observed in the northern
portion of the municipality particularly in Untaga, Cabatang and Progreso. This occupies 574.79 hectares
or 5.02% of the total land area. (CLUP Alicia, p. 7-8) The project area (Katipunan) has none to low in
terms of its susceptibility to landslide and flooding (MGB Geo- hazard Summary)

Flooding The soil types of Alicia have high capacity to drain water from the rain, thus the municipality is
not prone to flooding and any hazards attendant to floods. On certain occasions, however, portions of
the Poblacion and Napo experience flooding particularly the eastern part when the Cabatang River
overflows. Approximately 420.21 hectares or 3.67% of the total land areas will be most likely affected
when flooding happens. (CLUP Alicia, p. 7)

Forest/ Vegetation Cover

Type Forest/Agricultural (coconut, rice, corn, fruits, vegetables, pasture grasses, native and exotic tree
species, banana, mangoes, rootcrops) and other non- forest products, like bamboos, rattan

JCT(LIR) Mahayag-Katipunan Road (Alicia side)


Coverage area The forest is an important natural resource that provides a wide range of benefits to the
community even as in the case of Alicia, it only consists mostly of pastureland. It has been and continues
to be subjected to numerous conflicting uses that include food production, human settlements and a
variety of economic activities or a combination of the above. This has resulted in accelerated soil
erosion, siltation of rivers and waterways, shortages of wood and other forest products and the
destruction of plant and animal habitats. (CLUP Alicia, p. 24)

Protected Areas

Forest/Timberland

The municipality has a relatively small timberland area of 407 hectares representing 3.5% of its total
land area which can be found in 4 of the 15 barangays: Cagongcagong (71 hectares); Del Monte (109
hectares); Mahayag (128 hectares); Sudlon (99 hectares) (CLUP Alicia, p.78) The Municipality of Alicia is
within the Carood Watershed.

Coastal/Inland Waters

None

Land Area and Existing Land Use

Land Area (ha) 11,450 hectares (CLUP Alicia, p.77) Land Classification & Use

The municipality has 11,450 hectares. 11,043 hectares or 96.45% are classified as Alienable and
Disposable Land, while 407 hectares or 3.55% are classified as Timberland Area. (CLUP, Alicia, p. 77). The
existing general land use pattern of the Municipality of Alicia is typical of Philippine rural communities.
Predominantly agricultural, the settlements are widely dispersed and scattered. Houses are constructed
along the road and in the middle of their farms, which makes it difficult to introduce basic facilities and
services. There are areas, however where the concentration of settlements is located near their sources
of livelihood. (CLUP Alicia, p. 83)

Population (Latest Census Data)


Total Population 4th Class municipality with 23,422 people as of 2007 census in 14 barangays
(nso.gov.ph)

Total Households 4,065 HH with an average HH size of 5.31 persons Ethnic Group (%) 100% Boholanos
Est. Total Beneficiaries

Four (4) Target Barangays with a total 2012 projected population of 8,926: Katipunan, Alicia (2,738);
Mahayag, San Miguel (2,738); San Isidro, Pilar (2,543) and Babag, Dagohoy (1,319)

JCT(LIR) Mahayag-Katipunan Road (Alicia side)

Local Economy

Total Labor force 7,037 Main Income source Farming / Agriculture

Basic Services and Infrastructures

Water supply Level 3 water system 310 HH population served; Level II water system 1,671 HH
population served; Level I water system: 75 shallow wells serving 5,683 HH, 20 deep wells serving 2,296
HH and 101 improved springs serving 19,146 HH. (CLUP Alicia, p. 41-42)

Sanitary toilets 53 HH with water sealed toilets; 3,102 water- sealed/other depository used exclusively
by the household; 76 closed pit (Antipolo type) toilet; 187 open pit toiler and 201 without sanitary
latrines. (CLUP Alicia, p. 59)

Electricity 14 Barangays have access to electricity provided by BOHECO II.

