Saudi Arabian Grid Code
Saudi Arabian Grid Code
Saudi Arabian Grid Code
Issue: 01
Revision: 00
May 2007
Prepared by:
Saudi Electricity Company (SEC)
Sr.
Revision No. Date Detail of the Revision
No.
TABLE OF CONTENTS
FOREWORD ................................................................................................viii
PREFACE.......................................................................................................ix
1.3 Scope....................................................................................................................... 1
FOREWORD
This is the first issue of the Saudi Arabian Grid Code. This work has been
accomplished by extensive efforts from Saudi Electricity Company (SEC) and was
subjected to thorough technical and legal reviews by internationally renowned
consultants including ESBI of Ireland and CMS Cameron McKenna of UK as well as
a number of major Saudi stakeholders and the Electricity & Co-Generation
Regulatory Authority (ECRA).
The Grid Code is designed to indicate the procedures for both planning and
operational purposes and covers both normal and exceptional circumstances. It is
however a live working document. It will be, from time to time, subjected to changes
and/or revisions to reflect stages of development of the regulatory framework of the
industry and changes to comply with legislations and good industry practices. The
proposals for changes will be received by the Grid Code Supervisory Committee
(GCSC). The rules and responsibilities of the GCSC are described in section 1.10 of
the Grid Code. Upon receipt of such proposals for changes, the GCSC will carry out
the necessary process as appropriate to study these proposals and officially prepare
a report of recommendations to ECRA for its approval. The GCSC is a stakeholder
representative panel and its composition is laid down in section 1.10.3 of the Grid
Code.
As a user of this Grid Code, it is your responsibility to ensure that you acquire the
most up to date issue of the Grid Code which can be downloaded from ECRA’s web
site WWW.ECRA.GOV.SA.
This Preface is provided to users and to prospective users for their information only
and does not constitute a part of the Grid Code.
PREFACE
The Saudi Arabian Grid Code has been developed to define the rules and regulations
for various Participants for accessing and using the Transmission Grid of the Saudi
Electricity Company. The objective is to establish the obligations of the Transmission
Service Provider (TSP) and other Grid Users—Generators, Distribution Entities, and
Directly-connected Customers—for accessing and using the Grid, in specific to: (i)
define obligations, responsibilities, and accountabilities of all the parties towards
ensuring open, transparent, non-discriminatory, and economic access and use of the
Grid while maintaining its safe, reliable, and efficient operation; (ii) define minimum
technical requirements for the Participants; and (iii) set out the information exchange
obligations of the Participants.
Through its 7 chapters, the Saudi Arabian Grid Code attempts to cover matters such
as defining of technical, design, and operational criteria for Grid access and use,
planning for Grid development and reinforcement, System operation criteria and
standards, Scheduling and Dispatch of supply and demand resources, exchange of
data and information, and metering policies and systems to account for the Power
and Energy transactions in the Grid.
Chapter 1, General Conditions, contains provisions which are of general nature and
apply to all sections of the Grid Code. Their objective is to ensure that the various
sections of the Grid Code work collectively and in harmony with each other for the
benefit of all Participants.
Chapter 3, Planning Code, provides a framework for enabling the TSP and Users to
interact in relation to planning and development of the Transmission System and also
specifies the data and information that they have to exchange with each other for this
purpose.
Chapter 4, Operating Code, covers a host of topics relating to proper operation of the
Chapter 6, Data and Information Exchange Code, sets out the obligations and
responsibilities of the TSP and Users in relation to the supply of data and information
to each other, and also lists the various categories of data and information to be
exchanged between the TSP and the Users.
Chapter 7, Metering Code, deals with metering and recording requirements for
Participants and clarifies on their obligations relating to such installations. It also sets
the minimum technical, design and operational criteria to be complied with by Grid
Participants relating to metering and data collection Equipment and installations.
The Glossary and Definitions at the end provides brief definitions and explanation of
the various terms that have been used in the various parts of the Grid Code. These
terms appear in the Grid Code with their initial letters in uppercase.
The provisions of the Grid Code have been organized using an hierarchical list style
numbering system. For instance, the provision numbered as 3.5.2.1, represents
clause number 1 of Chapter 3, section 5, and subsection 2. Similarly, the provision
numbered as 4.5.3.2 represents clause number 2 of Chapter 4, section 5, and
subsection 3.
LIST OF ABBREVIATIONS
A ampere
AC alternating current
ANSI American National Standards Institute
AVR Automatic Voltage Regulator
CT Current Transformer
DC direct current
DPD Detailed Planning Data
(E)HV (Extra) High Voltage
GCSC Grid Code Supervisory Committee
HV High Voltage
Hz hertz
IEC International Electrotechnical Commission
IEEE Institute of Electrical and Electronics Engineers
ITU International Telecommunication Union
kA kilo ampere
kV kilo volt
kvar kilo var
kW kilo watt
kWh kilo watt hour
kvarh kilo var hour
LV Low Voltage
min minute
MVA mega volt ampere
Mvar mega var
Mvarh mega var hour
MW mega watt
MWh mega watt hour
NIOM Notification of Inadequate Operating Margin
NMDR Negative Minimum Demand Regulation
OD Operational Data
Plt Flicker Severity Index (Long-term)
Pst Flicker Severity Index (Short-term)
PSS Power System Stabilizer
PSS/E Power System Simulator/Engineering
PTI Power Technologies International
RMS root mean square
RPM revolutions per minute
RTU remote terminal unit
s second
SCADA supervisory control and data acquisition
SPD Standard Planning Data
STPM Short Term Planned Maintenance
TSP Transmission Service Provider
U Generating Unit
V volt
VA volt ampere
var volt ampere reactive
VT Voltage Transformer
W watt
Wh watt hour
1.1 Introduction
This chapter contains provisions which are of general nature and apply to all
sections of the Grid Code. Their objective is to ensure, to the maximum
possible extent, that the various sections of the Grid Code work collectively
and in harmony with each other for the benefit of all Participants.
1.2 Objectives
1.3 Scope
1.3.1 The Grid Code applies to the TSP and to all Users of the Grid, including all
persons/parties to whom any individual section of the Grid Code applies. In
specific the following:
(i) The Transmission Service Provider (TSP);
(ii) Generators;
(iii) Distribution Entities; and
(iv) Directly-connected Customers.
1.3.2 The provisions under this Code apply to Users seeking new Connection, or
modification of an existing Connection, to the Transmission System. Users
currently connected to the Transmission System may have been designed to
different standards and, therefore, may not be able to comply in whole or in
part with some or all of these conditions. Such Users should seek Derogation
by following the procedure set out in (1.11).
1.4.1 The TSP shall be responsible for the Grid Code implementation and
enforcement.
1.4.2 For the above purposes, the TSP may need access to the services and
facilities of Users or to issue instructions to Users in order to implement and
enforce the Grid Code (for example, to isolate or disconnect Plant or
Apparatus, etc.). All Users, therefore, are required not only to abide by the
letter and spirit of the Grid Code, but also to provide the TSP with such rights
of access, services and facilities and to comply with such instructions as the
TSP may reasonably require to implement and enforce the Grid Code.
1.4.3 Each party shall, at all times in its dealings with the other parties to the Grid
Code, act in good faith and in accordance with the established Good Industry
Practices.
In case of a dispute between the TSP and a User about any provision of the
Grid Code or any issue relating to that provision, the TSP and the User shall
first try to settle it bilaterally by making all reasonable endeavors for resolving
the dispute. If they cannot resolve the dispute bilaterally, the dispute parties
will proceed to deal with the dispute according to the procedure prescribed for
this purpose in the Electricity Law or guidelines issued by the Regulator.
If circumstances arise which the provisions of the Grid Code have not
foreseen, the TSP shall, to the extent practicable, consult all Affected Users in
an effort to muster consensus on the action required. If agreement between
the TSP and such Users cannot be reached in the time available, the TSP
shall determine the best course of action. Each User shall comply with all
instructions given to it by the TSP following such a determination provided
that the instructions are consistent with the then current technical parameters
of the relevant User’s System registered under the Grid Code. The TSP shall,
as soon as reasonably practicable following the occurrence of the unforeseen
The provisions (in part or in whole) of the Grid Code may be suspended
under abnormal conditions or pursuant to any directions given by the
Regulator or the Government.
1.10.1 The TSP shall constitute and host the Grid Code Supervisory Committee
(GCSC) in accordance with the guidelines of the Regulator. The GCSC shall
be a standing body carrying out the functions referred to in (1.10.2) below.
1.10.2 The GCSC shall:
(i) keep the Grid Code and its working under review;
(ii) review all suggestions for amendments to the Grid Code which the
Regulator or any Participant may submit to the GCSC for
consideration from time to time or the GCSC initiates at its own;
(iii) make recommendations to the Regulator for amendments to the Grid
Code which the GCSC feels are necessary or desirable and record
the reasons for the recommendations;
(iv) issue guidance in relation to the Grid Code and its implementation,
performance, and interpretation upon the reasonable request of any
Participant;
(v) consider what changes are necessary to the Grid Code arising out of
any unforeseen circumstances referred to it by the TSP under (1.6);
and
(vi) review and make recommendation to the Regulator for final decision
on any request that a Grid Participant submits to the GCSC to seek
Derogation from any provision(s) of the Grid Code.
1.10.3 The GCSC shall be a stakeholder representative panel and shall consist of
the following members:
(i) a Chairman and three (3) persons appointed by the TSP;
(ii) a person appointed by the Regulator;
(iii) two (2) persons representing Generators each having Generating
Station with a total Registered Capacity exceeding 500 MW;
(iv) one person representing Generators each having Generating Station
with a total Registered Capacity 500 MW or less;
(v) one person representing each Distribution Entity in the Kingdom of
Saudi Arabia, in total four (4); and
(vi) one person to represent Directly-connected Customers.
1.10.4 The GCSC shall establish and comply at all times with its own rules and
procedures relating to the conduct of its business, which shall be approved by
the Regulator and published by the GCSC within three (3) months of the
formation of the GCSC.
1.10.5 The TSP shall provide administrative and logistic support to the GCSC for the
GCSC’s functioning by establishing the Grid Code Secretariat. This decision
may be reviewed by the Regulator. The Secretariat shall be accountable to
the Regulator as well as to the GCSC for its activities. The detailed functions
and responsibilities, administrative structure, and modes of operation of the
Secretariat will be further elaborated by the GCSC in its rules and procedure
as laid down in (1.10.4) above.
1.11.1 The Regulator is the approving authority for the Grid Code, as well as for
making amendments to it and for granting any Derogation from its provisions.
For approving any request for amendment or Derogation, the Regulator will
be guided by the GCSC recommendations on the relevant matter.
1.11.2 Any Participant, GCSC member, or the Regulator itself may propose
amendments to the Grid Code.
1.11.3 Any Participant can seek Derogation from complying with one or more
provisions of the Grid Code. The Derogation may be granted by the Regulator
on the following grounds:
(i) to provide for existing Plant and/or Apparatus that has not been
designed in accordance with the provisions of the Grid Code;
(ii) to facilitate a smooth transition to the Grid Code from the existing
situation; and/or
(iii) to ease temporary constraints that prevent compliance and
necessitate exemption.
1.11.4 A Participant seeking Derogation shall make a written request to the GCSC
and shall be required to justify the request in terms of both the specific
circumstances and the expected duration. As a minimum, the application
must include the following information:
(i) detail of the applicant;
(ii) relevant provision(s) of the Grid Code and the required performance;
(iii) a description of the relevant Plant and/or Apparatus and the nature
and extent of non-compliance;
(iv) a description of the proposal for restoring compliance (where
applicable) including details of actions to mitigate risks and restore
compliance including timetable;
(v) a description of the reasonable alternative actions that have been
considered; and
(vi) a statement of the expected duration of the non-compliance.
1.11.5 The process for seeking amendments to the Grid Code or seeking Derogation
from its provisions is depicted in Figure 1.1.
Draft
proposal
GCSC sends
recommendation
to Regulator
1.11.6 On receipt of any request for Grid Code amendment or Derogation, the
GCSC shall promptly consider such request (by seeking expert
advice/opinion on the request, if necessary) and submit its
recommendation(s) to the Regulator for a final decision.
1.11.7 The Regulator shall consider the request in light of the recommendation(s) of
the GCSC, and shall decide as appropriate. In deciding on the request, the
Regulator may invite the relevant Participant or any member of the GCSC to
seek clarification on the request.
1.11.8 The Regulator shall communicate its final decision to GCSC for informing the
relevant Participant and/or for taking further action, as appropriate.
1.11.9 If a Derogation is granted, then the relevant Participant will not be obliged to
comply with the applicable provision of the Grid Code (to the extent and for
the period of the Derogation) and shall comply with any alternate provision as
set forth in the Derogation.
1.11.10 A Derogation from the Grid Code will normally have an expiry date in order
to review its continued need and monitor performance towards compliance.
1.11.11 Every Derogation will be entered on a register maintained by the Regulator
for this purpose.
1.12.1 Unless otherwise specified in the Grid Code, all instructions given by the TSP
and communications (other than those relating to the submission of data and
notices) between the TSP and Users (other than Generators) shall take place
between the TSP Control Engineer based at the TSP Control Center notified
by the TSP to each User prior to Connection and the relevant User’s
Responsible Engineer at the User’s Control Center notified by the User to the
TSP prior to Connection or such other person as the TSP or the User (as the
case may be) may, from time to time, notify to the other for such purposes.
1.12.2 Unless otherwise specified in the Grid Code, all instructions given by the TSP
and communications (other than those relating to the submission of data and
notices) between the TSP and a Generator shall take place between the TSP
Control Engineer based at the TSP Control Center notified by the TSP to
each Generator prior to Connection and the Generator’s Responsible
Engineer at the Generator’s Control Center notified by the Generator to the
TSP prior to Connection or such other person as the TSP or the Generator
(as the case may be) may from time to time notify to the other for such
purposes.
1.12.3 Unless otherwise specified in the Grid Code, all instructions given by the TSP
and communications (other than those relating to the submission of data and
notices) between the TSP and Users will be by telephone, fax, or any other
acceptable electronic means, with a facility to record messages permanently.
1.12.4 Where instructions or communications are given under the Grid Code by
means of a communications system with a facility to record (by whatever
means) messages permanently and without access to erase or modify the
recorded instructions and communications, such recording (to be retained for
at least one [1] year) shall be accepted by the TSP and Users as evidence of
those instructions or communications.
1.13.1 All data and Notices required under the Grid Code (other than data which is
the subject of a specific requirement of the Grid Code as to the manner of its
delivery) shall be submitted electronically or through any other suitable means
agreed upon by the concerned parties. Written notices under the Grid Code
shall be served either by hand delivery, registered first-class pre-paid mail,
courier service, or facsimile to the TSP or the User, as the case may be.
1.13.2 All data submitted by a User to the TSP, prior to Connection or before the
TSP’s making an Offer of Connection, in compliance with the Grid Code
provisions shall be treated as confidential.
1.13.3 Appropriate data shall be made available by the TSP when requested by a
User. These data shall be used only for the purpose specified in the request
and shall be treated by the User as confidential.
1.13.4 Data delivered pursuant to paragraph (1.13.1) shall:
(i) in the case of data to be submitted by a User prior to the Connection
of its Plant and/or Apparatus to the Transmission System, in relation
to that Plant and/or Apparatus, be addressed to Manager,
Transmission Asset Planning Department, at the address notified by
the TSP to the User following receipt of an application for Connection
to the Transmission System, or to such other department within the
TSP or address as the TSP may notify to the User from time to time;
and
(ii) in the case of data to be submitted by a User in respect of Plant
and/or Apparatus already connected to the Transmission System, be
addressed to Manager, Transmission Asset Planning Department, at
the address notified by the TSP to the User prior to Connection to the
Transmission System, or to such other department within the TSP or
address as the TSP may notify to the User from time to time.
1.13.5 Notices submitted to Users shall be addressed to such person as may be
notified in writing to the TSP from time to time by the relevant User at its
address(es) notified by the User to the TSP in writing from time to time for
submission of data and service of Notices under the Grid Code (or failing
which to the registered or principal office of the User).
1.13.6 All data items, where relevant, will be referenced to nominal voltage and
frequency unless otherwise stated.
References in the Grid Code to Plant and/or Apparatus of a User shall include
Plant and/or Apparatus owned by a User and Plant and/or Apparatus used by
a User under any agreement with a third party.
Where a User System (or part thereof) is, by agreement, under the control of
the TSP for the purpose of communication and coordination in operational
matters, the TSP can (for those purposes only) treat that User System (or part
thereof) as part of the TSP System, but otherwise, it shall remain to be
treated as the User System (or part thereof). This will also include any User
System or facility used by the TSP as part of the TSP’s Transmission path.
1.16.1 Precedence
In the event of any conflict between the provisions of the Grid Code and any
contract or agreement between the TSP and a User, the provisions of the
Grid Code shall govern, unless the Grid Code expressly provides otherwise.
The Preface, Table of Contents, and Titles have been added for the
information and convenience of the users of the Grid Code. These, therefore,
shall not be considered in interpreting the provisions of the Grid Code.
1.16.8 Figures
Figures are provided in some sections of the Grid Code for the convenience
of the Users, and only to illustrate a process. In case of any discrepancy
between the text and figures regarding any provision of the Grid Code, the
text shall prevail. Such discrepancies, when noticed, will be brought to the
notice of the GCSC and will be removed during the next revising of the Grid
Code.
2.1 Introduction
2.1.1 This chapter specifies certain principles and establishes a set of minimum
technical, design, and operational conditions for the Users for connecting to
and using the Transmission System. The purpose is to protect the TSP
facilities as well as the Plant and Apparatus of the Users, and to ensure safe,
stable, and secure operation of the System. This chapter also provides detail
on the performance characteristics of the Transmission System at the
Connection Point to enable the Users to design their own facilities accordingly
and to provide suitable control and Protection Schemes for them.
2.1.2 In addition to this Connection Code, there may be additional provisions in the
individual Connection Agreements between the TSP and the Users, defining,
in greater detail and in more specific terms, the mutual obligations of each
party.
2.2 Objectives
procedure specified in this section, prior to the actual Connection to the Grid.
This procedure is depicted in Figure 2.1 on page (35).
2.3.1.2 The TSP shall establish the procedures for the processing of User
applications for new, or modification of an existing, Connection to the Grid.
The TSP will also set out the time for Connection after receiving all the
required information from the applicant.
2.3.1.3 The time periods for a User’s new, or modification of an existing, Connection
shall be negotiated and agreed upon upfront, between the TSP and the User,
in every case. Users will be connected to the Transmission System based on
Grid Impact Studies.
2.3.1.4 The conditions under this section apply to Users seeking new Connections to
the Transmission System. Users currently connected to the Transmission
System may have been designed to different standards and, therefore, may
not be able to comply in whole or in part with some or all of these conditions.
Such Users should seek Derogations in accordance with the provisions of
(1.11) of Chapter 1: General Conditions. However, these conditions shall be
applied to Users if new installations or modifications (e.g. in the Excitation
System, etc.) are introduced on the User Site.
2.3.1.5 All Plant and Apparatus at the Connection Point shall comply with the relevant
TSP standards, or in their absence, other IEC, ANSI, or IEEE standards,
unless modified by any provision in the applicable Connection Agreement.
2.3.1.6 The Transmission System voltage level at which a User will be connected and
the Busbar configuration which a User’s System uses will depend upon, but
not limited to, the following:
(i) the size of the Generating Units and the number of Generating Units
comprised in the User System (for Generators);
(ii) the size of the MW Demand at the Connection Point (for Distribution
Entities and Directly-connected Customers);
(iii) consistency with future development of the Transmission System as
well as the coordinated planning of the Transmission System and of
the Distribution System/User System;
(iv) proximity to the existing Transmission System; and
(v) the cost of the proposed Connection.
2.3.1.7 The method of Connection used may exceed the relevant standards where
this is required by the User and is acceptable to the TSP.
2.3.1.8 The TSP shall deliver or take electric Energy at the Connection Point and
shall not be responsible in any manner whatsoever beyond that point.
2.3.1.9 In case of a dispute, the TSP shall try first to settle it bilaterally through
negotiation with the User. If can not settle it, the TSP will deal with the dispute
according to the procedures and mechanisms prescribed by the Regulator for
this purpose.
2.3.2.1 The TSP shall develop and maintain a set of required technical planning
studies for evaluating the impact on the Grid of any proposed Connection or
modification to an existing Connection.
2.3.2.2 The TSP shall specify which of the planning studies described in (3.3.6) of
Chapter 3 will be carried out to evaluate the impact of the proposed User
Development on the Grid.
2.3.2.3 Based on the magnitude and complexity of the proposed User Development,
the TSP may need to conduct more extensive planning studies. In such a
case, the TSP will indicate in its Offer of Connection this requirement.
