Force Majeure Clauses
Force Majeure Clauses
Force Majeure Clauses
Coronavirus
All sorts of businesses are affected by Coronavirus: contractors, IT professionals,
manufacturers, management consultants, business agents, recruitment
consultants and service providers.
Is the reason for force majeure a valid one? Does it fall within the legal meaning of
the force majeure clause?
These questions are central to whether performance of a contract is covered by
force majeure, and whether a business can wiggle out of their legal obligations.
When it comes to Coronavirus and force majeure clauses, there are at least 3
moving parts in play:
1. the type of legal obligations contract the contract provides for - what are the
precise performance requirements under the contract of each of the parties?
1. Does the contract contemplate a high level of personal interaction
between the parties: aka a relational contract?
2. Is a manufacturer simply required to deliver manufactured goods?
b. The precise terms of the force majeure clause that appear in the contract,
such as the length of delay permitted in the contract
c. Alternative methods available to perform the contract, if any
You may be able to imagine how the rise and adoption of tools such as Zoom and
Skype and remote working come into play when a party says that a force majeure
clause comes into operation in a contract for services of an individual.
1. don’t amount to only to acts of God (ie those without human intervention);
and
2. could have been prevented or avoided, to some extent.
You can extend the legal terms to allow for events which will hinder, delay,
prevent performance of the contract that wouldn’t fallen into the meaning of
“beyond the control of the parties”.
That's because businesses are perfectly entitled to provide for what will happen in
the event of difficulties arising in the performance of their contracts.
They can be for their own convenience, even if they don’t render performance
impossible.
That has to be a good thing.
It better protects the parties that will come to rely on them if it comes to pass.
13.2 Acts or events constituting Force Majeure Events shall include, but not
limited to Act of God, government intervention, directives or policies.
13.3 The party affected by a Force Majeure Event shall notify the other as soon as
soon as reasonably practicable after commencement of a Force Majeure Event.
1. Triggers or qualifying events: these are the type of events that bring the
force majeure clause in operation.
They are the excuses for non-performance.
Clause 13.1 sets the baseline with, "delayed or hindered...", but then they're
expanded in clause 13.2.
This can’t be understated. The words that the parties are used in the contract
that count. Not some larger concept of “force majeure” or the general intention
of the parties.
For legal purposes there are major differences between:
1. events outside the control of a party
2. foreseeable events: events which could have been planned for (a
storm, yes. But an unseasonally harsh storm, no)
3. events which reduce profitability of the contract
4. events which could have been overcome or worked around.
I'll take these in turn in a moment.
So, there is no liability for “failures” or “delays” by either the seller or the buyer
if a trigger is true.
These could include one or more of the following:
1. You qualify under a Trigger Event: The actual event fits within the
force majeure meaning in the contract. The event relied on falls within the
meaning specific words used in the trigger of the force majeure clause
2. You lack control: The events were genuinely beyond the control of the
party, unless the contract says otherwise
3. Causation: The delay was caused by the event relied on. You were
prevented, delayed or hindered by reason – ie caused directly – by the force
majeure event
4. You took steps to mitigate or avoid the effect: There were no
reasonable steps that could have been taken to avoid or mitigate the event and
its consequences (that you didn't take).
1. Acts of God
2. government requests brought about for political reasons or not
3. changes of law, including deleted legislation and executive orders
4. strikes, industrial disputes
5. riots, rebellion and wars
6. refusals of a grant of licence, such as a licence to import goods
What the contracts uses depends on how the goods or services are delivered.
Acts of God and government requests and interference are common, and can be
improved on.
Acts of God is probably the most important one for most businesses.
Changes of Law; Government Requests
A change in the law is legislative or administrative interference by governments
imposed by government authorities.
The government "requests" relied upon under force majeure clause:
are not governmental in nature when they are made for a party to avoid its
contractual obligations
must be for the public good, as opposed to a private purpose.
Acts of God
Acts of God satisfy these criteria:
The supplier promised to send the customer the first 2,500 cans of ½ lb salmon
packed during the season.
There two different canneries that could supply. The ½ lb cans used by one
cannery were found to be defective at the beginning of the season. They couldn’t
be used. The other cannery used 1 lb cans.
Neither of the canneries produced any ½ lb cans of salmon during the season.
By the time replacement cans could be obtained, there was no more salmon
available.
The failure to supply was not due to any failure of the fish crop. The catch was
larger than usual.
The cause of the failure was the failure of the first cannery to have good tins. The
second cannery chose to pack 1 lb cans in priority.
By reason of these events the sellers were unable to fulfil the two contracts.
The force majeure clause was not available to the supplier to avoid liability for
breach of contract.
It was their own defective supply chain that caused the failure to deliver.
Not an event outside the supplier's control.
4. less profitability.
If a business is to be relieved as a result of a events which have this result, they
must be specified in the contract, other than by way of a force majeure clause.
It calls for what is known as a "condition subsequent". An express contractual
clause entitling a party to terminate the contract when a specified condition or set
of conditions are satisfied.