Transportation
The growing demands for well-maintained farm-to- market roads have not been adequately responded;
road maintenance of existing roads had been poor and access to and from these areas have slightly
improved. The municipality has satisfied the standard of 1 kilometer per square kilometer of land area
since it has a total road length of 128.02 which the standard would only require 114.5 kilometers. There
are 11 bridges in the municipality with a total of 325.6 lm: (National 7; Provincial 1; Barangay 3).

Communication 1. Telephone: The municipality has two Public Calling Office (PCO); Islacom/Globelines
provides household connections in the Poblation area; Cellular Phones provided by SMART, GLOBE and
Sun Cellular

2. Telegraph – Telecommunications Office (TelOff) 3. Postal Service 4. Portable radio transceivers 5.


Broadcast media 6. Print media 7. BLECS (CLUP Alicia, pp. 31-33)

Education The municipality has 2 Primary Schools; 12 elementary

schools out of 14 barangays and 2 secondary schools. (CLUP Alicia, p. 46).

10

JCT(LIR) Mahayag-Katipunan Road (Alicia side)

Health The municipality has adequate health facilities and personnel to attend to health needs of its
populace. It has 5 Barangay Health Stations, Municipal Health Office and the Alicia Municipal Hospital.
(CLUP Alicia pp. 56- 57)

Social Welfare There are 15 Day Care Centers and 15 Social Welfare Officers out of 14 barangays with
registration services; Senior Citizens Center; Municipal Social Welfare and Development Office and
Provincial Social Welfare and Development Officer Social Welfare services include Family Life Education
and Counseling, Family Planning Assistance, Day Care Services, Supplemental Feeding, Medical Care,
Relief/Rehabilitation, Senior Citizens Care. (CLUP Alicia, p. 66)

Religious Buildings Catholic Church (1) located at the Poblacion area Police/Fire Protection There are 15
policemen currently stations in Alicia with
a police to population ratio of !:1,335. There is also a Military outpost located at La Hacienda, Alicia.
There are also Barangay Tanods in the 14 Barangays of the municipality. No Fire Station in Alicia.

11

JCT(LIR) Mahayag-Katipunan Road (Alicia side)

4.0 EVALUATION OF PROJECT ISSUES WITH RESPECT TO POTENTIAL ENVIRONMENTAL

IMPACT Table 4 presents the Environmental Impact Screening Matrix for the proposed road
rehabilitation project. No significant adverse environmental impacts have been identified and
determined to arise during project implementation. There is a portion of the road section that would
require cutting of a few planted trees. Considering that the road section is generally flat, some rice fields
will be affected by the road widening and raise up processes, thus road design should consider
adjustments especially in the embankment. The purpose of the road rehabilitation project will have to
be communicated effectively to the barangay officials and residents of the affected areas to gain
support. Only few houses in the area have bamboo fences that will be affected in the project. Table 4.
Environmental Impact Screening Matrix

Project Activities

Potential Environmental Issues and

Concerns Arising from Project Activities

None or Insignificant

Impact

Significant Impact Duration of Impact


Low Mod High Short term Long- term

Pre- construction Stage

Affect existing forested area  Require tree cutting or vegetation clearing



Remove permanent structures of value

Damage cultural and historic resources

Impair local aesthetic or scenic resources

Require additional land for ROW acquisition

Cause relocation and resettlement  Damage present local service facilities

Damage to properties or belongings


Impose additional demand on local services

Restrict public access to the area  Pose human health and safety hazards

Create job opportunities/local hired labor

12

JCT(LIR) Mahayag-Katipunan Road (Alicia side)

Project Activities

Potential Environmental Issues and

Concerns Arising from Project Activities

None or Insignificant

Impact
Significant Impact Duration of Impact

Low Mod High Short term Long- term

Construction Stage

Generate excess excavation materials



Generate construction wastes and debris



Generate wash/wastewater/runoff  Induce topsoil erosion/deposition  Create nuisance noise, dust


and vibrations



Pose human health and safety hazards



Impose additional demand for local services



Affect pedestrian/vehicular traffic flow




Create increased demand for aggregates



Create job opportunities/local hired labor

+

Post- Construction & Operation Stage

Increase demand for water and power services



Increase demand for waste disposal



Increase demand for drainage/sewerage



Increase demand for traffic protection/control



Increase health and safety hazards   Create income and livelihood opportunities
+

