Dot 35104 DS1
Dot 35104 DS1
Dot 35104 DS1
Prepared by
The Transtec Group, Inc.
Submitted to
January 2018
By
cmr 18-003
4. Title and Subtitle 5. Report Date
Intelligent Compaction and Infrared Scanning Field Projects with Consulting January 2018
Support Published: February 2018
6. Performing Organization Code
9. Performing Organization Name and Address 10. Work Unit No. (TRAIS)
The Missouri Department of Transportation (MoDOT) was awarded a grant from the FHWA Accelerated Innovation
Deployment (AID) program, in 2016. MoDOT provided the required matching funds to support this Intelligent Compaction
(IC) and Infrared Scanning (IR) Field Projects with Consulting Support in 2017. The consulting support was provided by
the Transtec Group (Consultant) and includes the development MoDOT IC-IR Protocol and training materials, conducting
IC-IR training, on-site technical support to IC-IR field projects, data analysis, and reports of IC-IR field data. The original
IC-IR project included 10 field projects. Additional MoDOT funding was later added to support three additional IC-IR
projects, making a total of 13 field projects.
This document is the final report summarizing the two combined projects including field test results, lessons-learned and
recommendations.
Compaction; Infrared analysis; Paving. Intelligent compaction, thermal No restrictions. This document is
profiles, roller, paver, asphalt, overlay, quality control. available through the National
Technical Information Service,
Springfield, VA 22161.
19. Security Classif. (of this report) 20. Security Classif. (of this page) 21. No. of Pages 22. Price
2
SI* (MODERN METRIC) CONVERSION FACTORS
APPROXIMATE CONVERSIONS TO SI UNITS
Symbol When You Know Multiply By To Find Symbol
LENGTH
in inches 25.4 millimeters mm
ft feet 0.305 meters m
yd yards 0.914 meters m
mi miles 1.61 kilometers km
AREA
2 2
in square inches 645.2 square millimeters mm
2 2
ft square feet 0.093 square meters m
2 2
yd square yard 0.836 square meters m
ac acres 0.405 hectares ha
2 2
mi square miles 2.59 square kilometers km
VOLUME
fl oz fluid ounces 29.57 milliliters mL
gal gallons 3.785 liters L
3 3
ft cubic feet 0.028 cubic meters m
3 3
yd cubic yards 0.765 cubic meters m
3
NOTE: volumes greater than 1000 L shall be shown in m
MASS
oz ounces 28.35 grams g
lb pounds 0.454 kilograms kg
T short tons (2000 lb) 0.907 megagrams (or "metric ton") Mg (or "t")
TEMPERATURE (exact degrees)
o o
F Fahrenheit 5 (F-32)/9 Celsius C
or (F-32)/1.8
ILLUMINATION
fc foot-candles 10.76 lux lx
2 2
fl foot-Lamberts 3.426 candela/m cd/m
FORCE and PRESSURE or STRESS
lbf poundforce 4.45 newtons N
2
lbf/in poundforce per square inch 6.89 kilopascals kPa
4
Data Analysis and Results ........................................................................................................................... 39
IR Data Analysis ....................................................................................................................................... 39
IC Data Analysis ....................................................................................................................................... 48
Roller Passes ....................................................................................................................................... 48
ICMV .................................................................................................................................................... 48
Mat Temperature................................................................................................................................ 50
Analysis Example ..................................................................................................................................... 52
Summary of Results ................................................................................................................................ 59
Project No. 1 - J5P3117, RT 52 ............................................................................................................ 60
Project No. 2 - J4I3111, RT 29 ............................................................................................................. 66
Project No. 3 - J3I3042, I-70 ................................................................................................................ 72
Project No. 4 - JP3099, RT 36 .............................................................................................................. 80
Project No. 5 - J2P3100, RT 36 ............................................................................................................ 83
Project No. 6 - J2P3051, RT 24 ............................................................................................................ 87
Project No. 7 - J1P3005, RT 24 ............................................................................................................ 93
Project No. 8 - J9P3161, RT 17 ............................................................................................................ 98
Project No. 9 - J6S3123, RT 61 .......................................................................................................... 104
Project No. 10 - J7I3072, RT 49 ......................................................................................................... 109
Project No. 11 - J1S3028, RT 69 ........................................................................................................ 114
Project No. 12 - J5P3170, RT 5 .......................................................................................................... 120
Project No. 13 - J9P3296, RT 17 ........................................................................................................ 125
Comparison of IC-IR Results .................................................................................................................. 130
Project Evaluation ..................................................................................................................................... 134
GPS Verification ................................................................................................................................ 134
GPS and Cellular Signal Coverage ..................................................................................................... 134
Functioning of IC Equipment and System ......................................................................................... 134
Functioning of IR Equipment and System ......................................................................................... 134
Paving Boundary Measurements ...................................................................................................... 135
IC Data Collection and Submission.................................................................................................... 135
IR Data Collection and Submission ................................................................................................... 136
Other Data Collection and Submission (trial sections and core data) .............................................. 136
Completion of Check list ................................................................................................................... 137
Utilization of Full Capabilities of IC and IR Systems .......................................................................... 137
5
IC-IR Training Workshops .................................................................................................................. 137
IC-IR Data Completion ....................................................................................................................... 138
IC-IR Check List and Form Completion .............................................................................................. 139
IC-IR Specification Reviews ....................................................................................................................... 140
IR Specification ...................................................................................................................................... 140
Equipment Requirements ................................................................................................................. 140
Training Requirements...................................................................................................................... 140
Data and Analysis Requirements ...................................................................................................... 140
Acceptance Requirements ................................................................................................................ 140
IC Specification ...................................................................................................................................... 141
Equipment Requirements ................................................................................................................. 141
Training Requirements...................................................................................................................... 141
Field Operation Requirements .......................................................................................................... 141
Data and Analysis Requirements ...................................................................................................... 141
Acceptance Requirements ................................................................................................................ 141
Conclusions and Recommendations ......................................................................................................... 142
Conclusions ........................................................................................................................................... 142
Recommendations ................................................................................................................................ 143
6
LIST OF FIGURES
Figure 1. Example of IC Color-coded Displays for Roller Passes, Asphalt Temperatures, and ICMV. ........ 14
Figure 2. Examples of OEM Double-Drum IC Rollers. ................................................................................ 15
Figure 3. An Example of IC Retrofit Systems. ............................................................................................. 15
Figure 4. Method of Measuring and Calculating ICMV. ............................................................................. 16
Figure 5. An Illustration of an IR System. ................................................................................................... 18
Figure 6. An Example of IR Display of Thermal Profiles and Paver-Speed. ................................................ 19
Figure 7. AASHTO Standard Software Veta for Intelligent Construction Data Management. ................... 20
Figure 8. IC and IR Data Flow to Veta......................................................................................................... 21
Figure 9. IC Raw and Gridded data............................................................................................................. 21
Figure 10. IC All-Passes Data and Final Coverage data. ............................................................................. 22
Figure 11. Screenshots of Veta Displays and Analysis. .............................................................................. 22
Figure 12: MoDOT IC-IR Project Protocol................................................................................................... 26
Figure 13: Contractor’s Daily Check List..................................................................................................... 28
Figure 14: Contractor’s Daily Paving Record Form. ................................................................................... 29
Figure 15: Daily Check List for REs. ............................................................................................................ 30
Figure 16: MoDOT SharePoint IC-IR Project Folders. ................................................................................. 32
Figure 17: MoDOT SharePoint IC-IR Project Sub-Folders........................................................................... 33
Figure 18: MoDOT IC-IR Training Workshop Agenda. ................................................................................ 34
Figure 19: Photos from the MoDOT IC-IR Training Workshops. ................................................................ 35
Figure 20: MoDOT IC-IR Project and Workshop Locations. ....................................................................... 38
Figure 21: AASHTO PP80 IR Analysis Method: 10’ exclusion around a paver stop location...................... 39
Figure 22: AASHTO PP80 IR Analysis Method: Computation of “Range” value......................................... 40
Figure 23: AASHTO PP80 IR Analysis Method: Segregation categories ..................................................... 40
Figure 24: Example of MOBA PPM IR Analysis Screens. ............................................................................ 41
Figure 25: Example of Veta Viewer screen of IR data plots (J3I3042, RT70). ............................................ 42
Figure 26: Example of Veta Filter screen (J3I3042, RT70).......................................................................... 43
Figure 27: Example of a Veta Sublot screen (J3I3042, RT70). ................................................................... 44
Figure 28: Example of a Veta Sublot screen for IR data analysis (J3I3042, RT70). .................................... 45
Figure 29: Example of a Veta Analysis setup for IR data analysis (J3I3042, RT70). ................................... 45
Figure 30: Example of a Veta IR data analysis results (J3I3042, RT70). .................................................... 46
Figure 31: Example of a Veta Paver Stop plot (J3I3042, RT70). ................................................................ 46
Figure 32: Example of a Veta IR Temperature Differential report (J3I3042, RT70). ................................. 47
Figure 33: Target ICMV determined by Correlation between ICMV and Acceptance Spot Tests from Trial
Section Data. ............................................................................................................................................... 48
Figure 34: FWHA ICMV Tech Brief (FHWA-HIF-17-046). ............................................................................ 49
Figure 35: Target ICMV determined by an ICMV Compaction Curve when Acceptance Spot Tests from
Trial Section Data are Not Available. .......................................................................................................... 50
Figure 36: MODOT Requirement for Mat Temperatures during vibratory compaction. .......................... 51
Figure 37: Veta Data Filter and Analysis Setup for MODOT Requirement for Mat Temperatures during
vibratory compaction. ................................................................................................................................. 51
Figure 38: Trial Section Tests on 4/24/2017 (J1P3005 RT 24). ................................................................... 52
Figure 39: Compaction Curve from the Trial Section on 4/24/2017 (J1P3005 RT 24). ............................... 52
Figure 40: An Example Veta Analysis Screen showing Pass Count map (J1P3005 RT 24). ........................ 53
7
Figure 41: An Example Veta Analysis Screen showing Filter Groups (J1P3005 RT 24). ............................. 54
Figure 42: An Example Veta Analysis Screen showing spot tests (J1P3005 RT 24). .................................. 55
Figure 43: An Example Veta Analysis Screen showing correlation tests between ICMV and spot tests
(J1P3005 RT 24)........................................................................................................................................... 56
Figure 44: An Example Veta Analysis Screen showing the Roller Coverage report (J1P3005 RT 24). ....... 57
Figure 45: An Example Veta Analysis Screen showing the ICMV Coverage report (J1P3005 RT 24). ........ 57
Figure 46: An Example Veta Analysis Screen showing the Mat Temperature report (J1P3005 RT 24). .... 58
Figure 47: An Example MoDOT IC-IR Project Report. ................................................................................ 59
Figure 48 Compaction Curve from the Trial Section on 5/9/2017 (Project No. 1 - J5P3117, RT 52). ........ 60
Figure 49 Compaction Curve from the Trial Section on 5/12/2017 (Project No. 1 - J5P3117, RT 52). ...... 61
Figure 50: Summary of MOBA PPM Temperature Segregation Report (Project No. 1 - J5P3117, RT 52). . 63
Figure 51: Summary of Veta Temperature Segregation Report (Project No. 1 - J5P3117, RT 52). ............ 63
Figure 52: Summary of Roller Coverage Report (Project No. 1 - J5P3117, RT 52). .................................... 65
Figure 53 Compaction Curve SP190B from the Trial Section on 8/25/2017 (Project No. 2 - J4I3111, RT
29). .............................................................................................................................................................. 66
Figure 54 Compaction Curve SP095B from the Trial Section on8/26/2017 (Project No. 2 - J4I3111, RT 29).