2.3.2.4 The User shall indicate whether it wishes the TSP to undertake additional
planning studies. The User shall bear the full cost of the additional planning
studies, if carried out by the TSP.
2.3.2.5 To enable the TSP to carry out the necessary detailed Grid Impact Studies,
the TSP may require the User to provide some or all of the Detailed Planning
Data listed in (Appendix A3.2) of Chapter 3: Planning Code ahead of the
normal timescale shown there.
2.3.2.6 A User applying for a new, or a modification of an existing, Connection to the
Grid shall take all necessary measures to ensure that the proposed User
Development does not degrade the Grid. The TSP may disapprove an
application, if the Grid Impact Studies indicate that the proposed User
Development will (or may) result in the degradation of the Grid.
2.3.4.1 The TSP shall process the User application for new, or modification of an
existing, Connection within thirty (30) days from the submission of the
completed application form and settlement of the admissible fees.
2.3.4.2 After evaluating the application submitted by the User, the TSP shall inform
the User whether its application is acceptable or not. The TSP will be entitled
to reject a User application if:
(i) accepting of a User Development can lead the TSP to a breach of its
duties under the Electricity Law, Implementing Regulations, License
conditions, the Grid Code, or any other rule, regulation, or standard
relating to safe and secure operation of the Grid; or
will be rejected. The User may refer the matter to the GCSC if the User so
desires.
The Connection Agreement between the User and the TSP shall meet the
following basic conditions:
(i) The TSP and the User shall comply with the Grid Code in letter and
spirit.
(ii) The User shall submit reports containing technical and financial
information as required in the various sections of the Grid Code.
(iii) The TSP shall provide the User the relevant information in accordance
with its statutory and regulatory obligations.
(iv) The User shall provide to the TSP estimated details on the types of its
loads and the estimated profile of each major load (e.g. air
conditioning, combined heat and Power, motors, and drives, etc.).
(v) The User shall provide the TSP technical diagrams of the required
Connection as stated in this chapter or the application form.
(vi) The User shall provide the TSP details of Safety and Protection
schemes at the User facilities and for the Connection Point.
(vii) The Connection Agreement with the User shall also clearly specify the
operation and maintenance boundary between the User and the TSP.
The following shall be submitted by the User prior to the Commissioning date,
pursuant to the terms and conditions and schedules specified in the relevant
Connection Agreement:
(i) specifications of major Equipment not included in the Standard
Planning Data and Detailed Planning Data.
(ii) details of the Protection arrangements and settings referred to in
(2.5.2);
(iii) copies of all Safety Rules and instructions applicable to the User’s
Equipment and a list of Safety Representatives, pursuant to the
requirements of (4.10.8);
(iv) Electrical Diagrams of the User’s Equipment at the Connection Point
as described in (2.7.4);
(v) information that will enable the TSP to prepare the Connection Point
Drawings, referred to in (2.7.4);
(vi) a list of the names and telephone numbers of authorized
representatives, including the confirmation that they are fully
authorized to make binding decisions on behalf of the User, for
Significant Incidents pursuant to the procedures specified in section
4.5: Operational Liaison in Chapter 4: Operating Code;
(vii) proposed Maintenance Program;
(viii) Commissioning Tests procedures for the Connection Point and the
User Development; and
(ix) Site Test reports, clearance and readiness for Energization of the
proposed Connection Plant and Equipment.
2.3.7.1 Upon completion of the User Development, including work at the Connection
Point, the Equipment at the Connection Point and the User Development shall
be put to Commissioning Tests procedure as specified in (4.9.6) of Chapter 4:
Operating Code.
2.3.7.2 The User shall then submit to the TSP a statement of Readiness to Connect,
which shall include the Commissioning Test Reports.
2.3.7.3 Upon acceptance of the User’s statement of Readiness to Connect, the TSP
shall, within fifteen (15) days, issue a Technical Completion Certificate to the
User if the TSP finds the Commissioning Reports to be acceptable.
Otherwise, the TSP will ask the User to perform additional Tests as the TSP
may consider necessary.
2.3.7.4 The physical Connection to the Grid shall be made by the TSP within ten (10)
days of the issue of Technical Completion Certificate by the TSP to the User.
2.4.1.1 The TSP shall strive to maintain the Transmission System performance within
the limits and ranges specified in the Minimum National Power Quality
Standards for the Saudi Arabian Transmission Grid (currently under
development). Until such time, the TSP shall strive to maintain the
2.4.2.1 The Transmission System shall have a nominal frequency of 60 Hz and R-Y-
B counter-clock-wise phase rotation. The TSP shall maintain it within the
limits of 59.9 and 60.1 Hz during normal Grid operation.
2.4.2.2 The System frequency could rise to 62.5 Hz or fall to 57.0 Hz in exceptional
circumstances. To enable the TSP to maintain the frequency within the limits
specified in (2.4.2.1), the design of Generator’s Plant and Apparatus must
enable operation of that Plant and Apparatus in accordance with the
following:
Other Users should ensure that their Equipment is designed or protected for
these exceptional circumstances.
The voltage at any point on the TSP system will normally remain within the
nominal values as stated in the table below, unless abnormal conditions
prevail. Under exceptional circumstances, the maximum over voltage limits
stated below should not be exceeded for more than thirty (30 ) minutes:
30-Minute Over-
Nominal Voltage (kV) Normal Range
Voltage
110 kV ±5% + 10 %
132 kV ±5% + 10 %
230 kV ±5% + 10 %
380 kV ±5% + 10 %
2.4.4.1 All Plant and Apparatus connected to the Transmission System shall be
capable of withstanding the levels of Harmonic distortion expected to be
present on the Transmission System.
2.4.4.2 Plant and Apparatus connected to the Transmission System shall not impose
voltage Harmonics on the Transmission System which exceed the limits
specified in the relevant Connection Agreement, or when no such limits are
specified there, a Total Harmonic Distortion of 1.5% with no individual
Harmonic greater than 1%.
2.4.4.3 Plant and Apparatus connected to the Transmission System shall not impose
current Harmonics on the Transmission System which exceed the limits
specified in the relevant Connection Agreement, or when no such limits are
specified there, the limits specified in IEEE Standard 519-1992:
Recommended Practices and Requirements for Harmonic Control in
Electrical Power Systems.
The User facility shall not cause the phase-to-phase unbalance of the
System, as measured with no load and with balanced three-phase loading, to
exceed by more than one (1) % at the Connection Point.
2.4.6.1 The voltage fluctuation at any Connection Point with a fluctuating Demand
shall not exceed one (1)% of the nominal voltage level for step changes which
may occur repetitively. Any large voltage excursions other than step changes
may be allowed up to a level of three (3)% providing that this does not pose a
risk to the Transmission System or to the System of any other User.
2.4.6.2 The Flicker Severity at any Connection Point in the Transmission shall not
exceed the limits of Pst =0.8 and Plt=0.6, both 95th percentile values measured
over a period of one week.
2.4.7.1 The User Systems shall be designed and operated to include the devices that
will mitigate the effects of transient over voltages and transient voltage dips
on the Grid and the User System.
2.4.7.2 The User shall take into account the effect of electrical transients when
specifying the insulation of their electrical Equipment.
2.4.8 Grounding
2.4.8.1 At voltages 110 kV and above, the Grid is effectively grounded with specified
Ground Fault Factor below 1.4.
2.4.8.2 The TSP shall specify in the Connection Agreement the Grounding
requirements and the applicable Ground Fault Factor at the Connection
Points, if an exception is to be permitted in certain cases.
2.5.1.1 Each Connection between a User and the Transmission System shall be
controlled by a suitable isolating device (isolating switch or circuit breaker, as
determined by the TSP) capable of interrupting at the Connection Point, the
short circuit currents specified in the relevant Connection Agreement.
2.5.1.2 The User shall be responsible to ensure that all the User Plant and
Apparatus, including Protection Schemes, are tested and maintained and
remain rated for the duty required of them.
2.5.1.3 Users shall own, operate, and maintain all the facilities beyond the
Connection Point.
2.5.1.4 The TSP shall own, operate, and maintain all the facilities up to and including
those at the Connection Point.
2.5.1.5 The User shall comply with the operating instructions of the TSP with regard
to various systems (including all Plant and/or Apparatus) required to control
electric Power and Energy to (or from) that User’s facility.
2.5.2.1 All Users shall be responsible for providing Protection for the Equipment and
facilities at their respective sides when connected to the Transmission
System.
2.5.2.2 All User Protection Schemes, relays and their settings, shall require prior
coordination with and approval of the TSP’s relevant Protection engineering
office.
2.5.2.3 The Protection Schemes shall isolate the faulty section and Equipment in
case of Fault with the dependability, selectivity, speed, and sensitivity as
defined in the applicable Connection Agreement or the Grid Code.
2.5.2.4 The protective Equipment connected to the Transmission System shall be
tested to achieve the specified level of dependability, selectivity, speed, and
sensitivity in Fault clearing and to minimize the impacts on the Grid.
2.5.2.5 The Protection Scheme’s ability to initiate the successful tripping of the circuit
breaker which is associated with the faulty Equipment shall be measured by
System Protection Dependability Index exceeding 99%.
2.5.2.6 Users shall comply with the following requirements for Fault clearance times
(from Fault inception to circuit breaker arc extinction) by primary Protection
not exceeding:
380 kV 80 millisecond
The probability that these times will be exceeded for any given Fault must be
less than one (1)%.
2.5.2.7 To safeguard against failure of the primary Protection Systems provided to
meet the above Fault clearance time requirements, the Users shall also
provide backup Protection, which shall have Fault clearance time slower than
that specified for the User primary Protection. The TSP shall also provide
backup Protection, which shall have Fault clearance times slower than those
of the User backup Protection.
2.5.2.8 In case of the failure to trip of a User’s circuit breaker provided to interrupt
Fault current interchange with the Transmission System, circuit breaker fail
Protection shall be provided to trip all necessary electrically adjacent circuit
breakers within 300 milliseconds. The design reliability for Protection shall be
equal to or greater than 99%.
Where no circuit breaker is provided at the User Connection Point, the User
must provide to the TSP all necessary facilities and schemes to isolate with
discrimination and as necessary the Faults or Grid abnormalities, due to the
User Connection, on the Transmission System. In these circumstances, for
Faults on the User System, the User Protection should also trip higher voltage
TSP circuit breakers. These tripping facilities shall be in accordance with the
requirements specified in the relevant Connection Agreement.
(i) Protection and relay settings shall be coordinated by the TSP and
User(s) across the Connection Point in accordance with the
Connection Agreement to ensure effective Disconnection of faulty
Apparatus. In case of a dispute between any party on such issues, the
TSP shall be the final deciding authority.
(ii) The TSP may install special Protection Schemes to safeguard against
collapse of the System for any foreseeable situation, e.g. during high
summer load seasons. In the event of loss of major Transmission
line(s) leading to voltage collapse in the Transmission System, The
TSP may need to resort to a large scale load shedding to halt
damaging voltage collapse which may lead to brownouts and eventual
blackouts.
2.5.3.1 All Users responsible for the operation and maintenance shall also be
responsible for the Safety of Equipment, persons, and facilities at their
respective sides connected to the Transmission System. On Safety issues,
Users shall follow the procedures as laid down in section 4.10 of Chapter 4:
Operating Code and the Safety Rules referred to in that section.
2.5.3.2 Site Responsibility Schedule as provided in (2.7.5) will specify the ownership
responsibilities of each User connecting to the Transmission System for the
following:
(i) ownership of the Plant/Equipment;
(ii) the responsibility for operation and maintenance;
(iii) Safety Rules and Procedures; and
(iv) control of Plant/Equipments and facilities at their respective side.
2.5.4 Metering
2.5.5.1 All Generating Units must be capable of supplying rated Active Power output
at any point between the limits 85% Power Factor lagging and 95% Power
Factor leading at the Generating Unit terminals, unless otherwise agreed
expressly by the TSP in the Connection Agreement.
2.5.5.2 All Generating Units must be capable of continuously supplying their rated
Active Power output at the Generating Unit terminals within the System
frequency range 59.5 to 60.5 Hz. Any decrease of Active Power output
occurring in the frequency range 57.0 to 59.5 Hz should not be more than a
proportionate decrease in the frequency.
2.5.5.3 The Active Power output at the Generating Unit terminals under steady state
conditions should not be affected by voltage changes in the normal operating
range specified in (2.4.3).
2.5.5.4 Transformation ratio and tap changer of step up transformer and the auxiliary
services transformer, as well as the voltage range and Excitation of the
Generating Unit shall be designed and adjusted so that the Generating Unit is
at normal operating voltage of the Grid, capable of producing or absorbing (as
the case may be), continuously the Reactive Power defined by the capability
curve of the Generating Unit (at Generating Unit voltage level). The
Generating Unit’s continuous Reactive Power capability shall not be
restrained by main or auxiliary Equipment, control, Protection, or operating
procedures.
2.5.5.5 The Generating Unit shall be capable of absorbing continuously the Reactive
Power (under Excitation operation) defined by the capability curve of the
Generating Unit also at maximum voltages (380, 230, 132, 115, and 110 kV
of the Grid) assuming that Stability is maintained.
2.5.5.6 The Reactive Power output at the Generating Unit terminals under steady
state conditions and at rated Active Power should be fully available within the
range ± five (5)% of nominal voltage at the Connection Point.
2.5.5.7 The TSP may require a Black Start capability from certain strategically
located Generating Units/Stations. In such cases, Generators will provide
Black Start capability through an agreement with the TSP. If an agreement
cannot be reached on this issue, the TSP or the Generator shall refer the
matter to the Regulator for resolution. Generators, committing to provide
Black Start capability, shall also allow to the TSP access to their Black Start
Units for testing and drills, as and when required by the TSP.
2.5.5.8 In case the System frequency momentarily rises to 62.5 Hz or falls to 57.0 Hz,
all Generating Units shall remain in synchronism with the Transmission
System for the operating times stated in (2.4.2) to allow the TSP to undertake
measures to correct the situation. Each Generating Unit must be capable of
contributing to, in a manner satisfactory to the TSP, Frequency and Voltage
Control by modulation of Active Power and Reactive Power supplied to the
Transmission System or a User System.
2.5.5.9 The System frequency could vary within the limits given in (2.4.2) and
Generating Units are required to be capable of satisfactory operation at any
frequency within this range unless the TSP has agreed in the Connection
Agreement to the use of any frequency-level relays and/or rate-of-change-of-
frequency relays which will trip Generating Unit within this frequency range.
2.5.5.10 Each Generating Unit shall be fitted with a fast-acting Speed Governor
System to provide Power and Frequency Control under normal operating
conditions. The Speed Governor System shall be designed and operated
freely to regulate System frequency and shall have adjustable Governor
Droop setting within 2% to 8%. The normal set point will be generally at 5%.
Total Governor Deadband (inherent plus intentional) should be 0.05 Hz or
less. The above Droop and Deadband requirement shall apply for an entire
combined-cycle Generation facility. Users shall not change frequency or
load related control settings of Speed Governors without the prior agreement
of the TSP. In islanding situations, the Generating Unit’s Speed Governor
System must also be able to operate at frequency range between 57.5 Hz
and 60.2Hz.
2.5.5.11 Each Generating Unit shall be equipped with high response Excitation
System with continuously acting Automatic Voltage Regulation (AVR)
system to control the Unit terminal voltage. The AVR shall be designed and
operated to maintain the steady-state terminal voltage within ± 0.5% of the
set point in the normal voltage range as specified in (2.4.3) without instability
over the entire operating range of the Unit. Ceiling voltage for static Exciters
shall be at least twice, and for brushless Exciters at least 1.6 times the rated
field voltage of the Generating Unit. The Excitation System shall be capable
of supplying its ceiling voltage for 10 seconds. Generators shall not disable
this automatic control mode without prior approval of the TSP. Each
Generating Unit shall be required to include Power System Stabilizing (PSS)
and var limiting Equipment as well.
2.5.5.12 On-load tap changing facilities shall be required on Generator step-up
transformers for Dispatch of Reactive Power. The transformer voltage ratio,
tapping range, and step sizes must be such that the Reactive Power
requirements specified in (2.5.5.6) are fully complied with.
2.5.5.13 The TSP shall be entitled to acquire such operational metering, control
parameters, and Plant data as it may reasonably require for the purposes of
discharging its statutory and regulatory obligations.
2.5.5.14 A Generating Unit, and the Station in which the Generating Unit is located,
must be capable of continuous uninterrupted operation for the voltage
variation specified in (2.4.3), and for Faults on the Transmission System
which may cause the voltage at the Connection Point to drop to between 0%
and 80% of the nominal voltage for a period of up to 300 millisecond in any
one phase or combination of phases, followed by a period of one (1) second
where voltage may vary in the range 80-110% of the nominal voltage, and a
subsequent return of the voltage within the range 90-110% of the nominal
voltage.
2.5.5.15 Generating Units shall be capable of withstanding, without tripping, a
negative phase sequence loading appropriate to their rated full load in
accordance with the IEEE Standard C37.102-1995: IEEE Guide for AC
Generator Protection. In addition they shall be required to withstand, without
tripping, the negative phase sequence loading incurred by clearance of a
close-up phase-to-phase Fault by backup Protection on the User System of
which they are a part.
2.5.5.16 The higher voltage windings of the Generating Unit step-up transformer
connecting the Generating Unit to the Transmission System must be star
connected with the star point grounded in accordance with IEEE Standard
C37.101-1993: IEEE Guide for Generator Ground Protection. If adjacent to a
2.5.6.1 At nominal System voltages of 110 kV and above, the higher voltage windings
of three phase transformers and transformer banks connected to the
Transmission System, if star-connected, shall have their star point suitable for
connection to Ground. For this purpose neutral connection must be brought
out of the tank to enable external connection to Ground. The Grounding and
lower voltage winding arrangement shall be such as to ensure that the
Ground Fault Factor requirement as stated in (2.4.8.1) of the Grid Code are
satisfactorily met on the Transmission System at nominal System voltages of
110 kV and above.
2.5.6.2 As required in Chapter 4: Operating Code, each Distribution Entity shall make
arrangements that shall facilitate automatic low frequency Disconnection of
Demand. The Connection Agreement shall specify the manner in which
Demand subject to low frequency Disconnection shall be split into discrete
MW blocks with associated Under Frequency Relay settings. Technical
requirements relating to Under Frequency Relays will be specified in the
Connection Agreement or relevant standards.
2.5.6.3 The Under Frequency Relays for Automatic Load Dropping shall be provided
at the Connection Point by the Users as per the Connection Agreement. The
TSP may allow a User to have such schemes installed on User side of the
Connection Point providing that, if considered necessary and required by the
TSP, one hundred (100) % of the User load may be shed.
2.5.6.4 Distribution Entities and Directly-connected Customers shall ensure that the
Power Factor at the Connection Point does not fall below 85% lagging at any
time and shall provide appropriate Power Factor improvement facilities to
ensure that.
2.5.6.5 Reactive Power compensation shall be provided by the Distribution Entities at
Low Voltage System close to the load point to avoid excessive Reactive
Power losses and to enable the TSP to maintain the Transmission System
voltage within the limits as specified in (2.4.3).
2.7.2.1 Any User entering and working on its Plant and/or Apparatus on a TSP Site
shall work to the TSP Safety Rules.
2.7.2.2 The TSP entering and working on its Plant and/or Apparatus on a User Site
shall work to the TSP Safety Rules. However, for User Sites where the TSP
staff may be exposed to some special risks (for instance, hazardous or toxic
substances or gases, etc.), the TSP, in addition to its own Safety Rules, will
follow the User Safety Rules also.
2.7.3.1 The TSP shall provide to each User details of TSP’s current numbering and
nomenclature system to enable the User to plan the numbering and
nomenclature of its own (E)HV Plant and Apparatus on the Connection Site.
2.7.3.2 The party installing Plant and/or Apparatus shall be responsible for providing
and installing of clear and unambiguous labels showing the Site and
Equipment identification at its respective System.
2.7.3.3 The numbering and nomenclature of each item of Plant and/or Apparatus
shall be included in the Operation Diagram prepared for each Site.
(i) If the TSP intends to install its E(HV) Plant and/or Apparatus on a
User Site, it shall notify the relevant User of its intent in writing by
showing the proposed Plant and/or Apparatus, with clear numbers and
nomenclature, on an Operation Diagram and by giving date of the
proposed installation, at least six (6) months ahead of the proposed
installation.
(ii) the relevant User will confirm to the TSP in writing within one (1)
month of the receipt of such notification, either its acceptance of the
TSP proposal or objection(s), if any, by stating the reasons for the
objection(s).
(iii) the relevant User will not install, or permit the installation of, any
(E)HV Plant and/or Apparatus on such User Site which has numbering
and/or nomenclature which could be confused with that of (E)HV Plant
and/or Apparatus of the TSP already on that User Site or about which
the TSP has notified to that User that it intends to install on that Site.