Improve delivery of goods and services

+

Contribute to effective land use & development

+

Promote/ support in peace development

+

Note: + means potential beneficial impact

13

JCT(LIR) Mahayag-Katipunan Road (Alicia side)

5.0 ENVIRONMENTAL MANAGEMENT PLAN (Recommended Mitigation, Monitoring

and Evaluation Measures) The Environmental Management Plan (EMP) shown in Table 5 is prepared to
guide implementation of recommended impact mitigation and monitoring measures by the responsible
persons or agency to assure satisfactory compliance of the plan.

14
JCT(LIR) Mahayag-Katipunan Road (Alicia side)

Table 5: Environmental Impacts Management Plan

Project Phase / Environmental

Aspect Source of Impact Potential Impact

Magnitude (Slight,

Moderate, Severe)

Time Frame (Short,

Medium, Long)

Affected Road Section

Affected Area Outside of the Road Section

Prevention / Mitigation or Enhancement Measures Recommendations

Pre-construction

Land Mobilization of contracted physical works; Road works preparation

Clearing and grubbing of trees and other vegetation. Disturbances and damages to public and private
lands and associated properties. Vehicular traffic disturbances. Uncovered or unrelated Auger borings
and test pits.
Slight Slight Slight Slight

Short Short Short Short

Bunkhouse Portion of the road section Entire road section Selected section

None None None None

Surveyors must preserve and protect all existing vegetation in the area. Site clearing, if necessary, must
be regulated and minimized. Proper protocols of surveying must be observed. Re-vegetation required.
Allocate funds for damages Assign flagman Holes and borings must be properly replaced;

• Identify area for clearing

• Tree Inventory • Coordinate with the

affected land owner. • Enter into agreement

and settlement • Installing of signage

and traffic route. • Re-routing of traffic or

using one lane. • Replace materials on

test pits after boring

Air Depletion of air quality


Slight Short Entire road section

None Deployment of good- conditioned vehicles and equipment.

• Conduct community awareness

• Provision of PPE ex.

15

JCT(LIR) Mahayag-Katipunan Road (Alicia side)

Project Phase / Environmental

Aspect Source of Impact Potential Impact

Magnitude (Slight,

Moderate, Severe)

Time Frame (Short,

Medium, Long)

Affected Road Section

Affected Area Outside of the Road Section

Prevention / Mitigation or Enhancement Measures Recommendations


Regular check up of vehicles and equipment conditions.

mask

Air pollution/increase of noise in the area.

Slight Short Entire road section

Immediate neighboring areas

Limit loud and vibratory activities only during the daytime. Use mufflers and sound insulators.
Deployment of well maintained vehicles and equipment.

• Conduct community awareness

Water Increase usage and competition of domestic water resources.

Slight Short Entire road section

None Controlled use of local water. • Conduct community awareness

Generation of domestic wastes that reduce water quality, potential for bacterial diseases.

Slight Short Entire road section

None Right management of liquid and solid wastes in work camps. Proper implementation of waste
segregation and immediate disposal of putrescible and domestic wastes
• Identify dumping area for waste disposal and segregation

• IEC

People Roadworks In-migration of construction workers

Slight Short Provide opportunities for employment Priority for local labor

Construction

Land Clearing and grubbing

Disturbance of flora and fauna

Moderate Medium Entire road section

None • Limit activity only within road right of way.

• Re-vegetation, replacement

or replanting of trees.

• Strictly adhere to the road design

• Replacement of trees cut on designated area (1 tree cut

16

JCT(LIR) Mahayag-Katipunan Road (Alicia side)


Project Phase / Environmental

Aspect Source of Impact Potential Impact

Magnitude (Slight,

Moderate, Severe)

Time Frame (Short,

Medium, Long)

Affected Road Section

Affected Area Outside of the Road Section

Prevention / Mitigation or Enhancement Measures Recommendations

replaced with 10 trees planted in a designated area using indigenous species)

• Identify dumping area of uprooted vegetation.

