Work Sampling
Work Sampling
Each observation records what is happening at that instant and the percentage of
observations recorded for a particular activity or delay/idleness is a measure of the
percentage of time during which that activity or delay/idleness occurs
• work sampling is the statistical technique for determining the proportions that is
our target proportions of time spent by workers or machines in various categories of
activities.
• For example, if a work sampling study finds, the work sampling study was conducted
and it finds that workers in a facility spend large amount of their time waiting for
work. So it has been found the time study analyst maybe he visited 8 times in an 8-
hour shift and out of that 4 times if he has found that the workers are waiting for the
raw material to arrive or the material to process waiting for the work.
Basic Concept
Work sampling is a commonly used industrial engineering technique designed to
measure how resources, again the same thing is being repeated, how resources such
as people, machines, facilities or equipment are being used.
Based on the findings in this sample, statements can be made about the activity.
the standards derived from the work sampling might specify the proportion of time
that should be devoted to a specific activity, rather than the actual amount of time
required to perform a task.
The Need for work Sampling
To obtain a complete and accurate picture of the productive time and
idle time of the machines in a specific production area.
Performance Sampling
To measure working time and non working time of a person on a manual task, and a
performance index
Work Measurement
To establish time standard for an operation
Example of Work Sampling
Working 17
Idle 03
The Percentage working Time is 17/20*100% = 85% and The percentage of idle time 15% .
If this study covered one operator for an 8 hour day , the results would indicate that the operator
was idle 15 % or 480*0.15=72 minutes of the day
Take 5 coins
• Toss each of the coin in one set
• Count number of time a given combination of head and tail is
obtained
Combination No of
Heads (p) Tails (q) Combinations
5 0 3
4 1 17
3 2 30
2 3 30
1 4 17
0 5 3
Total 100
Distribution of Curve showing probabilities of combinations when large
sample size is used
Confidence Level
Determine the percentage of idle time of an automatic screw cutting machine by Work Sampling. Assume that a
confidence level of 95% and an accuracy of ±5% have been considered. Determine how many random observations will
be required to give the desired results.
Solution:
In this example, it is necessary to estimate the value of P first. It means a trial study would be made to get a first estimate
about the percentage of the idle time.
Let us assume that 100 observations were made, out of which 25 observations showed the machine to be idle. The
percentage of idle time, would be 25%, i.e. P = 0.25.
The standard formula is
After the work study is in progress and 500 observations have been taken, a new calculation is to be made in order to
recheck the value for N.
Determination of “Accuracy” for a Given Number of Observations:
When the study is over, a calculation is made to find whether the results are within the desired
accuracy or not.
Numerical 4
• The study was conducted in a machine shop where 1000 observations were
found working and 150 observations showed that the machine was idle.
Determine desired accuracy to obtain desire results assuming 95%
confidence level.
Use of Random Numbers
The random numbers table helps to determine the time of day that an
observation should be made
• The first digit of this number might indicate the hour, second and third
digits the minutes
• Observations are not made during the lunch periods or scheduled rest
periods.
Enables the analyst to plot the daily or the cumulative results of the work sampling
study
Control Charts
The 3 sigma limit is used in determining the upper control limit (UCL) and Lower
control Limit (LCL)
Formula for determining the control limits for p
1 100 9 9
2 100 10 10
3 100 12 12
4 100 8 8
5 100 6 6
6 100 9 9
7 100 23 23
8 100 9 9
9 100 8 8
10 100 9 9
11 100 9 9
12 100 8 8
N = Total Number of observations = 1200
p = 120/1200 = 0.10
20
UCL
% OCCURENCE
15
10
5
LCL
0
1 2 3 4 5 6 7 8 9 10 11 12
DAY OF STUDY
Control Charts
The 3 sigma limit is used in determining the upper control limit (UCL) and Lower
control Limit (LCL)
Formula for determining the control limits for p
1 100 9 9
2 100 10 10
3 100 12 12
4 100 8 8
5 100 6 6
6 100 9 9
7 100 23 23
8 100 9 9
9 100 8 8
10 100 9 9
11 100 9 9
12 100 8 8
N = Total Number of observations = 1200
p = 120/1200 = 0.10
20
UCL
% OCCURENCE
15
10
5
LCL
0
1 2 3 4 5 6 7 8 9 10 11 12
DAY OF STUDY
Procedure for making work sampling study
1) Define the Problem
3)Determine the desired accuracy of the final results. Confidence level should also
be stated
6)Make the observations according to the plan. Analyse and summarize the data
7) Check the accuracy or precision of the data at the end of each day
3)Determine the desired accuracy of the final results. Confidence level should also
be stated
6)Make the observations according to the plan. Analyse and summarize the data
7) Check the accuracy or precision of the data at the end of each day
Work Sampling can be used profitability for measuring log cycle operations and where
people are employed in groups, and activities that do not lend themselves to time
study.
Determine the percentage of the day that a person is idle and the percentage of the
day he is working.
Determine the average performance index
Allowances
Standard time estimation
Solution:
= 1.26 𝑀𝑖𝑛𝑢𝑡𝑒𝑠
Example 2 :
A work sampling study was carried out in a production unit which
give following results
Total time observed = 6000 Minutes
No. of working Observations = 3000
No. of Idle observations = 270
No. of Parts Produced = 500
Performance Rating = 80%
Allowance =10%
Calculate Standard Time
6000×0.91×0.80 100
Standard Time per piece = ×
500 100−10
= 9.70 𝑀𝑖𝑛𝑢𝑡𝑒𝑠
Establishing Time standard for an assembly operation
13650×0.987×1.236 100
Standard Time per piece = ×
16314 100−15
= 1.20 𝑀𝑖𝑛𝑢𝑡𝑒𝑠
Advantages of Work Sampling Over Time Study
1. Operator is not subjected to long-period of observations.
5. Observations may be taken over a period of days or weeks, thus decreasing the
chance of day to day or week to week variations affecting the results.
6. The man hours spent by the analyst are much less.
7. A work sampling study can be stopped at any time without affecting the results.
1.Work sampling can be applied for the estimation of the percentage utilization of
machine tools, cranes, fork trucks etc.
2. Work sampling can also be used to estimate the unavoidable delay times for
deciding the delay allowances.
3. To estimate the percentage of the time consumed by various job activities, i.e.
supervision, repair, inspection etc.
4. Work sampling is also used to find out time standards, specially where the job
is not repetitive and where time study is not possible, e.g. for maintenance work,
office work, repair work, ship building etc.
Disadvantages of Work Sampling over Time Study
3. Study made of a group presents average while there is no information about the
magnitude of individual differences.
5. Some-time no record is kept about the study on the operator, therefore, a new
study must be made when a change occurs in any element.
Establishing Time standard for an assembly operation
19500×0.98×1.03 100
Standard Time per piece = ×
2565 100−12
= 𝟖. 𝟕𝟐 𝑴𝒊𝒏𝒖𝒕𝒆𝒔
A work sampling study was carried out to determine standard time. The
observations were made at random intervals of time for 100 hours. Total 10000
observations were carried out. Out of 10000 observations , 2000 observations
involved in non-working activities. The ratio between manual and machine
element was 1:3. Average performance rating was estimated as 90%. Total
number of pieces produced during the period of the study were 600. calculate
standard time of the job by considering 20% as allowances.
Solution:
Step1. Calculate overall time per piece (To)
100×60
To = = 10 Minutes
600
6000 6000
Tm = Te × =8×
8000 8000
=6 Minutes
2000 2000
Th = Te × =8×
8000 8000
= 2 Minutes
Step 4: Calculate Normal Time
NT = Th × 𝑹𝒂𝒕𝒊𝒏𝒈 + Tm
= 2 × 0.90 + 6
= 7.8 Minutes
Days 1 2 3 4 5
No. of observations 230 240 200 180 225
Occurrence of activity 200 190 170 150 210
1.Work sampling can be applied for the estimation of the percentage utilization of
machine tools, cranes, fork trucks etc.
2. Work sampling can also be used to estimate the unavoidable delay times for
deciding the delay allowances.
3. To estimate the percentage of the time consumed by various job activities, i.e.
supervision, repair, inspection etc.
4. Work sampling is also used to find out time standards, specially where the job
is not repetitive and where time study is not possible, e.g. for maintenance work,
office work, repair work, ship building etc.
Advantages and Disadvantages 0f work sampling in comparison with time
study
1. Work sampling is not economical for studying a single operator or machine, or for
studying operators and machines located over wide areas.
2. Time study permits a finer breakdown of activities and delays than is possible with
work sampling
3. The operator may change his or her work pattern upon sight of the observer. If this
occurs, the results of such work sampling study may be little value.
4. Management and workers may not understand statistical work sampling as readily
as they do time study.