Etap MCQ: and The Applied Derating Percentage Is %, This
Etap MCQ: and The Applied Derating Percentage Is %, This
1. In (Metric) unit system applications in ETAP Program, the standard value of applied frequency is:
a) 60
b) 100
c) 25
d) None of the above
2. The adjusted operating mode for up – stream utility unit in load flow analysis is:
a) Voltage Control Mode
b) Mvar Control Mode
c) Slack Mode
d) None of the above
3. In ETAP program, the transformer rating is 𝟓𝟎𝟎𝑴𝑽𝑨 and the applied derating percentage is 𝟓%, this
means that the maximum value of MVA of transformer rating should be used in operation is:
a) 500
b) 475
c) 575
d) 525
4. In ETAP program, if the grounding type of transformer primary or secondary winding is changed
from solid type to open type, the load flow results will:
a) Increasingly change
b) Decreasingly change
c) Be the same
d) None of the above
6. In ETAP program, if the 𝑿/𝑹 ratio for up – stream utility unit or transformer increases from the value
of 30 to the value of 50, the load flow results will sharply change:
a) true
b) false
7. In ETAP program, the standard value of Demand factor for spare load is:
a) 1
b) 0.5
c) 0
d) None of the above
8. In ETAP program, the changing of altitude of transformer position over or above its standard value
(𝟏𝟎𝟎𝟎𝒎) affects the operating and loading rated values of this transformer:
a) true
b) false
9. In (English) unit system applications in ETAP Program, the standard value of applied frequency is:
(a) 60
(b) 100
(c) 25
(d) None of the above
10. All the following modes confirms that the up – stream utility unit is out of service operation except:
(a) Removed Mode
(b) Repair – shop Mode
(c) Abandoned state Mode
(d) As – built Mode
11. In ETAP program, the transformer rating is 𝟓𝟎𝟎𝑴𝑽𝑨 and the applied derating percentage is −𝟓%,
this means that the maximum value of MVA of transformer rating should be used in operation is:
(a) 500
(b) 475
(c) 575
(d) 525
12. In ETAP program, if the grounding type of transformer primary or secondary winding is changed
from open type to solid type, the load flow results will:
(a) Be the same
(b) Increasingly change
(c) Decreasingly change
(d) None of the above
14. In ETAP program, if the 𝑿/𝑹 ratio for up – stream utility unit or transformer increases from the value
of 30 to the value of 50, the load flow results will be almost the same:
(a) true
(b) false
15. In ETAP program, the standard value of Demand factor for continous load is:
(a) 1
(b) 0.5
(c) 0
(d) None of the above
16. In ETAP program, the changing of ambient temperature of transformer surrounding position over or
above its standard value (𝟑𝟎° 𝑪) not affects the operating and loading rated values of this transformer:
(a) true
(b) false
17. In ETAP program, the standard value of Demand factor for intermediate load is:
(a) 1
(b) 0.5
(c) 0
(d) None of the above
18. In ETAP program, the changing of altitude of transformer position over or above its standard value
(𝟏𝟎𝟎𝟎𝒎) not affects the operating and loading rated values of this transformer:
(a) true
(b) false
Answers
1. D
2. C
3. B
4. C
5. A
6. B
7. C
8. A
9. A
10. D
11. D
12. A
13. B
14. A
15. A
16. B
17. B
18. B