Format No: GPL-NZ-QUALITY-F-97
Rev. No:01
GODREJ PROPERTIES LIMITED Effective Date :03.10.2019
NON-CONFORMANCE REPORT
Project Name: Godrej Golf Links NCR Ref No: GGL/GEM/SSB/05 (Evoke)
Proj. Manager: Mr. Saurabh Madaan Date of Issue: 05-08-2021
Consultant: GEM NCR for: System Implementation
Contractor: SSB Quality √
NC √ Major NC √ Critical NC Others
Description of the Non-Conformance – Marble flooring work.
Location: V5/Villa no 53 and 54 Evoke
Major shade variation observed in Italian marble in dining area & Living area Ground floor.
Issued By: Rajeev Kumar Signature:
Reference Documents: Received By:
Specs/Stand: Name:
Drawings: Position:
Section/Clause: Signature:
Others: Date:
A) Proposed Correction (to be filled by Auditee):
B) Acceptance of Proposal: Approved – proceed as proposed. Approved w/comments –
proceed and follow below comments. Not Acceptable – submit new proposal.
Name: Signature: Date:
C) Root Cause: N/A
D) Corrective action to prevent recurrence (Proposed/implemented): (to be filled by Auditee)
Proposed:
Implemented:
Name: Signature: Date:
E) Acceptance of Corrective action: Approved – proceed as proposed. Approved
w/comments – can be closed only after attending all comments. Not Acceptable – Re work
required.
Name: Signature: Date:
F) Comments by Auditor/Consultant:
Name: Signature: Date:
G) Non-conformance closed out satisfactorily after implementation of corrective action Yes
No
Name: Signature: Date:
GPL
Name Designation Signature Date