INDORE SMART CITY PROJECT
INDORE SMART CITY DEVELOPMENT LIMITED
SMART CITY INDORE
MASTER-PLAN BOUNDARY TOTAL PROJECT COST – Rs. 5099 CR.
PAN CITY AREA
RETROFITTING ABD AREA
REDEVELOPMENT on PPP-mode
ABD AREA
PAN CITY AREA
ABD AREA
PAN CITY AREA – 276 SQ.KM. • TOTAL AREA – 742 ACRE (1.1%)
• POPULATION – 25 LACS • POPULATION – 1.25 LACS (5%)
• PROJECT COST – RS. 700 CR. FOR ICT SOLUTIONS • PROJECT COST – RS. 1400 CR.
SMART CITY INDORE
ABD AREA
MAIN COMPONENTS
• CONSERVATION OF HERITAGE STRUCTURE
ABD AREA • RESTORATION OF CULTURAL HERITAGE
• ECONOMY & EMPLOYMENT
• IT CONNECTIVITY & IT ENABLED GOVT.
REDEVELOPMENT AREA
SERVICES
• TRANSPORTATION & WALKABILITY
• 24X7 WATER SUPPLY
• SEWERAGE LINE
• SOLID WASTE MANAGEMENT
• 24X7 ELECTRICITY WITH UNDERGROUND
CABLING
• ROADS WITH FOOTPATH
• PARKING
• RIVERFRONT DEVELOPMENT
REDEVELOPMENT AREA- 54 ACRES • VENDOR MARKET
PROJECT COST – RS 2900 CR. PPP • SECURITY SYSTEM BY CCTV CAMERA
SMART CITY INDORE
ABD AREA
URBAN FORM– PEDESTRIAN ZONE ABD AREA
RAJWADA AREA AND SURROUNDINGS URBAN FORM– NO VEHICLE ZONE & PLAZA
TRANSFORMATION RAJWADA AND SURROUNDINGS TRANSFORMATION
BEFORE
BEFORE BEFORE
AFTER AFTER
SARAFA RAJWADA
SMART CITY INDORE
REDEVELOPMENT AREA RIVERFRONT DEVELOPMENT
ON TOD PRINCIPLE LENGTH - 3.9 KM
MOG LINE AREA – 56.5 ACRES
BEFORE
BEFORE AFTER
BEFORE
AFTER
AFTER
MOG LINE AREA –ON PPP RIVER DEVELOPMENT
MAJOR SMART ROADS IN ABD AREA
11 key roads of length
10.7 km.
Project cost – Rs.135 Crores
Cement concrete
pavement (ROW 12 -30MT.)
RCC duct for electrical
cables and RCC pipes for
OFC on both sides of the
road
RCC median with central
LED smart lighting
MAJOR ROADS IN ABD AREA
EARLIER SCENARIO SITE PREPARATION WORK NEAR COMPLETION
Typical section of the road showing all the utility services
MAJOR ROADS IN ABD AREA
ROAD CONSTRUCTION IN CENTRAL DIVIDER WITH SMART
PROGRESS STREET LIGHTING
SHIFTING OF RELIGIOUS RCC DUCTS FOR UNDERGROUND
STRUCTURES CABLING
NMV ZONE & MULTI LEVEL PARKING
NMV ROUTE
MLP
NMV ROUTE LENGTH : 2.3 KM
TOTAL PROPOSED MLP : 14
REQUIRED PARKING (CARS ) : 1000
PROPOSED PARKING (CARS ) : 1100
REQUIRED PARKING (2-WHEELER ) : 3000
PROPOSED PARKING (2-WHEELER) : 3500
STREET TRANSFORMATION & FAÇADE REDEVELOPMENT
HERITAGE WALK
3. Ghat
CONSTRUCTION OF CHANDRABHAGA BRIDGE
EXISTING PROPOSED
Present 6.0 M. wide bridge constructed in WORK IN PROGRESS
year 1901.
To ease traffic congestion, 24.0 M. wide
high level bridge being constructed.
Project cost Rs. 5.026 Crore
Project completion period - 11 Months
RIVERFRONT DEVELOPMENT
RIVERFRONT DEVELOPMENT
Length of the river from subhash Total 11 bridges ( 9
Total project cost – River width varies
marg bridge to lalbagh bridge is 78.0 Cr. vehicular & 2
from 15m to 46 m
approx 3.9 km. Pedestrian
Est. Cost
No. Phase / Section Remarks
(Rs. Crore)
1 Phase 1 / Section 1: Subhash Marg Bridge to MG Road Bridge 4.0 LOA Issued.
2 Phase 1 / Section 2: MG Road Bridge to Jawahar Marg Bridge 23.0 RFP Finalized
RFP Issued on
3 Phase 1 / Section 3: Jawahar Marg Bridge to Chandrabhaga Bridge 17.5
27th May.