• Cut trees should be at the disposal of the owner.

Generation of construction wastes

Moderate Medium Entire road section


None • Solid waste management plan to include waste segregation, recycling and reuse of generated
wastes.

• Proper coordination with

LGU on the proper disposal of generated construction wastes

• Construct waste disposal facility

• Identify site with LGU

on disposal

Generation of spoils

Moderate Medium Entire road section

None All excess soil generated by the project will be reused or disposed at designated disposal sites.

• Identify excess soil disposal site

Quarry/borrow pit for road aggregates.

Depletion of mineral resources

Moderate Medium Identified site

Quarry areas Selection of suitable intermediate borrow pit nearer to works if possible.
• Borrow pit for road aggregates must be from a permitted area as recommended by BEMO

17

JCT(LIR) Mahayag-Katipunan Road (Alicia side)

Project Phase / Environmental

Aspect Source of Impact Potential Impact

Magnitude (Slight,

Moderate, Severe)

Time Frame (Short,

Medium, Long)

Affected Road Section

Affected Area Outside of the Road Section

Prevention / Mitigation or Enhancement Measures Recommendations

Earthworks and gravel road construction

Soil quality degradation

Slight Short Selected section


None Scrapped productive top soil be returned to sustain soil fertility/productivity in the nearby areas

Terrestrial ecosystem temporary disruption

Slight Short Selected section

None Replacement or re-planting of tree and other vegetation

• Tree planting on identified site

Potential for elevated erosion

Slight Short Selected section

Immediate area of the project site

Strictly follow sound design requirements and specifications like stabilization of slopes. Minimize ground
disturbance and always consider local climate and inclement weather. Soil compaction in excavated
areas (i.e. culverts, drainages) Provision of biological soil erosion control measures

• Install slope protection

• Install drainage and

pipe culverts • Construct line canal • Planting of vetiver

plant Unmanaged road spills of hydrocarbons from diesel generators, fuel storage tanks, and from
maintenance of vehicles and equipment.
Moderate Medium Entire road section

None Appropriate management of petroleum (e.g. fuels, oil and lubricants) products handling and
vehicles maintenance.

• Preventive maintenance of equipment

18

JCT(LIR) Mahayag-Katipunan Road (Alicia side)

Project Phase / Environmental

Aspect Source of Impact Potential Impact

Magnitude (Slight,

Moderate, Severe)

Time Frame (Short,

Medium, Long)

Affected Road Section

Affected Area Outside of the Road Section

Prevention / Mitigation or Enhancement Measures Recommendations


Air Loading, transport and unloading of construction materials and aggregates; Construction of facilities

Air Pollution due to Increase in total suspended particles (TSP)

Moderate Medium Entire road section

Immediate vicinity of the project site

Use of tarpaulin covers for delivery trucks.

• Community information and monitoring

Earthworks and gravel road construction

Air Pollution due to increased emission of TSP, SOx and NOx.

Moderate Medium Entire road section

None Regular water spraying on aggregate piles and exposed areas. Regular watering of construction
site when needed. Proper operation and regular engine maintenance.

• Community information

Noise Pollution due to increase of noise in the area.

Moderate Medium Entire road section

None Limit loud and vibratory activities only during the daytime. Use mufflers and sound insulators.
Proper operation and regular engine maintenance.
• Community information

Water Loading, transport and unloading of construction materials and aggregates;

Siltation of drainage line and water body due to washed aggregates

Slight Short Entire road section

Nearby water sources

Proper stockpiling of aggregates. Build perimeter fence to shield the construction area from outsiders

• Installation of signages

19

JCT(LIR) Mahayag-Katipunan Road (Alicia side)

Project Phase / Environmental

Aspect Source of Impact Potential Impact

Magnitude (Slight,

Moderate, Severe)

Time Frame (Short,


Medium, Long)

Affected Road Section

Affected Area Outside of the Road Section

Prevention / Mitigation or Enhancement Measures Recommendations

Construction of facilities and work camps.

