PEGS-12059-COR-055 - Technical Assessment of Coating Plants

Download as pdf or txt
Download as pdf or txt
You are on page 1of 26

PTT Exploration and Production Public Company Limited

PTTEP Engineering General Specification

PEGS

Technical Assessment of Coating Plants

Document No: PEGS-12059-COR-055

Revision No: 0-0

Revision Date: February 2015


PTT Exploration and Production Public Company Limited

Revision History

Rev Description of Revision Authorised by Date


0-0 New document, update division code as new PTTEP organization (1
Jan 2015).

February 2015 Rev.0-0 History


UNCONTROLLED when printed, visit PTTEP Intranet for latest version
Technical Assessment of Coating Plants PEGS-12059-COR-055

TABLE OF CONTENTS

1.0 Purpose................................................................................................................... 1
2.0 Scope ...................................................................................................................... 1
3.0 Definitions .............................................................................................................. 2
3.1 Language .................................................................................................................................. 2
3.2 Terminology .............................................................................................................................. 2
3.3 Common Acronyms .................................................................................................................. 2
4.0 References.............................................................................................................. 3
4.1 PTTEP Internal References ...................................................................................................... 4
4.2 International Standards ............................................................................................................. 4
4.3 Industry Codes and Standards ................................................................................................. 4
5.0 Requirements for Technical Assessment Process of Coating Plants ................ 5
5.1 Step 1: Gathering of Information ............................................................................................... 5
5.2 Step 2: Data Analysis of Appendix 1 and Following Actions .................................................... 5
5.3 Step 3: Assessment notification to the Coater .......................................................................... 5
5.4 PQT / PPT to perform during Audit of the Coater Production Site ........................................... 6
6.0 APPENDICES .......................................................................................................... 7
Appendix 1. Technical Information Analysis Form: Coating Plant - EXCEL spreadsheet .................. 7

February 2015 Rev.0-0 TOC


UNCONTROLLED when printed, visit PTTEP Intranet for latest version
Technical Assessment of Coating Plants PEGS-12059-COR-055

1.0 PURPOSE

The purpose of the PTTEP Engineering General Specification, PEGS-0710-COR-055


Technical Assessment of Coating Plants is to specify general and fundamental rules and
procedures; assuring technical integrity and fitness of purpose with optimum life cycle cost.

2.0 SCOPE

This Specification defines the COMPANY’s practices and tools used to perform technical
assessments of coating plants.

February 2015 Rev.0-0 Page 1 of 22


UNCONTROLLED when printed, visit PTTEP Intranet for latest version
Technical Assessment of Coating Plants PEGS-12059-COR-055

3.0 DEFINITIONS

A number of different terms are commonly used to describe the work stages, processes, and
approvals which take place during the early stages of a development. This can often be a
source of confusion so the following section is intended to show the PTTEP preferred
terminology as used in this document.

3.1 LANGUAGE

In this document, the words should and shall have the following meanings:

Should Indicates a preferred course of action. Should is a non-mandatory word and


is not forbidden, but use in the body of the text should be the exception.
Where none mandatory terms are used, each paragraph within these clauses
shall also have an associated commentary paragraph that provides the
rationale for why the stated choices and modifications are appropriate and
circumstance under which the stated choices and modifications might be
different.
Shall Indicates a course of action with a mandatory status. The term “shall” shall
be used if a requirement is considered to be necessary to claim compliance
with a PEGS document.

3.2 TERMINOLOGY

Terminology Description

Approval The authorization in writing given by the COMPANY to the Contractor on a procedure
or to proceed with the performance of a specific part of the work without releasing in
any way the Contractor from any of his obligations to conform with the technical
specifications, requisitions, etc. The words “Approve”, “Approved” and “Approval” shall
be construed accordingly
Contractor Per contract: Contractor – ‘The contractor who is a PARTY to this CONTRACT and
where the context so requires, any and all SUBCONTRACTORS utilised by
CONTRACTOR for the performance of the WORK’

3.3 COMMON ACRONYMS

Set out below in alphabetical order are common acronyms as found within this document:

N/A

February 2015 Rev.0-0 Page 2 of 22


UNCONTROLLED when printed, visit PTTEP Intranet for latest version
Technical Assessment of Coating Plants PEGS-12059-COR-055

4.0 REFERENCES

The reference documents listed below, including Industry Codes and Standards and
COMPANY specifications, form an integral part of this Engineering General Specification.
Unless otherwise stipulated, the applicable version of these documents, including relevant
appendices and supplements, is the latest revision published on the effective date of a
contract.

The overall order of precedence of the applicable documents shall be:

1. Applicable Laws, Rules and Regulations of the country in which the system/equipment
will be operated (if any);

2. Purchase Order/ Service Order/ Contract Documents (Only applicable for direct
purchase by COMPANY);

3. Project Particular Specification (PPS), and relevant data sheet(s) if any;

4. COMPANY General Specification;

5. Codes and Standards in reference.

Any conflict between any of the Contract Documents, or between this specification and any
other Contract Document, shall be reported to COMPANY for decision. In such a case, and
unless otherwise agreed or decided by COMPANY, it is understood that the more stringent
requirement shall apply.

Exceptions to, or deviations from this specification are not permitted unless previously
accepted in writing by COMPANY. For this purpose, requests for substitutions or changes of
any kind shall be complete with all pertinent information required for COMPANY assessment.
COMPANY’s approval, nevertheless, will not, in any way, relieve the responsibility of the
Contractor to meet the requirements of the industry Codes and Standards referred to and
amended herein, in the event of conflict.

February 2015 Rev.0-0 Page 3 of 22


UNCONTROLLED when printed, visit PTTEP Intranet for latest version
Technical Assessment of Coating Plants PEGS-12059-COR-055

4.1 PTTEP INTERNAL REFERENCES

Internal documents applicable to this document are indicated in the table below.

Document Number Document Title

PEGS-0842-COR-001 External anticorrosion coating for pipelines

4.2 INTERNATIONAL STANDARDS

International standards applicable to this document are indicated in the table below
i.e. ISO, IEC or ITU.

Document Number Document Title

N/A N/A

4.3 INDUSTRY CODES AND STANDARDS

Industry codes, standards and regional legislation applicable to this document are indicated in
the table below.

Document Number Document Title

N/A N/A

February 2015 Rev.0-0 Page 4 of 22


UNCONTROLLED when printed, visit PTTEP Intranet for latest version
Technical Assessment of Coating Plants PEGS-12059-COR-055

5.0 REQUIREMENTS FOR TECHNICAL ASSESSMENT PROCESS OF COATING


PLANTS

The technical assessment process of a coating plant is part of the global assessment process
of a Supplier, led by the COMPANY Purchasing Division.

5.1 STEP 1: GATHERING OF INFORMATION

To start the technical assessment process, Appendix 1 of this document (Technical


Information Analysis Form) shall be sent to the Coater, by the COMPANY.

The Coater shall fill and send back this Form, to the COMPANY, with all the others necessary
documents requested

5.2 STEP 2: DATA ANALYSIS OF APPENDIX 1 AND FOLLOWING ACTIONS

After data analysis of Appendix 1, the COMPANY Corrosion Engineers, shall take a decision
to proceed or not to the next step of the Coater technical assessment process

5.2.1 CASE 1: NEGATIVE RESULT GIVEN BY THE DATA ANALYSIS OF APPENDIX 1

In case of negative result given by the data analysis of Appendix 1, the technical assessment
process shall stop at this step. The technical assessment result of the Coater is negative.

5.2.2 CASE 2: POSITIVE RESULT GIVEN BY THE DATA ANALYSIS OF APPENDIX 1 -


AUDIT OF COATER PRODUCTION SITE MANDATORY

Following positive result of Appendix 1 data analysis, an audit of the Coater production site is
deemed mandatory by the COR discipline of Engineering group.

This audit shall be performed by the COMPANY Corrosion Engineers, or by their


representative, and will give final result of the Coater technical assessment.

5.2.3 CASE 3: POSITIVE RESULT GIVEN BY THE DATA ANALYSIS OF APPENDIX 1 -


AUDIT OF COATER PRODUCTION SITE NOT NECESSARY

Following positive result of Appendix 1 data analysis, an audit of the Coater production site, is
not deemed necessary, by the COMPANY Corrosion Engineers, to complete the technical
assessment process. The technical assessment result of the Coater is positive.

