Nsspu-Gp 06-10-1
Nsspu-Gp 06-10-1
Nsspu-Gp 06-10-1
Corrosion Management
NSSPU-GP 06-10-1
Corrosion Management NSSPU-GP-06-10-01
Contents
Paragraph Page
1 Introduction 1
2 Use of Language 2
3 Scope 2
3.1 Topsides Facilities, Onshore Plant and Onshore and
Offshore Pipelines 3
Table
1 STP Conformance Terminology and Approval Levels
for Deviation 2
Figure
1 BP Corrosion Control System 13
2 Corrosion Management – Summary of Main Activities 14
3 Pressure Systems Corrosion Management: Integration of
Activities 16
Contents (cont’d)
1 Introduction
One of the requirements of the Integrity Management (IM) Standard is that a corrosion
management strategy shall be in place for each Performance Unit (PU). In support of
this requirement, the Engineering Technical Practices (ETP) ‘Guidance on Practice for
Corrosion Management’ (GP 06-10) provides high level guidance regarding the
essential elements of corrosion management.
The purpose of this document is to provide more detailed instructions regarding the
minimum requirements for an effective Corrosion Management System (CMS) to be in
place within each PU in the North Sea Strategic Performance Unit (SPU). All PUs in the
North Sea shall comply with the requirements of this document.
Since corrosion management has been in place for many years in the North Sea, lessons
have been learned and these best practices, mainly in the form of Addendums, have
been incorporated into this document so that they are available for all PUs as a means
of sharing and as continuous improvement.
Each PU shall have suitable documentation in place to manage corrosion on topsides
facilities, structures and pipelines. The PU strategy shall include:
An outline of the process for managing corrosion within the PU, including roles and
responsibilities
A summary of the corrosion threats, mitigation measures, online monitoring and
inspection plans – for each topsides system, each pipeline and each structure (this is
the output from the Risk-based Inspection (RBI) process)
A scheme which outlines the strategy for managing each material degradation
(ie corrosion) threat (eg the Corrosion Under Insulation (CUI) threat is managed by
adhering to the Practical Application of Risk-based Inspection (NSSPU-GP-06-10-2),
Addendum 4
The term ‘corrosion’ is used throughout this document. This term is used for ease, in
lieu of the terms material degradation or material deterioration. Corrosion, material
deterioration and material degradation are all terms that have the same meaning.
They cover the following: pitting corrosion, general corrosion, erosion, crevice
corrosion, fatigue cracking and stress corrosion cracking, stress corrosion cracking
and CUI.
Addendum 9 provides a typical example of what should be included in a corrosion
management strategy for each PU/installation.
2 Use of Language
Table 1 details the intended application of conformance words, and the level of approval
required (depending on risk exposure) to deviate. Each PU is required to maintain a
register of deviation from the standard.
All text displayed as italic and coloured blue is termed commentary text and is
supplementary guidance to the requirements of the standard.
3 Scope
This standard shall be applicable to all equipment that is subject to corrosion as a result
of exposure to process or natural environments in the North Sea and associated onshore
plants. Typical equipment is identified within ETP G6-10 and includes:
All topsides facilities, in particular vessels, pipework, tanks and exchangers
(downstream of xmas tree)
Onshore pipework, vessels and tanks
Pipelines and subsea facilities (downstream of xmas tree)
Structures
This standard provides an outline of what is required to be in place in order to manage
corrosion in these areas.
Minimum Requirements
In order to effectively manage corrosion the corrosion threats for each pipework
system, vessel, tank, pipeline and structure shall be identified and qualified.
When the threats have been identified, mitigation measures shall be determined and
implemented along with the most appropriate inspection plan or Written Scheme of
Examination (WSE) for the identified threats.