(i) If a User intends to install its (E)HV Plant and/or Apparatus on a TSP
Site, it shall notify the TSP of its intent in writing by showing the
proposed Plant and/or Apparatus, with clear numbers and
nomenclature, on the Operation Diagram and by giving date of the
proposed installation, at least six (6) months ahead of the proposed
installation.
(ii) the TSP will respond in writing to the User within one (1) month of the
receipt of the notification either confirming its acceptance of the User
proposed numbering and nomenclature or, if they are not acceptable,
by giving details of the numbering and nomenclature which the User
shall adopt for that (E)HV Apparatus.
2.7.3.6 Changes
2.7.4.1 Connection Point Drawings shall be prepared for each Connection Site and
shall include Site layout drawings, mechanical drawings, electrical layout
drawings, electrical Single Line Diagrams, common Protection/control
drawings, and common services drawings.
2.7.4.2 The TSP shall specify the procedure and format to be followed in the
preparation of the Connection Point Drawings for any Connection Point.
2.7.4.3 The User shall prepare and submit to the TSP, drawings for all the
Equipment, circuits, and facilities on the User’s side of the Connection Point,
in accordance with the schedule specified in the Connection Agreement.
2.7.4.4 The TSP shall provide the User with drawings for all the Equipment, circuits,
and facilities on the TSP side of the Connection Point, in accordance with the
schedule specified in the Connection Agreement.
2.7.4.5 If the Connection Point is at the User’s Site, the User shall prepare and
distribute Connection Point Drawings for the entire Connection Point.
Otherwise, the TSP shall prepare and distribute the Connection Point
Drawings for the entire Connection Point.
2.7.4.6 The Connection Point Drawings shall provide an accurate record of the layout
and circuit connections, ratings and identification of Equipment, and related
Apparatus and devices at the Connection Point.
2.7.4.7 If possible, all the electrical Equipment at the Connection Point shall be
shown in one Connection Point Drawing. When more than one Drawing is
necessary, duplication of identical information shall be minimized. The
Connection Point Drawing(s) shall represent, as closely as possible, the
physical arrangement of the Equipment and their electrical connections.
2.7.4.8 The Connection Point Drawing shall be prepared using the Site and
Equipment identification and labeling prescribed in (2.7.3).
2.7.4.9 The title block of the Connection Point Drawings shall include the names of
authorized persons together with provisions for the details of revisions, dates,
and signatures.
2.7.4.10 The Connection Point Drawings shall have the TSP stamp. The master copy
of the Connection Point Drawings shall remain with the TSP.
2.7.4.11 If a dispute arises, a meeting shall be held between the TSP and the User to
resolve the dispute at the shortest possible time.
(i) In the case of a Connection Point at a User Site, the TSP shall
prepare and submit to the User, Connection Point Drawings for the
TSP side of the Connection Point in accordance with the requirements
of the Connection Agreement.
(ii) The User shall then prepare, produce, and distribute, using the
information provided by the TSP, Connection Point Drawings for the
complete Connection Site in accordance with the requirements of the
Connection Agreement for approval by the TSP.
(i) In the case of a Connection Point at a TSP Site, the User shall
prepare and submit to the TSP, Connection Point Drawings for the
User side of the Connection Point in accordance with the
requirements of the Connection Agreement.
(ii) The TSP shall then prepare, produce, and distribute, using the
information submitted by the User, Connection Point Drawings for the
complete Connection Site in accordance with the requirements of the
Connection Agreement.
(i) A User feeling the necessity to change any aspect of the Connection
Point Drawings at a Connection Site shall do the following:
(a) for a Connection Point at a User Site, the User shall prepare,
produce, and distribute, after getting them approved by the
TSP, revised Connection Point Drawings for the complete
Connection Site; and
(b) for a TSP Site, the User shall prepare and submit to the TSP
revised Connection Point Drawings for the User side of the
Connection Point and the TSP shall then prepare, produce,
and distribute, using the information submitted by the User,
revised Connection Point Drawings for the complete
Connection Site.
(ii) If the User change can be dealt with by it notifying the TSP in writing
of the change and for each party to amend its copy of the Connection
Point Drawings then the User shall so notify, and each party shall so
amend (subject to TSP’s acceptance of the proposed changes).
(i) The TSP feeling the necessity to change any aspect of the Connection
Point Drawings at a Connection Site shall do the following:
(a) for a TSP Site, the TSP shall prepare, produce and distribute
revised Connection Point Drawings for the complete
Connection Site; and
(b) for a User Site, the TSP shall prepare and submit to the User
revised Connection Point Drawings for the TSP side of the
Connection Point and the User shall then prepare, produce
and distribute, using the information submitted by the TSP,
revised Connection Point Drawings for the complete
Connection Site for approval of the TSP.
(ii) If the TSP change can be dealt with by it notifying the User in writing
of the change and for each party to amend its copy of the Connection
Point Drawings then the TSP shall so notify, and each party shall so
amend.
(i) The Connection Point Drawings for the complete Connection Site
prepared by the User or the TSP, as the case may be, shall be the
definitive Connection Point Drawings for all operational and
maintenance and planning activities associated with the
Connection Site.
(ii) If a dispute arises as to the accuracy of the Connection Point
Drawings, a meeting shall be held at the Site, as soon as
reasonably practicable, between the TSP and the User, and both
shall strive to resolve the matter in dispute.
2.7.5.1 In order to inform the Site operational staff and the TSP Control Engineers of
the agreed responsibilities for Plant and/or Apparatus at the Connection
Point, a Site Responsibility Schedule shall be produced for the TSP and the
Users with whom it will interface.
2.7.5.2 The format, principles and basic procedure to be used in the preparation of
Site Responsibility Schedules are set down in (Appendix A2.1) to this chapter.
2.7.6.1 The provisions relating to access to the TSP Sites by Users, and to User
Sites by the TSP, will be set out in each Connection Agreement between the
TSP and the User. In addition to those provisions, where a Site belonging to
the TSP contains exposed (E)HV conductors, unaccompanied access shall
only be granted to individuals holding Authority for Access from the TSP.
2.7.6.2 The User shall permit unhindered access to TSP personnel (including their
tools, Equipment, and vehicles) for accessing the TSP Equipment at the
Connection Point and inside the User premises as may be required during
normal and contingency conditions.
2.7.7.1 User Plant and Apparatus on the TSP Sites shall be maintained adequately
(not less than the TSP standards) for the purpose for which it is intended and
to ensure that it does not pose a threat to the Safety of any of the TSP Plant,
Apparatus, or personnel on the TSP Site. The TSP shall have the right to
inspect the test results and maintenance records relating to such Plant and/or
Apparatus at any time. The TSP shall also have the right to inspect the User
Equipment at the Connection Point, if considered necessary by the TSP.
2.7.7.2 All the TSP Plant and/or Apparatus on User Sites shall be maintained
adequately (not less than TSP standards) for the purposes for which it is
intended to ensure that it does not pose a threat to the Safety of any of the
User Plant, Apparatus, or personnel on the User Site.
The TSP and the Users, must make available staff to take necessary Safety
Precautions and carry out operational duties as may be required to enable
work/Testing to be carried out and for the operation of Plant and/or Apparatus
connected to the System.
No
Application Application returned User
acceptable? with suggestions for Yes User revises the
accepts?
revision, if application.
practicable.
Yes
Yes No
No
TSP conducts Grid TSP and User meet Dispute
Impact Studies. to resolve dispute. resolved?
Additional study
Yes
Yes
No
Additional User Dispute
TSP and User
Study accepts to resolved?
meet
Required? Yes pay study
No
No
No
User
Offer accepted by the User application
rejected
Yes
Connection Agreement
between User and TSP is No
User may User
approach accepts
Preparation of project GCSC
documents by User.
Yes
Completion of User
Development work.
Case closed
Energization
A2.1.1 Principles
A2.1.1.1 At all Sites, the following Site Responsibility Schedule shall be drawn up
using the Pro forma Table A2.1 or with such variations as may be agreed
between the TSP and Users. In the absence of agreement, the Pro forma
Table A2.1 shall be used:
(i) Schedule of (E)HV Apparatus;
(ii) Schedule of LV Plant, Apparatus, services and supplies;
(iii) Schedule of telecommunications and measurement Apparatus.
A2.1.1.2 Each Site Responsibility Schedule for a Connection Site shall be prepared
by the TSP in consultation with other Users at least one (1) month prior to
the Completion Date under the Connection Agreement for that Connection
Site (which may form part of a Site).
A2.1.1.3 Each User shall, in accordance with the timing requirements of the
Connection Agreement, provide information to the TSP to enable it to
prepare the Site Responsibility Schedule.
A2.1.1.4 Each Site Responsibility Schedule shall be subdivided to take account of
any separate Connection Sites on that Site.
A2.1.1.5 Each Site Responsibility Schedule shall detail for each item of Plant
and/or Apparatus:
(i) Plant/Apparatus ownership;
(ii) Responsible Manager (Controller);
(iii) Safety standards (applicable Safety Rules and standards);
(iv) Responsible person(s) responsible for coordinating on Safety
matters;
(v) operations (applicable operational procedures and Control
Engineer); and
(vi) responsibility to undertake maintenance.
A2.1.1.6 The (E)HV Apparatus Site Responsibility Schedule for each Connection
Site must include lines and cables emanating from the Connection Site.
A2.1.1.7 Every page of the Site Responsibility Schedule shall bear the date of
issue and the issue number.
A2.1.1.8 When a Site Responsibility Schedule is prepared, it shall be sent by the
A2.1.3.1 Each User shall, prior to the Completion Date under each Connection
Agreement, supply to the TSP the name of that User’s manager who has
been duly authorized to sign Site Responsibility Schedules on behalf of
the User. The TSP shall, prior to the Completion Date under each
Connection Agreement, also supply to that User the name of its own
manager responsible for the area in which the Site is situated.
Safety Operations
Signature of Signature of
TSP representative: _________________________ User representative: __________________________
Chapter 2: Connection Code
39
The Saudi Arabian Grid Code Chapter 3: Planning Code
3.1 Introduction
3.1.1 This chapter provides a framework for enabling the TSP and Users to interact
with each other in relation to planning and development of the Transmission
System. It also specifies the information and data that the Users shall provide
to the TSP or the TSP shall provide to the Users for this purpose.
3.1.2 All Users, existing as well as prospective, will be bound by the planning
conditions laid down in this chapter prior to generating, transmitting,
distributing, or consuming electricity, as the case may be.
3.2 Objectives
3.3.1.1 The TSP shall have the primary and lead responsibility for planning the Grid
development, including carrying out of all necessary studies, assessments,
and evaluations.
3.3.1.2 In planning for Grid development, the TSP may require a User, or a group of
Users, to modify or install new Plant and/or Apparatus, where the TSP
3.3.2.1 Users, existing as well as prospective, will be able to assess conditions for
connecting to, and using of, the Grid through the following:
(i) a forecast statement, prepared by the TSP, showing for each of the 5
succeeding years, the opportunities available for connecting to, and
using of, the Grid and indicating those parts of the Grid that are most
suited to new Connections and transport of further quantities of
electricity; or
(ii) an offer by the TSP to enter into a Connection Agreement with a User
for Connection to, or use of, the Grid.
3.3.2.2 To enable the TSP to properly plan for Grid development, Users will be
required to submit to the TSP all data that the TSP may require from them for
this purpose. The details of the data requirements from Users for planning
purposes are set out in (3.3.3).
3.3.2.3 Any User proposing to close, retire, withdraw from service, or otherwise
cease to maintain and keep available for Dispatch in accordance with Good
Industry Practice any Generating Station or Generating Units with Registered
Capacity greater than ten (10) MW in aggregate shall give the TSP at least
twenty-four (24) calendar months’ notice of such action.
3.3.3.1 For the TSP to undertake planning and development of the Grid, the TSP will
require the Users to provide data and information before Connection, and
also afterwards at regular intervals. These data will be provided to the TSP
using the schedules provided for this purpose in Chapter 6: Data and
Information Code. These data and information will be treated as Grid
Planning Data.
3.3.3.2 For planning purposes, Grid Planning Data will be classified into three (3)
main categories: (i) Project Planning Data; (ii) Standard Planning Data; and
(iii) Detailed Planning Data. These data categories are further explained
below:
(i) Project Planning Data: The TSP will require Users applying for a new,
or modification of an existing, Connection, to submit some or all of the
data items listed under Standard Planning Data and Detailed Planning
Data in this chapter. Such data will be treated by the TSP as Project
Planning Data until a User is actually connected to the Grid.
(ii) Standard Planning Data: Standard Planning Data are data that must
be submitted by all existing Users at regular intervals.
(iii) Detailed Planning Data: Detailed Planning Data are data that the TSP
may require from any existing User in support of the Standard
Planning Data.
3.3.3.3 As regards the Project Planning Data, the TSP may require different levels of
detail and quality of information through the various stages of the User
Development, as elaborated on below:
(i) At the time a User applies for a new, or modification of an existing,
Connection but before the TSP makes an Offer of Connection, the
data relating to the proposed User Development will be considered
Preliminary Project Planning Data and shall contain such data as may
be required by the TSP to evaluate the Connection application and, if
applicable, any other data directly relevant to, and submitted in
support of, the application. These data will be treated by the TSP as
confidential within the scope of TSP’s policy for confidentiality.
(ii) On formal acceptance by the prospective User of the Offer of
Connection, the data relating to the User Development, previously
submitted as Preliminary Planning Data, including any subsequent
data supplied in support of its application, will become Committed
Project Planning Data. Data at this stage will not be treated as
confidential to the extent that the TSP is required to use or disclose
these to discharge its contractual or regulatory obligations.
(iii) As soon as is practical, and not later than the Operational Date, all
data requirements as stated in this section, not previously requested
by the TSP or supplied by the User, will be submitted by the User to
the TSP. This will include confirming any estimated values assumed
for planning purposes or, where practical, replacing them by validated
actual values and by updating estimates for Forecast Data items such
as Demand. Data provided at this stage of the project will become
Registered Project Planning Data.
3.3.3.4 All existing Users shall submit to the TSP, each year, the Standard Planning
Data referred to in (3.3.3.2) and listed in (Appendix A3.1) of this chapter.
These data should be submitted by end of March each year and should cover
the current year and each of the five (5) succeeding years. Where from the
date of one submission to a date of subsequent submission there is no
change in the data to be submitted for any given year, instead of resubmitting
the data, a User may submit a written statement that there has been no
change from the data submitted the previous time, pertaining to the particular
year specified.
3.3.3.5 The TSP may also require additional data or information from a User referred
to as Detailed Planning Data in (3.3.3.2) and listed in (Appendix A3.2) of this
chapter. Where the TSP considers that this information is required, then the
User shall submit the information to the TSP within thirty (30) days, or such
other period as may be agreed between the TSP and the User, after the date
of such request.
(i) In cases of doubtful accuracy of the supplied data, the TSP may ask
the User to supply additional information to verify the data accuracy.
(ii) The TSP may demand the User to carry out specific Tests to verify the
data in conformity with applicable standards, if the information
supplied pursuant to (i) above is still suspect. Where such Test or
Tests are requested, they will be subject to the relevant provisions of
Chapter 4: Operating Code.
(iii) If as a result of the Test(s) in (ii) above, the User data is found to be
incorrect, then the User will bear the full cost of such Test(s), and the
TSP will use for its studies the data values as ascertained by such
Test(s). If any additional burden is imposed on the TSP in terms of
repeating or performing additional studies, then the User will also bear
the cost reasonably incurred by the TSP for such additional burden.
3.3.4.1 The TSP shall collate and process the Grid Planning Data submitted by the
Users into a cohesive and consolidated Grid planning dataset and shall use
this for conducting the various planning studies and also for preparing any
forecast statements and capacity development/reinforcement plans for the
Transmission System.
3.3.4.2 If any User believes that the cohesive Forecast Data prepared by the TSP
does not accurately reflect that User’s planning data, it shall immediately
notify the TSP of its concern. The TSP and the User shall promptly meet to
address the concern of the User.
The TSP shall apply the TSP Planning Criteria and Standards (to be
established by the TSP in due course), in the planning and development of
the Transmission System.
3.3.6.1 The TSP shall conduct Grid planning studies periodically or on as required
basis to ensure the economic, safe, reliable, and stable functioning of the
Transmission System, specifically for the following:
(i) preparation of the Transmission forecast statement for next five years;
A3.1.1.1 Each User directly connected to the TSP System shall provide to the TSP
its actual monthly Energy and Demand consumption at each Connection
Point for the immediate past year.
A3.1.1.2 The User shall also provide the TSP with actual hourly load profiles for a
TSP-specified weekday, weekend, and holiday for each season of the
year.
A3.1.2.1 The User shall provide to the TSP its Energy and Demand Forecasts at
each Connection Point for the current year and the five (5) succeeding
years. Where the User System is connected to the Grid at more than one
Connection Points, the Demand Data to be provided by the User shall
also include the Coincident Peak Active Power Demand.
A3.1.2.2 The Forecast Data for the first year shall include monthly Energy and
Demand Forecasts, while for the remaining years shall include only the
annual Energy and Demand forecasts.
A3.1.2.3 The User shall also provide to the TSP forecast hourly load profiles for a
TSP-specified weekday, weekend, and holiday for each season of the
year.
A3.1.2.4 The User shall provide the net values of Energy and Demand Forecast for
its System at each Connection Point after any deductions to reflect the
output of any Embedded/Captive Generating Units/Station. Such
deductions shall be stated separately in the Forecast Data.
A3.1.2.5 Generators shall submit to the TSP their expected Demand to be served
by each Generating Unit/Station. Forecast Data for Embedded/Captive
Generating Units/Stations shall be submitted through the Distribution
Entities, if applicable.
A3.1.2.6 In order to avoid duplication of Forecast Data, each User shall indicate the
Energy and Demand requirements that it shall meet under a contract.
Where the User shall meet only a portion of the Energy and Demand
requirements, it shall indicate in the Forecast Data that portion of the
A3.1.3.1 The Generator shall provide to the TSP data relating to the Generating
Units of its Generating Station(s).
A3.1.3.2 The Distribution Entities and Directly-connected Customers shall provide
the TSP with data relating to the Generating Units of each
Embedded/Captive Generating Station, if applicable.
A3.1.3.3 The following information shall be provided for the Generating Units of
each Generating Station or Embedded/Captive Generating Units/Station
of the other Users:
(i) nominal Capacity rating;
(ii) nominal voltage rating;
(iii) maximum continuous rating;
(iv) emergency rating;
(v) minimum rating;
(vi) speed;
(vii) type of Generating Unit and expected running mode(s);
(viii) auxiliary Power requirements;
(ix) direct axis sub-transient reactance;
(x) capability curve; and
(xi) Grounding arrangement.
A3.1.3.4 For the Generating Unit step-up transformer, the following:
(i) rated Capacity;
(ii) rated voltage;
(iii) cooling stages and capacity rating at each stage;
(iv) number of windings and winding arrangement;
(v) voltage ratio;
(vi) tap changer arrangement (on-load/off-load; at HV or LV), range,
and step size;
A3.1.4.1 The User shall provide the Electrical Diagrams and Connection Point
Drawings of its System and the Connection Point, respectively. The
Diagrams and Drawings shall indicate the quantities, ratings, and
operating parameters of the following:
(i) Equipment (e.g., Generating Units, Power transformers, and circuit
breakers);
(ii) electrical circuits (e.g., overhead lines and underground cables);
(iii) Substation bus arrangements;
(iv) Grounding arrangements;
(v) Protection Schemes, their description and maintenance plans;
(vi) interrupting devices;
(vii) phase configuration;
(viii) switching facilities;
(ix) operating voltages; and
(x) numbering and nomenclature.
A3.1.4.2 The User shall provide the values of the following parameters of the
overhead lines and/or underground cables from the User System
Substation to the Connection Point in the Grid:
(i) rated and operating voltage;
(x) chopped impulse withstand voltage, required for all circuit breakers
and Disconnect Switches rated 230 kV and above; and
(xi) switching impulse withstand voltage, required for all circuit
breakers and Disconnect Switches rated 230 kV and above.
A3.1.4.5 The User shall provide the details of its System Grounding. This shall
include the rated short time withstand current, zero sequence impedance,
and short time rating of the Grounding Equipment.
A3.1.4.6 The User shall provide the data on independently-switched Reactive
Power compensation Equipment at the Connection Point and/or at the
Substation of the User System. This shall include the following
information:
(i) rated Capacity;
(ii) rated voltage;
(iii) type (e.g., shunt reactor, shunt capacitor, static var compensator);
and
(iv) operation and control details (e.g. fixed or variable, automatic, or
manual).
A3.1.4.7 If a significant portion of the User Demand may be supplied from
alternative Connection Point(s), the relevant information on the Demand
transfer capability shall be provided by the User including the following:
(i) the alternative Connection Point(s);
(ii) the Demand normally supplied from each alternative Connection
Point;
(iii) the Demand which may be transferred from or to each alternative
Connection Point; and
(iv) the control (e.g., manual or automatic) arrangements for transfer
including the time required to effect the transfer for Forced Outage
and planned maintenance conditions.
A3.1.4.8 If a User System has Embedded/Captive Generating Stations and
significantly large-sized motors, the short circuit contribution of the
Embedded/Captive Generating Units and the large motors at the
Connection Point shall be provided by the Distribution Entities (or the
other Users). The short-circuit current shall be calculated in accordance
with the TSP Standards, or in their absence, the relevant IEC Standards
or their equivalent Saudi national standards.
A3.1.4.9 If the User System has fluctuating loads, the following information shall be
provided to the TSP:
(i) cyclic variation of Active Power over time;
(ii) cyclic variation of Reactive Power over time;
(iii) maximum rate of change of Active Power;
(iv) maximum rate of change of Reactive Power;
(v) largest step change of Active Power; and
(vi) largest step change of Reactive Power.
A3.1.4.10 If the User System has commutating Power electronic loads, their detail
such as number of pulses, maximum voltage notch, and Harmonic
distortion potential (up to the 50th Harmonic) shall be provided to the TSP.
A3.2.1.1 The following additional information shall be provided for the Generating
Units of each Generating Station:
(i) de-rated Capacity on a monthly basis, if applicable;
(ii) additional capacity obtainable from Generating Units in excess of
Net Declared Capability;
(iii) Minimum Stable Loading ;
(iv) stator armature resistance;
(v) direct axis synchronous, transient, and sub-transient reactances;
(vi) quadrature axis synchronous, transient, and sub-transient
reactances;
(vii) direct-axis transient and sub-transient time constants;
(viii) quadrature axis transient and sub-transient time constants;
(ix) turbine and Generating Unit inertia constant ;
(x) rated field current at rated MW and MVAR output and at rated
terminal voltage; and
(xi) short circuit and open circuit characteristic curves.
A3.2.1.2 The following Excitation System parameters shall be provided for each
Generating Unit:
(i) type (static or rotating);
(ii) make and model;
(iii) DC gain of Excitation loop;
(iv) rating (peak voltage/ peak current);
(v) maximum field voltage;
(vi) minimum field voltage;
(vii) maximum rate of change of field voltage (rising);
(viii) maximum rate of change of field voltage (falling);
(ix) details of Excitation loop described in a diagram form showing
transfer functions of individual elements;
(x) dynamic characteristics of over-Excitation limiter;
(xi) dynamic characteristics of under-Excitation limiter;
(xii) exciter model (in IEEE or PTI’s PSS/E format).
A3.2.2.1 For all HV motors of size 10,000 HP and above, the following for each
such motor:
(i) type;
(ii) MW rating;
(iii) MVA rating;
(iv) Power Factor;
(v) full-load current rating;
(vi) starting method and starting current;
(vii) number of start ups per day;
(viii) torque/speed characteristics for the motor;
(ix) torque/speed characteristics for the relevant load;
(x) inertia constant for the motor and the driven load; and
(xi) dynamic parameters (for synchronous motors).
A3.2.2.2 For each transformer between the Transmission System and the User
System, the following:
(i) MVA rating;
(ii) rated voltage ratio;
(iii) winding arrangement and vector group;
(iv) positive sequence resistance and reactance;
(v) zero sequence reactance;
(vi) tap changer type: on-load or off-load;
(vii) tap changer range and step size; and
(viii) Grounding method: direct, resistance or reactance.
A3.2.2.3 To facilitate the TSP to undertake transient over voltage and insulation
coordination studies, the TSP may require from a User the following data:
(i) Busbar layout, including dimensions and geometry together with
electrical parameters of any associated Current Transformers,
Voltage Transformers, wall bushings, and support insulators;
(ii) physical and electrical parameters of lines, cables, transformers,
reactors and shunt compensator Equipment connected at that
Busbar or by lines or cables to that Busbar.
(iii) specification details of all Apparatus connected directly or by lines
and cables to the Busbar including basic insulation levels;
(iv) characteristics of over voltage Protection at the Busbar and at the
termination of lines and cables connected at the Busbar;
(v) Generating Unit or Station transformer details (whether three or
five limb cores or single phase units) and operating peak flux
density at nominal voltage.
A3.2.2.4 For any User Protection Equipment which can trip or inter-trip or close any
Connection Point circuit breaker or any TSP circuit breaker, the following
data:
(i) full description, including estimated settings, for all relays and
Protection Systems installed or to be installed on the User System;
(ii) a full description of any auto-reclose facility installed or to be
installed on the User System, including type and time delays;
(iii) a full description, including estimated settings, for all relays and
Protection Systems or to be installed on the Generating Unit,
This chapter covers a range of issues relating to the proper operation of the
Grid. The provisions of this chapter are organized in to the following 9
sections:
Section 4.4, System Services, deals with arranging and providing of System
Services essential for the proper functioning of the Grid, specifically the
following:
o Frequency Control;
o Voltage Control;
o System Control;
o Operating Margin; and
o Black Start.
4.2.1.1 This section deals with Demand forecasting for operational purposes, and
lays down the procedures to be followed and data to be supplied by Users to
the TSP to enable the TSP to forecast Demand on the Transmission System
for the period ranging from five (5) years ahead down to real time operation.
4.2.1.2 This section also deals with the provision of data on Demand Control in the
Operational Planning Phase, the Programming Phase, Control Phase, and
the Post Control Phase.
4.2.1.3 The TSP shall be responsible for developing Demand Forecasts for the
Operational Planning Phase after taking into account the Demand Forecasts
supplied by Distribution Entities and Directly-connected Customers.
4.2.1.4 In the Programming Phase and Control Phase, the TSP shall develop its own
Demand Forecasts after taking into account, information to be furnished by
Distribution Entities, Directly-connected Customers, and Generators.
4.2.2 Definitions
4.2.2.1 In this section, a reference to Year 0 shall mean the current calendar year,
Year 1 shall mean the next calendar year, Year 2 shall mean the calendar
year after Year 1, and so forth.
4.2.2.2 A reference to data being supplied on an hourly basis shall refer to it being
supplied for each period of 60 minutes ending on the hour.
4.2.2.3 Reactive Power Demand shall include the series reactive losses of the User
System bus but exclude any network susceptance and any reactive
compensation on that System. The TSP shall obtain the lumped network
susceptance and details of the reactive compensation from the data supplied
by the User as provided in Chapter 3: Planning Code.
4.2.3 Objectives
4.2.4.1 Each User shall supply data to the TSP in relation to that User’s Demand and
Active Energy relating to various operational phases as stated in the relevant
parts of this section. Figure 4.1 highlights timescales involved with each
Phase.
Programming Phase
8 weeks (i) Each Saturday, Distribution Entities and Directly-
ahead of connected Customers provide to the TSP, MW profile,
Schedule on hourly and Connection Point basis, of Demand
Day
Control for the next 8 weeks
(ii) The TSP develops 8-weeks Demand Forecast
Control Phase
Day (i) Distribution Entities and Directly-connected
ahead of Customers provide to the TSP Demand changes, on
Schedule hourly and Connection Point basis.
Day
(ii) The TSP develops day-ahead Demand Forecast
Schedule
Day
Post-Control Phase
Distribution Entities and Directly-connected Customers
Subsequent provide to TSP, on hourly and Connection Point basis,
Day
the actual Demand Control carried out.
Figure 4.1. Description and time flow of various operational planning phases
(i) No later than 31 January each year, the TSP shall notify each User in
writing of the following (for the current year and for each of the
succeeding five (5) calendar years:
(a) the date and time of its expected annual peak Demand at
Annual Maximum Demand Conditions; and
(b) the date and time of its expected annual minimum Demand at
Average Conditions.
(ii) By end of March each year, every User, as further elaborated below,
shall provide to the TSP in writing, the forecast information listed
below for the current year and each of the succeeding five (5)
calendar years:
(a) for each Distribution Entity (summed over all Connection
Points) and for each Directly-connected Customers (at the
Connection Point), the hourly forecast profile of Active Power
Demand for the day of that User’s Maximum Demand and for
the specified day of the annual peak Demand of the TSP, both
at their respective Annual Maximum Demand Conditions;
(b) for each Distribution Entity (summed over all Connection
Points) and for each Directly-connected Customer (at the
Connection Point) the annual Active Energy requirements for
Average Conditions segregated into different usage categories
such as, residential, commercial, Government, industrial,
agriculture, street lighting, hospitals, etc., wherever practicable;
(c) for each Distribution Entity (summed over all Connection
Points) and Directly-connected Customer (at the Connection
Point) the hourly forecast profile of Active Demand for the
specified day of the minimum Demand of the TSP at Average
Conditions;
(d) individual Connection Point Demand (Active Power) and
Power Factor at Annual Maximum Demand Conditions for the
annual peak hour at the Connection Point and at the specified
hour of the annual peak of the TSP Demand; and
For 1 to 8 weeks ahead of the Schedule Day, each Distribution Entity and
Directly-connected Customer shall supply to the TSP, in writing, by 10:00
hours each Saturday, hourly MW profiles of the amount and duration of their
proposed use of Demand Control which may result in a Demand change of
five (5) MW or more on an hourly and Connection Point basis.
4.2.5.1 The following factors will be taken into account by the TSP when conducting
Demand Forecasts in the Programming Phase and Control Phase:
(i) historic Demand data including Transmission System losses;
4.3.1 Introduction
4.3.1.1 This section specifies conditions, requirements, and procedures that the TSP
and Users shall follow to match Generation Capacity with Forecast Demand
on the Transmission System over various operational planning horizons in
order to achieve, to the maximum possible degree, the Reliability and
Security standards expected of the TSP.
4.3.1.2 The section mainly concerns with the following:
(i) the planning, coordination, and approval of scheduled and un-
scheduled Outages of the Generating Unit and the Transmission
System; and
(ii) the provision of planning parameters to the TSP by Generators for
operational planning purposes only.
4.3.1.3 The provisions of this section shall apply to all proposed Outages that may
affect the ability of a Generating Unit to achieve its full Registered Capacity
appropriate to each Registered Fuel in accordance with its Registered
Operating Characteristics.
4.3.1.4 This section also mandates the Generators to inform the TSP of any other
proposed maintenance of a Generating Unit or any associated Power Station
Plant or Apparatus, which can affect the availability of System Services from
that Generating Unit.
4.3.1.5 In complying with the various provisions of this section, each Grid Participant
shall act reasonably, in good faith, and in accordance with Good Industry
Practices when planning Outages for its own system and also when
coordinating the scheduling of these Outages with those of the others. This
will be imperative to avoid a situation arising in which a Participant is obliged
to request an Outage during the Outage Planning process as a consequence
of that Participant’s not having planned its Outages in accordance with Good
Industry Practice.
4.3.2 Definitions
In this section, a reference to Year 0 shall mean the current calendar year,
Year 1 shall mean the next calendar year, Year 2 shall mean the calendar
year after Year 1, and so forth.
4.3.3 Objective
4.3.4.1 The Outage planning process in respect of a Generating Unit shall commence
not later than five (5) years prior to the scheduled Operational Date or from
the date of the relevant agreements, whichever is the later. The process shall
culminate in developing of the following three Programs scheduled over the
time scales indicated against each:
(i) Committed Outage Program, covering real time up to end of Year 1;
(ii) Provisional Outage Program, covering Year 2-3; and
(iii) Indicative Outage Program, covering Year 4-5.
The time horizon for planning of Generation Outages is shown in Figure 4.2
below.
Year 4 and Year 5 Year 2 and Year 3 March till end -Year 1
4.3.4.2 In rolling over the Generation Outage Program from one year to the next, for
every year (except, in any such case, to the extent that the Generator is
reasonably responding to changed circumstances), the procedure set out
below is to be followed:
(i) submissions by the Generator for Year 2 should reflect the current
Provisional Outage Program for Year 3; and
(ii) submissions by the Generator for Year 1 should reflect the current
Provisional Outage Program for Year 2.
4.3.4.3 The procedure set out below is to be followed in each calendar year.
(i) Generators shall provide the TSP in writing, for each Generating Unit,
the following details of Planned Outages and estimates of probabilities
of Forced Outages for including in the Committed, Provisional, and
Indicative Outage Programs as defined in (4.3.4.1) above:
(a) identity of the Generating Units concerned;
(b) MW unavailable (and MW that will still be available, if any,
notwithstanding the Outage);
(c) expected duration of the Outage;
(d) preferred start date and start time or range of start dates and
start times;
(e) whether the Outage is a Flexible Planned Outage or an
Inflexible Planned Outage;
(f) if it is a Flexible Planned Outage, the period for which the
Outage could be deferred if requested by the TSP, which shall
be not less than thirty (30) days in length, and the period for
which the Outage could be advanced at the request of the
TSP, which shall be not less than ten (10) days in length.
(ii) In relation to (e) above, the Generator must provide the TSP with such
evidence as the TSP may reasonably require in order to substantiate
the declaration as an Inflexible Planned Outage. If the Generator fails
to establish to the reasonable satisfaction of the TSP that the Outage
is required to be an Inflexible Planned Outage, the Outage shall be
deemed to have been submitted as a Flexible Planned Outage with an
attendant Flexible Planned Outage period of ten (10) days for
advancement and thirty (30) days for deferment.
(iii) The updates to the program for a previously submitted Year when, by
the passage of time, that Year becomes a new Year (for instance,
Year 3 becoming Year 2) may only reflect the Generator's reasonable
response to changed circumstances and changes which, in the
context of the Outage Program, are minimal in their effect on the
operation of the Transmission System, otherwise it must reflect the
Provisional Outage Program for that Year issued previously.
4.3.4.5 Between the end of March and the end of September Year 0
(i) The TSP shall conduct Reliability analysis of the Transmission System
for the operational planning horizon in light of the proposed Outages,
and calculate the weekly peak Generation Capacity required from
Generating Unit/Station for the various planning periods (Year 0, 1, 2,
etc.) by considering the following factors:
(a) Demand Forecasts;
(b) the TSP’s estimate of User Demand Control;
(c) the Operating Margin as set by the TSP;
(d) Transmission System and Distribution System constraints; and
(i) The TSP will, having taken into account the information notified to it
and, having discussed it with Users if appropriate, or settled in
accordance with Regulatory Guidelines, provide each Generator and
Distribution Entity in writing with a final Outage Program showing the
Generating Units that may be potentially withdrawn from service
during each week of Years 0,1,2 3,4, and 5 for a Planned Outage and
showing the Flexible Planned Outage Periods, by way of amendment
to, or confirmation of, the suggested Outage Program submitted by
the Generator.
(ii) The final Outage Program may differ from the suggested Outage
Program as follows:
(a) the Flexible Planned Outages and Inflexible Planned Outages
may have been moved to coordinate all Outage proposals
received by the TSP or for reasons relating to the proper
operation of the Transmission System. When dealing with Year
2 and subsequent Years, the TSP will give priority to including
proposed Inflexible Planned Outages for the dates proposed
by the Generator in the case of newly proposed Inflexible
Planned Outages and for the dates included in the Outage
Program prepared the previous September in the case of
Inflexible Planned Outages which were included in that Outage
Program; and
(b) a Flexible Planned Outage may have been re-designated as
an Inflexible Planned Outage.
(iii) In situations, where the TSP could not otherwise meet its statutory or
regulatory obligations, it may request that a Flexible Planned Outage
or an Inflexible Planned Outage be either excluded from the
Committed or Provisional Outage Program or may be re-scheduled to
make it acceptable.
(i) A Generator may request the TSP at any time during Year 0, by giving
not less than seven (7) days notice before the earliest start date, for a
(v) Any such deferral shall be for so long as the above circumstances
exist, but shall not be beyond the end of the month following the end
of the three months of peak summer Demand.
(vi) In the event that an STPM Outage is scheduled pursuant to (4.3.4.9),
the TSP shall confirm the details within one(1) Business Day after the
details of the STPM Outage have been settled. Such notice shall
contain the following information:
(a) the identity of the Generating Unit(s) concerned;
(b) MW on Outage (and MW which would still be available, if any,
notwithstanding the Outage);
(c) duration of the Outage; and
(d) the start date and start time of the Outage.
(i) In the event that a Generating Unit suffers a Forced Outage, the
Generator shall inform the TSP within ten (10) minutes of the
commencement of the Outage. As soon as possible after the
commencement of the Outage, the Generator shall also inform the
TSP of the cause of the Outage and the Generator's best estimate of
the date and time by which the Generating Unit is likely to be repaired
and restored to its full level of Availability. If the Generator is unable
for any reason to comply with this requirement, the Generator shall not
later than twenty-four (24) hours after the commencement of the
Forced Outage, provide the TSP such information as is then known to
the Generator regarding the date and time of return from such Outage
and shall provide such updates thereafter as the TSP may reasonably
require.
(ii) In such an event, the TSP shall have the right to inspect the
Generating Unit and all relevant records on any Business Day and at
a reasonable time. The Generator shall fully cooperate with the TSP
during any such inspection.
(iii) A Generator shall use all reasonable endeavors to ensure that,
following a Forced Outage, the Generating Unit is repaired and
restored to its full level of Availability as soon as possible and in
accordance with Good Industry Practice.
(i) The Generators may only undertake Planned Outages with the TSP
agreement in accordance with the Outage Program produced
pursuant to the provisions of this section.
(ii) In real time operation, Generating Units must not be withdrawn for a
Planned Outage or a Short Term Planned Maintenance (STPM)
Outage without express formal permission of the TSP for such release
according to the procedures set out below.
(iii) The TSP’s express formal permission shall specify:
(a) the identity of the Generating Unit and MW on Outage (and MW
which would still be Available, if any, notwithstanding the Outage);
(b) the duration of the Outage; and
(c) the start date and start time of the Outage.
(iv) The TSP may withhold its permission for the release of a Generating
Unit for a Planned Outage or a Short Term Planned Maintenance
Outage where such Outage has previously been planned in
accordance with this section’s provisions where, in the TSP’s
reasonable opinion (were such Outage not to be deferred):
(i) For a Planned Outage, not later than seven (7) days before the expiry
of the Flexible Planned Outage period or the Inflexible Planned
Outage period, the Generator must notify the TSP either that its
Generating Unit is returning to service earlier than expected, or at the
time and date expected, or later than expected and if, upon return, it is
expected to be fully available. Where a Generating Unit is not
expected to be fully available upon its return to service, the Generator
shall state the MW level at which the Generating Unit is expected to
be available. In the case of a Generating Unit which is capable of firing
both on gas and on oil, the Availability must be stated for each fuel.
(ii) In the case of a return from a Planned Outage later than expected, the
notice of return to service must be given not later than required above
and shall state the reason for the delay in the return of the Generating
Unit to service and the Generator’s best estimate of the date and time
at which the Generating Unit will return to service.
(iii) In the case of a return from a Planned Outage earlier than expected, a
notice of return to service must be given as far as possible in advance
of return, but in any event not later than required above.
(iv) A Generator must use all reasonable endeavors to ensure that, in
respect of each Planned Outage of the Generator’s Generating Units,
the Outage schedule as included in the Committed Outage Program
(or as moved in accordance with the provisions of this section) is
followed.
(v) Before returning from any Outage other than a Planned Outage, a
Generator must inform the TSP, as far in advance as reasonably
possible that its Generating Unit is returning to service. The Generator
must, in addition, give an Availability Notice in accordance with the
provisions of Chapter 5: Scheduling and Dispatch Code on the day
4.3.5.1 The procedure set out in this subsection shall be followed in each calendar
year for planning of Transmission System Outages (see Figure 4.3 below).
4.3.5.2 The TSP shall plan Transmission System Outages required in Years 2 and 3
as a result of construction or refurbishment works taking due account of the
known requirements. The planning of Transmission System Outages required
By the end of September Year 0, the TSP will draw up a draft Transmission
System Outage Program covering the period Years 2 and 3 for TSP’s internal
use and will notify each User in writing of those aspects of the draft plan
which may operationally affect such User including, in particular, proposed
start dates and end dates of relevant Transmission System Outages. The
TSP will indicate to a Generator where a need may exist to use inter-tripping
or other measures including restrictions on the Scheduling and Dispatch of
Generating Units to allow the Security of the Transmission System to be
maintained within the statutory or regulatory requirements.
The plan produced pursuant to (4.3.5.4) will become the draft Transmission
System Outage Program for Year 1 when, by the passage of time, Year 2
becomes Year 1. Each calendar year, the TSP shall update the draft
Transmission System Outage plan and shall, in addition, take into account
Outages required as a result of maintenance work.
(i) By the end of June Year 0, the TSP will draw up a draft Provisional
Transmission Outage Program and will inform each User of any
potential restrictions which may affect it and generally the impact on
the Transmission System in Year 1.