5.3 STEP 3: ASSESSMENT NOTIFICATION TO THE COATER

The outcome of step 2 analysis (negative, positive...) is consolidated by the authorized


COMPANY entity, together with others parameters (financial, contractual and social
responsibility, quality, HSE...) for final decision.

Then, the authorized COMPANY entity will notify the Coater of the outcome of global
assessment.

February 2015 Rev.0-0 Page 5 of 22


UNCONTROLLED when printed, visit PTTEP Intranet for latest version
Technical Assessment of Coating Plants PEGS-12059-COR-055

5.4 PQT / PPT TO PERFORM DURING AUDIT OF THE COATER PRODUCTION SITE

If an audit of the Coater production site is deemed mandatory, a PQT/PPT shall be performed
on 10 pipes, in order to demonstrate the capacity of the Coater to respect the COMPANY
requirements.

February 2015 Rev.0-0 Page 6 of 22


UNCONTROLLED when printed, visit PTTEP Intranet for latest version
Technical Assessment of Coating Plants PEGS-12059-COR-055

6.0 APPENDICES

Appendix 1. Technical Information Analysis Form: Coating Plant - EXCEL Spreadsheet


PEGS-12059-COR-055
Appendix 1
Technical Information Analysis Form :
Coating Plant Revision 0-0
Date : February 2015

This document has to be sent to the manufacturer to start technical assessment process before any survey at manufacturer location.
The manufacturer has to fill all information requested in all tables.

1) "Production Range" card :


On this card, the manufacturer has to indicate all its production ranges submitted for approval.
After technical assessment, PTTEP or its representative, is able to indicate for which production ranges the manufacturer is finally approved.

2) "Theme I to Theme III" cards :


The manufacturer has to fill all tables of each cards, in order to have a better understanding of its production capacities.
After analysis of manufacturer answers, PTTEP or its representative, can make comments, in blue column, for each manufacturer answers.

3) "Global Synthesis" cards :


On this card all general information (name, address, contact of manufacturer, date of audit, assessment report n°, PTTEP specifications linked,…)
written will be automatically pasted in all the others cards.

First section of this card has to be filled by the manufacturer by indicating general informations : name, address, contact, process concerned,…
The three others sections have to be filled by PTTEP of its representative to summarize result and decision after analysis of the
Technical Information Analysis Form.

In the last section, the signature of PTTEP or its representative will be done, in order to validate the analysis result of this Form.

February 2015 Rev.0-0 Page 7 of 22


UNCONTROLLED when printed, visit PTTEP Intranet for latest version
Technical Assessment of Coating Plants PEGS-12059-COR-055

PEGS-12059-COR-055
Appendix 1
Technical Information Analysis Form :
Coating Plant Revision 0-0
Date : February 2015

According specifications :
PEGS-0842-COR- 001 Assessment report N° :

COATER

Coater Name Activity and Process of Audited Workshop Audit Date

xxx xxx xxx

Coater Head Office Address Coater contacts (name, function, email, phone,…)

xxx

Name & Address of


Audited Workshop

xxx

PTTEP OR REPRESENTATIVE COMPANY TEAM - TO BE FILLED BY PTTEP OR REPRESENTATIVE

PTTEP Project Concerned PTTEP or Representative Responsible for Technical Information Analysis (Name, Function, Service)

xxx

Objectives of the Technical Information Analysis

TECHNICAL INFORMATION ANALYSIS / TECHNICAL ASSESSMENT RESULT (FOR THE PRODUCTION RANGE CONSIDERED) -
TO BE FILLED BY PTTEP OR REPRESENTATIVE

Result of Information Analysis of -PEGS-12059-COR-055 - Appendix 1, filled by the Manufacturer


Yes / No Comments
Level of information is appropriate
On site Audit Requested

Result of Technical Assessment of Manufacturer (to be filled if on site audit is not deemed necessary)
Decision * Comments
Satisfactory
Reserves to close to be satisfactory
Not satisfactory
Notes : * : Tip when appropriate
CONCLUSIONS OF TECHNICAL INFORMATION ANALYSIS / GENERAL COMMENTS