Work in
4 Phase 1 / Section 4: Chandrabhaga Bridge to Harsiddhi Bridge 4.5
progress
Phase 2 : Harsiddhi Bridge,Gangour bridge, jairam bridge, Lalbagh DPR under
5 29.0
bridge preparation
RIVERFRONT DEVELOPMENT
WORK IN PROGRESS TRANSFORMATION OF RIVERFRONT
RIVERFRONT DEVELOPMENT
PROPOSED VIEW
• Park near Krishnapura Chhatri: 4000 sqm.
• Redevelopment of vegetable & fruit market (230 hawker shops & 135 fruit shops)
• Underground parking for 250 4-Wheeler & 800 2-Wheeler
SECTION
BUILT HERITAGE
Preservation of cultural and historical
values with promotion of Tourism
Built Heritage projects under Smart City
Conservation Conservation Conservation of
of Chhatri Bagh of Rajwada Gopal Mandir
Comprehensive Approach
Adaptive Re-use
Scientific Conservation
1 – CHHATRI BAGH (WORK IN PROGRESS)
Conservation Of Chhatris
Conservation Of Kund
Landscaping
Monument Lighting
Parking And Toilets
TOTAL PROJECT COST INR 4.43 CR.
DURATION 15 MONTHS
2 – RAJWADA
Reconstruction Of North Redeveloping Peripheral
Building Platform
Restoration Of Front Façade Restoration Of Outer Wall
Renovation Of Darbar Hall Restoration Of Woodwork
EST. COST – RFP ISSUED ON
INR 20.0 CRORE 29 th MAY 2017
EAST SIDE ELEVATION
3-GOPAL MANDIR
Conservation Restoration Adaptive Reuse
Est. Cost – Rs. 15 Crore (Phase 1)
RFP Issued on 9 th May 2017.
BLOCK D:
SHOPS &
BLOCK C:
OFFICES
PERFORMANCE
PLACE
BLOCK B:
ARTS & CRAFTS BLOCK A:
PROMOTION TEMPLE
PLACE BLOCK
SITE LOCATION SITE PLAN
3-GOPAL MANDIR
PROPOSED FOOD COURT AT PROPOSED AMPHITHEATRE AT
B BLOCK C-BLOCK
SHOPPING COMPLEX FRONT FAÇADE OF THE
FOR REHABILITATION OF EXISTING SHOPS TEMPLE COMPLEX
JINSI HAAT VENDORS’ MARKET
Development Of Road, Organic Waste Converter
Inclusive Development
Parking And Footpath Unit
Project Cost – Rs.9.12 Cr Total no. of shops - 510 Skill Development Centre
SITE PLAN
JINSI HAAT VENDORS’ MARKET
TRANSFORMATION OF HAAT SPACE
WORK IN PROGRESS
REDEVELOPMENT: MOG LINES AREA
4 pockets is spread over
56.5 acres.
Mix Land use, TOD, High
density, Smart features
Compensatory Housing. 23 hectares /
Total Land Area for Redevelopment
56.5 acres
FAR (incl incentive for
3.00
DPR prepared for 1st Land rehabilitation /compensation)
Parcel. Total Built-up Area 6,30,000 sqm
Residential Built-up Area @ 70% 4,41,000 sqm
Transfer of land to SPV in Commercial Built-up Area @ 20% 1,26,000 sqm
process
Institutional Built-up Area @ 10% 63,000 sqm
SMART EDUCATION
SCOPE OF WORK INCLUDES:
HARDWARE AND NETWORK SETUP DEPLOYMENT AND
AND INSTALLATION. TRAINING.
SMART SOLUTION APPLICATION
SOFTWARE INSTALLATION
WITH ALL MODULES.
MODULE DESIGN / COURSE
PROGRAM DEVELOPMENT
CONTENT
Five bids were received and opened on 20th June 2017.
· Technical presentation scheduled for 28 June.
· Financial Bid opening 05 July.
· Award of contract by 12 July .