(iii) Between the end of June and the end of September Year 0, the
TSP will draw up a final Transmission System Outage Plan covering
Year 1.
(iv) By the end of September Year 0, the TSP will issue the final
Transmission System Outage Plan for Year 1. The TSP will notify
each User in writing of those aspects of the plan which may
operationally affect that User including, in particular, proposed start
dates and end dates of relevant Transmission System Outages. The
TSP will also indicate where a need exists to use inter-tripping,
emergency switching, emergency load management, or other
measures including restrictions on the Scheduling and Dispatch of
Generating Units to allow the Security of the Transmission System to
be maintained within allowable limits.
The Transmission System Outage plan for Year 1 issued under section
(4.3.5.5) will become the Committed Outage Program for Year 0 when by the
passage of time Year 1 becomes Year 0.
(i) By 14:00 hours each Wednesday, the TSP shall update the
Transmission System Outage plan for the following one (1) week
period beginning on the Saturday.
(ii) The TSP will notify each User in writing of those aspects of the plan
which may operationally affect such User including in particular
proposed start dates and end dates of relevant Transmission System
Outage. The TSP will also indicate where a need exists to use inter-
tripping, emergency switching, emergency load management, or other
measures including, restrictions on the Dispatch of Generating Units
to allow the Security of the Transmission System to be maintained
within allowable limits.
(iii) During the Programming Phase, the User and the TSP will inform
each other immediately if there is any unavoidable requirement to
depart from the Outage Plan and actions determined and notified
under this subsection.
4.3.6.1 When requested initially under a Power Purchase Agreement and thereafter
by end of December each calendar year, each Generator shall in respect of
each of its Generating Units submit to the TSP in writing the Generator
Performance Chart and the Generation Planning Parameters to be applied
from the beginning of next year onwards, using the schedules provided in
Chapter 6: Data and Information Exchange Code. The Generation Planning
Parameters shall be used by the TSP for Operational Planning purposes only
and not in Scheduling and Dispatch.
4.3.6.2 In the case of a Generating Unit which is capable of firing on two different
fuels, the Generator must submit to the TSP, by separate written notifications,
the Generation Planning Parameters in respect of each fuel, clearly marked to
indicate for which fuel it applies, and also the primary and the standby fuel.
4.3.6.3 The Generator Performance Chart must be on a Generating Unit specific
basis at the Generating Unit terminals and must include details of the
Generator step-up transformer parameters and demonstrate the limitation on
Reactive Power capability of the Transmission System voltage at three (3)%
above nominal.
4.3.6.4 For each Generating Unit whose performance varies significantly with
ambient temperature, the Generator Performance Chart shall show curves for
at least two values of ambient temperature so that the TSP can assess the
variation in performance over all likely ambient temperatures by a process of
linear interpolation or extrapolation. One of these curves shall be for the
ambient temperature at which the Generating Unit output equals its
Registered Capacity.
4.4.1 Introduction
4.4.1.1 This section deals with System Services which are essential to the proper
functioning of the Transmission System, and which also determine the Quality
of supply. This section specifically deals with the following System Services:
(i) Frequency Control;
(ii) Voltage Control;
(iii) System Control;
(iv) Operating Margin; and
4.4.2 Objectives
4.4.3.1 The TSP will achieve Frequency Control through Primary Frequency Control
and Secondary Frequency Control, as set out below:
(i) Primary Frequency Control takes place in the period of up to thirty (30)
seconds after a change in frequency and is achieved by automatic
corrective measures to frequency deviations occurring on the
Transmission System. Automatic Primary Frequency Control Actions
in response to normal frequency fluctuations, within the levels
specified in (2.4.2) on the Transmission System are also commonly
termed as "Frequency Regulation".
(ii) frequency deviations, outside the levels specified in (2.4.2) such as
those that may occur on the loss of one or more Generating Unit(s), or
other MW input into the Transmission System or the Distribution
System are corrected through the use of Operating Reserve.
4.4.4.2 The TSP shall strive to maintain sufficient availability of dynamic and static
Reactive Power capability in order to maintain Transmission System voltages
at Connection Points within the levels specified in (2.4.3) of Chapter 2:
Connection Code, at all times by means of one or more of the following
measures:
(i) the charging capacitance of the Transmission System;
(ii) User Mvar Demand;
(iii) Transmission System Mvar losses;
(iv) Generating Unit Mvar production or absorption;
(v) through on-load tap changing of Generating Unit step-up transformer;
(vi) Voltage Control facilities, such as capacitor banks and reactors; and
(vii) dynamic voltage support.
The TSP shall control System voltage to minimize system losses and cost of
System Services. The TSP shall determine and modify, as appropriate,
general procedures for use in controlling voltage on the Transmission
System. These procedures shall be formulated with due regard to minimizing
cost of the Transmission System operation and optimizing System Safety and
Reliability. In particular, the Voltage Control shall take cognizance of the daily,
weekly and seasonal factors, and the TSP shall determine:
(i) suitable target voltages in order to limit/control the effect of
Transmission capacitance;
(ii) best utilization of dedicated Voltage Control facilities; and
(iii) Mvar dynamic reserve requirements.
(vii) Other facilities which shall be utilized by the TSP, where appropriate,
in order to exercise Voltage Control shall include one or more of the
following:
(a) switching in or out of dedicated Voltage Control facilities, such
as capacitor banks and reactors;
(b) tap-changing on (E)HV Transmission System transformers;
and/or
(c) switching out of Transmission (E)HV cables (and occasionally
Transmission lines) in order to reduce the capacitive
contribution of the Transmission System.
(viii) The TSP may, occasionally, reschedule Generating Units away from
their Nominations in order to achieve Transmission System voltages
at Connection Points within the levels specified in (2.4.3). However,
the TSP will resort to such rescheduling only to deal with emergencies
or contingencies that threaten the Stability and Security of the
Transmission System.
network switching and Control Actions which may, from time to time, affect
the operations of Users or Security of supply to Users.
4.4.5.2 Operational network switching may be required by the TSP for a number of
purposes including the following:
(i) Outages of Transmission Plant and/or Apparatus for the purposes of
maintenance, new works, Operational Tests, Protection Testing, and
work by Users;
(ii) Outages of Transmission Plant and/or due to suspected or potential
Faults and Emergency repairs;
(iii) Voltage Control; or
(iv) limiting Power flows on the Transmission System to levels consistent
with the capabilities of the Transmission Plant and System Security.
4.4.5.3 System switching may also occur automatically and without advance warning
due to operation of Protection schemes in isolating or clearing of Faults on
Transmission Plant or on User Plant which is connected to the Transmission
System.
4.4.5.4 Automatic switching sequences may also be established to limit Power flows
or voltage or frequency deviations in the event of Faults elsewhere on the
Transmission System.
(i) The TSP will only inform the User of a Control Action on the
Transmission System if the Control Action has (or expected to have)
a Material Effect for the User.
(ii) Where the TSP is unable to inform the Users prior to the Control
Actions, then the provisions of (4.4.5.6) shall apply.
(iii) Where it is identified and agreed, in accordance with the terms of the
Connection Agreements and/or operating agreements, between the
TSP and a User that a specific Control Action (usually an action
affecting the Transmission System configuration) has an Operational
Effect on a User and that there is merit in notifying the User in
advance of the Control Action, then the TSP will notify the User of the
Control Action (if planned and where time permits), in accordance with
any standing agreement with the User.
(iv) Typical examples of actions notified in accordance with (iii) above may
include:
(i) The TSP may have to De-energize a User's Plant and Apparatus from
time to time if, and to the extent, that the TSP reasonably considers it
necessary in order to provide for safe and secure operation of the
Transmission System in circumstances which otherwise cause or
likely to cause one or more of the following:
(a) risk to the Safety of personnel;
(b) risk to the Stability of the Transmission System;
(c) risk to the Transmission System or any User's Plant and/or
Apparatus;
(d) Transmission System elements to become loaded beyond their
emergency limits;
4.4.6.1 In order to deal with Demand Forecast uncertainties and to safeguard against
a sudden loss of Generation from the Transmission System, it is imperative
that a suitable Operating Margin be maintained through the Control Phase.
Operating Margin is required to have Capacity available in the System that
can be utilized for reliable and secure balancing of supply and Demand.
4.4.6.2 Operating Margin is the additional output from Generating Plants or Demand
Control which is realizable in real time to aid in containing and correcting any
System frequency falling to an acceptable level due to loss of Generation or a
mismatch between supply and Demand.
4.4.6.3 The Operating Margin consists of Operating Reserve (further divided into 3
categories, Primary, Secondary, and Tertiary Operating Reserve) and
Contingency Reserve as further elaborated in the following paragraphs.
Operating Reserve
(i) The TSP shall determine the amount of Primary Operating Reserve,
Secondary Operating Reserve, and Tertiary Operating Reserve to be
carried at any time to ensure system Security. Due consideration will
be given to relevant factors, including but not limited to the following:
(a) the relevant TSP operating policy in existence at that time;
(b) the extent to which User Disconnections allowed under the
relevant standard have already occurred within the then
relevant period;
(c) the elapsed time since the last User Disconnection Incident;
(d) particular events of national or widespread significance, which
may justify provision of additional Operating Reserve;
(e) the cost of providing Operating Reserve at any point in time;
(f) the magnitude and number of the largest Generation infeeds to
the Transmission System at that time, including infeeds over
external interconnections and also over single Transmission
feeders within the Transmission System;
(g) ambient weather conditions, insofar as they may affect (directly
or indirectly) Generating Unit and/or Transmission System
Reliability; and
(h) the predicted frequency drop on the loss of the largest infeed
as may be determined through simulation using a dynamic
model of the Power System.
(ii) The TSP shall keep records of significant alterations to the Operating
Margin policy as and when such alterations occur.
(iii) The TSP shall, in accordance with Good Industry Practice, Dispatch
Generation and otherwise operate the Transmission System in
compliance with the TSP's determinations as to the Operating Margin
Policy made from time to time.
(iv) The TSP's sole responsibility, having met its obligations under the
preceding provisions of this subsection, shall be to, acting in
accordance with Good Industry Practice, Dispatch such Generating
Units as are required to meet:
(a) System Demand; and
(b) the level of Operating Reserve required by the TSP's then
Operating Margin policy.
Contingency Reserve
(v) The TSP shall determine the amount of Contingency Reserve required
for each time scale up to 24 hours ahead, taking due consideration of
relevant factors including but not limited to the following:
(a) historical Availability and Reliability performance of individual
Generating Units;
(b) notified risk to the Reliability of individual Generating Units;
and
(c) Demand Forecast uncertainties.
4.4.7.3 The Generating Units agreeing to provide Black Start capability must provide
frequency and voltage within the prescribed limits during line Energization
and remote load pick up.
4.4.7.4 The TSP shall verify the actual performance of Black Start capability in the
event actual system Blackout conditions occur.
4.4.7.5 Generators providing Black Start capability will also be required to provide
voice and communication facilities linked with the TSP and capable of
operating without an external AC Power supply for the period as specified by
the TSP in the relevant agreement.
(iii) The Generator shall report to the TSP all the required operational
procedures to operate the Black Start Unit.
4.5.1 Introduction
This section specifies the procedure and terms and conditions of Operational
Liaison between the TSP and the Users of the Transmission System to
ensure that the emergencies do not jeopardize the operation of the
Transmission System or the health of Plant and Equipment.
4.5.2 Objectives
4.5.3.1 The TSP shall notify an Operation, Event, and/or Significant Incident on the
Transmission System which may have an Operational Effect on the System of
any other Users.
4.5.3.2 A User shall notify an Operation, Event, and/or Significant Incident on the
System of that User which may have an Operational Effect on the
Transmission System. On notification by the relevant User, the TSP will notify
any other User(s) on whose System(s) the Operation, Event, or Significant
Incident will (or, in the TSP’s opinion, may) have an Operational Effect.
Where a User notifies the TSP pursuant to this section of an Event which the
TSP considers has had or may have had a significant effect on the
Transmission System, the TSP will require the User to report that Event in
writing in accordance with the provisions of this section. Such Event will be
termed a "Significant Incident" and may include the following:
(i) voltage outside operational limits;
(ii) System frequency outside statutory limits;
(iii) Load Disconnection;
(iv) islanding conditions; and
(v) System instability.
4.5.5.1 An Amber Alert, further defined in (4.7.4), will be issued by the TSP
(subsequently to be confirmed in writing) to Users who may be affected
when the TSP realizes that there is a risk of widespread and serious
disturbance to the whole, or a part of, the Transmission System.
4.5.5.2 The Amber Alert will contain such information as the TSP deems
appropriate.
4.5.5.3 For the duration of an Amber Alert, each User receiving the Amber Alert
shall take necessary steps to warn its operational staff and maintain its Plant
and/or Apparatus in the condition in which it is best able to withstand the
anticipated disturbance.
4.5.6.1 A Significant Incident Notice shall be issued by the TSP or a User, as the
case may be, as soon as possible after the occurrence of the Significant
Incident, and shall identify the following, if possible:
4.6.1 Introduction
4.6.2 Objectives
4.6.3.1 The contact location between the TSP and the User for communicating on
matters pertaining to Transmission System operation shall be the TSP
Control Center for the TSP, and the User Control Center for the User.
4.6.3.2 The User is required to establish and maintain a Control Center that shall be
staffed at appropriate levels at all times.
4.6.3.3 The User shall designate a Responsible Engineer at its Control Center who
shall respond to communications from the TSP without undue delay. The
User’s Responsible Engineer should have adequate experience and training,
and must be authorized to perform the following operations on behalf of the
User:
(i) to receive and acknowledge receipt of a given instruction from the
TSP; and
(ii) to accept and execute instructions from the TSP.
4.6.3.4 The User’s contact locations and personnel (including their electronic mailing
addresses, if any) shall be notified by the Users to the TSP prior to
Connection and updated thereafter as appropriate.
4.6.3.5 If the TSP Control Center or the User Control Center is moved to another
location, the TSP shall notify the Users or the relevant User shall notify the
TSP (as the case may be) without delay of the new location and any changes
to the communication facilities necessitated by such a move.
4.6.3.6 The communications (other than relating to the submission of data and
notices) between the TSP and the User shall take place between the TSP
Control Engineer and the relevant User’s Responsible Engineer as provided
in section (1.12) in Chapter 1: General Conditions.
4.6.3.7 Each User shall have one telephone and one facsimile unit on separate lines
reserved for operational purposes only, which must be continuously attended
to and answered without undue delay.
4.6.3.8 The TSP and Users shall keep all Operational Data communicated between
them as confidential.
4.6.4.1 For communication between the TSP and Users, SCADA and other
communication facilities for voice as well as data transmission shall be
provided. These facilities shall be designed, maintained, upgraded, and kept
compatible with the SCADA and Communication facilities of the TSP, in
accordance with the terms and conditions and standards as laid down in the
relevant Connection Agreement.
4.6.4.2 The TSP shall provide (at the cost of the relevant User) the SCADA system
for monitoring real time information and controlling the Equipment at facilities
of respective sides.
4.6.4.3 All Users shall provide a TSP approved voice communication service to
provide both primary and alternate communication link between the TSP and
the operator controlling the User facility.
4.6.4.4 All Users shall provide monitoring and recording instruments at their
respective sides connected to the Transmission System.
4.6.4.5 All communication facilities shall be constructed, operated, and maintained
according to the TSP standards for such facilities, or in their absence, to
relevant standards of the International Telecommunication Union (ITU), IEC,
or their Saudi national equivalents.
4.6.5.1 The TSP shall provide SCADA outstation interface Equipment. The User shall
provide such voltage, current, frequency, Active Power and Reactive Power
measurement outputs and Plant status indications and alarms to the TSP
SCADA outstation interface Equipment as required by the TSP in accordance
with the terms and conditions of the relevant Connection Agreement.
4.6.5.2 Active Power and Reactive Power measurements, circuit breaker and
Disconnector status indications from Generating Units must each be provided
to the TSP on an individual Generating Unit basis.
4.6.5.3 The manner in which information is required to be presented to the outstation
Equipment shall be set out in the relevant Connection Agreement.
4.6.5.4 The TSP shall provide Data Acquisition Systems, Disturbance Recorders,
and/or Event Loggers (as the case may be) for recording the performance of
the Transmission System.
4.6.5.5 Monitoring Equipment shall be provided on the Transmission System by the
TSP to monitor the System dynamic performance.
4.6.6.1 The SCADA system should be capable of exchanging the System status and
data from the TSP to the User, and vice versa.
4.6.6.2 Participants shall interface via the standard digital interfaces. Interface
cabinets shall be installed in the Participant’s Plant and Equipment room. The
provision and maintenance of the wiring and signaling from the Participant’s
Plant and Equipment to the interface cabinets shall be the responsibility of the
Participant.
4.6.6.3 The information exchange shall support data acquisition from remote terminal
units (RTUs). The TSP should be able to monitor the system status and data
via telemetry from the RTUs connected to the Users’ Plant.
4.6.6.4 The TSP shall have the capability to deactivate and reactivate the scanning of
a given RTU, as well as the capability of monitoring the availability of all RTUs
from a central location.
4.6.6.5 All communication facilities (including SCADA) shall be secured against
unauthorized access. The TSP shall agree with the User, the procedures
governing security and access to the User’s SCADA, computer, and
communication facilities. The procedures shall allow access to the Equipment
and information by the TSP or its nominated representative(s) for the
purposes of maintenance, repair, testing, and reading of meters.
4.7.1 Introduction
4.7.1.1 In Emergency situations, the Security of the Transmission System can come
under abnormal stresses and the electricity supply systems can suffer Partial
or Total Shutdown. To deal with such eventualities, and to ensure that the
System gets back to its normal state as quickly and safely as practicable, the
instructions and procedure established in this section shall be followed by the
TSP and Users.
4.7.1.2 The TSP shall include Generators providing Black Start capability in
conducting System-wide training and drills, as considered necessary by the
TSP to re-Energize the Transmission System following a Partial or Total
System Shutdown.
4.7.1.3 Any emergency drills conducted by either the TSP or the User shall be
coordinated between the TSP and the relevant User, and also with any other
Affected User(s).
4.7.2 Objective
4.7.3.1 Emergency Plans shall allow for quick and orderly recovery from a Partial or
Total Shutdown, with minimum impacts on the Users.
4.7.3.2 All Contingency and/or Emergency Plans shall be periodically verified by
actual tests to the greatest practical extent. When such tests can cause
undue risk or undue cost to a User, the TSP shall take such risks or costs into
consideration when deciding whether to conduct the tests or not. Tests shall
be carried out at a time that is least disruptive to the Participants. The costs of
these tests shall be borne by the respective asset owner(s). The TSP shall
ensure the coordination of the tests in consultation with all Affected Users.
4.7.3.3 Users shall comply with the TSP’s requirements for Contingency and
Emergency Plans.
4.7.3.4 The TSP shall set the requirements for Automatic and Manual Load Dropping
after consulting and agreeing on the schedules with the Users. The Users
shall make available options and schemes to comply with these requirements.
4.7.3.5 The TSP shall be responsible for determining all operational limits on the
Transmission System, updating these periodically, and making these
available to the User.
4.7.3.6 The TSP shall conduct necessary system studies regularly to determine the
effect that various component failures would have on the Reliability of the
Transmission System. At the request of the TSP, Distribution Entities shall
also perform requisite system studies on their part(s) of the network and
make the results available to the TSP.
4.7.3.7 Following Emergency operations as may be necessary to protect the integrity
of the Transmission System or the Safety of Equipment and human life, the
Participants shall work diligently towards removing the cause of the
Emergency and the supply shall be restored immediately after the Emergency
Conditions have passed.
4.7.3.8 Emergency drills shall be conducted at least once a year to familiarize all staff
responsible for Emergency and System Restoration activities with the
Emergency and System Restoration procedures. The drills shall simulate
realistic emergency situations. A drill evaluation shall be performed and
deficiencies in procedures and responses shall be identified and corrected.
4.7.3.9 The TSP shall develop and maintain Contingency Plans to manage system
contingencies and emergencies that are relevant to the performance of the
Transmission System. Such Contingency Plans shall be developed in
consultation with all Users involved in the Transmission System, shall be
consistent with internationally accepted practices, and shall include but shall
not be limited to the following:
(i) under frequency load shedding;
(ii) under voltage load shedding;
(iii) disasters management (natural disasters, or other unexpected
events), including the necessary minimum load requirements;
(iv) Forced Outages at all Connection Points, and
(v) supply restoration.
the hourly schedule before 10:00 hours of the current day. The notification
shall contain the following information:
(i) The proposed (in the case of prior notification) and actual (in the case
of subsequent notification) date, time, and duration of implementation
of the Demand Disconnection; and
(ii) The magnitude of the proposed reduction by the use of Demand
Disconnection.