SIGNATURE OF PTTEP OR REPRESENTATIVE TEAM


NAME DATE NAME DATE

THIS TECHNICAL INFORMATION ANALYSIS DOESN'T REPLACE THE PQT / PPT THAT HAVE TO BE PERFORMED FOR EACH NEW PROJECT

February 2015 Rev.0-0 Page 8 of 22


UNCONTROLLED when printed, visit PTTEP Intranet for latest version
Technical Assessment of Coating Plants PEGS-12059-COR-055

PEGS-12059-COR-055
Appendix 1
Technical Information Analysis Form :
Coating Plant Revision 0-0
Date : February 2015

According specifications :
PEGS-0842-COR- 001 Assessment report N° :

COATER

Name & Address of


Activity and Process of Audited Workshop Audit Date
Audited Workshop

xxx xxx xxx

ACTUAL PRODUCTION RANGE / APPROVED PRODUCTION RANGE OF THE COATER


To list all the actual production ranges of the coater and select and comment the approved ones.

To be completed by PTTEP or
To be completed by the coater
representative Company

Actual maximum diameter and base Approved maximum diameter and


Type Code Designation materials (carbon steel and base materials (carbon steel and
stainless steel) stainless steel)

5514 Pipeline coating applicators


Coating
5523 Subsea thermal coating applicators

February 2015 Rev.0-0 Page 9 of 22


UNCONTROLLED when printed, visit PTTEP Intranet for latest version
Technical Assessment of Coating Plants PEGS-12059-COR-055

PEGS-12059-COR-055
Appendix 1
Technical Information Analysis Form :
Coating Plant Revision 0-0
Date : February 2015

According specifications :
PEGS-0842-COR- 001 Assessment report N° :

COATER

Name & Address of


Activity and Process of Audited Workshop Audit Date
Audited Workshop

xxx xxx xxx

THEME I - GENERAL ORGANIZATION


All facilities described herein are meant to be permanent in-house facilities only. Any sub-contracted activity must be clearly indicated showing the names and
addresses of related Subcontractors. The number, type and status of all listed equipment are subject to thorough checks by the COMPANY representative in
charge of the Plant Survey during his visit of the facilities.

Table 1.1.a - General Organization - Surface area (Plot plan to be joined if available)

Comments
Zone Surface area (m2) Description
To be filled by PTTEP or Company representative

Overall

Covered areas

Yard areas

Offices

Manufacturing workshops

Laboratory

Material and extrusion


equipment

Testing workshops

Warehouses

Covered storage areas

Table 1.1.b - General Organization - Manufacturer Management : organization chart to join

Comments
Position Names Comments
To be filled by PTTEP or Company representative

Managing Director

Sales Manager

Plant / Yard Manager

Production Manager

Quality Assurance Manager

Quality Control Manager

HSE Manager

Logistic Manager

Others

February 2015 Rev.0-0 Page 10 of 22


UNCONTROLLED when printed, visit PTTEP Intranet for latest version
Technical Assessment of Coating Plants PEGS-12059-COR-055

PEGS-12059-COR-055
Appendix 1
Technical Information Analysis Form :
Coating Plant Revision 0-0
Date : February 2015

According specifications :
PEGS-0842-COR- 001 Assessment report N° :

COATER

Name & Address of


Activity and Process of Audited Workshop Audit Date
Audited Workshop

xxx xxx xxx

THEME I - GENERAL ORGANIZATION

All facilities described herein are meant to be permanent in-house facilities only. Any sub-contracted activity must be clearly indicated showing the names and
addresses of related Subcontractors. The number, type and status of all listed equipment are subject to thorough checks by the COMPANY representative in
charge of the Plant Survey during his visit of the facilities.

Table 1.1.c - General Organization - Personnel

Contracted
Personnel
Average
Staff Quantity Quantity
(personnel from years of Personnel qualication Comments
Quality of Employees (coater's
external company service level (curriculum vitae) To be filled by PTTEP or Company representative
personnel)
which are (staff)
working at the
coater)

Commercial department

Administration

Project Management
R&D

Laboratory

Procurement

Expediting / Shipment

Production

Quality Inspection Manager

Quality Inspector (for testing


: NDT, DT,...)
Quality Inspector (on line)

Quality assurance

Quality for in-coming material

Supervisory Personnel

Management

HSE employees

Others

Total number of Employees

Table 1.1.d - General Organization - Certification of employees


Quality of employees Type of certification Comments
Name of employees (engineers, technicians, (NACE, ACQPA, FROSIO, Level of certification To be filled by PTTEP or Company
supervisors, operators…) others,…) representative

Table 1.1.e - General Organization - Communication With Customer / Working Documents Language

Documents (testing
Which department team (engineering,
Language used with procedures, drawing, Comments
commercial, production,…) and how
customer : control procedures,…) To be filled by PTTEP or Company
many people are able to discuss in other
YES / NO ? available in which representative
language than mother tongue ?
language ?