For topsides pipework and equipment, inspection plans associated with corrosion
management shall be in place to monitor deterioration rates and measure the
effectiveness of corrosion mitigation measures. Mitigation measures include materials
selection, process control, corrosion inhibitor in topsides facilities, regular pipeline
pigging, corrosion inhibition of subsea pipelines and cathodic protection systems on
subsea structures.
Regular performance assessments shall be undertaken to re-evaluate threats, revise
specific mitigation and inspection activities and review overall corrosion management
strategies.
An effective CMS shall, as a minimum, have the following in place:
Definition of the Plant or PU scope covered by the CMS
BP ownership of the Corrosion Management Process and Strategy
A competent team in place involving corrosion and inspection engineers
Roles and responsibilities that are understood
Corrosion Risk Assessments for all process systems, pipelines and structures updated
on a regular basis, so that:
All corrosion threats are identified
Mitigation methods are identified and implemented
Inspection and online monitoring activities are in place in order to measure the
effectiveness of any mitigation and to determine the level of deterioration
caused by each threat
Management schemes outlining how each corrosion threat is to be managed
Performance assessments (reporting and tactical reviews) carried out regularly within
the asset team (4 to 8 week frequency)
Annual Corrosion Management Review overviewing asset condition and forward plan
of recommendations
Strategic reviews carried out on an annual basis – utilising the findings of the Annual
Corrosion Management Review
Corrosion management health checks/external peer reviews carried out at
3-year intervals
4.4.1 Mitigation
Corrosion mitigation is fundamental to an integrated corrosion control programme.
The objective of the corrosion mitigation is to reduce the impact of the identified corrosion
threat to enable life of the asset to be effectively managed.
Mitigation of corrosion shall be achieved by a number of factors which include the
following:
Removal of a corrosive agent (such as removal of oxygen from the Water Injection
System)
Addition of corrosion inhibitor to produced fluids to prevent pipe wall corrosion
Addition of biocide to mitigate microbiological corrosion
Control of pH in closed loop cooling water systems
Material selection or material change
Modification of the process or operating parameters
Corrosion control matrices shall be developed and shall record the following for each
corrosion threat within a process system:
All possible control options
Target control levels
Actions to be taken when there are excursions outwith allowable targets
Clear roles and responsibilities identified to act on excursions
An example of a typical set of corrosion control matrices is provided in Addendum 2.
When starting to look at process system corrosion controls, good practice advice is to
concentrate on getting the most important controls (ie the top five) working efficiently
first rather than trying to look at all corrosion controls at the same time and getting none
of them to work effectively.
The above mitigation measures relate to internal corrosion control. External corrosion
mitigation of topsides pipework is usually by coatings but sometimes also by materials
selection.
External corrosion, either on insulated or uninsulated pipework and vessels, is one of the
most difficult threats to manage in the North Sea SPU. The documents that have been
developed to help manage this threat are:
Design and Prevention of CUI (ETP GP06-25) (which covers mainly the design
aspects for coatings and insulation)
Management of Corrosion Under Insulation (NSSPU-GP-06-10-2, Addendum 4)
(which relates to strategic guidance for inspection for the CUI threat in operation)
Fabric Maintenance Standard and Guidance (UKCS-TI-029)
4.4.2 Monitoring
Corrosion monitoring is fundamental to an integrated corrosion control programme.
The objectives of the corrosion monitoring programme can be summarised in the
following statements:
Corrosion monitoring activities should provide essential information on plant
condition, to enable the plant to be run in a safe and efficient manner
Corrosion monitoring data should be continuously evaluated and reviewed to
ensure the integrity of plant and equipment; thereby helping to avoid unplanned
shutdowns as a result of corrosion
Corrosion monitoring data should be used to progress the inter-relationship between
corrosion parameters and operating variables as they change with time in order to
improve the effectiveness of the corrosion control strategy
There is no single monitoring method to cover all of the above objectives; several
methods are used. Typically, the most common methods used in the North Sea SPU are
weight loss coupons, corrosion probes, visual inspection and non-intrusive instrumented
inspection such as ultrasonic wall thickness determination and radiography.