Earthworks and gravel road construction

Unmanaged road spills of hydrocarbons from diesel generators, fuel storage tanks, and from
maintenance of vehicles and equipment.

Slight Short Entire road section

None Appropriate management of petroleum (e.g. fuels, oil and lubricants) products handling and
vehicles maintenance.

• Contractor to formulate Operational Control Procedure on Vehicle Maintenance so as to prevent


water pollution in the surrounding area of the project site

Potential soil and water contamination with impacts on ecosystem and people

Slight Short Entire road section

None Strictly observe and implement road design and implementation of liquid waste management

• Close monitoring of road works


Potential for water blockage or drainage issues; potential for erosion; surface water impacts from
sediments

Slight Short Portion of the section

Near rice field areas

Follow appropriate construction guidelines and install culverts/drains as required to cater for surface
water flows.

Proper embankment

River siltation and surface water quality impacts from sediments.

Slight Short Portion of the section

Near a creek Provision of silt traps structures.

Monitoring of silt contamination in rivers and creeks

20

JCT(LIR) Mahayag-Katipunan Road (Alicia side)

Project Phase / Environmental

Aspect Source of Impact Potential Impact


Magnitude (Slight,

Moderate, Severe)

Time Frame (Short,

Medium, Long)

Affected Road Section

Affected Area Outside of the Road Section

Prevention / Mitigation or Enhancement Measures Recommendations

Failure to use and apply material correctly could potentially cause erosion and surface water impacts
from sediments.

Slight Short Entire road section

None Construct pavement using sub- base course, base course, and wearing course placed in layers,
shaped to profiles and compacted using selected materials in accordance with the engineering design
standards and specifications.

Identify erosion problem areas along the road section and mark appropriately

Failure to construct suitable roadside drainage ditches can result in erosion as well as impacts on
drinking water quality and nearby riverine ecosystems

Slight Short Portion of the section


Malitbog River near Katipunan

Form roadside drains comprising earth ditches with drains comprising earth ditches with selected
sections lined as appropriate to prevent erosion, in accordance with the engineering design standards
and specifications.

Identify erosion problem areas along the road section and mark appropriately

People Mobilization of contracted physical works; Road works preparation; and Construction of
facilities.

In-migration of construction workers, personnel and other migrants. Probable disorder.

Slight Short Entire road section

None Provide opportunities for employment or livelihood. Observe peace and order. Maintain good
working relation between workers and local residents.

Hire local laborere

Sanitation - Generation of domestic wastes and reduced water quality, potential for

Slight Short Entire road section

None Right management of liquid and solid wastes in work camps. Proper implementation of waste
segregation and immediate disposal of putrescible and domestic waste in coordination

• Contactor to establish proper disposal of liquid and solid waste at work camps.

21
JCT(LIR) Mahayag-Katipunan Road (Alicia side)

Project Phase / Environmental

Aspect Source of Impact Potential Impact

Magnitude (Slight,

Moderate, Severe)

Time Frame (Short,

Medium, Long)

Affected Road Section

Affected Area Outside of the Road Section

Prevention / Mitigation or Enhancement Measures Recommendations

bacterial diseases with the MLGUs • Construct latrines for stay in workers.

• Bacteriological testing of drinking water

Hiring of local fit- to-work construction workers

Increase of local employment and improve local economy.


Moderate Medium Entire road section

Other influenced barangays

Local employment is recommended to maximize benefits to the community. Priority of hiring to be


given to qualified residents of the hosts and nearby barangays.

Post appropriate manpower hiring notice on time

Use of heavy equipment and vehicles during hauling and construction.

Health impacts - possible incidences of respiratory illnesses.

Slight Short Entire road section

None Ensure protection of workers and residents from dusts coming from the operation of vehicles and
equipment (e.g. use of personal protective equipment)

Provide PPEs and orient workers on the health risk associated with the work

Earthworks and gravel road construction

Potential accidents of workers

Slight Short Entire road section

None Adopt appropriate safety measures; provide first-aid services; and make workers aware of risks
and how to avoid them.