English

French

Others

February 2015 Rev.0-0 Page 11 of 22


UNCONTROLLED when printed, visit PTTEP Intranet for latest version
Technical Assessment of Coating Plants PEGS-12059-COR-055

PEGS-12059-COR-055
Appendix 1
Technical Information Analysis Form :
Coating Plant Revision 0-0
Date : February 2015

According specifications :
PEGS-0842-COR- 001 Assessment report N° :

COATER

Name & Address of


Activity and Process of Audited Workshop Audit Date
Audited Workshop

xxx xxx xxx

THEME I - GENERAL ORGANIZATION

All facilities described herein are meant to be permanent in-house facilities only. Any sub-contracted activity must be clearly indicated showing the names and
addresses of related Subcontractors. The number, type and status of all listed equipment are subject to thorough checks by the COMPANY representative in
charge of the Plant Survey during his visit of the facilities.

Table 1.1.f - General Organization - Work Load Status and Commercial data

Comments
Items to check Description
To be filled by PTTEP or Company representative

Ownership

Annual turnover in M$ or M€ (3 previous year)

Men hour capacity

Work shift : normal, 2x8, 3x8

Present and future work load (%)

Future investment (tools, building, human


ressources,…)

Number of international subsidiaries

Location of international and/or others


subsidiaries

Table 1.1.g - General Organization - References on similar jobs

Customer Total fabricated pipes length (by coating types) Comments


Country of Name / Description of
Year built (PTTEP, To be filled by PTTEP or
installation project
others,…) FBE 3xLPE 3xLPP Others Company representative

Table 1.1.h - General Organization - R&D Capacity


Quantity of Comments
Permanent Description of R&D activities Staff Qualifications Sub-contracted (if any) To be filled by PTTEP or Company
Staff representative

February 2015 Rev.0-0 Page 12 of 22


UNCONTROLLED when printed, visit PTTEP Intranet for latest version
Technical Assessment of Coating Plants PEGS-12059-COR-055

PEGS-12059-COR-055
Appendix 1
Technical Information Analysis Form :
Coating Plant Revision 0-0
Date : February 2015

According specifications :
PEGS-0842-COR- 001 Assessment report N° :

COATER

Name & Address of


Activity and Process of Audited Workshop Audit Date
Audited Workshop

xxx xxx xxx

THEME I - GENERAL ORGANIZATION


All facilities described herein are meant to be permanent in-house facilities only. Any sub-contracted activity must be clearly indicated showing the names and
addresses of related Subcontractors. The number, type and status of all listed equipment are subject to thorough checks by the COMPANY representative in charge
of the Plant Survey during his visit of the facilities.

Table 1.1.i - General Organization - International Standards and PTTEP Specifications used

Deviation list
Comments
Standards / PTTEP Date of
Available for Submitted to Description / Comments To be filled by PTTEP or Company
specification revision
review : Company : representative
Yes / No Yes / No

PEGS-0842-COR-001

ASTM D 570
ASTM D 1693
ASTM D 4940

CSA Z245-20

ISO 306
ISO 527-1
ISO 527-2
ISO 868
ISO 1133
ISO 1183
ISO 2808
ISO 2811-1
ISO 4287
ISO 4892-2
ISO 6964
ISO 8130-6
ISO 8501-1
ISO 8502-3
ISO 8502-6
ISO 8502-9
ISO 8503-4
ISO 11357-1
ISO 11357-3
NF A49-710
NACE RP0274
Others

February 2015 Rev.0-0 Page 13 of 22


UNCONTROLLED when printed, visit PTTEP Intranet for latest version
Technical Assessment of Coating Plants PEGS-12059-COR-055

PEGS-12059-COR-055
Appendix 1
Technical Information Analysis Form :
Coating Plant Revision 0-0
Date : February 2015

According specifications :
PEGS-0842-COR- 001 Assessment report N° :

COATER

Name & Address of


Activity and Process of Audited Workshop Audit Date
Audited Workshop

xxx xxx xxx

THEME I - GENERAL ORGANIZATION

All facilities described herein are meant to be permanent in-house facilities only. Any sub-contracted activity must be clearly indicated showing the names and
addresses of related Subcontractors. The number, type and status of all listed equipment are subject to thorough checks by the COMPANY representative in charge
of the Plant Survey during his visit of the facilities.