4.7.4.11 If the Demand Control involves the Disconnection of an industrial load,
Voluntary Load Curtailment or any similar scheme shall be implemented by
staggering the Curtailment wherein the Customers are divided into different
Curtailment Groups (e.g. Saturday Group, Sunday Group, etc.). Users
participating in the Voluntary Load Curtailment shall voluntarily reduce their
respective loads for a certain period of time depending on the extent of the
Generation deficiency. Industrial Users who implement a Voluntary Load
Curtailment shall provide the TSP with the amount of the Demand reduction
actually achieved.
4.7.4.12 The User shall provide the TSP with the amount of Demand reduction
actually achieved by the use of the Demand Disconnection.
4.7.5.1 To ensure that in the event of a Partial or Total Shutdown of the Transmission
System, normal supply is restored to all Users as quickly and as safely as
practicable, it is necessary to provide in the Grid Code a mechanism on how
such Partial or Total Shutdown of the Transmission System is to be dealt
with, and to ensure that the necessary procedures and facilities are in place
to support rapid re-establishing of the Shutdown parts, and to restore Supply
to Users.
4.7.5.2 The Objectives of System Restoration are the following:
(i) to provide a general System Restoration strategy which will be
adopted by the TSP in the event of a Partial or Total Shutdown of the
Transmission System;
(ii) to establish the responsibility of the TSP to produce and maintain a
comprehensive System Restoration Plan, covering both Partial and
Total Shutdowns;
(iii) to establish the responsibility of Users to co-operate with the TSP in
the development and execution of the System Restoration Plan; and
(iv) to ensure that the TSP and User staff who will be potentially involved
with the System Restoration Plan, should be adequately trained and
fully familiar with the relevant details of the Plan.
4.7.5.3 During restoration process of the Transmission System, the normal standards
of voltage and frequency shall not apply.
4.7.5.4 The TSP shall conduct drills, at least once each year, to train the Users for
Emergency preparedness. The date and time of execution of such drills shall
be agreed by the TSP with Users in advance and the TSP shall issue a Blue
Alert for such a drill. The Users must cooperate with the TSP for conducting
such drills/testing.
(i) The TSP shall issue instructions for the Generators with Black Start
Capability to initiate the Start-up. The Generator providing Black Start
shall then inform the TSP that its Generating Unit is dispatchable
within thirty (30) minutes.
(ii) Upon receipt of the instruction from the TSP, Generating Unit
providing Black Start shall Start-up immediately to Energize a part of
the System and/or Synchronize with the System.
(iii) The overall strategy in restoring of the System after a Partial or Total
Shutdown shall, in general, include the following:
(a) overlapping phases of restoration of islanded parts of the
System;
(b) step-by-step integration of the islanded parts of the System
into larger sections; and
(c) eventual restoration of the whole System.
(iv) The TSP shall coordinate the providing of Backup Reserve by thermal
Generating Units so that these can be put back to the Grid without
going to the full restart procedure.
(v) The TSP shall inform the Users, after completing the System
Restoration procedure and the restoration of the System, that the
Blackout no longer exists and that the System is back to the normal
state.
(vi) The TSP will coordinate with Generators to provide start up Power
(not reserve) to steam Units/Plants as the first priority.
(i) When parts of the System are not Synchronized with each other, the
TSP shall instruct Users to regulate Generation and/or Demand to re-
Synchronize the islanded parts of the System.
(ii) If a part of the System is not connected to the rest of the System, but
there is no Blackout in that part, the TSP shall undertake the re-
Synchronization/reconnection of that part to the rest of the System.
4.8.1 Introduction
4.8.2 Objective
(iii) a proposed Test Procedure specifying the switching sequence and the
timing of the switching sequence.
4.8.3.2 The Test Proponent shall provide sufficient time for the TSP to plan the
proposed test. The TSP shall determine the time required for each type of the
test and the associated costs that shall be borne by the User requesting the
test(s).
4.8.3.3 The TSP may require additional information before approving the proposed
test if the information contained in the Test Request is insufficient or the
proposed Test Procedure cannot ensure the Safety of personnel or the
Security of the Grid.
4.8.3.4 The TSP shall determine and notify other Users, other than the Test
Proponent, that may be affected by the proposed Operational Test.
4.8.3.5 The TSP may also initiate an Operational Test if it determines that this test is
necessary to ensure the Safety, Stability, Security, and Reliability of the
Transmission System.
4.8.4.1 Within one (1) month after the acceptance of a Test Request, the TSP shall
notify the Test Proponent, and the Affected Users of the proposed test. The
notice shall contain the following:
(i) the purpose and nature of the proposed test, the extent and condition
of the Equipment involved, the identity of the Test Proponent, and the
Affected Users;
(ii) an invitation to nominate representative(s) for the Test Group to be
established to coordinate the proposed test; and
(iii) if the test involves work or testing on (E)HV Equipment, the
responsible person(s) for Safety Assurance shall be informed and the
Safety procedures specified in section 4.10: Cross-boundary Safety
Assurance shall be followed.
4.8.4.2 The Test Proponent and the Affected Users shall nominate their
representative(s) to the Test Group within one (1) month after receiving the
notice from the TSP.
4.8.4.3 If an Affected User fails to nominate its representative within the period
stipulated in (4.8.4.2), the TSP will issue a reminder to that User asking the
User to nominate his representative to the Test Group within one (1) week’s
time. If the User still does not nominate its representative, The TSP may
decide to proceed with the proposed test and may appoint another TSP
person to the Test Group to represent the interests of that User.
4.8.4.4 The TSP shall establish a Test Group and appoint a Test Coordinator, who
shall act as chairman of the Test Group. The Test Coordinator may come
from the TSP or the Test Proponent.
4.8.4.5 The members of the Test Group shall meet within one (1) month after the
Test Group is established. The Test Coordinator shall convene the Test
Group as often as necessary.
4.8.4.6 The agenda for the meeting of the Test Group shall include the following:
(i) the details of the purpose and nature of the proposed Test and other
matters included in the Test Request;
(ii) evaluation of the Test Procedure as submitted by the Test Proponent
and making necessary modifications to come up with the final Test
Procedure;
(iii) the possibility of scheduling the proposed test simultaneously with any
other test(s) and with Equipment maintenance which may arise
pursuant to the Maintenance Program requirements of the TSP or the
Users; and
(iv) the economic, operational, and risk implications of the proposed test
on the Transmission System, and the Scheduling and Dispatch of the
Generating Unit/Station.
4.8.4.7 The Test Proponent and the Affected Users (including those which are not
represented in the Test Group) shall provide the Test Group, upon request,
with such details as the Test Group reasonably requires for carrying out the
proposed Operational Test.
4.8.5.1 Within two (2) months after the first meeting and at least one (1) month prior
to the date of the proposed Operational Test, the Test Group shall submit to
the TSP, the Test Proponent, and the Affected Users a proposed Test
Program which shall contain the following:
(i) a plan for carrying out the test;
(ii) the procedure to be followed for the test, including the manner in
which the test is to be monitored;
4.8.6.1 Within one (1) month or a shorter period as the Test Group may agree after
the conclusion of the test, the Test Proponent shall prepare and submit a Test
Report to the TSP, the Affected Users, and the members of the Test Group.
4.8.6.2 After the submission of the Test Report, the Test Group shall stand dissolved.
4.9.1 Introduction
4.9.1.1 In order to discharge its responsibilities for safe, secure, and economic
operation of the Transmission System, the TSP will need to carry out certain
testing to monitor, investigate, and verify the performance of Users’ Plant.
4.9.1.2 The TSP shall treat all information and data collected from User pursuant to
the provisions of this section as confidential.
4.9.2 Objective
The primary objective is to establish a procedure for verifying that the Users
are operating within their design, operating and other contractual
requirements, as specified in the relevant Connection Agreement between the
User and the TSP.
4.9.3 Monitoring
4.9.3.1 Monitoring shall be either continuous or continuous for periods of time, and
shall be done by monitoring, data recording, and analysis, or by such other
methods as the TSP reasonably determines to be appropriate in the
circumstances. Advance notification from the TSP to Users may not be
necessary in every case.
4.9.3.2 Where a data recording and analysis system is used for monitoring, the TSP
shall inform the User that such data recording and analysis system is being
used and, on request from the User, shall make available to the User
reasonable information in respect of the data recording and analysis system.
4.9.3.3 Monitoring may be carried out at any time by the TSP and may result, without
the application of further testing, in the evaluation by the TSP of Users’
noncompliance.
4.9.3.4 Where the User disputes a finding of non-compliance, the TSP shall provide
the User any data collected during the monitoring over the period of alleged
non-compliance and such other documentation as may be reasonably
necessary to prove evidence of non-compliance.
4.9.3.5 Performance parameters that the TSP shall monitor may include, but not
limited to, the following:
(i) compliance with Dispatch Instructions; and
4.9.4 Investigation
4.9.4.1 The TSP may, if it suspects noncompliance by the User, carry out
investigation to acquire or verify information relevant to User's Plant and/or
Apparatus design, operation, or other contractual requirements under the Grid
Code, or the Connection Agreement.
4.9.4.2 Investigation by the TSP usually applies to information not collected on a
regular basis by means of monitoring and testing. The TSP may, having given
reasonable notice, send a representative or subcontractor to a User’s Site to
investigate any Equipment or operational procedure on or applicable to the
User Site insofar as the condition of that Equipment or operational procedure
is relevant to compliance with the Grid Code, Connection Agreement, and/or
any other agreement(s) between the User and the TSP.
4.9.5.1 The results of a test to verify performance may be derived from the monitoring
of performance during the test.
4.9.5.2 The TSP may:
(i) for the purposes of above testing, issue a Dispatch Instruction; and
(ii) induce controlled Power System frequency or voltage conditions or
variations for the purpose of determining that the Generating Unit’s
response is in accordance with its Declared Availability, System
Service capabilities, and/or Operating Characteristics.
4.9.5.3 If the TSP subcontracts testing work on a User's Site, then the User and the
TSP must be in agreement on the selection of a suitable subcontractor.
and other systems to verify the correct functioning of the User Development.
The TSP will witness the Commissioning Tests. After the Commissioning
Tests and their acceptance by the TSP, the User facility is considered ready
for Energization.
4.9.6.2 The following Commissioning Test procedure shall be followed:
(i) All the tests specified in the Connection Agreement shall be carried
out in the presence of designated personnel of the TSP or its
authorized representative(s). All test results must be signed by such
personnel or representative(s). All tests shall be performed in
accordance with the Commissioning Test schedules pre-approved by
the TSP.
(ii) The User shall prepare and submit a Commissioning Test
schedule/plan, specifying the acceptance criteria, for review and
approval of the TSP, at least six (6) months before the schedule date
for these tests.
(iii) The User shall provide test Equipment that has sufficient capacity and
accuracy to properly perform the tests.
(iv) The User shall submit to the TSP the particulars of personnel
assigned for the Commissioning Tests and valid calibration certificates
of all the test Equipment for TSP’s review and approval.
(v) The User shall fill-in any form required by the TSP and submit the
same to the TSP for review and acceptance.
(vi) The TSP shall witness the Commissioning Tests, and verify all test
results recorded in the Site test reports.
(vii) The TSP shall request the User to rectify deficiencies, if any, observed
during the Commissioning Tests.
(viii) The User shall mark-up all the “issued for construction” drawings
indicating the modifications done to wiring etc., during the
Commissioning Tests.
(ix) One set of marked-up drawings shall be kept at the facility or in the
control room for any trouble shooting until the "as-built" drawings are
prepared and turned over by the User to the TSP.
(x) The TSP shall proceed with the routing of Energization certificate on
completion of the Commissioning Tests. The facility will be ready for
Energization once the Energization certificate is duly signed and
Test Requirements
4.9.7.1 Tests shall be conducted, in accordance with the agreed procedure and
standards, to confirm the compliance of Generating Units for the following:
(i) capability of Generating Units to operate within their Registered
Generation Planning Parameters;
(ii) capability of the Generating Units to meet the applicable requirements
of the Grid Code;
(iii) capability to deliver the System Service(s) that the Generator has
agreed to provide; and
(iv) Availability of Generating Units in accordance with their capability
Declaration.
4.9.7.2 All tests shall be recorded and witnessed by the authorized representatives of
the TSP, Generator, and/or User.
4.9.7.3 The Generator shall demonstrate to the TSP the reliability and accuracy of
the test instruments and Equipment to be used in the test.
4.9.7.4 The TSP may at any time issue instructions requiring tests to be carried out
on any Generating Unit. All tests shall be of sufficient duration and shall be
conducted no more than twice a year except when there are reasonable
grounds to justify the necessity for further tests.
4.9.7.5 If a Generating Unit fails the test, the Generator shall correct the deficiency
within an agreed period to attain the relevant registered parameters for that
Generating Unit.
4.9.7.6 Once the Generator achieves the registered parameters of its Generating Unit
that previously had failed the test, it shall immediately notify the TSP. The
TSP shall then require the Generator to conduct a new test in order to verify
that the appropriate parameter has been restored to its Registered value.
4.9.7.7 If a dispute arises relating to the failure of a Generating Unit to pass a given
test, the TSP, the Generator, and/or User shall seek to resolve the dispute
among themselves. Failing to agree, the dispute shall be resolved in
accordance with the Regulatory Guidelines for this purpose.
Tests to be Performed
4.9.7.8 Reactive Power Test shall demonstrate that the Generating Unit meets the
registered Reactive Power capability requirements as specified in Chapter
2: Connection Code. The Generating Unit shall pass the test if the
measured values are within ± five (5) percent of the Capability as
registered with the TSP.
4.9.7.9 Primary Response Test shall demonstrate that the Generating Unit has the
capability to provide Primary Response. The Generating Unit shall pass the
test if the measured response in MW/Hz is within ± five (5) percent of the
required level of response within five (5) seconds.
4.9.7.10 Fast Start Capability Test shall demonstrate that the Generating Unit has
the capability to Start-up, Synchronize with the Grid within ten (10)
minutes, and be loaded up to its offered capability. The Generating Unit
shall pass the test if it meets the Fast Start capability requirements.
4.9.7.11 Black Start Test shall demonstrate that the Generating Plant with Black
Start capability can implement a Black Start procedure. To pass the test,
the Generating Unit shall start on its own, Synchronize with the Grid, and
carry load without the need for external Power supply.
4.9.7.12 Declared Data Capability Test shall demonstrate that the Generating Unit
can be Scheduled and Dispatched in accordance with the Declared Data.
To pass the test, the Unit shall satisfy the ability to achieve the Declared
Data.
4.9.7.13 Dispatch Accuracy Test shall demonstrate that the Generating Unit meets
the relevant Generation Scheduling and Dispatch Parameters. The
Generating Unit shall pass the test if:
(i) in the case of Synchronization, the process is achieved within ± five
(5) minutes of the registered Synchronization time;
(ii) in the case of Synchronizing Generation (if registered as a Generation
Scheduling and Dispatch Parameters), the Synchronizing Generation
achieved is within an error level equivalent to ±2.5% of Net Declared
Capability;
(iii) in the case of meeting Ramp Rates, the actual Ramp Rate is within ±
ten (10)% of the registered Ramp Rate;
(iv) in the case of meeting Load Reduction rates, the actual Load
Reduction rate is within ± ten (10)% of the registered Load Reduction
rate;
(v) in the case of minimum base load Generating Units, variation of + ten
(10) % will be acceptable; and
(vi) in the case of all other Generation Scheduling and Dispatch
Parameters, values are within ± 1.5% of the declared values
4.9.7.14 The TSP may advise the Generators one or more of the following tests
also, if considered necessary by the TSP:
(i) deep voltage transient by short-circuit;
(ii) Generating Unit’s changeover to House Load Operation;
(iii) Generating Unit House Load Operation for one hour;
(iv) step response of Generating Unit voltage;
(v) Power System Stabilizer (PSS); and
(vi) overload Capacity.
4.9.7.15 System Service Acceptability Test shall determine the committed services
in terms of parameter quantity or volume, timeliness, and other
operational requirements. Generators providing System Services shall
conduct the test or define the committed service. However, monitoring by
the TSP of System Service performance in response to System-derived
inputs shall also be carried out.
4.10.1 Introduction
4.10.1.1 At times, the TSP and the Users may need to work on, or in close proximity
to, each other’s Systems. It will be, consequently, imperative that the TSP
and Users operate strictly in accordance with approved Safety Rules and
procedures to ensure Safety of life, network, and Equipment for such
situations.
4.10.1.2 This section, therefore, specifies the rules and procedures to be used by the
TSP and Users for coordinating, establishing, and maintaining of necessary
Safety Precautions when work is to be carried out on, or in close proximity
of, the Transmission System and/or the User System.
4.10.1.3 For the purpose of assurance of Safety relating to (E)HV System and
Apparatus the term "Safety Precautions" means Isolation and/or Grounding.
4.10.2 Objective
The objective is to establish rules and procedures for Safety Assurance for
the TSP and Users to operate in accordance with approved Safety Rules, to
ensure safe working conditions for the personnel working on, or in close
proximity to, the Transmission System Plant and/or Apparatus or those who
may have to work at or use the Equipment at the Connection Point.
The TSP and the Users shall maintain proper Logs (in chronological
sequence) to record all messages relating to Safety. These Logs shall be
retained for at least three (3) years.
4.10.7.1 For each Connection Site, the User shall supply to the TSP a copy of its
Safety Rules relating to its side of the Connection Point.
4.10.7.2 The TSP will supply to each User a copy of its own Safety Rules relating to
the TSP side of the Connection Point at each Connection Site.
4.10.7.3 Prior to Connection, each party must agree to the other’s Safety Rules in
relation to Isolation and Grounding.
4.10.7.4 If the User’s Safety Rules are more stringent relating to Isolation and/or
Grounding than those of the TSP, then the User Safety Rules shall apply.
Otherwise, the TSP Safety Rules shall apply.
4.10.7.5 If, after agreement, a party wishes to incorporate a change in its Safety
Rules relating to Isolation and/or Grounding, it shall inform the other party. If
the change is to make the provisions more stringent, then the other party
merely will note the changes. If the change is to make the provisions less
stringent, then the other party will need to approve the new provisions and
the procedures referred to above shall apply.
4.10.9.1 To carry out work on a System which requires Safety Precautions on (E)HV
Apparatus, the Representative who is identified on the relevant Site
Responsibility Schedule as responsible for the (E)HV Apparatus on which
Safety from the System is to be achieved (the "Requesting Party") shall
(i) When the TSP or a User wishes to carry out work on the System, the
Requesting Party will contact the Implementing Party in order to agree
the location at which the Safety Precautions will be implemented or
applied. The Requesting Party shall specify the proposed location(s)
at which Isolation and/or Grounding are to be established.
(ii) When the Implementing Party is of the opinion that Safety Precautions
are required on the Requesting Party’s System, the Implementing
Party shall inform the Requesting Party.
(iii) When the TSP wishes to carry out work on the Transmission System,
and it is of the opinion that for this to be done safely, Safety
Precautions are required on the System of more than one User, the
provisions of this subsection shall be followed with regard to each
User separately.
(i) The Requesting Party shall inform the Implementing Party of the
(E)HV Apparatus on which Safety from the System is to be achieved
and they will need to agree on the location(s) at which Isolation is to
be established.
(ii) The Implementing Party shall then inform the Requesting Party of the
following:
(a) for each location, the identity (by means of (E)HV Apparatus
name, nomenclature, and numbering or position) of each point
of Isolation;
(b) whether Isolation is to be achieved by an Isolating Device in
the isolating position or by physical separation; and
(c) where an Isolating device is to be used, the isolating position
will be maintained and/or secured by such a method which
must be in accordance with the Local Safety Instructions of the
TSP or that User.
If the Requesting Party and the Implementing Party are unable to agree on
the location of the Isolation and (if requested) Grounding, it shall be at the
closest available points on the infeeds to the (E)HV Apparatus on which
Safety from the System is to be achieved as indicated on the Operation
Diagram.
Once the Location of Isolation and (if requested) Grounding has been
agreed in accordance with the above provisions, the following procedure (as
further detailed in the TSP’s Safety Manual) shall be followed:
(i) the Implementing Party will ensure the implementation of Isolation;
(ii) the Implementing Party will confirm to the Requesting Party that the
Isolation has been established on its System and that Isolation has
been established on the System of any other User;
5.1 Introduction
5.1.1 This chapter specifies the responsibilities and obligations of the TSP and
Users with respect to Scheduling and Dispatch of Generating Units and other
Demand resources. It sets out the procedure for supplying of timely and
accurate information by the Users to the TSP, the TSP’s preparing and
issuing of Generation Schedules, and issuing of Dispatch Instructions.
