METHOD STATEMENT FOR Backfilling - Rev 0
METHOD STATEMENT FOR Backfilling - Rev 0
METHOD STATEMENT FOR Backfilling - Rev 0
REVISION HISTORY
0 Hafez
23/04/2013
Makdissi - Issued forAhmad
Approval
Deeb JDP-KPI-MS-02/R0
Osama Zarzour
Rev Section(s Reference No.
Date DescriptionQA/QC
of Change
.Technical Engineer ) Project Manager
Authorized to Submit
Originated By Reviewed By By
Client Consultant Main Contractor Sub Contractor
CONTENTS
1. Scope 3
2. References 3
3. Responsibilities 3
4. Procedure / Method to be Employed 4
5. Manpower Requirement 4
6. Material Requirements 5
7. Equipment Requirement 5
8. Health and Safety Provisions 5
9. Attachments 6
Page 2 of 5
1. Scope
This Method Statement details procedures to be followed for back filling (if any) of Foundations, Sub-
structures & Trenches, soft and hard landscape . It includes survey works, excavation, backfilling, compaction
and area cleaning after the completion of works.
2. References
Contract Specifications
DOT. Environment, Health & Safety Management System (EHSMS)
Al Jurf QHSE Management System and Project Specific Safety Plan
3. Responsibilities
It is the Project Manager’s duty to ensure that all necessary safety and protective equipment are provided
along with the properly trained and qualified personnel.
It is the QA/QC Engineer’s duty to ensure that the Method Statement Procedure is adhered to by all
personnel.
It is the Site Engineer’s and the Foreman duty to organize the work in a safe manner, and in accordance with
the standards.
It is the duty of Safety Officer (assigned Foreman) to supervise and monitor activities and perform as per the
guidelines of HSE standards.
It is also the duty of Safety Officers (assigned Foreman) to report any accidents, near misses, and dangerous
occurrences to Safety Engineer and participate in the investigation process.
It is the Safety Officer’s (assigned Foreman) duty to initiate appropriate action for excellent safety
performance / repeated unsafe acts of personnel and implement safety measures as per HSE plan.
It is the Engineer’s/Foreman duty to ensure that all the works are performed to the satisfaction of the
Company and as per the project specifications.
It is the worker’s duty to adhere to all the safety rules. They must perform the work in accordance wit the
Method of Statement.
Page 3 of 5
The backfilling shall be done in layers not exceeding 300 mm in depth after compaction to 95% of MDD.
The filling material should be free from, organic or other unsuitable matter and to be capable of compaction.
Select sample of proposed back fill material for the Engineer approval.
Before placing the back fill material complete the following : All construction below soil such as water
proofing .Surveying the underground utilities for record documents.
All filled area shall be left neat, smooth and will complete.
Service trenches shall not be backfilled until all required tests are performed and until the Engineer has
verified that the utility systems have been installed in accordance with the specifications and drawings.
5 Manpower Requirement
Site engineer
foreman
Charge hands
Surveyors
Skilled and Unskilled labors
6 Material Requirements
Page 4 of 5
7 Equipment Requirement
Dumpy Level
Plate / Roller Compactor
Air Compressor with Jack Hammers (if required)
Loader
Tipper Trucks
Hand tolls like shovel, rake, etc.
Water Tanker
All the works will be undertaken in accordance with site safety regulations as stated in the contract
documents.
The site will be kept clean and tidy in accordance with site safety regulations, mainly at the time of soil
spreading and after spreading activities.
All the machinery will be checked (daily routine maintenance) before starting the work by the operators and
then by Safety Officer.
All the machinery works will be performed in accordance with site safety regulations for utmost safety.
9 Attachments
ITP
Organization Chart
Risk Assessment
Work Program
Specification Reference
Page 5 of 5