• Workers provided with PPEs


• Conduct Work Safety Orientation

Coordinate with nearest hospital and concerned government agency for emergency medical response
and rescue operations

• Emergency vehicle on stand-by

• Emergency Numbers posted at the work camps

Disruption of road traffic

Slight Short Entire road section

None Rerouting traffic and installation of road traffic signages

• Assign flagmen to direct traffic

22

JCT(LIR) Mahayag-Katipunan Road (Alicia side)

Project Phase / Environmental

Aspect Source of Impact Potential Impact

Magnitude (Slight,

Moderate, Severe)
Time Frame (Short,

Medium, Long)

Affected Road Section

Affected Area Outside of the Road Section

Prevention / Mitigation or Enhancement Measures Recommendations

Abandonment

Land, Air, Water and People

General clean up of the work staging areas, from temporary structures, unserviceable equipment,
formworks, used oils, lubricants and sanitation facilities.

Erosion, increase in bacterial insect- borne disease from waste and others due to failure to rehabilitate
work- site, including borrow areas and work camps

Moderate Medium Entire road section and Bunkhouse

Depository areas for excess materials

Works Specification and Conditions of Contract. Ensure work camp is removed/rehabilitated in


accordance with DPWH guidelines.

Conduct final inspection of the work camp and staging areas


Continued monitoring, auditing and appropriate resourcing

Decline in road quality and resultant impacts across the range of issues due to failure to continue with
established practices, monitoring and auditing.

Moderate Long Entire road section

Other surrounding areas influenced by the project

Budget set aside for monitoring and EMoP in place.

• Conduct regular EMP Monitoring as scheduled.

• Leveling and compilation of lessons learned.

• Establish the Adopt a Road Program.

23

JCT(LIR) Mahayag-Katipunan Road (Alicia side)

Table 6: Environmental Monitoring Plan (EMoP)

Responsible Entity : Provincial Engineer’s Office Name of the Contractor:

Project Phase / Environmental

Aspect Source of Impact Potential Impact Prevention / Mitigation or Enhancement Measures


Parameters to be Monitored Road Section Recommendations

Pre-construction Land Mobilization of

contracted physical works; Road works preparation

Clearing and grubbing of trees and other vegetation. Disturbances and damages to public and private
lands and associated properties. Vehicular traffic disturbances. Uncovered Auger borings and test pits.

Surveyors must preserve and protect all existing vegetation in the area. Site clearing, if necessary, must
be regulated and minimized. Proper protocols of surveying must be observed. Holes and borings must
be properly replaced; Re-vegetation.

Design specifications; Integrity of existing vegetations in the proposed project Bore holes

Whole section of the road

Replanting of affected/cleared trees (1 tree cut replaced with 10 trees planted

Air Depletion of air quality Deployment of good-conditioned vehicles and equipment. Regular check up
of vehicles and equipment’ conditions.

Air quality; Condition of vehicle

Entire road section

Get emission test results of heavy equipment

Increase of noise in the area. Limit loud and vibratory activities only during the daytime. Use mufflers
and sound insulators. Deployment of well maintained vehicles and equipment.
Noise level; Vibration

Entire road section

Daytime operation only and using of mufflers and other sound insulators

Water Increase usage and competition of domestic water resources.

Water conservation measures Water usage Encourage use of rain water

Generation of domestic waste that reduce water quality, potential for bacterial diseases.

Right management of liquid and solid wastes in work camps. Proper implementation of waste
segregation and immediate disposal

Solid and liquid waste generated

Implement waste segregation

24

JCT(LIR) Mahayag-Katipunan Road (Alicia side)

Project Phase / Environmental

Aspect Source of Impact Potential Impact Prevention / Mitigation or Enhancement Measures

Parameters to be Monitored Road Section Recommendations


of putrescible and domestic wastes

People Involuntary resettlement issues for Project Affected Persons (PAPs)

The proponent shall establish in their final survey the PAPs that will be affected by the project.
Corresponding mechanism for payment shall be done based on Philippine laws.

