Sample Estimate For Building
Sample Estimate For Building
C. GRAVEL FILL
STRUCTURE AREA ELEV. VOLUME QUANTITY TOTAL
Porch 6.00 0.20 1.2 1 1.2
Car port 20.00 0.20 4 1 4
Stairs 8.00 0.20 1.6 1 1.6
Living area 28.00 0.20 5.6 1 5.6
Office 14.00 0.20 2.8 1 2.8
Dinning 28.00 0.20 5.6 1 5.6
T&B 6.00 0.20 1.2 1 1.2
Maid's room 10.00 0.20 2 1 2
Laundry 4.00 0.20 0.8 1 0.8
Kitchen 14.00 0.20 2.8 1 2.8
Lanai 6.00 0.20 1.2 1 1.2
Guest room 14.00 0.20 2.8 1 2.8
Guest T&B 4.50 0.20 0.9 1 0.9
TOTAL 32.5
NOTE: 3 m3/day
calc:
32.5/3 = 11 days
B. COLUMN
SRTUCTURE AREA LENGTH VOLUME QUANTITY TOTAL
C1a 0.06 8.05 0.50 10 5.03
C1b 0.06 5.05 0.32 8 2.53
C2a 0.08 8.05 0.60 3 1.81
C2b 0.08 5.05 0.38 1 0.38
TOTAL 9.75
NOTE: 2 men pour 0.5 m3 concrete/day
calc:
9.75 / 0.5 = 20 days
CEMENT:
9.75 X 9.0 = 88
= 88 + 25%
= 110 bags
SAND:
9.75 X 0.5 = 5
= 5 + 25%
= 7 m3
GRAVEL:
9.75 x 1.0 = 10
= 10 + 25%
= 13 m3
SAND:
17.47 X 0.5 = 9
= 9 + 25%
= 12 m3
GRAVEL:
17.47 X 1.0 = 18
= 18 + 25%
= 23 m3
calc:
108.74x3.221 = 360 pcs. (12mmФx6m Def.bars)
TIE WIRE
108.74X0.35 = 40 kg (#16 GI wire)
E. LATERAL TIES
STRUCTURE LENGTH QUANTITY TOTAL
Beam 1.24 2085 2585.4
Column 1.04 720 748.8
TOTAL 3334.2
SAND:
Total area = 468.11 m2
calc:
468.11x0.438 = 206 m3
C. PLASTERING
Total area = 468.11x2 = 936.22 m2
CEMENT(16mm thick):
calc:
936.22x0.192 = 180 bags
NOTE: 2 men plaster 8 m2/day
calc:
936.22/8 = 118 days
SAND:
calc:
936.22x0.016 = 15 m3
D. REINFORCEMENT FOR CHB
No. of CHB = 6023 pcs.
Vertical bars(spaced at 80 cm):
5852 x 0.128 = 749.056