INFRASTRUCTURAL DEVELOPMENT OF GOVERNMENT SCHOOLS
(ABD AREA)
Rationalization of schools in proportion
POOR CONDITION
to the strength of students
Construction Of Additional Classrooms
SCOPE OF WORK:
Construction Of Toilet Block
Electrical Works
WORK IN PROGRESS
Construction Of New Compound Wall
Development Of Playground
Miscellaneous Repair Works, Drainage
System.
SMART HEALTH (ATM)
ACTION ITEM STATUS
Assessment of
completed
AS-IS situation
Workshop on
completed
smart health
Feasibility
completed
study
Last week of
POC to be
June by Dell &
establish
Yolo Health.
SMART POLE (PPP)
500 Smart poles of height (12 M. to 15 M)
with Mobile Micro Towers, Wi-Fi Access
Points, Surveillance Camera, Digital
Billboard, Environmental Sensor etc.
500 km OFC with 4 core for ISCDL.
Integration with Central Control &
Command Centre.
O & M of the complete system for 15 years,
at no cost to ISCDL.
RFP in June last week (2nd call)
INSTALLATION AND O & M OF LED LIGHTS IN PAN-CITY
Install / Replace 70,000 streetlights in Indore
City
Design and supply of energy efficient luminaire with Smart
control including poles, cabling, control panel etc.
Design of Web-based System for complete control over the
streetlights to monitor their operations such as Scheduling, Dimming
Operation and maintenance of the complete system for 7 years.
ISCDL shall give an annual grant per LED fixture as a part contribution towards
CAPEX and OPEX.
SMART PBS INDORE (PUBLIC BICYCLE SHARING)
CAPEX and OPEX Model with financial RFP ISSUED ON 21ST JUNE 2017
support.
• Planning and installation
1000 cycles - 100 stations.
of Cycles and Stations
Contract Period of 5 +2 years, granted
• Central Control System
for the installation and operation of • Redistribution System
SCOPE OF WORK
the Indore Cycle Sharing System
• Depots / Workshops for
maintenance
• Registration of Users
• Fare Collection System
• User Information System
• Advertisement Space
• Marketing and User
Education
GPS-BASED VEHICLE TRACKING & MONITORING SYSTEM
GPS devices installed over 700
vehicles of IMC .
Configuration of cloud based
vehicle tracking system
completed.
RFID Tag
Surveillance CCTV Cameras
on
Vehicle
installed at Landfill site and PT/ CT.
Data
Server
INTEGRATED SOLID WASTE MANAGEMENT SYSTEM
The objective of ISWM project is to introduce analytical tools for automated decision
making to help in effective monitoring of solid waste management operations.
The project will be implemented in 6 months and the Contractor will provide
O & M Services for 3 years.
SWM TRANSFER STATIONS WITH PORTABLE COMPACTORS
Technology
Cylindrical Design prevents
corrosion and Hydraulic
Mounted Compactors
Efficiency
Capacity – 16/20 CuM.
Transfer Station at Sirpur
Transfer Station at Sanwer Road
Transfer Station at Kabit Khedi
INDORE 311
311 Is the APP made
for people of Indore
to log their complain,
to track about the
project, traffic
information, field
inspection etc.
CITIZEN COMPLAINT
REGISTRATION CREATION
COMPLAINT COMPLAINT COMPLAINT COMPLAINT COMPLAINT COMPLAINT
SUBMISSION SUBMISSION NOTIFICATION NOTIFICATION RESOLUTION RESOLUTION
SOLAR POWER
As per Smart City Mission Guideline, to meet 10% of
Indore’s power demand (35 MW) through Solar Power.
ISCDL signed MoU with SECI in August 2016. SECI official
visited Indore in March 2017.
ISCDL has identified land areas and roof –tops over
government schools and parking buildings for solar
panel installations.
Cost of Plant -Rs.12Cr.
Sites has been finalised for installation Expected Power Generation
Approx.- 500 Units/hr
ISCDL is in discussion with MP Urja Vikas Nigam Ltd. M/s
Mundra Solar Pvt. Ltd. (for 50 KW+)/M/s Ujaas Energy
Ltd. (for < 50 KW) have been selected to assess
suitability of sites.
2 MW Solar Power Plant at
Sewerage Treatment Plant, Indore
MUNICIPAL BONDS
Indore would be one of the earliest Smart cities to issue
Municipal Bonds
Tranche 1: Issue Size- INR 250 Crores
for funding specific Projects
Bond rating by CARE and Brickwork
Expected date of Issue - End of June 2017
Plan for TraNCHE ii Municipal Bonds in Jan 2019