The analysis and interpretation of the monitoring data collected from on line monitoring,
inspection and process monitoring (as identified in the corrosion control matrices) allows
short and long-term corrosion trends to be established.
The ETP ‘Guidance on Practice for Corrosion Monitoring’ (GP 06-70) provides
guidance for the selection, installation and use of technologies for the monitoring of
internal corrosion within in-service piping and equipment.
4.4.3 Inspection
Inspection is fundamental to an integrated corrosion control programme and is a major
contributor to achieving the objectives as highlighted in Paragraph 4.4.2.
Inspection plans shall be derived as an output from the Process System Risk
Assessment which is covered in the document Practical Application of Risk-based
Inspection (NSSPU-GP-06-10-2).
Inspection scopes and inspection frequencies are dependent on a knowledge of the
corrosion rate and type of corrosion predicted. For example, more coverage may be
required for pipework which has a pitting corrosion threat compared with a pipework
system which has a general corrosion threat.
In addition to the guidance provided for the development and implementation of
inspection plans that are provided in NSSPU-GP-06-10-2, the following ETPs shall also
be consulted with respect to inspection of pipework and equipment:
Guidance on Practice for In-service Inspection and Testing – Common Requirements
(NSSPU-GP-32-40)
Guidance on Practice for In-service Inspection and Testing of Vessels, Tanks and
Exchangers (NSSPU-GP-32-41)
Guidance on Practice for In-service Inspection and Testing of Piping Systems
(NSSPU-GP-32-42)
Guidance on Practice for In-service Inspection and Testing of Pressure Containing
Envelope of Rotating Equipment (NSSPU-GP-32-43)
Guidance on Practice for In-service Inspection and Testing of Above Ground
Atmospheric and Low Pressure Storage Tanks (NSSPU-GP-32-44)
Guidance on Practice for In-service Inspection and Testing of Fired Boilers and
Heaters (NSSPU-GP-32-45)
Guidance on Practice for In-service Inspection and Testing of Onshore Civil/Structural
Facilities (NSSPU-GP-32-46)
Guidance on Practice for In-service Inspection and Testing of Mechanical Protective
Devices (NSSPU-GP-32-47)
Guidance on Practice for In-service Inspection and Testing of Heat Exchangers
(NSSPU-GP-32-48)
Guidance on Practice for In-service Inspection and Testing of Special and Other
Equipment (NSSPU-GP-32-49)
4.4.5 Repairs
All corrosion damage should initially be properly assessed by competent personnel
within the inspection and corrosion service provider, in conjunction with the PU Integrity
Engineer. Any repairs and/or replacements should be carried out within the timeframe
specified by the competent personnel. In order to avoid any overdue repair orders on
critical pipework and equipment, all repair orders should be properly risk ranked
(ie consideration of both probability and consequence of failure).
Weldless Repairs to Piping (UKCS-TI-026) outlines the process for carrying out
temporary repairs to pipework.
Guidance is provided in Figure 3 regarding the persons responsible for data flow for the
main activities within the corrosion management process.
4.5.1 Assessments
Recording and communicating findings from corrosion monitoring programmes is
essential in order to establish effectiveness of the programmes.
As well as routine daily communications, more formal regular updates of findings
and trends should be produced for discussion at the tactical review meetings (refer to
Paragraph 4.5.2).
In addition, on an annual basis, a report which summaries the condition of each process
system shall also be produced and shall be the basis for the strategic review (refer to
Paragraph 4.5.3). Addendum 6 provides an example of what should typically be included
in the Annual Corrosion Management Report.
Meetings shall be minuted and actions resulting from the meeting shall be logged
and tracked.
A typical example of the Annual Corrosion Management Report is included in
Addendum 6. A example of a typical output from the strategic review is included in
Addendum 8.
