Self Practice Exercise Introductory Session

The document provides instructions for a self-practice exercise in Primavera P6 to create a project, work breakdown structure, and activities for constructing a new home with relationships between activities. It includes creating a project, adding WBS items and activities, assigning predecessors and relationships, and generating a schedule log report.

Uploaded by

shiv saurabh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
89 views6 pages

Self Practice Exercise Introductory Session

The document provides instructions for a self-practice exercise in Primavera P6 to create a project, work breakdown structure, and activities for constructing a new home with relationships between activities. It includes creating a project, adding WBS items and activities, assigning predecessors and relationships, and generating a schedule log report.

Uploaded by

shiv saurabh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

Self-Practice Exercise Primavera P6

Learning Objectives:

 Creating Project, WBS and Activities in P6


 Creating Activity Relationships
 Scheduling project and generating schedule log report

1. Create a new EPS Node having under “All initiatives”:


 EPS Code: Five letters as EC_ _ _ (Last 3 digits of your Enrolment Number)
 EPS Name: Engineering and Construction
2. In the Projects view, create a new project under the EPS you have created, with the following
attributes:
 Project ID: EC00_ _ _ (Last 3 digits of your Enrolment Number)
 Project Name: New Home Construction
 Project Planned Start: 04-FEB-2019
 Currency: Indian National Rupees
 Project Calendar: 6x8
3. In the WBS view, create the following Work Breakdown Structure for your New Home
Construction project:

4. Create a new layout for Activity Entry with the columns selected as shown below:
5. Add the following activities to your New Home Construction project:
6. Enter the following relationships in P6 file:

Activity Activity Name Predecessor Predecessor Name Relationship Lag


ID ID Type
EC00_ _ _ New Home Construction
A1000 Project Start - -
A1010 Project Management A1000 Project Start SS 0
A1020 Project Complete A1010 Project Management FF 0
A1150 Install HVAC Unit FF 0
A1170 Finish Wiring FF 0
A1230 Install Kitchen FF 0
A1220 Door Casings and FF 0
Baseboards
A1260 Lay Turf and Plant FF 0
Trees
EC00_ _ _.1 Grading
A1030 Survey and Mark Out A1000 Project Start SS 0
Site
A1040 Grade Site A1030 Survey and Mark Out FS 0
Site
EC00_ _ _.2 Foundation
A1050 Install Foundation A1040 Grade Site FS 0
Forms
A1060 Install Slab Plumbing A1050 Install Foundation FS 0
Forms
A1070 Pour and Float Slab A1060 Install Slab Plumbing FS 0
Concrete
EC00_ _ _.3 Structure
EC00_ _ _.3.1 Framing
A1080 Erect Exterior Wall A1070 Pour and Float Slab FS 7
Frames Concrete
A1090 Erect Interior Stud A1080 Erect Exterior Wall FS 0
Walls Frames
A1100 Install OSB Exterior A1080 Erect Exterior Wall FS 0
Cladding Frames
EC00_ _ _.3.2 Roof
A1110 Install Trusses A1080 Erect Exterior Wall FS 0
Frames
A1120 Install Roof Sheeting A1110 Install Trusses FS 0
A1130 Install Paper and A1120 Install Roof Sheeting FS 0
Shingles
EC00_ _ _.3.3 Interior
EC00_ _ _.3.3.1 Mechanical
A1140 Install HVAC Ducting A1130 Install Paper and FS 0
Shingles
A1150 Install HVAC Unit A1140 Install HVAC Ducting SS 0
EC00_ _ _.3.3.2 Electrical
A1160 Install Breaker Box and A1080 Erect Exterior Wall FS 0
Rough Wiring Frames
A1170 Finish Wiring A1160 Inst. Brkr Box & Rough FS 0
Wiring
EC00_ _ _.3.3.3 Plumbing
A1180 Install Rough Plumbing A1080 Erect Exterior Wall FS 0
Lines Frames
EC00_ _ _.3.3.4 Drywall
A1190 Install Drywall Sheeting A1090 Erect Interior Stud FS 0
Walls
A1180 Install Rough FS 0
Plumbing Lines
A1200 Tape and Mud A1190 Install Drywall SS 0
Sheeting
EC00_ _ _.3.3.5 Decor
A1210 Install Doors A1200 Tape and Mud FS 0
A1220 Door Casings and A1210 Install Doors FS 0
Baseboards
A1230 Install Kitchen A1200 Tape and Mud FS 0
EC00_ _ _.3.4 Exterior
A1240 Install Windows A1100 Install OSB Exterior FS 0
Cladding
A1250 Install Siding A1240 Install Windows FS 0
EC00_ _ _.4 Landscaping
A1260 Lay Turf and Plant A1250 Install Siding FS 0
Trees

7. Perform a Schedule process on the New Home Construction project and verify the project
planned finish date
8. Check the Schedule Log for any Errors and Warnings.
The final result should appear similar to the following: