LS4
LS4
Hydrograph
A plot of discharge over a period of time.
- can be annual, monthly, seasonal, or flood
hydrograph (stream flow due to a heavy storm);
Annual hydrograph classifies the channel as
perennial, intermittent and ephemeral.
Why
Construct & Analyse Hydrographs?
To find out discharge patterns of a particular
drainage basin;
2
mm
4
1 3
0 12 24 36 48 30 72
Hours from start of rain storm
Discharge (m3/s)
river. The rising when all parts of basins
3
limb rises slowly contribute at the outlet
in the early simultaneously at the
stage of the maximum rate.
flood but more 2
Base flow
rapidly toward mm
the end portion. 4 Normal discharge
1 3 of the river
2
Base flow
2 the center of
mm mass of the
4 direct runoff
1 3 hydrograph.
2
0 12 24 36 48 30 72
Hours from start of rain storm
0 12 24 36 48 30 72
Hours from start of rain storm
0.5
0.3
0.2 1
0.9
0.1
Derived unit hydrograph is the
0.8
result of approximately 6
0 hours of excess precipitation.
0 1 2 3 4 5 6 7 8 9 10111213141516171819 0.7
0.4
0.3
0.2
0.1
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Time (hrs.)
Example (finding a storm hydrograph) : Given a triangular 1-h UH as
follows (hourly),
36
48
60
72
84
Dr. M Alauddin CED, DUET
Steps in Deriving a Unit Hydrograph
➢ Separate the base flow and obtain the direct runoff
hydrograph (DRH).
15000
Flow (cfs)
unit hydrograph
10000
basef low
5000
0
7
0
105
119
133
112
126
21
35
49
63
77
91
14
28
42
56
70
84
98
Time (hrs.)
Dr. M Alauddin CED, DUET
Example: Given are the hydrograph data in table below. Derive a 6
hour unit hydrograph if this data is obtained from a storm of 6 (six)
hours and the catchment area is 3200 sq.km.
Date Time (day) Discharge (m³/s) Base Flow (m³/s)
11-Jan 1st 21 21
12-Jan 2nd 21 21
13-Jan 3rd 21 21
14-Jan 4th 20 20
15-Jan 5th 20 20
16-Jan 6th 20 20
17-Jan 7th 20 20
18-Jan 8th 20 20
19-Jan 9th 521 11
20-Jan 10th 160 21
21-Jan 11th 82 29
22-Jan 12th 63 35
23-Jan 13th 59 47
24-Jan 14th 53 53
25-Jan 15th 47 47
26-Jan 16th 45 45
27-Jan 17th 38 38
Multiplyi
ng DRO
by sec
of 1 day
Total=64.11x10^6
Changing the Duration
Very often, it will be necessary to change the duration
of unit hydrograph; if unit hydrographs are to be
averaged, then they must be of the same duration.
There are two methods: (i) Method of superposition,
(ii) S-curve Method.
(i) If a D-h unit hydrograph is available, then nD-h UH
(n is an integer = 2,3,4, etc.) is obtained by
superposing n UHs separated by D hour.
(ii) Another common method of altering the duration
(like mD-h, here m is a fraction) of a unit hydrograph
is by the S-curve method. An S-curve involves
continually lagging a unit hydrograph by its duration and
adding the ordinates.
Dr. M Alauddin CED, DUET
(i) Method of superposition
➢ This is done by displacing the unit
hydrograph
Prob: A 2-hr Unit Hydrograph is given as
follows and a 4-hr Unit Hydrograph is
needed.
Given
Time (hr) Q Time (hr) UHO Displaced UH Sum 4-hr UHO
0 0 (lagged by 2hr) =(2)+(3) =(4)/2
0 0 0 0
1 2
1 2 2 1
2 4 2 4 0 4 2
3 6 3 6 2 8 4
4 10 4 10 4 14 7
5 6 5 6 6 12 6
6 4 6 4 10 14 7
7 3 6 9 4.5
7 3
8 2 4 6 3
8 2 9 1 3 4 2
9 1 10 0 2 2 1
10 0 11 1 1 0.5
(ii) The S-curve
For example, the 6-h unit hydrograph is continually
lagged by 6 hours and the ordinates are added.
D D D D D D D D D D
60000
50000
40000
S-curve
Flow (cfs)
30000
20000
10000
114
12
18
30
36
42
48
60
66
72
78
90
96
24
54
84
102
120
108
6
0
Time (hrs.)
Dr. M Alauddin CED, DUET
Finding S-curve:
Problem: 6-hr UH ordinates are given (first two columns). Derive S-
curve ordinates.
Solution:
=u1
=u2 =u1
. =u2
. .
.
Alternative method of deriving S-curve
D D D D D D D D D D
60000
50000
Ordinate, S1 = u1
40000
S 2 = u2 + u 1
Flow (cfs)
30000 S3 = u3 + u2 + u1 = u3 + S2
……. S2
20000
Si = ui + Si-1
10000
114
12
18
30
36
42
48
60
66
72
78
90
96
24
54
84
102
120
108
6
0
Time (hrs.)
0
5
5
15
15
50
50
120
120
201
201
Topic: Synthetic Unit Hydrographs (SUH)
Learning objectives: You’ll be able to
- derive UH, where rainfall-discharge records
are not available;
- learn
i. Snyder’s method
ii. SCS UH (SCS – US Soil Conservation
Services)
Synthetic Unit Hydrographs
◼All the methods of deriving a UH discussed
previously require rainfall and runoff records.
However, for some drainage basins rainfall–runoff
data may not be available. For those basins, some
kind of techniques is needed to generate UH. The
UH so derived is called synthetic UH.