Addendum 1
Process System Corrosion Management Strategy
Overview – Typical
Addendum 2
Corrosion Control Matrices (Typical Example)
1 Process Systems 1
2 Utility Systems 3
5 Subsea Fields 6
6 Structures (External) 7
7 Diesel 8
1 Process Systems
2 Utility Systems
5 Subsea Fields
6 Structures (External)
7 Diesel
Addendum 3
Outline of Process for Preparation of
Corrosion Awareness Material
Addendum 4
Roles and Responsibilities
1 Scope 1
2 Responsibilities 1
2.1 BP 1
2.2 Inspection and Corrosion Management Service Provider 2
2.3 Asset Production Chemist, Onshore 5
1 Scope
Typical roles and responsibilities for corrosion management in a North Sea PU are
identified below.
2 Responsibilities
2.1 BP
BP is responsible for the effective management of inspection and corrosion on their
offshore and onshore facilities in order to minimise the potential for hydrocarbon leaks
and to ensure production can be maintained safely.
Providing an end of trip report after each trip summarising work completed, anomalies
reported and reports issued. Also to include a summary of all overdue inspections and
those due within the next 90 days (Maximo workflow) with details of plans to closeout.
Refer to Addendum 1 for report template
Ensuring Maximo is updated with a summary of all inspection activities as work is
completed
Maintaining and filing offshore reports and supporting documentation to allow easy
future access
Providing general inspection support to Installation personnel as required
Liaising with offshore planners as required supporting project delivery
He/she is responsible for informing the ACE of any changes in production chemistry and
consequent changes in the types and quantities of chemicals injected both downhole and
topsides. The ACE consults with the BP Corrosion Consultant (BPCC) on changes in
corrosion inhibitor deployment prior to implementation.
The ACE participates in the regular review and revision of the corrosion control
matrices.
The ACE provides a monthly and annual review and analysis of changes in production
well operations and chemical usage data for summarised inclusion in the monthly and
annual corrosion reports
Addendum 5
Material Degradation Reporting
To allow for a central database of material degradation issues to be created which can be easily
tracked and shared to create a cross Strategic Performance Unit (SPU) understanding, the
Material Degradation Report (MDR) system has been created.
A MDR should be raised under the following conditions:
Failures or unplanned changeouts (below retirement thickness) due to material degradation
(eg corrosion, erosion, fatigue)
Planned repair or changeout of item (ie item is below retiral and has been identified by
routine inspection)
The intention is for the MDRs to focus on integrity problems, normally those within the
workscope of the inspection corrosion management contractor ie issues with electrical
equipment or similar would not be routinely included.
There can be some discretion as to what else can be included in a MDR. It is not the intention
that all fabric maintenance repairs are included in a MDR. However, if the inspection/corrosion
personnel become aware of an issue that they think needs to be shared, this should be
included.
The material degradation record should be entered into the spreadsheet by the responsible
asset nominated inspection or corrosion personnel. The asset nominated engineer will be held
accountable for the entrance of these into the system by the Asset BP Integrity Engineer.
Only inspection and corrosion specialist personnel should be involved in raising, updating and
completing a MDR. The corrosion engineer shall have final endorsement of the failure
mechanism.
Each asset spreadsheet will be collated typically every six months (at the end of the month)
by the BP North Sea Corrosion Consultant who will arrange for a central spreadsheet to
be compiled from all asset data and the information made available online for cross asset
awareness and understanding.
An example of part of the MDR spreadsheet contained within Sharepoint is given here.
Addendum 6
Annual Corrosion Management Report
(Typical Example)
1 Scope 1
2 Executive Summary 1
3 Safety 1
6 Modifications 3
8 Documentation 3
Note: This is a typical example to cover topsides mechanical integrity statement as influenced
by corrosion management.
1 Scope
This topside annual corrosion management statement is designed to primarily cover the
mechanical integrity of topsides facilities. This statement will provide a summary of the
main activities that have taken place to manage corrosion, along with a summary of the
assessed condition for each process system. There are associated Annual Integrity
Statements designed to cover structural and pipeline systems produced by the
designated disciplined engineers.