5.1.2 This chapter is divided into two sections: Generation Scheduling and
Generation Dispatch. Section 5.3, Generation Scheduling, deals with
submitting of Availability Notices and relevant information by Generators and
any modification to them subsequently, if required. The section also describes
the procedure to be followed by the TSP for preparing and issuing of
Generation Schedule to specify which Generating Units may be required for
Dispatch. This section also details the Special Actions that the TSP may
require from users to match supply with Demand and ensure the requisite
Stability and Reliability on the Grid. Section 5.4, Generation Dispatch, deals
with Dispatch of Generating Units and executing of other Special Actions to
minimize cost of Supply procurement while ensuring the availability of
adequate level of Operating Margin and other System Services.
5.2 Objective
The objective of this chapter is to enable the TSP to Schedule and Dispatch
adequate Generation resources to meet electricity Demand at all times at
minimum cost while ensuring the integrity of the System, as well as the
requisite levels of supply Quality and Reliability.
5.3.1.1 The TSP will carry out Scheduling daily to develop a Generation Schedule for
the next following Schedule Day. This process will be phased and iterative to
allow appropriate interactions of the TSP with Generators and other Users to
match Demand with supply on an instant-by-instant basis with the requisite
5.3.3.1 Each Generator shall submit to the TSP, Scheduling and Dispatch
Parameters relating to each of its Generating Units proposed to be included in
the Generation Schedule as per the detail provided in Appendix A5.1.
5.3.3.2 Generators shall, in respect of each Generating Unit which the Generator
shall have declared available, also submit to the TSP the following:
(i) details of any special factors which may have a Material Effect on the
likely output of such Generating Unit;
(ii) any temporary changes, and their possible duration, to the Scheduling
and Dispatch Parameters of such Generating Unit;
(iii) any temporary changes, and their possible duration, to the availability
of System Services from the Generating Unit, if applicable; and
(iv) details of any Generating Unit Commissioning or re-Commissioning
programs.
Each Generator shall nominate its expected supply to the TSP for the next
following Schedule Day by 10:00 hours on the day ahead of the Schedule
Day. The information that the Generator shall supply as part of the
Nomination shall be detailed in the Commercial/Market Code (to be
developed by the TSP).
5.3.6.1 Each day by 15:00 hours, the TSP shall develop, by means of an appropriate
Scheduling program or process, a Generation Schedule for the next following
Schedule Day that will utilize the last valid set of Scheduling and Dispatch
Parameters for the Generating Unit as applicable.
5.3.6.2 The Generation Schedule shall be prepared by the TSP to Schedule such
Generating Units for which the TSP had received Availability Notice to
achieve the following:
(i) minimize the cost of procuring the required Electricity in accordance
with the relevant Power Purchase Agreements to match the Forecast
Demand;
(ii) match at all times (to the extent possible) the Forecast Demand with
an appropriate Operating Margin;
(iii) match minimum electricity Demand levels together with a sufficient
Minimum Demand Regulation; and
(iv) maintain Frequency Control.
In preparing the Generation Schedule, the TSP will consider the following
factors:
(i) Forecast Demand and its geographical distribution;
(ii) Declared MW capabilities of Generators;
(iii) System Services capabilities of Generators;
(iv) Operating Characteristics of Generators;
(v) System Constraints;
(vi) Generation costs of each Generating Unit;
(vii) Generating Unit Outages;
(viii) Voltage Control requirements;
(ix) System Stability factors;
(x) Operating Margin requirements;
(xi) System losses;
(xii) System Frequency Control requirements;
(xiii) any testing to be carried out;
(xiv) operation of Generating Unit to provide a sufficient Minimum Demand
Regulation; and
(xv) any other factors as may be reasonably considered by the TSP to be
of relevance to the Generation Schedule.
5.3.6.4 The Generation Schedule issued to each Generator by the TSP shall contain
the information relating to the Generating Units of that Generator only.
5.3.6.5 The Generation Schedule will be only indicative, and will be intended to
provide a guide to the expected output requirements from Generators and will
not be construed as Dispatch Instructions or orders by itself.
5.3.6.6 The information contained in the Generation Schedule will indicate on an
individual Generating Unit basis the period for which it is Scheduled during
the following Schedule Day.
At any time between 10:00 hours each day and the expiry of the next
following Schedule Day, a Generator may submit to the TSP any revisions to
the submitted data:
(i) If the revised Generation Data is received by the TSP before 15:00
hours on the day prior to the relevant Schedule Day, the TSP shall, if
possible, take into account the revised Availability Notice in preparing
the Generation Schedule.
(ii) If the revised Generation Data is received by the TSP at or after 15:00
hours but before the end of the next following Schedule Day, the TSP
shall, if it re-Schedules the Generating Units, take into account the
revised Availability Notice in that re-Scheduling.
After the completion of the Scheduling Process, but before the issue of the
Generation Schedule, the TSP may consider it necessary to make
adjustments to the output of the Scheduling process. Such adjustments may
be made necessary by the following factors:
(i) changes to Availability and/or Operating Characteristics of Generating
Units notified to the TSP after the commencement of the Scheduling
process;
(ii) changes to TSP Demand Forecast;
(iii) changes to Transmission constraints emerging from the iterative
process of Scheduling and System Security assessment, including:
(a) changes to the numerical values prescribed to existing
constraint groups;
(b) identification of new constraint groups;
(c) changes to Generating Unit requirements within constraint
groups, following reappraisal of Demand Forecast within that
constraint group;
(d) changes to any conditions that would impose increased risk to
the System and would therefore require the TSP to increase
Operating Margin levels. Examples may be:
(1) unpredicted Equipment Outages which place more than
the equivalent of one large Generating Unit at risk to a
Fault;
(2) unpredicted outage of Generating Plant or Equipment
which imposes increased risk to the Generating Station
output;
(3) volatile weather situation giving rise to low confidence
in the Transmission Demand Forecasts;
(4) severe (unpredicted) weather conditions imposing high
risk to the System; and
(5) adjustments necessary to make the output of the
Scheduling process to reflect the allocation of
Operating Margin.
5.3.6.10 The TSP will re-optimize the Schedules when, in its reasonable judgment,
a need arises. As it may be the case that no notice will be given prior to
5.3.7.1 The TSP will issue the Generation Schedule by 15:00 hours each day for the
next following Schedule Day, providing that it gets all the necessary
information by 10:00 hours. However, if during the period in which the
Generation Schedule is being prepared, Incidents on the System (for
example, loss of Generation in a critical part of the System) occur which
require a substantial amendment to the data being used in preparing the
Generation Schedule, the TSP may extend the timescale for issuing of the
Generation Schedule to the extent necessary as a result of such Incidents.
5.3.7.2 The TSP may inform Generating Units before the issue of the Generation
Schedule for the Schedule Day to which the Instruction relates, if the length of
Notice to Synchronize requires the Instruction to be given at that time. When
the length of the time required for Notice to Synchronize is within thirty (30)
minutes of causing the Generating Unit to be unable to meet the indicative
Synchronizing time in the Generation Schedule or a subsequent Dispatch
Instruction, the Generator must inform the TSP without delay.
5.3.9.1 In the period following 10:00 hours each day and in relation to the following
Schedule Day, the TSP will monitor the output data of the Generation
Schedule against Forecast Demand and the Operating Margin to see whether
the anticipated level of the Operating Margin for any period is insufficient.
5.3.9.2 Where this level for any period is anticipated to be insufficient, the TSP will
send a Notification of Inadequate Operating Margin (NIOM) to each
Generator and Distribution Entity. The NIOM will indicate the insufficiency and
the period for which the insufficiency is anticipated.
5.3.9.3 The monitoring will be regular and revised NIOMs may be sent out from time
to time. These will reflect any changes in declared Availability which have
been notified to the TSP, and will reflect any Demand Control which has also
been so notified. They will also reflect generally any changes in the Forecast
Demand and the relevant Operating Margin.
5.4.1.1 Based on the Generation Schedule prepared and issued in accordance with
the provisions of the previous section, the TSP will issue Dispatch Instructions
to Generators and other Users. The Disptach process is shown in Figure 5.2
on page 132.
5.4.1.2 Dispatch Instructions relating to the Schedule Day will normally be issued at
any time during the period beginning immediately after the issue of the
Generation Schedule in respect of that Schedule Day.
5.4.1.3 A Dispatch Instruction may be subsequently cancelled or varied.
5.4.5.1 To ensure that a satisfactory System voltage profile is maintained and that
sufficient Reactive Power reserves are maintained, the TSP may issue
Dispatch Instructions in relation to Reactive Power.
5.4.5.2 Mvar output: Where a Generating Unit is instructed to a specific output, the
Generator must achieve that output within a tolerance of ± two (2) % or ±
one (1) Mvar (or such other figure as may be agreed with the TSP) by:
(i) on load tap changing on the Generating Unit step-up transformer; or
(ii) adjusting the Generating Unit Excitation System.
5.4.5.3 Once this has been achieved, the Generator will not tap change or adjust
the Excitation System without prior consultation with and agreement of the
TSP, on the basis that Mvar output will be allowed to vary with System
conditions.
5.4.5.4 Target voltage levels: Where a Generating Unit is instructed to a specific
target voltage, the Generators must achieve that target within a tolerance of
± one (1) kV (or such other figure as may be agreed with the TSP) by either:
(i) on load tap changing on the Generating Unit step-up transformer; or
(ii) adjusting the Generating Unit Excitation System.
5.4.5.5 Under normal operating conditions, once this target voltage level has been
achieved, the Generators will not tap or adjust terminal voltage again before
consulting with and seeking agreement of the TSP.
5.4.5.6 Maximum Mvar production ("maximum Excitation"): Under certain
conditions, such as low System voltage, an instruction to maximum Mvar
output at instructed MW output ("maximum Excitation") may be given, and a
Generator should take appropriate actions to maximize Mvar output.
5.4.5.7 Maximum Mvar absorption ("minimum Excitation"): Under certain
conditions, such as high System voltage, an instruction to maximum Mvar
absorption at instructed MW output ("minimum Excitation") may be given,
and a Generator should take appropriate actions to maximize Mvar
absorption.
5.4.5.8 The Excitation System, unless otherwise agreed with the TSP, must be
operated only in its constant terminal voltage mode of operation with var
limiters in service, with any constant Reactive Power output control mode or
constant Power Factor output control mode always disabled, unless
expressly agreed otherwise with the TSP. In the event of any change in
System voltage, Generators must not take any action to override automatic
Mvar response which is produced as a result of constant terminal voltage
mode of operation unless instructed otherwise by the TSP or unless
immediate action is necessary to comply with Stability limits.
5.4.8.1 Each Generator at its Generating Unit/Station will without delay notify the
TSP by telephone of any change or loss (temporary or otherwise) to the
operational capability including any changes to the Scheduling and
Dispatch Parameters of each Generating Unit which is Synchronized or has
been instructed to Synchronize within the next three (3) hours.
5.4.8.2 If, for any reason, including a change of Availability or Scheduling and
Dispatch Parameters made by the Generator, the prevailing Dispatch
Instruction in respect of any Generating Unit is no longer within the
applicable Availability or Scheduling and Dispatch Parameters then:
(i) the Generator will use reasonable endeavors to secure that a revised
Dispatch Instruction is issued by the TSP such that the new Dispatch
Instruction is within the now applicable Availability and/or Scheduling
and Dispatch Parameters; and
(ii) if the TSP fails to issue such a new Dispatch Instruction within a
reasonable time then the relevant Generator shall be entitled to
change the operation of such Generating Unit to bring its operation
within the applicable Availability and/or Scheduling and Dispatch
Parameters until the TSP issues a new Dispatch Instruction within the
applicable Availability and/or Scheduling and Dispatch Parameters.
Prior to making such a change in operation, the Generator will use
reasonable endeavors to advise the TSP (by telephone and then
confirming it by fax) of its intended action and the timing of the
intended action.
Each Generator shall operate its Generating Units with automatic voltage
regulator (AVR), var limiters, and Power System Stabilizers (PSS), as
required under their respective Connection Agreement, in service at all
times unless released from this obligation by the TSP.
The format of and the terms to be used by the TSP in issuing instructions
together with their meanings will be provided by the TSP to participating
Users.
131
Chapter 5: Scheduling and Dispatch Code
15:00 hours
10:00 hours 12:00 hours
Generators submit TSP receives Yes
TSP Prepares TSP adjusts/re- TSP issues Gen. TSP revises
Declarations/Nominations these by 10:00 optimizes Generation Schedule by generation
hours? Generation Schedule
to TSP by 10:00 hours Schedule, if required 15:00 hours Schedule, if required
i d
No
TSP contacts relevant
Special Actions by
Generator to get
Generator
Declaration/Nomination
Special Actions by
Distribution Entity/
Directly-connected
Customer
Generator Yes
submits
Declaration/
Nomination by Negative Minimum
No Notice of Inadequate
TSP estimates the
Operating tem
Declaration/
Yes Margin
Nomination
No
Generator submits TSP receives
revised Parameters to these before
TSP, if necessary 15:00 hours?
Figure 5.1 Overview of Generation Scheduling Process
TSP revises Generator
Instructions, if discusses and
132
Chapter 5: Scheduling and Dispatch Code
(i) Generating Unit inflexibility (inflexibility description, start date and time, end
date and time, MW);
(ii) Generating Unit Synchronizing intervals (hot time interval, off-load time
interval);
(iii) Station Generating Unit De-Synchronizing intervals;
(iv) Generating Unit basic data:
(a) Minimum Generation;
(b) Minimum Shutdown time;
(v) Generating Unit duty-cycle limitation;
(vi) Generating Unit minimum on time;
(vii) Generating Unit Synchronizing MW;
(viii) Generating Unit Synchronizing groups;
(ix) Generating Unit run-up rates with MW breakpoints;
(x) Generating Unit run-down rates with MW breakpoints;
(xi) Generating Unit loading rates covering the range from Minimum Generation
to Net Dependable Power Capacity;
(xii) Generating Unit de-loading rates covering the range from Net Dependable
Power Capacity to Minimum Generation.
6.1 Introduction
6.1.1 The proper and timely exchange of data and information between the TSP
and Users is critical for ensuring non-discriminatory access to the
Transmission System and the safe and reliable provision of Transmission
services. This chapter, therefore, sets out the obligations and responsibilities
of the TSP and Users in relation to the supply of data and information to each
other, and also lists the various categories of data and information to be
exchanged between the TSP and the Users.
6.1.2 The data which is specified in different chapters of the Grid Code are collated
here in this chapter. The relevant chapters also specify the procedures and
timings for the supply of the requisite data.
6.1.3 The various chapters of the Grid Code also specify the information that the
TSP will supply to Users. This information is summarized in a single schedule
in this chapter.
6.1.4 The data listed in the various chapters of the Grid Code contain only the
typical range of data which may be required by the TSP. The actual data
required will be advised by the TSP at the time of assessment of the User
application for new, or modification of an existing, Connection.
6.1.5 In the event of any inconsistency between any other chapter of the Grid Code
and the Data and Information Exchange Code, the provisions of that chapter
of the Grid Code shall prevail.
6.2 Objective
6.3.1 The following types of data and information shall be required to be registered
by the User:
(i) Standard Planning Data: Each User shall provide to the TSP the
standard data of the Equipment connected to the Transmission
System for planning purposes. The detail of the required data is
provided in Appendix A3.1 of Chapter 3: Planning Code.
(ii) Detailed Planning Data: Each User shall provide to the TSP the
detailed data for the Equipment connected to the Transmission
System for planning purposes. The detail of the data is provided in
Appendix A3.2 of Chapter 3: Planning Code.
(iii) Operational Data: Each User shall provide to the TSP the operational
parameters of the Equipment connected to the Transmission System
for the safe and reliable operation of the system. The detail of the
required data is provided in Chapter 4: Operating Code.
6.4.1 In accordance with the provisions of the various sections of the Grid Code,
each User shall submit data and information as listed in Schedules 1 to 12 in
Appendix A6.1.
6.4.2 The TSP shall be responsible for data and information storage and archiving.
6.4.3 All the data and information systems must be auditable by the Regulator or an
independent agency designated by the Regulator. The systems must provide
for clear and accessible audit trails on all relevant operational transactions. All
requests that require an audit on a system shall be undertaken with
reasonable notice to the Users.
6.4.4 The TSP shall keep all paper-based information for a period of at least five (5)
years commencing from the date the information was created.
6.4.5 Participants shall ensure reasonable security against unauthorized access,
use, and loss of information (i.e. have a backup strategy) for the systems that
contain the information.
6.4.6 Participants shall store planning information that is kept electronically for at
least five (5) years.
6.4.7 The TSP shall archive operational information, in a historical repository sized
for five (5) years’ data. These data shall include the following:
6.5.1 The data must be submitted to the TSP’s relevant contact as specified in
(1.12) and (1.13) of Chapter 1. The name of the person who is submitting
each Schedule of data must be included.
6.5.2 The data may be submitted via electronic means (if such a data link exists
between the User and the TSP after obtaining prior written consent from the
TSP), or through a computer-readable medium.
6.5.3 The Users must notify the TSP of any changes to data which are already
submitted and registered in accordance with the various provisions of the Grid
Code.
6.5.4 If a User fails to supply data when that User is required to provide that to the
TSP, the TSP will estimate such data if and when, in the view of the TSP, it is
necessary to do so.
6.5.5 If the TSP fails to supply data to a User, the User to whom that data ought to
have been supplied, will estimate such data if and when, in the view of that
User, it is necessary to do so.
6.5.6 Such estimates will, in each case be based upon data supplied previously for
the same Plant or Apparatus or using corresponding data for similar Plant
and/or Apparatus or such other information as the TSP or User, as the case
may be, deems appropriate.
6.5.7 The TSP will advise a User in writing of any estimated data it intends to use
relating directly to that User Plant and/or Apparatus in the event of data not
supplied.
6.5.8 The User will advise the TSP in writing of any estimated data it intends to use
in the event of data not supplied.
6.5.9 Any risk associated with the use of estimated data will be borne by the party
that has failed to provide the required data.
6.5.10 Wherever practicable, Users, while submitting data, should identify the
recognized national or international standard to which their Plant, Equipment,
and/or Apparatus was designed.
(x) Schedule 10: Fault Infeed Data. This shall comprise data related to
short circuit infeed of User Equipment to the Transmission System.
(xi) Schedule 11: User Demand Profiles and Active Energy Data. This
shall comprise data related to Demand profiles.
6.6.2 The following Schedule shall be made available by the TSP to Users:
(i) Schedule 12: Data Supplied by the TSP to all Users. This shall
comprise data supplied by the TSP to Users.