Presence of PAPs along road right of way

Inventory of PAPs Inform the officers and members of the Carood Watershed Management Council of
the project

Construction Land Clearing and

grubbing Disturbance of flora and fauna Limit activity only within road right

of way. Magnitude of affected area Species affected

Indicate road section that will be affected

Consider re-design alignment of road section to minimize impacts of clearing and grubbing

Re-vegetation, replacement or replanting of affected trees

Number of trees affected and planted

Indicate road section that will be affected


Replacement planting of affected trees 1 tree cut:10 trees replanted using indigenous tree species
Identification of planting sites and number of trees to be planted

Generation of construction wastes

Solid waste management plan to include waste segregation, recycling and reuse of generated wastes.

solid waste generated

Implement requirements of RA 9003 Cut trees will be at the disposal of the owner

Proper coordination with the concerned LGUs on the proper disposal of generated construction

Solid Waste Management practices

Entire road section

Refer to ESWM Plan of the LGU

25

JCT(LIR) Mahayag-Katipunan Road (Alicia side)

Project Phase / Environmental

Aspect Source of Impact Potential Impact Prevention / Mitigation or Enhancement Measures

Parameters to be Monitored Road Section Recommendations


waste

Generation of spoils All excess soil generated by the project will be reused or disposed at designated
disposal sites.

Volume of excess soil or spoils

Road section Use excess soil as embankment material

Quarry/borrow pit for road aggregates.

Depletion of mineral resources/ Insufficient quarry/borrow pits to provide aggregate

Selection of suitable intermediate borrow pit nearer to works if possible.

Location of quarry areas Volume of quarry materials needed

Road section Comply with the provisions of the Provincial Ordinance No 2008-025 (Provincial Mining
Ordinance)

Depletion of mineral resources/unlicensed quarry site.

Identify, secure, and comply with all permitting requirements.

Quarry permit either from PLGU (equal or less than 5 hectares) or Mines and Geosciences Bureau (more
than 5 hectares)

Entire road section

Check with BEMO on the permitted quarry sites near the project area
Earthworks and gravel road construction

Soil quality degradation Scrapped productive top soil be returned to sustain soil fertility/productivity

Volume of scrapped top soil

Entire road section

Deposit top soil in a designated area for future use

Terrestrial ecosystem temporary disruption

Replacement or re-planting of tree and other vegetation

Number of trees affected by the project

Portion of the road section

Replacement planting 1 tree cut: 10 trees replaced and planted in a designated area

Potential for elevated soil erosion in the project site and nearby rice field areas

Strictly follow sound design requirements and specifications like stabilization of slopes.

Soil erosion in the project site and nearby rice field areas

Implement soil stabilization techniques


Minimize ground disturbance and always consider local climate and inclement weather.

Soil compaction in excavated areas Use appropriate culvert size

26

JCT(LIR) Mahayag-Katipunan Road (Alicia side)

Project Phase / Environmental

Aspect Source of Impact Potential Impact Prevention / Mitigation or Enhancement Measures

Parameters to be Monitored Road Section Recommendations

(i.e. culverts, drainages).

Provision of biological soil erosion control measures

Planting of soil stabilization grasses like vetiver grass

Soil contamination due to unmanaged road spills of hydrocarbons from diesel generators, fuel storage
tanks, and from maintenance of vehicles and equipment.

Appropriate management of petroleum (e.g. fuels, oil and lubricants) products handling and vehicles
maintenance.

Presence of road spills from vehicles and volume of spills

Implement safety standards to avoid oil and fuel spillages Formulate and implement Operational Control
Procedures
Air Loading, transport and unloading of construction materials and aggregates; Construction of facilities

Air pollution due to Increase in total suspended particles (TSP)

Use of tarpaulin covers for delivery trucks.

TSP level Delivery trucks must at all times be covered when hauling materials

Earthworks and gravel road construction

Air pollution due to Increased emission of TSP, SOx and NOx.

Regular water spraying on aggregate piles and exposed areas.

Exhaust level from vehicles

You might also like