2 Executive Summary
This is a summary of main issues identified during the year.
3 Safety
Incidents: – Summary of incidents related to corrosion. Include number of Lost Time
Incidents (LTIs) and High Potentials (HIPOs) as a result of inspection activities.
Failures: – Summary of failures as a result of corrosion with subsequent actions and
current status.
Temporary Repairs: – Provide status of temporary repairs with emphasis on new ones
added during the year.
Anomaly Tracker: – Summary of anomalies identified in the year, along with status and
follow up activities.
Repair Orders: – Provide summary of overdue repair orders, with status and reasons.
Key Issue 3 – (eg integrity reviews): Provide status on this activity (note the Integrity
Reviews are sometimes called the Plant integrity review or the Risk-based Assessment
(RBI) review). Main output criteria for the system integrity reviews are: full review of
system current condition identifying areas of concern (where applicable), fitness for
service statement, forward inspection plan, action list and next scheduled review date.
Key Issue 4 (eg microbial corrosion): – Provide status on management of this issue.
Database: – Identify any issues and/or improvements with database trending of data.
Planning: – Identify any issues and/or improvements.
X-BU Issues: – Provide details of relevant issues.
5.2 Monitoring
Corrosion monitoring: probes and coupons, Field Signature Method (FSM) spools:
Retrievals – provide summary
Results – provide summary
Issues – provide summary
Monitoring:
Erosion: sand probes – provide summary
Vibration: provide summary
6 Modifications
Provide key modifications to the topsides facilities/systems
Include major changes to process conditions
8 Documentation
Strategies: provide summary on documentation updates in the year – examples given
below:
Facilities Integrity Management Scheme (FIMS), rev X issued
CUI general: continue with BP strategy Management of Corrosion Under Insulation
implementation
Chloride Stress Corrosion Cracking (CISCC) risk lines: Summary: strategy developed
for higher risk areas
KPIs: corrosion control matrices provide summary of corrosion control matrices for the
year, refer to diagram below. This can include corrosion mitigation and operational
controls as well as inspection activities.
Risk matrix: an integrity risk matrix is required to highlight the main threats to plant
integrity, their risk, manageability and the progress of remedial actions to mitigate them. It
is reviewed at the Integrity Team tactical meeting that occurs every 4 to 6 weeks. Once a
risk has been successfully managed and is no longer deemed to be an integrity threat it
is removed from the listing.
Addendum 7
Typical Examples of Tactical Review Summaries
As a minimum, the tactical review meetings should cover the following topics:
Mitigation/monitoring/inspection and system condition status as known
Near misses/Serious Occurrence Reports (SORs)/Alerts/Health, Safety and
Environment (HSE) notices
Temporary repairs
Leaks/failure investigations/issues arising in the month
Key Performance Indicators (KPIs)
Risk matrix
Action tracker review
Piping integrity review status – this is sometimes referred to as the Risk-based
Inspection (RBI) assessment or the plant integrity review
Any Other Business (AOB)
Two examples of the way in which the tactical review meeting output is recorded is
provided on the following pages.
Due Onshore/
Item Subject/Actions Actionee
Date Offshore
1.1 Corrosion KPIs: Monthly Onshore/
Meeting Offshore
Review % compliance over a
number of months.
1.2 Review Leaks: Monthly Onshore/
Meeting Offshore
Review number of hydrocarbon
leaks over a number of months.
1.3 Inspection KPIs: Monthly Onshore/
Meeting Offshore
For example, the following could
be recorded for current and
previous 2 months.
Overall 86% with respect to plan,
2 red – Repair order (RO) progress
and Workbook issue, 1 amber –
Corrosion Under Insulation (CUI)
progress.