.................................................................................................................................................................... 67
Figure 55: Summary of MOBA PPM Temperature Segregation Report (Project No. 2 - J4I3111, RT 29). .. 69
Figure 56: Summary of Veta Temperature Segregation Report (Project No. 2 - J4I3111, RT 29). ............. 69
Figure 57: Summary of Roller Coverage Report (Project No. 2 - J4I3111, RT 29). ..................................... 71
Figure 58: Density Compaction Curve from the Trial Section on 8/14/2017 (Project No. 3-J3I3042, I-70)
.................................................................................................................................................................... 72
Figure 59: NDG Density and ICMV Compaction Curves from the Trial Section on 8/14/2017 (Project No.
3 - J3I3042, I-70).......................................................................................................................................... 73
Figure 60: Incorrect distance reported by MOBA PPM for the data on 8/23/2017 (J3I3042, I-70). ......... 75
Figure 61: Correct IR Segregation Reported by Veta for the data on 8/23/2017 (Project No. 3 - J3I3042, I-
70). .............................................................................................................................................................. 76
Figure 62: Summary of MOBA PPM Temperature Segregation Report (Project No. 3 - J3I3042, I-70)...... 77
Figure 63: Summary of Veta Temperature Segregation Report (Project No. 3 - J3I3042, I-70). ................ 77
Figure 64: Summary of Roller Coverage Report. (Project No. 3 - J3I3042, I-70)......................................... 79
Figure 65: Incorrect Boundary File for 8/23/2017 (Project No. 3 - J3I3042, I-70). ..................................... 79
Figure 66: Summary of MOBA PPM Temperature Segregation Report (Project No. 4 - JP3099, RT 36). ... 81
Figure 67: Summary of Veta Temperature Segregation Report (Project No. 4 - JP3099, RT 36). .............. 81
Figure 68: Summary of Roller Coverage Report (Project No. 4 - JP3099, RT 36)........................................ 82
Figure 69: Summary of MOBA PPM Temperature Segregation Report (Project No. 5 - J2P3100, RT 36). . 84
Figure 70: Summary of Veta Temperature Segregation Report (Project No. 5 - J2P3100, RT 36). ............ 84
Figure 71: Summary of Roller Coverage Report (Project No. 5 - J2P3100, RT 36)...................................... 86
Figure 72: Compaction Curve from the Trial Section on 10/21/2016 (Project No. 6 - J2P3051, RT 24). .... 87
Figure 73: Compaction Curve from the Trial Section on 10/27/2016 (Project No. 6 - J2P3051, RT 24). .... 88
Figure 74: Summary of MOBA PPM Temperature Segregation Report (Project No. 6 - J2P3051, RT 24). . 90
Figure 75: Summary of Veta Temperature Segregation Report (Project No. 6 - J2P3051, RT 24). ............ 90
Figure 76: Summary of Roller Coverage Reports (Project No. 6 - J2P3051, RT 24). ................................... 92
Figure 77: Compaction Curve– Trial Section (4/24/2017) (Project No. 7 - J1P3005, RT 24)....................... 93
Figure 78: Summary of MOBA PPM Temperature Segregation Report (Project No. 7 - J1P3005, RT 24). . 95
8
Figure 79: Summary of Veta Temperature Segregation Report (Project No. 7 - J1P3005, RT 24). ............ 95
Figure 80: Summary of Roller Coverage Report (Project No. 7 - J1P3005, RT 24)...................................... 97
Figure 81: Compaction Curve from the Trial Section on 9/28/2017 (Project No. 8 - J9P3161, RT 17). ...... 98
Figure 82: Compaction Curve from the Trial Section (2017-10-2) (Project No. 8 - J9P3161, RT 17) .......... 99
Figure 83: Summary of MOBA PPM Temperature Segregation Report (Project No. 8 - J9P3161, RT 17).
.................................................................................................................................................................. 101
Figure 84: Summary of Veta Temperature Segregation Report (Project No. 8 - J9P3161, RT 17). .......... 101
Figure 85: Summary of Roller Coverage Report (Project No. 8 - J9P3161, RT 17).................................... 103
Figure 86 Compaction Curve– Trial Section (5/31/2017) (Project No. 9 - J6S3123, RT 61) ...................... 104
Figure 87: Summary of MOBA PPM Temperature Segregation Report (Project No. 9 - J6S3123, RT 61).106
Figure 88: Summary of Veta Temperature Segregation Report (Project No. 9 - J6S3123, RT 61)............ 106
Figure 89: Summary of Roller Coverage Report (Project No. 9 - J6S3123, RT 61). ................................... 108
Figure 90 Compaction Curve– Trial Section (6/12/2017) (Project No. 10 - J7I3072, RT 49)..................... 109
Figure 91: Summary of MOBA PPM Temperature Segregation Report (Project No. 10 - J7I3072, RT 49).
.................................................................................................................................................................. 111
Figure 92: Summary of Veta Temperature Segregation Report (Project No. 10 - J7I3072, RT 49). ......... 111
Figure 93: Summary of Roller Coverage Report (Project No. 10 - J7I3072, RT 49). .................................. 113
Figure 94 Compaction Curve from the Trial Section-1 on 6/30/2017 (Project No. 11 - J1S3028, RT 69). 114
Figure 95 Compaction Curve from the Trial Section-2 on 6/30/2017 (Project No. 11 - J1S3028, RT 69). 115
Figure 96. Compaction Curve from the Trial Section on 7/6/2017 (Project No. 11 - J1S3028, RT 69). .... 116
Figure 97: Summary of MOBA PPM Temperature Segregation Report (Project No. 11 - J1S3028, RT 69).
.................................................................................................................................................................. 118
Figure 98: Summary of Veta Temperature Segregation Report (Project No. 11 - J1S3028, RT 69).......... 118
Figure 99: Summary of Roller Coverage Report (J1S3028, RT69). ............................................................ 119
Figure 100: Density Compaction Curve from the Trial Section on 9/8/2017 (Project No. 12 - J5P3170, RT
5). .............................................................................................................................................................. 120
Figure 101: Summary of MOBA PPM Temperature Segregation Report (Project No. 12 - J5P3170, RT 5).
.................................................................................................................................................................. 122
Figure 102: Summary of Veta Temperature Segregation Report (Project No. 12 - J5P3170, RT 5). ........ 122
Figure 103: Summary of Roller Coverage Report (Project No. 12 - J5P3170, RT 5). ................................. 124
Figure 104: Compaction Curve from the Trial Section on 5/7/2017 (Project No. 13 - J9P3296, RT 17). .. 125
Figure 105: Core Sample from the Trial Section on 5/7/2017 (Project No. 13 - J9P3296, RT 17). ........... 125
Figure 106: Summary of MOBA PPM Temperature Segregation Report (Project No. 13 - J9P3296, RT 17).
.................................................................................................................................................................. 127
Figure 107: Summary of Veta Temperature Segregation Report (Project No. 13 - J9P3296, RT 17). ...... 127
Figure 108: Summary of Roller Coverage Report (Project No. 13 - J9P3296, RT 17). ............................... 129
Figure 109: Comparison of IR Segregation for all projects. ...................................................................... 130
Figure 110: Comparison of IR Segregation for projects by coded contractors. ........................................ 131
Figure 111: Comparison of IC Coverage for all projects. .......................................................................... 132
Figure 112: Comparison of IC Coverage for projects by coded contractors. ............................................ 133
LIST OF TABLES
Table 1. Summary of ICMV Model and Methods (FHWA ICMV Tech Brief). .............................................. 16
9
Table 2. Classification of ICMV Levels (FHWA ICMV Tech Brief). ............................................................... 17
Table 3. Timeline and Deliverable Schedule. .............................................................................................. 23
Table 4: Data File Naming Convention....................................................................................................... 31
Table 5. MoDOT IC-IR Training Workshop Schedule................................................................................... 35
Table 6. MoDOT IC-IR Project Schedule ...................................................................................................... 36
Table 7. MoDOT IC-IR Project Systems Used .............................................................................................. 37
Table 8. Example of MOBA PPM IR Analysis Report of Temperature Segregation. ................................... 42
Table 9. MoDOT IC Coverage Classification. ............................................................................................... 48
Table 10. MoDOT Target ICMV Coverage Classification. ............................................................................ 50
Table 11: Summary of IR Results (Project No. 1 - J5P3117, RT 52) ............................................................. 62
Table 12: Summary of IC Results (Project No. 1 - J5P3117, RT 52) ............................................................ 64
Table 13: Summary of IR Results (Project No. 2 - J4I3111, RT 29) ............................................................. 68
Table 14: Summary of IC Results (Project No. 2 - J4I3111, RT 29) ............................................................. 70
Table 15: Summary of IR Results (Project No. 3 - J3I3042, I-70)................................................................. 74
Table 16: Incorrect number of sublots reported by MOBA PPM for the data on 8/23/2017 (Project No. 3 -
J3I3042, I-70)............................................................................................................................................... 75
Table 17: Summary of IC Results (Project No. 3 - J3I3042, I-70)................................................................. 78
Table 18: Summary of IR Results (Project No. 4 - JP3099, RT 36) ............................................................... 80
Table 19: Summary of IC Results (Project No. 4 - JP3099, RT 36) ............................................................... 82
Table 20: Summary of IR Results (Project No. 5 - J2P3100, RT 36) ............................................................. 83
Table 21: Summary of IC Results (Project No. 5 - J2P3100, RT 36) ............................................................. 85
Table 22: Summary of IR Results (Project No. 6 - J2P3051, RT 24) ............................................................. 89
Table 23: Summary of IC Results (Project No. 6 - J2P3051, RT 24) ............................................................. 91
Table 24: Summary of IR Results (Project No. 7 - J1P3005, RT 24) ............................................................. 94
Table 25: Summary of IC Results (Project No. 7 - J1P3005, RT 24) ............................................................. 96
Table 26: Summary of IR Results (Project No. 8 - J9P3161, RT 17) ........................................................... 100
Table 27: Summary of IC Results (Project No. 8 - J9P3161, RT 17). .......................................................... 102
Table 28: Summary of IR Results (Project No. 9 - J6S3123, RT 61) ........................................................... 105
Table 29: Summary of IC Results (Project No. 9 - J6S3123, RT 61) .......................................................... 107
Table 30: Summary of IR Results (Project No. 10 - J7I3072, RT 49) .......................................................... 110
Table 31: Summary of IC Results (Project No. 10 - J7I3072, RT 49) .......................................................... 112
Table 32: Summary of IR Results (Project No. 11 - J1S3028, RT 69) ......................................................... 117
Table 33: Summary of IC Results (Project No. 11 - J1S3028, RT 69) ......................................................... 119
Table 34: Summary of IR Results (Project No. 12 - J5P3170, RT 5) ........................................................... 121
Table 35: Summary of IC Results (Project No. 12 - J5P3170, RT 5). .......................................................... 123
Table 36: Summary of IR Results (Project No. 13 - J9P3296, RT 17) ......................................................... 126
Table 37: Summary of IC Results (Project No. 13 - J9P3296, RT 17) ......................................................... 128
Table 38. Completion of IC-IR Data Collection. ......................................................................................... 138
Table 39. Completion of IC-IR Check Lists and Forms. .............................................................................. 139
10
Acknowledgement
The authors graciously thank the FHWA Accelerated Innovation Deployment (AID) program
and MoDOT for funding these IC and IR projects. The authors would also express gratitude
towards those IC and IR vendors, dealers, and contractors for their assistance and cooperation
during the field projects and subsequent data collection and analysis.
