Unit 03 - Project Management
Unit 03 - Project Management
Unit 3
PERT - Uses
• PERT is useful when activities can be done in parallel
rather than in sequence. The systems analyst can benefit
from PERT by applying it to systems projects on a smaller
scale, especially when team members are working on
certain activities at the same time
16
PERT - Representation
• Circles on the PERT diagram are called
events/nodes and can be identified by numbers,
letters, or any other form
• The Circular Nodes are present to
• recognize that an activity is completed
• indicate which activities need to be completed before a new activity
may be undertaken (precedence)
19
PERT - Precedence
• In reality, activity C may not be started until activity A is
completed
20
PERT - Example
• A project has a beginning, a middle portion and
an end
• the beginning is event 10 and the end is event
50
• In order to find the length of the project, each
path from beginning to end is identified and the
length of each path is calculated
21
PERT - Example
• In this example. path 10-20-40-50 has a length of
15 days, while path 10-30-40-50 has a length of 11
days
Critical Path
• The longest path is referred to as the Critical Path
• The critical path is determined by calculating the longest
path
Crash Time
• Crash Time is absolute minimum time in which an
activity be completed if additional money/resources are
funneled to the activity
24
Crashed Activity
• The activity that cannot be squeezed in terms of time is
called Crashed Activity
Slack Time
• Slack Time = Estimated Time – Crash Time
PERT - Advantages
• Therefore, there are many reasons for using a PERT
diagram Over a Gantt chart
Activity Table
ACTIVITY ID PRE REQUISITE NORMAL DAYS SLACK DAYS COST SLOPE
(Rs.)
A - 5 1 1000
B A 4 1 500
C B 4 2 800
D B 5 2 1000
E B 3 1 500
F C, D 2 0 0
G A, E 8 2 600
H E, F 5 2 400
32
Use MS Visio
to
Design DFDs, Context, Zero, One and next level DFDs of organization
Design Flow Charts of Selected Business Processes
Design Entity Relationship Diagram of Organization
Design Output Screens – Forms
FINAL PROJECT TASKS – UNIT 3
Use MS Project
to
Define Tasks to Complete Project, Number of Days for Each Activity, Assign
Tasks to Group Members, Check for Over Allocated Members
Create Gantt Chart, Network Diagram
GENERAL GUIDELINES