1.4 Progress on monitoring a key Ongoing Onshore/
threat such as CUI (but could be Offshore
any issue or area of concern) CUI
Survey Progress:
05/08/05 – Register now complete
05/08/05 – Initial line walk complete
14/07/05 – Line walk in progress to
verify which lines are insulated
(check against P&IDs) and check
current condition to permit
re-assessment of existing plan.
09/06/05 – Generate a register for
insulated lines. Plan 2 trips for
walking the lines to clarify what
lines are still insulated and what
are the problem areas.
1.5 Progress on monitoring key threat Onshore
– eg dead leg corrosion.
Provide status of what has
happened in current month.
Due Onshore/
Item Subject/Actions Actionee
Date Offshore
1.6 Corrosion Probes and Coupons: Monthly Onshore/
Meeting Offshore
Provide status of coupons/probes
removed during month (with
findings).
1.7 Summary of Sand Data: Monthly Onshore/
Meeting Offshore
Report on sand production and any
influence it may have on metal loss
topsides, influence on the sand
management strategy.
1.8 Summary of Process Changes: For info Onshore
Review process and operational Monthly
changes during month and possible Meeting
impact on material degradation.
1.9 Corrosion Related Modifications: Monthly Onshore
Meeting
Review any modifications that are
taking place and impact on material Ongoing
degradation.
1.10 Offshore ‘Corrosion Champion’ Monthly Offshore
Update: Meeting
Update team on corrosion
communications and review and
significant issues from platform
leak surveillance and walkabouts.
1.11 Verification Issues: As Onshore
required
Discuss any verification issues.
1.12 Corrosion Risk Matrix: Monthly Onshore/
Meeting Offshore
Discuss and update the corrosion
risk matrix – reference example
given at end of addendum.
1.13 Monthly Report/Repair Orders: Monthly Onshore
Discuss overdue RO data/status. Meeting
1.14 Meetings: As Onshore
required
Identify any additional key
meetings that are required.
3.2 Pipelines
Due Onshore/
Item Subject/Actions Actionee
Date Offshore
2.1 Review corrosion monitoring data Monthly Onshore/
collected during the month. Meeting Offshore
Onshore/
Onshore
3.3 Corrosion/Chemicals
Due Onshore/
Item Subject/Actions Actionee
Date Offshore
3.1 Any New Trials for the Ongoing Onshore
Scale/Corrosion Inhibitors:
Discuss status of any chemical
trials.
3.2 Chlorinator (or other key chemical Ongoing Offshore
delivery equipment):
Discuss status of any key
equipment that delivers a key
corrosion mitigation chemical such
as a chlorinator.
3.3 Corrosion Awareness: Toolbox Provide Offshore
talks: Timing
Discuss what awareness material
has been delivered during the
month and what will be delivered in
next month/quarter.
3.7 Include any details on further Ongoing Onshore/
additional sampling that has taken Offshore
place during the month or is due to
take place.
Due Onshore/
Item Subject/Actions Actionee
Date Offshore
4.1 Oil Export System: Provide Onshore
Date
Summarise any key activities that
have taken place in the month or
are due to take place in following
months.
4.2 Fatigue: Monthly Onshore
Meeting
Identify any issues.
4.3 Flowlines: Provide Onshore
Date
Summarise any key activities that
have taken place in the month or
are due to take place in following
months.
4.4 Flowlines/Chokes: Provide Onshore/
Date Offshore
Summarise any key activities that
have taken place in the month or
are due to take place in following
months.
4.5 Deadlegs: Provide Onshore
Date
Review of the pipework deadlegs
(currently in progress).
Addendum 8
Strategic Review Output
The purpose of the strategic review is to discuss the strategy that is presently in place to
manage corrosion in the Asset ie:
The process, including roles and responsibilities
The RBI outputs – monitoring, inspection and mitigation measures that have been in place
over the previous year
Management schemes that are in place for each corrosion threat
To establish whether changes or additions to the corrosion management strategy are
required
An outline of what may be covered during a strategic review is provided below, along with some
key questions to consider. The outcome from these discussions should be minuted and tracked:
Presentation of the annual report and corrosion management strategy
Review the threats in each system, is the monitoring, inspection and mitigation measure
still appropriate? Are there any corrosion mechanisms that are not being managed in a
particular process system?