Disclaimer
The opinions, findings, and conclusions expressed in this document are those of the
investigators. They are not necessarily those of the Missouri Department of Transportation, U.S.
Department of Transportation, or Federal Highway Administration. This information does not
constitute a standard or specification.
11
Acronyms and Symbols
AID : Accelerated Innovation Deployment, one FHWA’s programs to support innovative
highway technologies
CCV : Compaction Control Value, a type of ICMV manufactured by Sakai
CMV : Compaction Meter Value, a type of ICMV manufactured by German’s Volkel, used by
Caterpillar, Trimble, Dynapac, and Volvo
DMI : Distance Measurement Instrument
EDV: Estimated Density Value, a type of ICMV manufactured by Volvo
GNSS: Global Navigation Satellite System
GPS: Global Positioning System
IC : Intelligent Compaction
ICMV: Intelligent Compaction Measurement Values, a generic term for various solutions from
the industry
IR: Infrared Scanning
OEM : Original Engineering Manufacture
PMTP : Paver-Mounted Thermal Profiles
PPM: PaveProj Program, MOBA’s software program for the PAVE-IR thermal profile system
QA : Quality Assurance
QC : Quality Control
RE: Resident Engineers
12
Introduction
Project Scope
The Missouri Department of Transportation (MoDOT) was awarded a grant from the FHWA
Accelerated Innovation Deployment (AID) program in 2016. MoDOT provided the required
matching funding to support this Intelligent Compaction (IC) and Infrared Scanning (IR) Field
Projects with Consulting Support in 2017. The term “IC” is defined in the AASHTO PP81-17
terminology. The term “IR” is equivalent to the AASHTO PP80-17 terminology for Paver-
Mounted Thermal Profiles (PMTP).
The consulting support provided by the Transtec Group (Consultant) includes the development
of MoDOT IC-IR protocols and training materials, conducting IC-IR training, on-site technical
support to IC-IR field projects, and analysis and reports of IC-IR field data.
The first MoDOT IC-IR contract (No. TR2176) was funded by the AID grant and matching
funds, included support for ten (10) field projects. The second MoDOT IC-IR contract (No.
TR20182) was funded by MoDOT to add support tasks for three additional IC-IR field projects.
Therefore, a total of thirteen (13) IC-IR field projects were performed under these two contracts.
This report provides a summary of the two combined projects, including field test results,
lessons-learned and recommendations. In additional to this final report, other reports produced
under these projects include:
• MoDOT IC-IR Protocol: guidelines to plan and conduct IC-IR project
• MoDOT IC-IR workshop handouts: handout materials for workshop participants
• Individual MODOT IC-IR field project reports: 13 reports for the field projects
13
Innovative Technologies
The following is a comprehensive description of the main innovative technologies used for this
project: IC, IR, and Veta software.
IC Technologies
Intelligent compaction is an equipment-based technology to improve quality control of
compaction. IC vibratory rollers are equipped with a high precision global positioning system
(GPS), infrared temperature sensors, an accelerometer-based measurement system, and an
onboard tablet computer for real time display of color-coded maps (e.g., passes, temperature,
Intelligent Compaction Measurement Values, ICMV, etc. as shown in Figure 1). GPS is used
interchangeably with Global Navigation Satellite System (GNSS) in this report. IC can be used
to improve compaction control for various pavement materials including granular and clayey
soils, subbase materials, and asphalt materials. The accelerometer-based measurement system,
ICMV, is a core IC technology that was invented in the early 80’s and is still evolving today.
Courtesy of Volvo
Figure 1. Example of IC Color-coded Displays for Roller Passes, Asphalt Temperatures,
and ICMV.
IC systems are available in two forms: Original Engineering Manufacture (OEM, Figure 2) and
after-market IC retrofit (Figure 3). The OEM is directly from roller vendor’s factory. The IC
retrofit can be mounted on selected models of rollers.
14
Figure 2. Examples of OEM Double-Drum IC Rollers.
15
Figure 4. Method of Measuring and Calculating ICMV.
A recent FHWA IC Technical Brief provides a comprehensive description of ICMV and a
classification system based on its correlation with in-situ spot tests, whether valid when drum-
materials decouple, and whether it can be used to produce layer-specific mechanical properties.
Table 1 and Table 2 summarize key information from this Tech Brief.
Table 1. Summary of ICMV Model and Methods (FHWA ICMV Tech Brief).
16
Table 2. Classification of ICMV Levels (FHWA ICMV Tech Brief).
The ICMVs used for the MoDOT field projects included: Compaction Meter Value (CMV),
Compaction Control Value (CCV), and Estimated Density Value (EDV). The first two were
considered a Level 1 solution, while the third is not classified due to lack of third-party field
validation test data.
The IC systems used for the 13 MoDOT field projects included: OEM Caterpillar system, OEM
Volvo System, Trimble IC retrofit system, and TOPCON IC retrofit system. Wireless
transmitting of IC data to the vendors’ cloud was available for all of these systems except Volvo.
The Caterpillar and Trimble systems use VisionLink, while the TOPCON system uses
SITELINK3D. The cloud solution can prevent data loss and make future “direct import of data
from the cloud to Veta” feature possible. The limitation of using wireless data transmission is
cellular signal coverage in remote project locations. Machine-to-machine communication was
not available for the IC systems used under this project.
17
IR Technologies
The IR or PMTP systems make use of infrared scanners or thermal imaging techniques to
measure asphalt mat temperatures right behind the paver (Figure 5). The IR system is equipped
with GPS and a DMI to track the positions of thermal profiles and paver speeds (Figure 6). The
IR system used for the 13 field projects was the MOBA PAVE-IR system. Wireless transmitting
IR data to the vendors’ cloud was available for the MOBA PAVE-IR system.
Courtesy of MOBA
Figure 5. An Illustration of an IR System.
18
Figure 6. An Example of IR Display of Thermal Profiles and Paver-Speed.
19
Veta Software
Veta is a public-domain standardized software for IC and IR analysis. It is required in the
AASHTO PP81-17 specifications and most State Highway Agency (SHA) IC specifications. The
Consultant developed and is continuously enhancing Veta with the funding from the
Transportation Pooled Fund study, “TPF-5(334) Enhancement to the Intelligent Construction
Data Management System (Veta) and Implementation”.
Veta can import data from various IC machines and MOBA PAVE-IR thermal bars and scanners
to perform editing, data layering, point testing, and analysis (Figure 8). IC data are collected as
raw ungridded data as one point across the drum. The raw IC data are then gridded typically in 1
ft. X 1 ft. cells to better track detailed positions of roller coverage (Figure 9). The “all-passes” IC
data include all IC data through the entire compaction process. The final coverage is the final
product or the “bird’s-eye view” of the IC data layers (Figure 10). Veta now imports all-passes
data and produce final coverage data. Veta displays compaction information in easy-to-read
formats, including graphs and maps (Figure 11). Veta was used for all IC and IR analysis under
this project.
20
Figure 8. IC and IR Data Flow to Veta.
21
Figure 10. IC All-Passes Data and Final Coverage data.
22
Work Plan
The work plan for this project included five (5) main tasks.
• Task 1 – Kick Off Meeting
• Task 2 – IC-IR Data Management Protocol
• Task 3 – IC-IR Training Courses
• Task 4 – IC-IR Field Project Supports
• Task 5 – IC-IR Specifications
The timeline and deliverable schedule for all tasks are summarized below in Table 3.
X Contractor's effort
O MoDOT reviews
Schedule for project field support will depend on the paving schedule.
23
Deliverables include the IC-IR Data Management Protocol document.
One of the key components of the training courses was to train MoDOT staff and contractors
how to take advantage of IC and IR technologies for their own QC and Quality Assurance (QA)
benefits. The training stressed on trouble shooting in the field to ensure adequate IC-IR
operations and data collection.
24
Task 4-3: IC-IR Data Analysis
The Contractor conducted IC-IR data analysis for each field project. The analysis includes data
observations, statistics analysis and correlation analysis to indicate any issues and evaluate the
quality levels with field operations.
25
IC-IR Protocol
Summary of IC-IR Protocol Elements
The MODOT IC-IR Protocol (Figure 12) is a stand-alone document that includes the protocol to
manage intelligent compaction and infrared scanning data for the IC-IR field projects. The goal
is to ensure IC, IR, and associated data and derivative files are properly collected, stored, and
managed.
26
• Communication Methods
2. Data File Sharing
• MoDOT SharePoint
• Data Folder Structure
• Data Types
• Data File Naming Convention
3. Pre-Paving Setup and Checks
• IC System Setup and Checks
• IR Scanner System Setup and Checks
4. Paving Operation Records and Data
• Project Information
• Daily Paving Record
• Summary of Paving Activities and Machine Settings
• Summary of IR and IC Analysis Results
• Data Management
IC Data Management
GPS Daily Production Boundary Managements
IR Data Management
Data Files Inventory
Key elements of the MODOT IC-IR Protocol are described below. Further details can be found
in the actual MODOT IC-IR Protocol document.
27
Contractor's Check List
Route
Job No.
Date
Contractor
Yes No
Conduct IC GPS verification..
Conduct IR scanner DMI calibration.
Construct a trial section.
Record and export IC data.
Record and export daily production boundaries.
Record IR scanner data.
Record spot test data.
Create a Veta project file for IC data.
Produce MOBA IR Segment Report.
Fill daily paving record form.
Transmit all files to MoDOT SharePoint.
Notes
28
Route: Job No.
IC System:
IR System:
GNSS Ref:
Date:
Start time: Start Milepost: Length (ft): 0
Stop Time: Stop Milepost: HMA (tons):
GPS Verification
Nothing (m) Easting (m) Diff. (mm) < 30mm?
IC GPS Y
Rover Y
Trial Section
Opt Passes
Patterns
Paving
Direction Lane Lift Width (ft) Thickness (")
Compaction
Position Roller Passes Static/Vib Amp (mm) Freq (vpm)
Breakdown
Intermediate
Finishing
Notes
Submitted:
Figure 14: Contractor’s Daily Paving Record Form.