Table 1 - General Aptitude / Experience / Personnel - List of documents to send by the coater, to PTTEP, in English (or French, if available) languages,
with all Tables filled, before on site technical review

Documents available in
Documents received : English (or French) Comments
List of documents
YES / NO ? language : To be filled by PTTEP or Company representative
YES / NO ?

Plot plan, layout of the plant

General Organization Chart

Quality Control Organization Chart

Coating procedures (ITP)

Repair procedures

Control procedures

Non-conformities management procedures

In-coming material inspection procedures

Supplier evaluation, follow-up and audit


procedures

Quality manual

ISO, API, PED certificates, others,….

HSE policy

Example of audit report : audit made by


customer manufacturer or audit made by
manufacturer on its sub-suppliers

February 2015 Rev.0-0 Page 14 of 22


UNCONTROLLED when printed, visit PTTEP Intranet for latest version
Technical Assessment of Coating Plants PEGS-12059-COR-055

PEGS-12059-COR-055
Technical Information Analysis Form : Appendix 1

Coating Plant Revision 0-0


Date : February 2015
According specifications :
PEGS-0842-COR- 001 Assessment report N° :

COATER

Name & Address of


Activity and Process of Audited Workshop Audit Date
Audited Workshop

xxx xxx xxx

THEME II - MANUFACTURING
All facilities described herein are meant to be permanent in-house facilities only. Any sub-contracted activity must be clearly indicated showing the names and
addresses of related Subcontractors. The number, type and status of all listed equipment are subject to thorough checks by the COMPANY representative in
charge of the Plant Survey during his visit of the facilities.

Table 2.1.a - Workshop General Organization - Building Bay and Cranes Data of Covered Area / Handling facilities

Bay Type of Height Comments


Number of Capacity Electrical or Description
Bay n° Dimensions Crane / under To be filled by PTTEP or
Cranes (tons) Manual (certification date,…)
(m x m) Handling Hook (m) Company representative

1
2
3
4
5
6
7
8

Table 2.1.b - Workshop General Organization - Cranes Date of Open Air Area / Handling facilities

Height Comments
Number of Capacity Electrical Description (certification
Type of Crane / Handling under Hook To be filled by PTTEP or Company
Cranes (tons) or Manual date,…)
(m) representative

Table 2.2.a - Pre-heating - Description of Equipment in Place

Comments
Type of Max. Capacity
Description Quantity Comments / Description To be filled by PTTEP or Company
Equipment (meter/min)
representative

February 2015 Rev.0-0 Page 15 of 22


UNCONTROLLED when printed, visit PTTEP Intranet for latest version
Technical Assessment of Coating Plants PEGS-12059-COR-055

PEGS-12059-COR-055
Technical Information Analysis Form : Appendix 1

Coating Plant Revision 0-0


Date : February 2015
According specifications :
PEGS-0842-COR- 001 Assessment report N° :

COATER

Name & Address of


Activity and Process of Audited Workshop Audit Date
Audited Workshop

xxx xxx xxx

THEME II - MANUFACTURING

All facilities described herein are meant to be permanent in-house facilities only. Any sub-contracted activity must be clearly indicated showing the names and
addresses of related Subcontractors. The number, type and status of all listed equipment are subject to thorough checks by the COMPANY representative in
charge of the Plant Survey during his visit of the facilities.