The customer purchased the gas at a price fixed by a formula. After the contract of
sale was agreed, the price of gas went up phenomenally – before the supplier
bought the gas to supply to the customer.
It made the contract of supply of the gas … unprofitable. The supplier was not able
to get out of the contract for force majeure for economic reasons.
There was nothing standing in the way of the supplier buying the gas (at a higher
than expected price) and deliver it to the customer. In addition, as the supplier
was a wholesaler in the gas industry, it knew prices could fluctuate.
The price could have gone down as well, which would have made them a windfall
that it wouldn't have complained about. The supplier had failed to deal with the
contingency in the contract (as a force majeure event or otherwise).
It could not save itself by relying on an event that they had not provided for in the
force majeure clause.
1. clauses are interpreted using the precise words that are used in the
contract, within the context of the background of the contract
2. the words used in the clause as assessed as at the date of the contract: not
at some time after the contract was signed
3. the clause will be interpreted to include matters with which the parties
would be concerned as at the date of the contract.
This means that if there is ambiguity about whether an event falls within the
trigger or not, it will probably go against the affected party.
These strict requirements imposed by courts can be lessened with clear terms of
contract in the force majeure clause.
3. Causation
Once you show a lack of control, you must show causation: that the failure to
perform the agreement was caused by the event, and not some other event that
happened at the same time.
It’s not as easy as it first seems.
The force majeure event must be sole cause of the failure to perform an obligation.
Reasonable steps must be taken to avoid or mitigate the intervening events and its
consequences: all reasonable steps to avoid its operation or mitigate its results.
The court had to decide whether the seller was entitled an extension of time for
delivery.
The sellers could only rely on the clause if they showed that one or more of the
defined force majeure events prevented delivery during the contractual shipment
period from the intended loading port. .
Once you show causation, need to show that you did everything you reasonably
could of the steps available to you to avoid the effects of the event.
That's next.
1. condition precedent. The other party must be told before they can rely
on the clause for the performance delay. The time bar prevents obtaining the
benefit of the force majeure event.
2. warranty. Here, the situation is different.
The affected party is not disentitled from obtaining the relief made available by
the clause, despite not complying with the time provision.
Whether it is a condition precedent depends on 3 factors.
They include:
a. The form of the clause itself:
- whether the clause said that notice was a condition precedent or that reliance on
force majeure was only available provided such notice was give (it is easy to
include such a clause)
- it can be said that the parties thought that the failure by one party to inform the
other immediately of the cause of its failure to perform, or a failure to give all
possible details as to the expected duration of the cause, should disentitle the
affected party from any reliance on the force majeure event
b. The relationship between the force majeure clause and the contract
as a whole:
- clear implication that the condition must have been intended for the benefit of
the clause
- whether the contract includes other cut off points or time bars
c. General considerations of law: The considerations will depend upon the
circumstances of the case. The relevant background might include:
- delay giving notice
- the information that the party had at the time
- what the party did next.
Standard to Meet
Things need to go so badly that performance of the contract is a completely
different proposition to what the parties had in mind when they entered the
contract. The event must change the deal between the parties, significantly.
That supervening event must change the nature of the contract so much, that it
would be unjust for the parties to be held to the contract.
An increase of expense or onerousness of the contract doesn’t frustrate a contract.
Consequences of Frustration
The law of contractual frustration means that:
Risk Management
Provide for precursors which need to be in place for lawful delivery under the
contract.
It does not make commercial sense to agree to accept a risk where it is not a risk
under your control. This may mean expanding the definition of force
majeure events and the effect of the affected party’s contractual obligations.
1. Courts can’t be too easy on parties to succeed in claims. The cases show
that. For example, if economic grounds were adequate to not perform a
contract, courts would be overwhelmed with cases. They couldn’t handle the
volume of litigation and disputes.
2. Parties are expected to take care of themselves and protect their own
interests in contracts they agree to.
3. Contracting parties can’t be let off performance requirements lightly.
Events are limited to events genuinely outside control in the absence of clear
words extending the reach of the trigger events
4. Also force majeure clauses won’t be interpreted to give a discretion whether
to deliver or not.
To do so would render the contract of no legal effect.
Epidemics
In the context of Covid-19, epidemics and pandemics:
Conclusion
Is a contracting party entitled to terminate the contract as they say, or are they
trying to squeeze an excuse into the contract to get out of it?
The reasons of the force majeure effect different contracts in different ways.
Whether cancellation of a contract is due to force majeure is a question of law
which depends on the terms of the contract and the facts that have arisen in the
context of the case that mater.
The circumstances of each contract need to be assessed on their own terms: with
contractors, IT professionals, suppliers, customers, event contracts. A force
majeure event may qualify as a termination event for one contract and allow
cancellation of a contract, but not another.
Need to assess terms and conditions or business contract for force majeure?
Contract cancellation due to force majeure is not always an available option.
There are always other options and different approaches available to address
hardship in the performance of contract.
Effects of Coronavirus
What about Coronavirus? Does COVID-19 come into play as an event force
majeure to prevent performance? What are the options available? It can be
difficult to know whether it will or whether it won't.