29
RE's Daily Check List
Route
Job No.
Date
RE
Yes No
Record daily field diaries.
Review IC Veta Project file submitted by contractor.
Review IR segment report submitted by contractor.
Transmit daily diaries to MoDOT SharePoint.
Notes
30
File Naming Convention
The standard data file convention (Table 4) was recommended to facilitate data file management.
The recommended file naming convention for the root name in this protocol is:
[job no]-[date]-[data Type].[extension]
Where:
[job no] : MoDOT field project job number (e.g., 2P3051) in 6 alpha-numeric
characters.
[date] : paving date in YYYMMDD.
[data type] : data type in 3 characters (see definition in Table 4.)
[extension] : data file extension.
31
naming convention will be used, such as: 2P3051-ICD.vetaproj, 2P3051-IRD.vetaproj.
• If MoDOT elects to use alignment files from design, the naming convention can be: [job
no]-[date]-ALN.kmz.
MoDOT SharePoint
The MoDOT SharePoint has been essential for all parties to share data files for the field projects.
Each project was assigned with a project folder (Figure 16).
Each field project folder will have the subfolders to store specific types of data (Figure 17):
Analysis files (analysis spreadsheet files)
GPSdata (GPS validation files and daily production boundary spreadsheet files)
IC data (raw IC data files and notes)
IRData (raw IR data files and IR PDF report files)
Notes_Reports (notes and report files)
PhotoVideos (field photo and video files)
SpotTest (spot test data spreadsheet files)
Veta (Veta project and report files)
32
Figure 17: MoDOT SharePoint IC-IR Project Sub-Folders.
Contactors were required to transmit the following data to the respected sub-folders:
• Contractor’s daily check list form,
• Daily paving record form,
• IC data,
• IR PDF reports,
• GPS paving boundary,
• Spot test data (core or nuke), and
• Photos (if any).
REs were required to transmit the following data to the respected sub-folders
• RE’s daily check list form,
• Daily diaries,
• Photos (if any)
The Consultant managed all data files in all sub-folders. All essential IC-IR documents (e.g.,
check lists, standard forms, protocol, workshop handouts, trial section spreadsheet, etc.) were
also uploaded to the SharePoint folders.
IC-IR Training
Training Materials
The Consultant developed IC-IR training materials in a package that includes:
• Workshop agenda
• Workshop trainers’ information
• Veta software and support
• Workshop slides
33
• Instructions for hands-on sample files
The workshop agenda is shown in Figure 18, below. The IC-IR workshop handout documents
include all the elements mentioned above.
Workshop Agenda
Objectives
• To familiarize attendees with the intelligent compaction (IC), infrared (IR) thermal
profiling and Veta software.
• To review the State Specifications, and protocol.
• To inform attendees of the advantages, limitations, and troubleshooting IC and IR
data.
• To provide an interactive and hands-on approach throughout the workshop.
Agenda
AM
08:00 am Session 1 – IC-IR Setup and Data Collection
08:45 am Hands-on Exercises
10:00 am Break
10:15 am Session 2 – Data Analysis with Veta
10:45 am Hands-on Exercises
11:45 am Break (Lunch)
PM
01:15 pm Session 3 – Trouble Shootings
01:45 pm Hands-on Exercises
02:45 pm Break
03:00 pm Hands-on Exercises
04:00 pm Adjourn
34
Training Workshops
The training workshops (Table 5, Figure 19) were scheduled to be as close as possible to the start
of paving of the field projects.
Paving
No. Job No. District County Route Start Date End Date Days
1 J5P3117 CD Morgan 52 5/9/2017 7/13/2017 19
2 J4I3111 KC Clay 29 8/18/2017 9/16/2017 7
3 J3I3042 KC Lafayette 70 8/14/2017 9/22/2017 19
4 J2P3099 NE Macon 36 5/8/2017 5/17/2017 7
5 J2P3100 NE Macon 36 5/25/2017 6/21/2017 12
6 J2P3051 NE Randolph 24 10/21/2016 11/3/2016 8
7 J1P3005 NW Chariton 24 4/24/2017 5/17/2017 10
8 J9P3161 SE Texas 17 9/28/2017 10/19/2017 11
9 J6S3123 SL Jefferson 61 5/31/2017 6/9/2017 9
10 J7I3072 SW McDonald 49 6/5/2017 7/6/2017 13
11 J1S3028 NW Daviess 69 6/29/2017 7/7/2017 5
12 J5P3170 CD Cooper 5 9/8/2017 9/19/2017 10
13 J9P3296 SE Texas 17 7/5/2017 8/18/2017 16
36
The IR and IC systems used for each of the MoDOT IC-IR field projects is listed in Table 7.
The contractor codes (1 to 8) are used for this report for protection of privacy and confidentiality.
37
The locations for the MoDOT IC-IR field projects and workshops are shown in Figure 20.
Training
0 4 -RT36
5 1 1 -RT69
0 5 -RT36
06-RT24
07-RT24
0 2 -RT29
6 0 3 -RT70
1 2 -RT5
3
1 7
0 1 -RT52
0 9 -RT61
0 8 -RT17
1 3 -RT17
2
4
1 0 -RT49
38
Data Analysis and Results
IR Data Analysis
The IR data was analyzed using the MOBA PaveProj Program (PPM) reports as per the MoDOT
IR specification. Veta (version 4.1) analysis reports were generated for informational purposes.
Veta uses the AASHTO PP 80-17 method to compute the “Range” values by taking the
differences between the 98.5-percentile value and 1-percentile value of thermal profile data with
a given 150 ft. sublot. The areas of any paver stop, 2 ft. before and 8 ft. after, were excluded
from temperature differential computation as per AASHTO PP 80-17 specification (Figure 21).
MOBA indicates that the intention of this exclusion is to capture temperature segregation during
“normal paving operation”.
The remaining data are used to calculate the Range value, 98.5th percentile – 1th percentile
(Figure 22). The classification of temperature segregation is based on the Range value as
follows: Low (Range ≤ 25.0 °F); Moderate (25.0 °F < Range ≤ 50.0 °F); and Severe (Range >
50.0 °F), as shown in Figure 23. The temperature segregation based on the above analysis
method does not consider the effects of paver stops.
Figure 21: AASHTO PP80 IR Analysis Method: 10’ exclusion around a paver stop
location
39
Figure 22: AASHTO PP80 IR Analysis Method: Computation of “Range” value
40
An example of IR data analysis from the August 14, 2017 data from J3I3042 RT 70 is shown in
Figure 24. The MOBA PAVE-IR data were downloaded from eRoutes, and the corresponding
MOBA PPM screenshot shown below. Note that there is erroneous time/speed data around
4,000 ft.
The MOBA PPM report indicates 57% no segregation, 38% moderate segregation, and 5%
severe segregation (Table 8). The MOBA PPM report is the data source used to determine
incentive/disincentive according to the IR Job Special Provision (JSP).
41
Table 8. Example of MOBA PPM IR Analysis Report of Temperature Segregation.
The MOBA raw data were imported to Veta, and Figure 25 shows the Veta Viewer screen of IR
data plot on a satellite base map for the project.
Figure 25: Example of Veta Viewer screen of IR data plots (J3I3042, RT70).
42
A Veta filter group is created to use Data Filters to exclude temperatures under 180°F and an
Operation Filter/Cold Edge filter to exclude any cold temperatures from adjacent existing
pavement/shoulder surfaces (Figure 26). Note that the IR data uploaded to VETA was for
research purposes and was not used to evaluate incentive/disincentive.
43
Further, 150-ft sublots were created for analysis (Figure 27).
44
Note the data gap at a bridge in the screenshot in Figure 28. The data gap is due to the fact that
there was no HMA placed on the bridge, and since the temperature of the surface was below the
threshold of 80oC, the data was filtered out by the MOBA. However, it is recommended that the
MOBA system be left “ON” while the paver mobilizes across a bridge (or similar situation) as
the distance data is continued to be collected and is used in data analysis.
Figure 28: Example of a Veta Sublot screen for IR data analysis (J3I3042, RT70).
A typical Veta analysis setup for this set of IR data is shown in Figure 29.
Figure 29: Example of a Veta Analysis setup for IR data analysis (J3I3042, RT70).
45
A typical Veta thermal profile, time diagram, and paver speed plot are shown in Figure 30. The
vertical black bar in the thermal profile, along with the time diagram plot and the paver speed,
indicates a paver stop for approximately 14 minutes at an approximate distance of 3,800 ft. from
beginning of the paving operation.
The Paver Stop map (Figure 31) plots a pink circle indicating paver stop locations, and text
indicating stop duration in minutes.
46
A sample Veta temperature differential report is shown in Figure 32. The reported length is
9,038 ft. (approximately 600 ft. different from the MOBA reported length).
47
IC Data Analysis
Roller Passes
The IC coverage analysis was based on the optimum pass count. The rolling pattern should
depend on the asphalt mix and decision by the RE and the contractor. The optimum pass count is
determined by the trial section. That may consist of vibratory passes, static passes, or a
combination of both. The “Roller Coverage” for each day of paving was classified according to
the percentage of paved area which met or exceeded the optimum number of rolling passes based
on the MoDOT Specification shown in Table 9.
ICMV
The target ICMV can be determined based on the correlation between the ICMV data and
acceptance spot tests from the trial section (Figure 33). The requirements for the acceptable
correlation between ICMV and acceptance spot tests is R< 0.7 or R2 < 0.5, based on most of the
international IC specifications.
Figure 33: Target ICMV determined by Correlation between ICMV and Acceptance Spot
Tests from Trial Section Data.
48
Note that ICMV and acceptance spot tests are often fundamentally different mechanisms and not
all ICMV methods are equal. The FHWA ICMV Tech Brief provides additional details on this
issue (FHWA-HIF-17-046).
49
Since ICMV is measured only with vibratory passes, the projects that use only static passes or
mix of vibratory/static passes did not have sufficient ICMV data for further analysis. When
vibratory passes are used but without companion acceptance spot tests, the target ICMV and
optimal passes can be determined based on the ICMV compaction curve where the increment of
ICMV with each subsequent pass is less than 5% (Figure 35).
Figure 35: Target ICMV determined by an ICMV Compaction Curve when Acceptance
Spot Tests from Trial Section Data are Not Available.
The target ICMV coverage was based on MoDOT IC specification, as shown in Table 10.
Mat Temperature
Based on MoDOT Specification Section 403.15 (Figure 36), during vibratory compaction, the
internal asphalt mat temperature requirement should be > 225 °F for non-warm mix or > 200°F
for warm mix paving. Consideration is given to the fact that the IC roller collects surface
temperatures while the intent of this specification is for internal temperatures.
50
Figure 36: MODOT Requirement for Mat Temperatures during vibratory compaction.
The Veta analysis for the temperature requirement makes use of a data filter for vibratory passes
only and an analysis setup for the target temperature coverage (Figure 37). While as
demonstrated in Figure 37, the capability exists with Veta to exclude vibratory passes under a
given temperature. However, due to the differences between roller surface temperature
measurements and internal temperatures, these passes were not excluded for the pilot projects.