Table 2.3.a - Blasting - Description of Equipment in Place


Max. Capacity Comments
Type of
Description Quantity (meter/min) Comments / Description To be filled by PTTEP or Company
Equipment
for Sa3 representative

Table 2.4.a - Dust removal - Description of Equipment in Place

Comments
Type of Max. Capacity
Description Quantity Comments / Description To be filled by PTTEP or Company
Equipment (meter/min)
representative

Table 2.5.a - Heating - Description of Equipment in Place

Comments
Oven n°1 Oven n°2 Oven n°3 To be filled by PTTEP or Company
representative

Heating source

Inside Dimensions
(Height x Width x Length) (m)

Automatic Control or Manual

Max line speed for 220°C with


12" pipe, WT = 12,7 mm

Maximum temperature

Maximum power

Pipe temperature recording

Table 2.6.a - Coating - Description of Equipment/Process in Place


Type of Process (lateral or annular, Comments
Type of Max. Capacity
adhesive application by extrusion or by Temperature To be filled by PTTEP or Company
Equipment (meter/min)
powder spraying) / Description representative

FBE
(electrostatic
gun)
PE/PP
Adhesive
extrusion
PE/PP
Extrusion

Table 2.7.a - Cooling - Description of Equipment in Place


Maximum water Comments
Type of Cooling
Description Comments / Description To be filled by PTTEP or Company
Equipment Temperature quantity (m3/min) representative

February 2015 Rev.0-0 Page 16 of 22


UNCONTROLLED when printed, visit PTTEP Intranet for latest version
Technical Assessment of Coating Plants PEGS-12059-COR-055

PEGS-12059-COR-055
Appendix 1
Technical Information Analysis Form :
Coating Plant Revision 0-0
Date : February 2015

According specifications :
PEGS-0842-COR- 001 Assessment report N° :

COATER

Name & Address of


Activity and Process of Audited Workshop Audit Date
Audited Workshop

xxx xxx xxx

THEME III - PRODUCTS MANAGEMENT (CONTROL, TESTING, INSPECTION, STORAGE)


All facilities described herein are meant to be permanent in-house facilities only. Any sub-contracted activity must be clearly indicated showing the names and
addresses of related Subcontractors. The number, type and status of all listed equipment are subject to thorough checks by the COMPANY representative in
charge of the Plant Survey during his visit of the facilities.

Table 3.1.a - In-coming Material Management - Material Storage

Comments
Type of Storage Dimension Material Stored
To be filled by PTTEP or Company representative

Covered storage yard


Open storage yard
Warehouse

Table 3.1.b - In-coming Material Management - Storage Conditions


Comments
Storage Conditions for : Description / Comments
To be filled by PTTEP or Company representative
FBE
PE
PP
Non conform raw material
Others

Table 3.2.a - Inspection, Testing and Quality Control - Non Destructive Testing Equipment
Testing
procedures and
Calibration
international Comments
Equipment Range Quantity of of Recording and
Type of test / control standards To be filled by PTTEP or
type capability Equipment Equipment traceability
(availability, Company representative
updated ?
issuance,
updating)
Pipes Temperature : pre
heating
Pipes Temperature : after
induction heating
Pipes Temperature : after
cooling
Thickness
Degree of surface
cleanliness
Salt contamination on
prepared surface
Dust level on prepared
surface
Roughness
Pipes travel speed
Gel time (FBE)
Extrusion temperature
(adhesive and PE/PP top
coat)

Residual magnetic intensity

DSC
Elongation at break :
adhesive

Elongation at break : PE/PP

Others

February 2015 Rev.0-0 Page 17 of 22


UNCONTROLLED when printed, visit PTTEP Intranet for latest version
Technical Assessment of Coating Plants PEGS-12059-COR-055

PEGS-12059-COR-055
Appendix 1
Technical Information Analysis Form :
Coating Plant Revision 0-0
Date : February 2015

According specifications :
PEGS-0842-COR- 001 Assessment report N° :

COATER

Name & Address of


Activity and Process of Audited Workshop Audit Date
Audited Workshop

xxx xxx xxx

THEME III - PRODUCTS MANAGEMENT (CONTROL, TESTING, INSPECTION, STORAGE)


All facilities described herein are meant to be permanent in-house facilities only. Any sub-contracted activity must be clearly indicated showing the names and addresses of
related Subcontractors. The number, type and status of all listed equipment are subject to thorough checks by the COMPANY representative in charge of the Plant Survey
during his visit of the facilities.