Are there any challenges or changes that need to be made in the present documentation
for managing corrosion, such as any revisions or developments required to the
management schemes for specific corrosion threats, any revision of roles and
responsibilities?
Review of the minutes/actions from the previous strategic meeting
What differences have these actions made?
Have the actions been implemented?
Vessels and pipework Risk-based Inspection (RBI) (integrity review) status
What are the issues with this activity?
Brainstorming session
Addendum 9
Corrosion Management Strategy Example
Addendum 10
Corrosion Management Audit (Health Check)
Are the targets for corrosion control identified for each option (ie performance
indicators)?
Who is involved in setting the control measures?
Have the key players been identified?
Are the roles and responsibilities identified?
Are the roles and responsibilities reviewed regularly?
Does everyone understand their role (eg what to do in an upset condition)?
Is the corrosion control plan visible to onshore/offshore?
Can changes in operational practices be accommodated within the corrosion control
plan (ie is it reviewed regularly)?
Does the corrosion control plan take into account the system desired life?
How is the effectiveness of the corrosion control plan measured?
Is there a plan for managing Corrosion Under Insulation (CUI)?
Does it comply with Management of Corrosion Under Insulation (NSSPU-GP-06-10-2,
Addendum 6)?
How is fabric maintenance managed? Does it comply with Fabric Maintenance
Standard and guidance (UKCS-TI-029)?
Who are the key players involved in the development of monitoring and inspection
programmes?
Are roles and responsibilities clearly understood?
Do the key players have access to other networks/corrosion bulletins?
How are results of the monitoring and inspection fed back into the corrosion control
plan and the strategies (short/long-term)?
2.8 Responsibilities
Explores roles and responsibilities between all key personnel involved in various
activities. Is everyone aware of their roles and responsibilities (offshore personnel and
BP onshore involvement/ownership)?
Who are the key players involved in corrosion management?
Are all key players aware of their roles and responsibilities?
Who is the offshore focal point for corrosion and inspection management in BP and in
the service provider? Who provides support and challenge on key issues?
Do any examples of roles and responsibility matrices exist? Review a sample
How do key players offshore relate to the key players onshore and vice versa?
Do offshore key players get involved in the Risk Assessments?
What reports exist which summarise activities and findings, eg does a monthly status
report exist? Review this
Does an annual corrosion management (material degradation) report exist to facilities
and for pipelines? Look at current and previous year report
Does a strategic annual review based on the annual corrosion report report take
place? Review the summary of the strategic review
What other ad hoc meetings exist?
Addendum 11
Terms of Reference and Assurance Protocol
Paragraph Page
1 Terms of Reference 1
1.1 Scope 1
1.2 Objectives 1
2 Assurance Protocol 2
1 Terms of Reference
This assurance protocol shall be used to check for compliance with the requirements
specified in the Procedure for Audit and Monitoring (UKCS-AL-001).
1.1 Scope
The assurance protocol is intended to serve two purposes. These are to provide:
An audit question set based upon all requirements for auditors to evaluate compliance
of the entire procedure at an Asset
A monitoring question set based upon relevant requirements to be used by Asset or
function personnel to evaluate compliance with parts of the procedure
1.2 Objectives
The assurance protocol shall:
Ensure that the requirements detailed in this document are being systematically
checked at an Asset or function
Provide a common approach to testing compliance across all Assets where this
procedure is applicable
Allow those involved in audit or monitoring activities to document findings and
recommendations in advance of report approval in Tr@ction
2 Assurance Protocol
For a usable version on the Assurance Protocol, please click here.