51
Analysis Example
An example of a complete IC analysis is presented below for the J1P3005 RT 24 project on
4/24/2017.
93
92
91.6
91.3
91 90.5 STATIC STATIC
VIBRATING
90
Density
89 89.1
VIBRATING
88
Average
87 Spot 1
86.8 Spot 2
VIBRATING Spot 3
86 Spot 4
Spot 5
85
0 1 2 3 4 5 6
Pass
Figure 39: Compaction Curve from the Trial Section on 4/24/2017 (J1P3005 RT 24).
52
The VisionLink IC data file was imported to Veta for analysis. Figure 40 shows the pass count
map.
Figure 40: An Example Veta Analysis Screen showing Pass Count map (J1P3005 RT 24).
53
Two filter groups were created, or Section 1 and Section 2 (Figure 41). A third filter group was
created by combining both sections.
Figure 41: An Example Veta Analysis Screen showing Filter Groups (J1P3005 RT 24).
54
Spot test data of core density were imported to Veta’s Spot Test Screen (Figure 42). The four
core density tests correspond to the second set of four test locations within the trial section.
Figure 42: An Example Veta Analysis Screen showing spot tests (J1P3005 RT 24).
55
The first round of the IC analysis is used to inspect the correlation analysis between CMV and
core density (Figure 43). Since the R2 is 0.62, it is valid to use the linear correlation to calculate
the target CMV based on 92% Gmm for the core density data. The resulting target CMV is 10.68.
Figure 43: An Example Veta Analysis Screen showing correlation tests between ICMV and
spot tests (J1P3005 RT 24).
The roller coverage for the target passes (four) is 95% (Figure 44), which passes the 90%
requirement criteria. The ICMV coverage for the target ICMV is 92% (Figure 45), which passes
the 70% criteria (i.e., not flagged).
56
Figure 44: An Example Veta Analysis Screen showing the Roller Coverage report
(J1P3005 RT 24).
Figure 45: An Example Veta Analysis Screen showing the ICMV Coverage report
(J1P3005 RT 24).
57
Another filter group is created for vibratory passes only. The temperature requirement was set to
the specification criteria of 225°F. The coverage for vibratory passes at or above the target
temperature is 51% (Figure 46), which fails the criteria of 100% (based on the MoDOT
specification requirements).
Figure 46: An Example Veta Analysis Screen showing the Mat Temperature report
(J1P3005 RT 24).
58
Summary of Results
An individual report was produced for each field project (Figure 47). The trial section
compaction curve, summary of MOBA/Veta temperature segregation reports, and summary of
IC roller coverage reports are presented for each project, below.
59
Project No. 1 - J5P3117, RT 52
Figure 48 Compaction Curve from the Trial Section on 5/9/2017 (Project No. 1 - J5P3117,
RT 52).
60
Trial Section (5/12/2017)
Optimum Rolling Pattern: The compaction curve is shown in Figure 49. The rolling pattern
established was four vibratory passes at high frequency and high amplitude with the breakdown
IC rollers, followed by four static passes by the intermediate double drum roller, and four passes
by the pneumatic roller.
Figure 49 Compaction Curve from the Trial Section on 5/12/2017 (Project No. 1 - J5P3117,
RT 52).
A summary of IR results is shown in Table 11, Figure 50, and Figure 51. Most of the
temperature segregation was in the “no segregation” and “moderate segregation” categories.
61
Table 11: Summary of IR Results (Project No. 1 - J5P3117, RT 52)
MOBA PPM Veta*
Day Date Low Moderate Severe Low Moderate Severe
# % # % # % # % # % # %
1 5/9/2017 33 48 33 48 3 4 33 53 27 44 2 3
2 5/10/2017 22 61 14 39 0 0 23 62 14 38 0 0
3 5/12/2017 38 63 22 37 0 0 44 71 18 29 0 0
4 5/13/2017 33 46 38 54 0 0 41 56 32 44 0 0
5 5/15/2017 65 73 24 27 0 0 78 85 14 15 0 0
6 5/16/2017 21 27 56 73 0 0 39 49 40 51 0 0
7 5/18/2017 46 61 29 38 1 1 47 60 31 39 1 1
8 6/5/2017 58 75 19 25 0 0 62 78 18 22 0 0
9 6/6/2017 37 61 24 39 0 0 46 73 17 27 0 0
10 6/7/2017 48 57 36 42 1 1 58 67 29 33 0 0
11 6/26/2017 12 38 17 59 1 3 13 44 16 53 1 3
12 6/27/2017 67 62 37 80 5 5 5 38 7 54 1 8
13 6/28/2017 67 62 37 35 3 3 72 73 25 26 1 1
14 6/29/2017 30 65 16 35 0 0 32 67 16 33 0 0
15 7/6/2017 59 79 15 20 1 1 63 81 15 19 0 0
16 7/10/2017 59 79 13 18 2 3 66 86 8 11 2 3
17 7/11/2017 62 73 15 18 8 9 68 77 14 16 6 7
18 7/12/2017 22 92 2 8 0 0 23 96 1 4 0 0
19 7/13/2017 32 75 10 23 1 2 38 86 6 14 0 0
*. Veta results are for information only.
Notes:
62
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Paving Dates
Figure 50: Summary of MOBA PPM Temperature Segregation Report (Project No. 1 -
J5P3117, RT 52).
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Paving Dates
Figure 51: Summary of Veta Temperature Segregation Report (Project No. 1 - J5P3117,
RT 52).
63
Note that the roller coverage reports are missing for Days 8, 11, and 15 due to malfunctioning of
the IC system. The roller coverage results were mixed without apparent trends of improvement.
8 6/5/2017 _ _ _
11 6/26/2017 _ _ _
15 7/6/2017 _ _ _
Total
Notes:
* Not a na l yzed s i nce no ta rget ICMV wa s determi ned from tri a l s ecti ons .
64
Again, the roller coverage reports are missing for Days 8, 11, and 15 due to malfunctioning of
the IC system. The roller coverage results were mixed without apparent trends of improvement.
100
90
80
Roller Coverage (%)
70
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Paving days
Figure 52: Summary of Roller Coverage Report (Project No. 1 - J5P3117, RT 52).
65
Project No. 2 - J4I3111, RT 29
Trial section tests were conducted on 8/25/2017 and 8/26/2017 for the SP190B and SP095B
mixtures, respectively.
Compaction Curve
98
96 95.55
94.55 94.575
94 94
92
Density
90.675
90 89.85
88.75
88
Average
86
84
82 81.95
80
1 2 3 4 5 6 7 8
Pass
Figure 53 Compaction Curve SP190B from the Trial Section on 8/25/2017 (Project No. 2 -
J4I3111, RT 29).
66
Trial Section – 8/26/2017 (SP095B)
Optimum Rolling Pattern: The compaction curve is shown in Figure 54. The rolling pattern
established was five vibratory passes for the breakdown IC rollers. From observations from the
data, the rollers were set to operate at low frequency and low amplitude.
Figure 54 Compaction Curve SP095B from the Trial Section on8/26/2017 (Project No. 2 -
J4I3111, RT 29).
A summary of IR results is shown in Table 13, Figure 55, and Figure 56. There was moderate
temperature segregation with limited severe segregation. Note that MOBA PPM results are not
available for Days 6 and 10 due to missing raw data, and Veta IR results were not available for
Day 10 due to missing raw data. Note that Day 12 results from MOBA PPM and Veta are
significantly different.
67
Table 13: Summary of IR Results (Project No. 2 - J4I3111, RT 29)
# % # % # % # % # % # %
1 SB/2/Base 8/25/2017 14 74 4 21 1 5 9 50 8 44 1 6
2 SB/2/Surface 9 60 5 33 1 7 5 36 8 57 1 7
8/26/2017
3 SB/3/Base 37 82 6 13 2 4 28 64 13 30 3 7
4 SB/3/Surface 8/27/2017 41 91 3 7 1 2 25 57 16 36 3 7
5 NB/2/Base 16 67 7 29 1 4 29 63 13 28 4 9
9/9/2017
6 SB/1/Base ** 30 65 13 28 3 7
7 NB/1/Base 17 68 5 20 3 12 22 48 19 41 5 11
8 NB/1/Surface 40 83 7 15 1 2 27 59 15 33 4 9
9/10/2017
9 NB/2/Surface 21 44 20 42 7 15 10 22 30 65 6 13
10 SB/1/Surface **
11 NB/3/Base 9/15/2017 28 97 1 3 0 0 27 87 3 10 1 3
12 NB/3/Surface 9/16/2017 39 85 5 11 2 4 10 22 24 52 12 26
* Veta results are for information only.
Notes:
** Data missing.
68
Again, the MOBA PPM results are not available for Days 6 and 10 due to missing raw data, and
Veta IR results were not available for Day 10 due to missing raw data.
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12
Paving Days
Figure 55: Summary of MOBA PPM Temperature Segregation Report (Project No. 2 -
J4I3111, RT 29).
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12
Paving Days
Figure 56: Summary of Veta Temperature Segregation Report (Project No. 2 - J4I3111, RT
29).
69
Table 14 and Figure 57 provide a summary of the roller coverage results. The roller coverage
results were mixed without apparent trends of improvement.
Notes: Minimum temprarture for vibratory passes is 200F since Warm Mix Technology was used.
* Not ca l cul a ted
70
100
90
80
70
Roller Coverage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12
Paving days
Figure 57: Summary of Roller Coverage Report (Project No. 2 - J4I3111, RT 29).
71
Project No. 3 - J3I3042, I-70
Figure 58: Density Compaction Curve from the Trial Section on 8/14/2017 (Project No.
3-J3I3042, I-70)
The Volvo ICMV-EDV were extracted from test locations of the trial section. The compaction
curves from both the nuclear density gauge (NDG) and EDV are compared in the Figure 59.
72
96
94
92
Density (%Gmm)
90
88
86
84
82
1 2 3 4 5 6 7 8 9
Passes
EDVday1 NDG
Figure 59: NDG Density and ICMV Compaction Curves from the Trial Section on
8/14/2017 (Project No. 3 - J3I3042, I-70)
A summary of IR results is shown in Table 15 and Table 16, and Figure 60 through Figure 63.
There was no noticeable severe temperature segregation for most paving days, with the exception
of Day 6, which showed severe temperature segregation. The lack of use of MTV may be one of
factors causing the severe temperature segregation on Day 6.
The MOBA PPM report for Day 5 (8/23/2017), shown in Figure 60, includes an 10,000-ft. offset
error in DMI. The reported length is only 3,088 ft., but the actual length is 13,215 ft. Therefore,
the reported number of sublots are incorrect due to the incorrect DMI (see Table 16). Since Veta
uses GPS as references, the Veta IR report, shown in Figure 61, is correct since it is not
influenced by the incorrect DMI. The Veta reported length is 13,215 ft. The actual length was
further verified by the IC data. Note that Day 5 results in Figure 62 are incorrect since the
MOBA PPM used incorrect DMI references, while the Day 5 result in Figure 63 are correct since
Veta uses GPS reference instead of DMI.