6.6.3 Forms for submitting various schedules are provided in Appendix A6.1 to this
section. Applicability of these schedules to each category of Users is
indicated in the following table:
Schedule Number
Users
1 2 3 4 5 6 7 8 9 10 11 12
Generators 9 9 9 9 9 9 9
Distribution Entities 9 9 9 9 9 9 9
Directly-connected
9 9 9 9 9 9 9
Customers
SCHEDULE FORMS
Page1 of 7
Schedule 1: Page2 of 7
Minimum Stable
DPD MVA
Loading
Stator armature % on
DPD
resistance MVA
Turbine and
MW-s/
Generating Unit inertia DPD
MVA
constants
Impedances
Schedule 1: Page 3 of 7
Schedule 1: Page 4 of 7
Schedule 1: Page 5 of 7
Schedule 1: Page 6 of 7
Rate of loading
following weekend DPD MW/min
Shutdown
Rate of loading
following an overnight DPD MW/min
Shutdown
Block load following
DPD MW
Synchronizing
Rate of Load
Reduction from normal DPD MW/min
rated
Regulating range DPD MW
Load rejection
capability while still
DPD MW
Synchronized and able
to supply load
Schedule 1: Page 7 of 7
Phone: City:
Fax: Email:
Data Time Update
Data Description Unit
Category Covered Time
Provisional Outage Program
Generating Next 5
End of
Generating Unit concerned OD Unit ID years
March
Next 5 End of
Power not available due to Outage OD MW
years March
Next 5 End of
Remaining Active Power of the Plant OD MW
years March
Next 5 End of
Duration of Outage OD Weeks
years March
Start date and time or a range of start Next 5 End of
OD hours
dates and times years March
Flexible/ Next 5 End of
Flexible or Inflexible Planned Outage OD
Inflexible years March
Flexible Planned Outage Period for
Next 5 End of
which the Outage could be deferred OD Days
years March
(not less than 30 days in length)
Flexible Planned Outage period for
Next 5 End of
which the Outage could be advanced OD Days
years March
(not less than 10 days in length)
TSP issues draft Outage Program OD Text End of June
TSP issues final Outage Program OD Text End of Sept
Short Term Planned
Maintenance Outage
OD Generating Year 0
Generating Unit concerned Unit ID
Active Power not available as a result
OD MW Year 0 7 Days
of Outage
before
Remaining Active Power of the Plant OD MW Year 0 Schedule
Day
Phone: City:
Fax: Email:
Phone: City:
Fax: Email:
Phone: City:
Fax: Email:
Data
Data Description Unit
Category
Electrical Diagrams and Drawings of the System
and the Connection Point, indicating the quantities,
ratings, and operating parameters for
Schedule 5: Page2 of 4
Data
Data Description Unit
Category
% on
Positive sequence resistance at max., min. and normal tap SPD
MVA
Basic lightning impulse insulation level SPD kV
Power frequency withstand voltage, required for all (E)HV
SPD kV
transformers
Chopped impulse withstand voltage, required for all
SPD kV
transformers rated 230 kV and above
Switching impulse withstand voltage, required for all
SPD kV
transformers rated 230 kV and above
Switchgears (i.e. circuit breakers, Disconnectors and
isolators) on all circuits directly connected to the
Connection Point including those at Substations of
the User
Schedule 5: Page 3 of 4
Data
Data Description Unit
Category
Schedule 5: Page 4 of 4
Data
Data Description Unit
Category
For each HV motor
Phone: City:
Fax: Email:
Up-
Data Data Year Year Year Year Year Year
Unit date
Description Category 0 1 2 3 4 5
Time
Annual peak
hour User SPD MW
Demand at
Annual
Maximum
SPD PF
Demand
Conditions
User Demand
SPD MW End of
at TSP peak
March
Demand at
Annual MD SPD PF
Conditions
User Demand
at minimum SPD MW
TSP Demand
at Average SPD PF
Conditions
Demand
transfer
capability
data
Phone: City:
Fax: Email:
Page1 of 2
Phone: City:
Fax: Email:
Schedule 8: Page 2 of 2
Phone: City:
Fax: Email:
Phone: City:
Fax: Email:
Symmetrical three-
phase short circuit kA
DPD
current infeed at instant
of Fault
Symmetrical single-
phase short circuit
DPD kA
current infeed at instant
of Fault
Symmetrical three-
phase short circuit
current infeed after sub-
DPD
transient Fault current kA
contribution has
substantially decayed
Zero sequence source
impedance values as
seen from the %on
DPD
Connection Point MVA
consistent with the
maximum infeed above
Positive sequence X/R
DPD
ratio at instance of Fault
Page1 of 2
Phone: City:
Fax: Email:
Data Description
The date and time of annual peak of TSP Demand at Annual Maximum Demand
Conditions
The date and time of annual minimum TSP Demand at Average Conditions
Transmission System data including
Symmetrical three-phase short-circuit current infeed at the instant of Fault from the
Transmission System
Symmetrical three-phase short circuit current from the Transmission System after the sub-
transient Fault current contribution has substantially decayed
Zero sequence source resistance and reactance values at the Connection Point,
consistent with the maximum infeed currents above
Pre-Fault voltage magnitude at which the maximum Fault currents were calculated
Positive sequence X/R ratio at the instant of Fault
Appropriate interconnection transformer data
Name of Safety Representatives
Provisional Outage program showing the Generating Units expected to be
withdrawn from service during each week of Years 2 and 3 for Planned Outages
Draft Outage Program showing the Generating Units expected to be
withdrawn from service during each week of Year 1 for Planned Outages
Maximum and minimum short circuit data relevant to the Connection Site
7.1 Introduction
7.1.1 In order to properly account for the flow of electricity through the
Transmission System, it is imperative that suitable and accurate metering and
recording facilities are provided at all Connection Points on the Grid. This
chapter, therefore, deals with metering and recording requirements for
Participants and clarifies on their obligations relating to such installations. It
also sets the minimum technical, design and operational criteria to be
complied with by Users relating to metering and data collection Equipment
and installations.
7.1.2 The provisions of this chapter are specifically applicable to issues relating to
the following:
(i) supply, installation, and maintenance of Metering Equipment (Main as
well as Check) and their testing and calibration;
(ii) collection, storage, and communication of metering data; and
(iii) competencies and standards of performance of Participants relating to
metering.
7.2 Objective
7.3.1 The TSP shall be responsible for managing and collecting metering
information and shall ensure that all points identified as Metering Points in the
relevant Connection Agreement have proper metering facilities.
7.3.2 The User shall be responsible to provide Meters and the associated
Equipment and facilities at the Connection Point and offer these for installing
and sealing by the TSP along with proofs of certification in respect of Meters
and the CTs and VTs by an accredited laboratory as set out in (7.3.4) below.
7.3.3 The User shall also be responsible to demonstrate that its Metering
Equipment meets all the technical requirements and standards set forth in this
chapter.
7.3.4 Prior to making them available to the TSP for installing and sealing, the Users
shall submit the Meters for certification to an independent laboratory
accredited for such purposes by the Regulator.
7.3.5 The TSP shall ensure that installation, Commissioning, maintenance,
auditing, and testing of Metering Equipment and allied systems are done in
accordance with the standards as specified in the relevant Connection
Agreement.
7.3.6 Notwithstanding (7.3.2 to 7.3.4) above, once installed, all Main Meters shall
be owned and operated by the TSP.
7.3.7 The User shall also provide to the TSP all the information that the TSP will
reasonably require to perform its metering duties properly.
(i) Meters;
(ii) Instrument Transformers;
(iii) Lightning Protection; and
(iv) All other interconnecting electric/telecommunication cables, wires, and
associated devices, etc.
7.5.1 The Metering Point shall be at the Connection Point on the Transmission
System, as specified in the relevant Connection Agreement.
7.5.2 The Actual Metering Point may differ from the Connection Point, if agreed by
the TSP and the User. The accuracy requirements of the Metering Code then
shall apply to the Actual Metering Point.
7.5.3 Where the Actual Metering Point and the Connection Point do not coincide,
then, where necessary, compensation for Power transformer and/or line
losses shall be provided. The compensation may be applied locally within the
Metering Equipment or remotely. In both cases, however, compensation
factors and the justification for them must be recorded.
7.6.1 Energy and Demand metering for both Active and Reactive Power shall be
required at every Metering Point.
7.6.2 The Meters shall have the capability to separately record the flow of Active
and Reactive Power and import and export of Energy at each Connection
Point on the Grid.
7.6.3 The Meters shall have the capability to measure Power flows in all the
quadrants in which such flow is possible.
7.6.4 The Meters shall be configured to record/store peak demand data in quarter-
hourly integration periods.
7.7.1 The TSP shall create, maintain and administer a metering database
containing the following information:
(i) name and unique identifier of the Metering Installation;
(ii) date of installation;
(iii) the date of Commissioning of the installation and Commissioning
documents;
(iv) the connecting parties at the Metering Installation;
(v) date of Energization;
(vi) Fault, repair, and maintenance history for each Metering Installation;
(vii) telephone numbers used to retrieve information from the Metering
Installation;
(viii) type of the Meter at the Metering Installation; and
(ix) calibration certificates for all the Metering Equipment.
7.7.2 Data storage facilities for metering data shall be provided as follows:
(i) a storage capacity of ninety-six (96) periods per day for a minimum of
thirty (30) days for all Demand Values;
(ii) the stored Demand Values shall be integer values of kW or kvar and
have a resolution of at least 0.1% (at full load);
(iii) the accuracy of the Energy values derived from Demand Values shall
be within ±0.1% (at full load) of the amount of Energy measured by
the associated Meter;
(iv) the value of any Energy measured in a Demand Period but not stored
in that Demand Period shall be carried forward to the next Demand
Period;
(v) in the event of a Metering Equipment Power supply failure, the
Metering Equipment shall protect all data stored up to the time of the
failure, and maintain the time accuracy in accordance with (7.11);
(vi) to cater for continuous supply failures, the clock, calendar and all data
shall be supported for a period of fifteen (15) days without an external
supply connected;
(vii) any "read" operation shall not delete or alter any stored metered data;
and
(viii) Upon request by the data collection system, the Metering Equipment
shall provide any portion of the stored data.
7.7.3 The TSP shall be the owner of all the metering data and shall keep these data
for at least five (5) years for audit trail purposes.
7.7.4 The TSP shall maintain in duplicate a continuous log on which shall be
recorded at the end of every billing period the readings of all the Meters and
instruments pertaining to delivery of, and billing for, Demand and Energy
supplied by the TSP or taken by it. Such logs shall also show a brief
statement giving complete facts of Interruption or other unusual Events
affecting the service. The TSP shall deliver one set of the said duplicates
each month to the User, upon request.
7.7.5 User’s metered data shall be considered strictly confidential and shall not be
disclosed to anyone, except to that User or the Regulator.
7.7.6 The TSP shall provide a User direct access to its Meter pulse data, if required
by the User. However, this access will be restricted to Check Meter data only
and will be in the same format that the Main Meter supplies to the TSP Meter
reading process. Any cost incurred by the TSP for this purpose shall be borne
in full by the relevant User.
7.7.7 All the Metering Systems shall have the capability of electronic data transfer.
However, during the transition period, on-Site meter reading and reporting
may be needed.
7.7.8 If on-Site meter reading is necessary, it shall be witnessed by authorized
representatives of all concerned parties.
7.7.9 The TSP shall connect a telecommunications medium to the meter/recorder
that will allow for remote downloading of metering data.
7.8.1 All Metering Equipment shall comply with the provisions set out in this
Metering Code. These provisions may be revised from time to time in
consultation with the Regulator to take account of changing technologies or
the requirements of the industry.
7.8.2 The Metering Equipment shall be accurate within the prescribed limits for
such Metering Equipment referred to in the relevant Connection Agreement or
set out in the Metering Code.
7.8.3 The accuracy of the various items of Metering Equipment shall conform to the
relevant IEC standards (or their equivalent Saudi national standards).
7.8.4 The Meters shall be calibrated by an independent calibrating agency
accredited by the Regulator for this purpose. The User shall provide
calibration certificate with expiry date of calibration.
(i) The Voltage Transformers shall comprise three (3) units for a three-
phase set, each of which complies with IEC Standard 60044-2:
Instrument Transformers — Part 2: Inductive Voltage Transformers (or
its equivalent ANSI/IEEE/Saudi national/TSP standard) for metering,
and shall be of the 0.2 accuracy class. These Voltage Transformers
shall be connected in the configuration as agreed in the relevant
Connection Agreement.
(i) The Current Transformers shall comprise three (3) units for a three-
phase set, each of which complies with the IEC Standard 60044-1:
Instrument Transformers — Part 1: Current Transformers (or its
equivalent ANSI/IEEE/Saudi national/TSP standard) for metering, and
shall be of 0.2 accuracy class. It is preferred that two (2) Current
Transformer cores with corresponding number of secondary coils per
phase be provided between the connection box and the terminal of the
metering element on the Meter so that the Current Transformer
connections for checking Meter pulses can be completely separated
from those provided for the Meters.
(ii) The Current Transformer’s rated secondary current shall be either 1 or
5 amperes. The neutral conductor shall be effectively Grounded at a
single point and shall be connected only to a Main Meter with a
burden that shall not affect the accuracy of measurement.
7.8.7 Meters
(i) Meters shall be of the three-element type independent for each phase,
rated for the required Site, comply with IEC Standard 62052-11:
Electricity Metering Equipment (AC) — General requirements, tests,
and testing conditions or IEC Standard 62053-21: Electricity Metering
Equipment (AC) — Particular requirements (or their equivalent
ANSI/IEEE/Saudi national/TSP standards), for static watt-hour meter
and other types of Meters, and shall be of the accuracy class of 0.2 or
equivalent. The Meters shall measure and locally display at least the
kW, kWh, kvar, kvarh, and cumulative Demand, with additional
features such as time-of-use, maintenance records, Power Quality
monitoring, and pulse output. The pulse output for remote metering
must be for all the major measurement features.
(ii) The Meters may be digital or analogue as per the agreement between
the TSP and the User.
7.9.1 All Meters, CTs and VTs, shall be tested for accuracy at initial
Commissioning. Tests shall also be carried out thereafter at intervals not less
frequently than every twelve (12) months for Main Meters and not less than
six (6) years for CTs and VTs, or as specified in the relevant Connection
Agreement to verify that their operation is within the prescribed limits of error.
7.9.2 Test terminals shall be provided for Main and Check Meters to facilitate on
site tests.
7.9.3 Meters shall be tested in service and should be tested out of service only if
the accuracy is suspected to be not within the limits.
7.9.4 A User may request a test and shall bear the full cost of such testing if the
Meter is found to be not operating within the prescribed limits. Tests will be
organized such that all relevant parties are notified of the tests, and are
invited to witness them, if required. Test results will be made available to the
User involved.
7.9.5 Meters may also be tested by the TSP whenever the TSP notices or suspects
an error in metering.
7.9.6 In carrying out of tests on Main Meters, any interruption to measurement will
be taken account of and appropriately compensated. The testing
measurement will be taken by another Meter and will be appropriately
compensated.
7.9.7 Care shall be taken in carrying out tests to ensure that any Interruption to
measurement is avoided or minimized.
7.9.8 Certified test Equipment and reference standards (traceable to a recognized
national or international standard) shall be used in such tests and if, by
7.10.1 For each Connection, Main and Check Metering shall be provided. Main and
Check Meters shall be from different manufacturers and shall operate from
separate CT and VT windings.
7.10.2 The provisions of this chapter shall apply equally to Main and Check Meters.
7.10.3 CT and VT windings and cables connecting such windings to Main Meters
shall be dedicated for such purposes and such cables and connections shall
be securely sealed.
7.10.4 The Main Meter, Check Meter and additional burdens shall have separately
fused VT supplies.
7.10.5 The loss of voltage to the Meters should give an alarm.
7.11 Timekeeping
7.11.1 All Metering Installation shall record time, based on Saudi Arabian Standard
Time.
7.11.2 The commencement of each Demand Period shall be within ±10 seconds of
the true time.
7.11.3 The duration of each Demand Period shall be accurate to within ± 0.1%
except where time synchronization has occurred in that period.
7.13.1 The Metering Equipment at the Connection Point shall be maintained by the
TSP at the witness of the User. All test results, Maintenance Programs, and
sealing records shall be kept for the life of the Metering Equipment, and for
five (5) years after the retirement of the Equipment. The Equipment data and
test records shall be made available to authorized parties.
7.13.2 The TSP shall repair the Metering System as soon as practical if a Metering
System malfunctions or requires maintenance. The TSP shall charge for the
metering services provided.
7.14.1 The TSP has the responsibility for Meter type approval, Meter certification,
and Meter testing for compliance with the provisions of the Metering Code.
7.14.2 Meter Equipment used in accordance with this Code shall be approved types.
The TSP shall maintain this list and shall make it available to Users on
request.
7.14.3 All Metering Equipment shall be from a manufacturer pre-qualified by the
TSP.
7.14.4 The TSP shall maintain records for all Metering Equipment relating to their
calibration including the dates and results of any tests, readings, and
adjustments.
7.14.5 Such records shall also include any other details as may be required by the
TSP. Such records shall be complete and accurate and retained for the life of
the relevant item.
7.14.6 The TSP shall make arrangements to seal all Metering Equipment, data
collection equipment, and associated modems and telephone links.
7.14.7 All new Metering Equipment shall be required to undergo relevant certification
tests which shall be performed in accordance with the relevant
international/Saudi national standards.
7.14.8 Meter Certificates shall be issued for a specified life span. The Meter
Certificate duration may differ for different Meter types and may change from
time to time.
7.14.9 Following certification, a certification seal will be applied. This seal must be
maintained intact in order for the Meter to retain certified status.
7.14.10 Meters removed from service must be re-certified before reconnection for
use.
7.15.1 The TSP shall make arrangement to remotely read the cumulative energy
values every month for checking purposes.
7.15.2 If cumulative energy values are not available remotely, then the TSP will take
manual readings each month for the above purposes.
7.15.3 Within three (3) weeks of the manual Meter reading, the TSP shall prepare a
Meter Reconciliation Statement in which it will record the difference between
the two successive manual Meter readings and compare it with the total
energy recorded for the same time period.
7.15.4 If any difference between the manual reading and electronically recorded
reading of more that 0.1 percent is noticed, it shall be highlighted and referred
to for further checking.
7.15.5 If as a result of the above check, the discrepancy is confirmed, then the TSP
will inform the relevant User and take appropriate action to deal with the
situation in accordance with the provisions of the Commercial/Market Code
(to be developed by the TSP in due course).
Active Energy The integral of the Active Power with respect to time,
measured in watt hour (Wh) or multiples thereof.
Unless otherwise qualified, the term “Energy” refers
to Active Energy
Adequacy (in relation to The ability of the electric system to supply the
Reliability) aggregate electrical Demand and Energy
requirements of the customers at all times, taking
into account scheduled and reasonably expected
unscheduled Outages of System elements.
Affected User A User who provides evidence to the TSP and in the
opinion of the TSP the evidence proves the User’s
sufficient interest in the matter.
Authority for Access An authority which grants the holder the right to un-
accompanied access to a Site containing (E)HV
conductors.
Black Start Test A Test carried out by a Generator with a Black Start
Unit, on the instructions of the TSP, to demonstrate
that the Unit has the contracted Black Start
capability.
Business Day Any day on which banks are open for business.
Coincident Peak The sum of two or more peaks that occur in the
same demand period.
Committed Outage The Outage Program that the TSP shall prepare for
Program (for Generation the period up to end of Year 1.
Outages)
Committed Outage The Outage Program that the TSP shall prepare for
Program (for the period up to end of Year 0.
Transmission Outages)
Committed Project The data for a User Development once an Offer for a
Planning Data Connection Agreement or an amended Connection
Agreement has been accepted by the User.
Connection Site The site at which the Plant and Apparatus of the
User at the User's side of the Connection Point is to
be installed including the land, spaces, roads and
any surfaces.
Current Transformer (CT) Device that reduces or scales down the actual
system current to proportional values of a few
amperes for use by a Protection System or Meter.
Detailed Planning Data The data that the TSP may require from any User in
support of the Standard Planning Data.
Electric Utility Industry Means all the stakeholders responsible for the
Generation, Transmission, Distribution, and use of
electricity.
Estimated Equipment It shall contain the User’s best estimate of the values
Data of parameters and information pertaining to its
Equipment and Apparatus and which on Connection
become fixed (subject to any subsequent change).
Flexible Planned Outage A Planned Outage which can be, at the request of
the TSP, deferred or advanced by a certain period.
Force Majeure Force Majeure shall mean any act of God, labor
disturbance, act of the public enemy, war,
insurrection, riot, fire, storm or flood, explosion,
breakage or accident to machinery or Equipment,
any order, regulation or restriction imposed by
governmental, military or lawfully established civilian
authorities, or any other cause beyond a party’s
control. A Force Majeure event does not include an
act of negligence or intentional wrongdoing.
Good Industry Practices Any of the practices, methods, and acts engaged in
or approved by a significant portion of the Electric
Utility Industry during the relevant time period which
could have been expected to accomplish the desired
results at a reasonable cost consistent with good
business practices, reliably, safely and with
expedition.
Ground Fault Factor The ratio of the highest RMS phase-to-ground Power
frequency voltage on a sound phase, at a selected
location, during a Fault to Ground affecting one or
more phases, to the RMS phase-to-ground Power
frequency voltage that would be obtained at the
selected location with the Fault removed.
Inflexible Planned A Planned Outage the start date and start time of
Outage which cannot be moved by TSP under Operating
Code.
Load Curtailment The Load Reduction obtained from Users who are
able and willing to curtail their usage of Power.
These loads are to be curtailed within one hour of
the instruction being issued by the TSP.
Minimum Stable Loading The minimum Demand that a Generating Unit can
safely maintain for an indefinite period of time.
Operational Tests Tests carried out by the TSP in order to maintain and
develop operational procedures, to train staff and to
acquire information in respect of Transmission
System behavior under abnormal System conditions,
and also tests carried out by other Users for similar
purposes in respect of their Plant and/or Apparatus.
Power Purchase (Supply) The agreement setting out the parameters and terms
Agreement and condition of purchase (supply) of Power from
(to) any source through legal contract.
Project Planning Data The data that the TSP will require from Users
applying for a new, or modification of an existing,
Connection. Project Planning Data will be further
classified into Preliminary Project Planning Data,
Committed Project Planning Data, or Registered
Project Planning Data.
Reactive Power The product of voltage and current and the sine of
the phase angle between them measured in units of
volt-amperes reactive (var) and multiples thereof.
Registered Project The data submitted by a User to the TSP at the time
Planning Data of Connection of the User System to the Grid.
Schedule Day The period from 0600 hours in the Schedule Day
until 0600 hours on the next following Day.
Speed Governor System A system which will result in Active Power output of a
Generating Unit changing, in response to a change
in System frequency, in a direction which assists in
the recovery to target frequency.
Standard Planning Data The general data required by the TSP from Users as
part of the application for a Connection Agreement or
amended Connection Agreement on a regular basis.
Under Frequency Relay An electrical relay that operates when the System
frequency decreases to a preset value.
User A person or entity that uses the Grid and its related
facilities. Also, a person or entity to which the Grid
Code applies. Includes prospective Users as well.