Table 3.2.b - Inspection, Testing and Quality Control - Destructive Testing Equipment

Testing
Testing sub-
procedures and
contracted ?
Calibration of international Comments
Equipment Range Number of If yes, Recording and
Type of test / control Equipment standards To be filled by PTTEP or
type capability Equipment indicate the traceability
updated ? (availability, Company representative
name of sub-
issuance,
contractor
updating)

Impact resistance
Hardness
Peeling force
Coating homogeneity
Indentation
Elongation
Flexibility
Cathodic disbonding (23, 65
& 80°C)
Others

Table 3.2.c - Inspection, Testing and Quality Control - Raw Material Chemical Analysis Equipment

Testing
Testing sub-
procedures and
contracted ?
Calibration of international Comments
Equipment Range Number of If yes, Recording and
Type of test / control Equipment standards To be filled by PTTEP or
type capability Equipment indicate the traceability
updated ? (availability, Company representative
name of sub-
issuance,
contractor
updating)

FBE :
Moisture content
DSC
Gel time
Density
Adhesive :
Vicat softening point
Melting point
PE/PP :
Density

Carbon black content

Vicat softening point


Melting point
Thermal ageing
UV ageing
PE : Stress cracking
Others

February 2015 Rev.0-0 Page 18 of 22


UNCONTROLLED when printed, visit PTTEP Intranet for latest version
Technical Assessment of Coating Plants PEGS-12059-COR-055

PEGS-12059-COR-055
Appendix 1
Technical Information Analysis Form :
Coating Plant Revision 0-0
Date : February 2015

According specifications :
PEGS-0842-COR- 001 Assessment report N° :

COATER

Name & Address of


Activity and Process of Audited Workshop Audit Date
Audited Workshop

xxx xxx xxx

THEME III - PRODUCTS MANAGEMENT (CONTROL, TESTING, INSPECTION, STORAGE)


All facilities described herein are meant to be permanent in-house facilities only. Any sub-contracted activity must be clearly indicated showing the names and addresses of
related Subcontractors. The number, type and status of all listed equipment are subject to thorough checks by the COMPANY representative in charge of the Plant Survey
during his visit of the facilities.

Table 3.3.a - Finished Goods Management - Goods Storage


Comments
Type of Storage Dimension Material Stored
To be filled by PTTEP or Company representative
Covered storage yard
Open storage yard
Warehouse

Table 3.3.b - Finished Goods Management - Storage Conditions


Comments
Storage Conditions for : Description / Comments
To be filled by PTTEP or Company representative

Table 3.3.c - Finished Goods Management - Shipping Facilities

Maximum Maximum Capacity (weight Comments


Type Comments
Dimension (m) in tons) To be filled by PTTEP or Company representative

Railroad siding with spur in


yard
Road / Trucking
Water

Table 3 - Procurement Practices - Coater's Suppliers List / Source of Materials


Number of Comments (follow-up Comments
Material Suppliers
audits / year procedures, approval,…) To be filled by PTTEP or Company representative

FBE

PE Adhesive

PE

PP adhesive

PP

Repaired products

February 2015 Rev.0-0 Page 19 of 22


UNCONTROLLED when printed, visit PTTEP Intranet for latest version
EMS User Feedback Form
This section for feedback provider input only

Details of feedback provider

Name:

Division/Dept:

Location:

Telephone:

E-mail:

Area of Concern: CMS Content CMS Relevance ISO standard Other standards

Others (please specify)

Document Title: Document I/D:

Feedback details (when referring to documents, please state chapter and page number where appropropriate.)

(Please add attachments if required)


February 2015 Rev.0-0 Page 20 of 22
UNCONTROLLED when printed, visit PTTEP Intranet for latest version
EMS User Feedback Form

This section for EMS Administrator use only

Date received: Feedback register updated:

Received by: Feedback register updated by:

Form receipt sent: Feedback Reference # EMS-FB-

Action taken

Date By Whom

Further Action
Recommended Action Deadline By Whom

Verification of closure of Feedback

By: Title: Dept.: Date:

Please send this form to [email protected]

February 2015 Rev.0-0 Page 21 of 22


UNCONTROLLED when printed, visit PTTEP Intranet for latest version
Technical Assessment of Coating Plants PEGS-12059-COR-055

LAST PAGE – INTENTIONALLY BLANK

February 2015 Rev.0-0 Page 22 of 22


UNCONTROLLED when printed, visit PTTEP Intranet for latest version