73
Table 15: Summary of IR Results (Project No. 3 - J3I3042, I-70)
MOBA PPM Veta*
Day Date Low Moderate Severe Low Moderate Severe
# % # % # % # % # % # %
1 8/14/2017 37 57 25 38 3 5 37 62 21 35 2 3
2 8/15/2017 43 70 18 30 0 0 42 70 18 30 0 0
3 8/17/2017 42 59 28 39 1 1 44 62 27 38 0 0
4 8/18/2017 27 56 20 42 1 2 27 59 18 39 1 2
5 8/23/2017 2 10 17 81 2 10 55 63 31 35 2 2
6 8/24/2017 2 8 0 0 23 92 2 8 0 0 23 92
7 8/25/2017 26 42 34 55 2 3 27 44 33 54 1 2
8 8/28/2017 56 58 41 42 0 0 48 49 49 51 0 0
9 8/29/2017 43 54 36 45 1 1 39 49 40 51 0 0
10 8/30/2017 34 52 30 46 1 2 28 43 35 54 2 3
11 8/31/2017 34 34 60 61 5 5 30 31 61 64 5 5
12 9/5/2017 37 47 42 53 0 0 37 47 41 53 0 0
13 9/6/2017 46 47 51 53 0 0 45 47 51 53 0 0
14 9/7/2017 37 45 41 50 4 5 39 48 40 49 2 2
15 9/8/2017 51 54 42 45 1 1 53 57 39 42 1 1
16 9/11/2017 60 61 39 39 0 0 60 61 38 39 0 0
17 9/12/2017 43 49 42 48 2 2 40 47 45 52 1 1
18 9/13/2017 29 56 22 42 1 2 29 55 22 42 2 4
19 9/22/2017 10 56 7 39 1 6 8 47 9 53 0 0
Notes: *. Veta results are for information only.
74
Figure 60: Incorrect distance reported by MOBA PPM for the data on 8/23/2017 (J3I3042,
I-70).
Table 16: Incorrect number of sublots reported by MOBA PPM for the data on 8/23/2017
(Project No. 3 - J3I3042, I-70).
75
Figure 61: Correct IR Segregation Reported by Veta for the data on 8/23/2017 (Project No.
3 - J3I3042, I-70).
76
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Paving Dates
Figure 62: Summary of MOBA PPM Temperature Segregation Report (Project No. 3 -
J3I3042, I-70).
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Paving Dates
Figure 63: Summary of Veta Temperature Segregation Report (Project No. 3 - J3I3042, I-
70).
77
Table 17 and Figure 64 provide a summary of the roller coverage results. The roller coverage
results were mixed but the trend indicated slight improvements as the project progressed. The IC
data on 8/23/2017 (Day 5) included an incorrect boundary file provided by the contractor (see
the tangled lines of boundary in Figure 65). Therefore, no roller coverage analysis could be
performed for this date.
78
The IC data on 8/23/2017 (Day 5) included an incorrect boundary file provided by the contractor.
Therefore, no roller coverage analysis could be performed for this date.
100
90
80
Roller Coverage (%)
70
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Paving days
Figure 64: Summary of Roller Coverage Report. (Project No. 3 - J3I3042, I-70)
Figure 65: Incorrect Boundary File for 8/23/2017 (Project No. 3 - J3I3042, I-70).
79
Project No. 4 - JP3099, RT 36
A summary of IR results is shown in Table 18, Figure 66, and Figure 67. The temperature
segregation was mostly in “No Segregation” and “Moderate Segregation” categories with very
limited severe temperature segregation.
# % # % # % # % # % # %
1 5/8/2017 43 53 37 46 1 1 48 59 30 37 4 5
2 5/9/2017 57 75 18 24 1 1 58 75 18 23 1 1
3 5/10/2017 42 76 16 24 0 0 50 72 18 26 1 1
4 5/11/2017 19 70 7 26 1 4 20 77 4 15 2 8
5 5/15/2017 94 94 6 6 0 0 93 92 8 8 0 0
6 5/16/2017 70 79 19 21 0 0 67 74 24 26 0 0
7 5/17/2017 58 87 9 13 0 0 56 82 12 18 0 0
*. Veta results are for information only.
Notes:
80
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7
Paving Dates
Figure 66: Summary of MOBA PPM Temperature Segregation Report (Project No. 4 -
JP3099, RT 36).
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7
Paving Dates
Figure 67: Summary of Veta Temperature Segregation Report (Project No. 4 - JP3099, RT
36).
81
Table 19 and Figure 68 provide a summary of the IC results. The roller coverage results were
mixed but the trend indicated improvements as the project progressed.
Table 19: Summary of IC Results (Project No. 4 - JP3099, RT 36)
Target Passes Target ICMV Temperature for vibrotory
No. Date
% Coverage Classification % Coverage Classification % Coverage Classification
1 5/8/2017 50 Failed NA NA 17 Failed
100
90
80
70
Roller Coverage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7
Paving days
Figure 68: Summary of Roller Coverage Report (Project No. 4 - JP3099, RT 36).
82
Project No. 5 - J2P3100, RT 36
A summary of IR results is shown in Table 20, Figure 69, and Figure 70. The temperature
segregation was mostly in “No Segregation” and “Moderate Segregation” categories with very
limited severe temperature segregation.
2 5/30/2017 47 82 7 12 3 5 48 83 5 9 5 9
3 5/31/2017 60 91 6 9 0 0 60 90 7 10 0 0
4 6/1/2017 27 84 5 16 0 0 26 81 6 19 0 0
5 6/5/2017 60 79 13 17 3 4 62 82 12 16 2 3
6 6/6/2017 49 75 16 25 0 0 56 85 10 15 0 0
7 6/12/2017 76 75 25 25 0 0 74 72 28 27 1 1
8 6/13/2017 25 74 9 26 0 0 27 79 7 21 0 0
9 6/16/2017 85 89 10 10 1 1 85 89 10 11 0 0
10 6/19/2017 40 89 5 11 0 0 40 89 5 11 0 0
11 6/20/2017 40 80 9 18 1 2 40 78 9 18 2 4
12 6/21/2017 23 82 4 4 1 4 21 75 6 21 1 4
*. Veta results are for information only.
Notes:
83
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12
Paving Dates
Figure 69: Summary of MOBA PPM Temperature Segregation Report (Project No. 5 -
J2P3100, RT 36).
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12
Paving Dates
84
Table 21 and Figure 71 provide a summary of the IC results. The roller coverage results were
mixed without apparent trends for improvements.
Temperature for
Target Passes Target ICMV
No. Date vibratory passes
% Coverage Classification % Coverage Classification % CoveragClassification
1 5/25/2017 66 Failed NA NA 29 Failed
85
100
90
80
Roller Coverage (%)
70
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12
Paving days
Figure 71: Summary of Roller Coverage Report (Project No. 5 - J2P3100, RT 36).
86
Project No. 6 - J2P3051, RT 24
Figure 72: Compaction Curve from the Trial Section on 10/21/2016 (Project No. 6 -
J2P3051, RT 24).
87
Trial Section (10/27/2016)
Optimum Rolling Pattern: The optimum number of passes, three (vibratory, static, vibratory),
was established based on the compaction curve in Figure 73. However, there were no vibrating
rolling passes used in the actual production passes.
Figure 73: Compaction Curve from the Trial Section on 10/27/2016 (Project No. 6 -
J2P3051, RT 24).
88
A summary of IR results is shown in Table 22, Figure 74, and Figure 75. There was significant
severe temperature segregation for most of the paving days. The MOBA IR data for 10/22,
10/27, 10/28 roll-over, and its reports cannot be separated for daily reports. Veta filters and
separates each day's data from the MOBA IR data based on time stamps.
2 10/22/2016 0 0 120 66 63 34 1 2 41 73 14 25
3 10/27/2016 0 0 120 66 63 34 3 20 11 73 1 7
4 10/28/2016 0 0 120 66 63 34 2 3 53 80 11 17
5 10/31/2016 3 4 66 89 5 7 3 3 79 91 5 6
6 11/1/2016 2 2 60 85 9 13 0 0 46 67 23 33
7 11/2/2016 1 1 58 88 7 11 0 0 44 69 20 31
8 11/3/2016 1 5 11 55 8 40 0 0 13 68 6 32
Notes:
* Veta report i s for i nforma ti on onl y
89
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8
Paving Dates
Figure 74: Summary of MOBA PPM Temperature Segregation Report (Project No. 6 -
J2P3051, RT 24).
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8
Paving Dates
90
Table 23 and Figure 76 provide a summary of the roller coverage results. Most of the roller
coverage are in the deficient category, and unexpectedly, the roller coverage was trending lower
as the project progressed.
Temperature
Roller Coverage ICMV
Day Date (vibratory passes
% Coverage Classification (Target: min. 70%)
<225 o F)
Notes:
* Not a na l yzed s i nce no ta rget ICMV wa s determi ned from tri a l s ecti ons .
NA - Not a ppl i ca bl e, compa cti on performed i n s ta ti c mode onl y
91
100
90
80
Roller Coverage (%)
70
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8
Paving days
Figure 76: Summary of Roller Coverage Reports (Project No. 6 - J2P3051, RT 24).
92
Project No. 7 - J1P3005, RT 24
Figure 77: Compaction Curve– Trial Section (4/24/2017) (Project No. 7 - J1P3005, RT 24)
A summary of IR results is shown in Table 24, Figure 78, and Figure 79. An MTV was used only
on Day 2 (4/25/2017). The summary temperature segregation reports in Figure 78 and Figure 79
show that the use of MTV on Day 2 reduced severe temperature segregation significantly
compared with other paving days without the use of MTV.
93
Table 24: Summary of IR Results (Project No. 7 - J1P3005, RT 24)
MOBA PPM Veta*
Day Date Low Moderate Severe Low Moderate Severe
# % # % # % # % # % # %
1 4/24/2017 0 0 3 3 87 97 0 0 1 1 77 99
2 4/25/2017 17 15 87 80 5 5 16 20 61 76 3 4
3 5/2/2017 0 0 26 23 85 77 0 0 18 18 82 82
4 5/5/2017 0 0 16 15 92 85 0 0 19 20 78 80
5 5/6/2017 0 0 29 25 86 75 0 0 25 24 78 76
6 5/8/2017 0 0 34 31 77 69 0 0 25 25 74 75
7 5/9/2017 0 0 77 59 53 41 0 0 70 60 47 40
8 5/15/2017 0 0 62 54 52 46 0 0 56 55 45 45
9 5/16/2017 0 0 23 64 13 36 0 0 39 47 44 53
10 5/17/2017 0 0 31 61 20 39 0 0 26 57 20 43
94
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10
Paving Dates
Figure 78: Summary of MOBA PPM Temperature Segregation Report (Project No. 7 -
J1P3005, RT 24).
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10
Paving Dates
Figure 79: Summary of Veta Temperature Segregation Report (Project No. 7 - J1P3005,
RT 24).
95
Table 25 and Figure 80 provide a summary of the IC results. Note that there were missing IC
data for Day 10 (5/17/2017) due to malfunctioning of IC system. The roller coverages were
excellent except for Day 10.
10 5/17/2017 22 Failed NA NA 0 NA
Notes:
Minimum temperature for the vibratory pass is 225F Static only for 5/16-17
5/17 IC data has missed 4,340 ft
96
100
90
80
70
Roller Coverage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10
Paving days
Figure 80: Summary of Roller Coverage Report (Project No. 7 - J1P3005, RT 24).
97
Project No. 8 - J9P3161, RT 17
Figure 81: Compaction Curve from the Trial Section on 9/28/2017 (Project No. 8 - J9P3161,
RT 17).
98
Trial Section (10/2/2017)
Optimum Rolling Pattern: The compaction curve was plotted based on the trial section data, as
shown in Figure 82. It was determined by the RE and the contractor that the rolling pattern for
the breakdown IC roller is three passes (one vibratory pass and two static passes) followed by a
finishing roller. Since only one vibratory pass was used, the ICMV (CMV in this case) was not
analyzed.
Figure 82: Compaction Curve from the Trial Section (2017-10-2) (Project No. 8 - J9P3161,
RT 17)
A summary of IR results is shown in Table 11, Table 26, Figure 83, and Figure 84. The
temperature segregation was mostly in “No Segregation” and “Moderate Segregation” categories
with very limited severe temperature segregation, likely due to the use of an MTV.
99
Table 26: Summary of IR Results (Project No. 8 - J9P3161, RT 17)
MOBA PPM Veta*
Day Date Low Moderate Severe Low Moderate Severe
# % # % # % # % # % # %
1 9/28/2017 20 15 98 75 12 9 16 12 100 75 17 13
3 9/30/2017 14 12 85 75 14 12 12 11 86 77 14 13
4 10/2/2017 8 16 36 73 5 10 11 23 34 71 3 6
7 10/14/2017 32 23 100 72 6 4 39 28 95 69 3 2
8 10/16/2017 42 41 60 58 1 1 56 55 46 45 0 0
9 10/17/2017 43 29 101 68 4 3 44 30 98 67 5 3
10 10/18/2017 78 51 70 46 5 3 85 56 60 40 6 4
11 10/19/2017 70 65 32 30 6 6 71 67 30 28 5 5
*. Veta results are for information only.
9/28 Section 1 IR data include incorrect DMI, length, nuumber of sublots.
Notes:
10/16 Section 1 data is calibration. Section 2 and 3 are disjointed due to a loss data caused by
blown fuse.
100
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11
Paving Days
Figure 83: Summary of MOBA PPM Temperature Segregation Report (Project No. 8 -
J9P3161, RT 17).
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11
Paving Days
Figure 84: Summary of Veta Temperature Segregation Report (Project No. 8 - J9P3161,
RT 17).
101
Table 27 and Figure 85 provide a summary of the roller coverage results. The roller coverage
results were excellent throughout all paving days.
102
100
90
80
Roller Coverage (%)
70
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11
Paving days
Figure 85: Summary of Roller Coverage Report (Project No. 8 - J9P3161, RT 17).
103
Project No. 9 - J6S3123, RT 61
Figure 86 Compaction Curve– Trial Section (5/31/2017) (Project No. 9 - J6S3123, RT 61)
A summary of IR results is shown in Table 28, Figure 87 and Figure 88. The temperature
segregation was mostly in “No Segregation” and “Moderate Segregation” categories with a
limited amount of severe temperature segregation.
104
Table 28: Summary of IR Results (Project No. 9 - J6S3123, RT 61)
# % # % # % # % # % # %
1 5/31/2017 6 40 6 40 3 20 3 20 8 53 4 27
2 6/1/2017 68 61 24 22 19 17 68 62 32 29 9 8
4 6/3/2017 94 86 13 12 2 2 96 88 11 10 2 2
5 6/5/2017 53 64 16 19 14 17 53 67 17 22 9 11
6 6/6/2017 55 57 31 32 11 11 63 61 30 29 11 11
7 6/7/2017 65 54 41 34 14 12 79 68 27 23 10 9
8 6/8/2017 38 61 16 26 8 13 39 61 17 27 8 13
9 6/9/2017 68 58 32 27 17 15 62 54 37 32 16 14
Notes:
*. Veta results are for information only.
105
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9
Paving Dates
Figure 87: Summary of MOBA PPM Temperature Segregation Report (Project No. 9 -
J6S3123, RT 61).
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9
Paving Dates
Figure 88: Summary of Veta Temperature Segregation Report (Project No. 9 - J6S3123,
RT 61).
106
Table 29 and Figure 89 provide a summary of the IC results. The roller coverages were poor
without trends of improvement.
107
100
90
80
Roller Coverage (%)
70
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9
Paving days
Figure 89: Summary of Roller Coverage Report (Project No. 9 - J6S3123, RT 61).
108
Project No. 10 - J7I3072, RT 49
Compaction Curve
93
92.625
Intermediate 92.25
92 91.85 STATIC
Intermediate 91.55
Intermediate
STATIC
VIBRATING Intermediate
91
STATIC
Density (%Gmm)
90 90
Pneumatic
89 Breakdown
VIBRATING Pneumatic
88.275 88.3
88
Breakdown
VIBRATING
87 87.075
1 2 3 4 5 6 7 8
Roller Passes
Figure 90 Compaction Curve– Trial Section (6/12/2017) (Project No. 10 - J7I3072, RT 49)
109
A summary of IR results is shown in Table 30, Figure 91, and Figure 92. The temperature
segregation was mostly in “No Segregation” and “Moderate Segregation” categories but the
Day 8 data indicated severe temperature segregation.
# % # % # % # % # % # %
1 6/5/2017 3 23 10 77 0 0 5 42 7 58 0 0
2 6/16/2017 1 17 5 83 0 0 1 8 11 92 0 0
3 6/19/2017 26 44 28 47 5 8 30 52 26 45 2 3
4 6/20/2017 51 50 51 50 1 1 57 55 44 42 3 3
5 6/21/2017 15 19 54 68 10 13 36 46 40 51 3 4
6 6/22/2017 52 54 41 42 4 4 54 56 37 39 5 5
7 6/23/2017 19 43 19 43 6 14 20 47 18 42 5 12
8 6/24/2017 15 18 34 41 33 40 20 24 34 41 28 34
9 6/26/2017 64 57 47 42 2 2 62 55 42 38 8 7
10 6/27/2017 10 37 15 56 2 7 12 46 13 50 1 4
11 6/28/2017 44 43 57 56 1 1 50 49 50 49 2 2
12 6/29/2017 58 49 57 48 3 3 67 57 50 42 1 1
13 7/6/2017 39 57 28 41 1 1 48 69 20 29 2 3
110
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13
Paving Days
Figure 91: Summary of MOBA PPM Temperature Segregation Report (Project No. 10 -
J7I3072, RT 49).
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13
Paving Days
Figure 92: Summary of Veta Temperature Segregation Report (Project No. 10 - J7I3072,
RT 49).
111
Table 31 and Figure 93 provide a summary of the roller coverage results. The roller coverage
was excellent after improving from Day 1.
Notes:
* Da ta not a va i l a bl e
112
100
90
80
70
Roller Coverage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13
Paving days
Figure 93: Summary of Roller Coverage Report (Project No. 10 - J7I3072, RT 49).
113
Project No. 11 - J1S3028, RT 69
Compaction Curve
100.00
99.58
99.50 99.30
Static
Vibrating
99.00
Density (%Gmm)
98.50 98.30
Static
97.90
98.00 Vibrating
97.50
97.00
1 2 3 4
Roller Passes
Figure 94 Compaction Curve from the Trial Section-1 on 6/30/2017 (Project No. 11 -
J1S3028, RT 69).
114
Trial Section-2 (6/30/2017)
Optimum Rolling Pattern: The compaction curve is shown in Figure 95. The rolling pattern
established was for the breakdown (CAT CB66B) IC roller to have one vibratory pass, and two
static passes. The roller was set to operate at high frequency and low amplitude.
Compaction Curve
100.00
99.13
99.00 98.40
Static
98.00 Static
Density (%Gmm)
96.98
97.00
Static
96.00 95.23
95.00
Vibrating
94.00
93.00
1 2 3 4
Roller Passes
Figure 95 Compaction Curve from the Trial Section-2 on 6/30/2017 (Project No. 11 -
J1S3028, RT 69).
115
Trial Section (7/6/2017)
Optimum Rolling Pattern: The compaction curve is shown in Figure 96. The rolling pattern
established was for the breakdown (Hamm HD+140i) IC roller to have one vibratory pass, and
two static passes. The roller was set to operate at high frequency and low amplitude.
Compaction Curve
99.00
98.50
98.00
97.28
97.50
Density (%Gmm)
Figure 96. Compaction Curve from the Trial Section on 7/6/2017 (Project No. 11 - J1S3028,
RT 69).
A summary of IR results is shown in Table 32, Figure 97, and Figure 98. The temperature
segregation is generally in the “No segregation” and “Moderate Segregation” categories with
limited severe temperature segregation.
116
Table 32: Summary of IR Results (Project No. 11 - J1S3028, RT 69)
# % # % # % # % # % # %
1 6/30/2017 8 36 13 59 1 5 26 46 27 48 3 5
2 7/1/2017 47 52 38 42 5 6 45 51 33 37 11 12
3 7/5/2017 74 65 34 30 6 5 67 61 40 36 3 3
4 7/6/2017 72 58 42 34 10 8 71 65 35 32 4 4
5 7/7/2017 56 64 24 27 8 9 54 62 22 25 11 13
117
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5
Paving Dates
Figure 97: Summary of MOBA PPM Temperature Segregation Report (Project No. 11 -
J1S3028, RT 69).
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5
Paving Dates
Figure 98: Summary of Veta Temperature Segregation Report (Project No. 11 - J1S3028,
RT 69).
118
Table 33 and Figure 99 provide a summary of the roller coverage results. The roller coverages
were excellent but fell on the last two days.
100
90
80
70
Roller Coverage (%)
60
50
40
30
20
10
0
1 2 3 4 5
Paving days
119
Project No. 12 - J5P3170, RT 5
Compaction Curve
97
96 96
95 95.1
Density (%Gmm)
94.2 Spot 1
94
Spot 2
93
Spot 3
92.35
92 Spot 4
AVG
91
90
0 1 2 3 4 5
Passes
Figure 100: Density Compaction Curve from the Trial Section on 9/8/2017 (Project No. 12
- J5P3170, RT 5).
120
A summary of IR results is shown in Table 34, Figure 101, and Figure 102. There was severe
temperature segregation throughout all paving days.
121
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10
10 11
10 12
Paving Dates NBL SBL
Figure 101: Summary of MOBA PPM Temperature Segregation Report (Project No. 12 -
J5P3170, RT 5).
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10
10 11
10 12
Paving Dates NBL SBL
Figure 102: Summary of Veta Temperature Segregation Report (Project No. 12 - J5P3170,
RT 5).
122
Table 35 and Figure 103 provide a summary of the roller coverage results. The roller coverage
results were mostly moderate with no apparent trends.
123
100
90
80
70
Roller Coverage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10
10 11
10
Paving days NBL SBL
Figure 103: Summary of Roller Coverage Report (Project No. 12 - J5P3170, RT 5).
124
Project No. 13 - J9P3296, RT 17
Figure 104: Compaction Curve from the Trial Section on 5/7/2017 (Project No. 13 -
J9P3296, RT 17).
Even though the compaction curve was established, the aggregates in the core appeared to be
crushed (Figure 105), likely due to over compaction.
Figure 105: Core Sample from the Trial Section on 5/7/2017 (Project No. 13 - J9P3296, RT
17).
125
A summary of IR results is shown in Table 36, Figure 106, and Figure 107. Note that due to
paving close to structures at nighttime, the contractor elected not to use IR for 7/21/2017, and
therefore there are no IR data for that date. Overall, there was severe temperature segregation
throughout all paving days.
2 7/7/2017 0 0 10 17 50 83 4 4 20 21 71 75
3 7/8/2017 0 0 15 19 62 81 1 1 39 30 91 69
4 7/10/2017 2 2 39 31 85 67 3 3 32 28 81 70
5 7/11/2017 0 0 14 14 86 86 10 6 48 27 119 67
6 7/12/2017 14 9 44 28 99 63 22 14 37 24 95 62
7 7/17/2017 0 0 11 17 54 83 20 14 50 34 76 52
8 7/21/2017 NA NA NA NA NA NA NA NA NA NA NA NA
11 8/1/2017 14 9 61 39 81 52 16 10 66 41 78 49
12 8/4/2017 6 4 60 37 98 60 8 5 57 38 87 57
13 8/7/2017 9 5 82 45 92 50 8 5 67 42 83 53
14 8/8/2017 4 2 87 49 87 49 8 5 68 45 76 50
15 8/12/2017 36 20 95 54 46 26 39 20 103 52 58 29
16 8/18/2017 26 16 100 60 41 25 28 16 94 55 48 28
Notes : *. Veta results are for information only.
The IR data for 7/21 were not collected since the contractor elected not to use it
close to structures at night time.
126
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Paving Dates
Figure 106: Summary of MOBA PPM Temperature Segregation Report (Project No. 13 -
J9P3296, RT 17).
100
90
80
70
Percentage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Paving Dates
Figure 107: Summary of Veta Temperature Segregation Report (Project No. 13 - J9P3296,
RT 17).
127
Table 37 and Figure 108 provide a summary of the roller coverage results. The roller coverage
results were excellent after improving from Day 1.
13 8/7/2017 99 Passed NA NA NA NA
128
100
90
80
70
Roller Coverage (%)
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Paving days
Figure 108: Summary of Roller Coverage Report (Project No. 13 - J9P3296, RT 17).
129
Comparison of IC-IR Results
In terms of mean values of temperature segregation for all projects, there were projects (No. 6, 7,
12, and 13) that had significant severe temperature segregation, projects (No. 1, 2, 3, 4, 5) which
showed only limited severe segregation, and projects (No. 8, 9, 10, 11) which had moderate
temperature segregation. Figure 109 shows a comparison of overall average temperature
segregation by project.
100
90
80
Avergae IR Segregation (%)
70
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13
Project No.
130
In terms of mean values of temperature segregation for those projects by the same contractors,
there were contractors (No. 1 and 8) whose projects showed significant severe temperature
segregation, contractors (No. 2, 3, 4) whose projects exhibited excellent uniform temperature
with only limited severe segregation, and contractors (No. 4, 5, 6, 7) whose projects fell in
between the above. Figure 110 shows a comparison of overall temperature segregation by
contractor.
100
90
80
Average IR Segregation (%)
70
60
50
40
30
20
10
0
1 2 3 4 5 6 7 8
Contractor Code
131
In terms of mean values of target pass coverage for all projects, there were projects (No. 6 and 9)
that did not meet the 70% minimum coverage requirements (i.e., deficient), there were projects
(No. 7, 8, 10, and 13) that met the 90% excellent coverage (i.e., passed), and there were projects
(No. 1, 2, 3, 4, 5, 11, and 12) which fell in between the above. Figure 111 provides an overall
summary of IC coverage for all projects.
132
In terms of mean values of target pass coverage for those projects by the same contractors, there
were contractors (No. 5) whose projects did not the 70% minimum coverage requirements (i.e.,
deficient), there were contractors (No. 4, 6, and 8) whose projects met the 90% excellent
coverage (i.e., passing), and there were contractors (No. 1, 3, and 7) in between the above (i.e.,
moderate).
133
Project Evaluation
The field projects were evaluated on various aspects as follow.
GPS Verification
• GPS verification is crucial to ensure GPS measurements from the IC system and hand-
held rover are consistent.
• GPS verification and record keeping has not always be done by contractors though it was
required in the Protocol.
• The actual field operation of GPS verification is straightforward and not time consuming.
It should be a natural part of the daily setup.
134
onsite technical support provided by a consultant, but others have to call MOBA directly
for assistance.
• The main issue of IR systems is that the DMI calibration was not always performed
correctly (i.e., rolling radius setting was incorrect).
• Incorrect DMI caused incorrectly reported distance and incorrect number of sublots by
the MOBA PPM software. However, the Veta report was not affected due to the use of
GPS records instead of DMI. The Veta display of IR thermal profiles was affected due to
the incorrect sampling intervals of IR data (e.g., 3 ft. instead of 1 ft.) caused by incorrect
rolling radius (e.g., 5 in. instead of 16 in.).
• There were still issues regarding lack of technical training and support from vendors’
dealers.
• The current requirement for GPS precision for IR system is still too poor, making it
difficult to combine with other data such as IC data and alignment files. It is expected
higher precision GPS will be used in future IR systems.
135
processes, especially when multiple files were produced for a given paving operation.
This is one of the weak links.
• Another hurdle is to learn vendors’ software systems (e.g., Trimble VisionLink,
TOPCON SiteLink3D) to filter, extract, and export data for a specific date, lift of
construction, paved lane, direction, and roller(s).
• The above exported files are generally very large due to the gridding results (i.e.,
populating raw recorded data, one point across a drum, to 1 ft. X 1 ft. grids), at 100 to
200 MB per roller. The size would challenge data transmission for areas with slow
internet connection.
• It is anticipated that most of the above issues can be resolved by upcoming feature in
Veta 5, which will provide a direct data import from the cloud to Veta.
• It is recommended to include a clause in the IC specification regarding data collection
and submission that tied to pay items (e.g., % of data collected/submitted).
Other Data Collection and Submission (trial sections and core data)
• Trial section data were mostly recorded for these projects.
• However, measurements of asphalt densities with nuclear density gauges are still
challenging to complete after each roller pass at selected locations with the last 400-ft of
a 1000-ft trial section.
• The gauge was intended to measure density for two-inch lifts (vs. the actual 1.75-inch lift
thickness). Troxler has published a Tech Brief regarding thin lift nuclear density gauge
without the influence from the underlying layers materials (https://aggrebind.com/wp-
content/uploads/2012/12/Troxler-Testing.pdf) In each case where spot readings were taken,
efforts were made to consistently record density measurements with the nuclear density
gauge at exactly the same spots. The effect of this data collection occurring repeatedly at
136
the same locations provided the benefit of reducing the influence of gauge settings and
underlying conditions.
• Most contractors use the first paving day’s trial section data to determine target passes
and vibration/static for the remaining of paving days.
• Core data and the associated GPS coordinates are often missing and miss-matched.
137
generation, etc.). Refresher and training in using those new features are recommended for
MoDOT staff, contractors, and IC-IR dealership.
Trial
Project Section IR IC GPS Core Analysis Report
No. Job No. District County Route Data Data Data Data Data Complete Complete
1 J5P3117 CD Morgan 52 Y Y Y Y N Y Y
2 J4I3111 KC Clay 29 Y Y Y Y Y Y Y
3 J3I3042 KC Lafayette 70 Y Y Y Y N Y Y
4 J2P3099 NE Macon 36 N Y Y Y N Y Y
5 J2P3100 NE Macon 36 N Y Y Y N Y Y
6 J2P3051 NE Randolph 24 N Y Y Y Y Y Y
7 J1P3005 NW Chariton 24 Y Y Y Y Y Y Y
8 J9P3161 SE Texas 17 Y Y Y Y N Y Y
9 J6S3123 SL Jefferson 61 Y Y P Y N Y Y
10 J7I3072 SW McDonald 49 Y Y Y Y N Y Y
11 J1S3028 NW Daviess 69 Y Y Y Y Y Y Y
12 J5P3170 CD Cooper 5 Y Y Y Y N Y Y
13 J9P3296 SE Texas 17 Y Y Y Y N Y Y
Legend: Y- Yes N- No P- Partial
138
IC-IR Check List and Form Completion
• The contractors’ check lists were mostly not submitted.
• There are limited number of contractors who submitted paving record forms.
• Those contractors who submitted the paving records have also performed MOBA PPM
and Veta analysis. There were two contractors performed the analysis but did not submit
paving record forms.
• The RE’s check lists were mostly not submitted.
• The RE’s diaries were mostly not submitted.
• Table 39 Summarizes the completion of IC-IR check lists and forms for the 13 field
projects.
Paving
Project Contractor Contractor Record Contractor RE check
No. Code Job No. District County Route Check List Forms Analysis List RE Diary
1 1 J5P3117 CD Morgan 52 N Y Y Y N
2 2 J4I3111 KC Clay 29 P P Y Y Y
3 3 J3I3042 KC Lafayette 70 N N N N N
4 3 J2P3099 NE Macon 36 N N N N Y
5 3 J2P3100 NE Macon 36 N N N N Y
6 1 J2P3051 NE Randolph 24 N N N N P
7 1 J1P3005 NW Chariton 24 N N N N Y
8 4 J9P3161 SE Texas 17 P Y Y Y N
9 5 J6S3123 SL Jefferson 61 N N N N N
10 6 J7I3072 SW McDonald 49 N Y Y N N
11 7 J1S3028 NW Daviess 69 N N Y N N
12 1 J5P3170 CD Cooper 5 N Y Y N N
13 8 J9P3296 SE Texas 17 N N Y Y N
Legend: Y- Yes N- No P- Partial
139
IC-IR Specification Reviews
The marked-up versions of MoDOT IC and IR specifications were submitted to MoDOT. The
following are the highlights of recommended modifications and comments.
IR Specification
Equipment Requirements
• The current equipment and software requirement is vendor-specific.
• It is recommended to make it generic to allow various thermal profile technologies:
infrared thermal scanners and thermal cameras.
Training Requirements
• The current 2-4 hours training is adequate for so-called just-in-time training.
• The requirement for trained personnel being onsite is adequate.
Acceptance Requirements
• The current requirement for temperature segregation is consistent with AASHTO PP80-
17.
• The AASHTO PP80-17 temperature segregation may not differentiate between moderate
and severe temperature segregation.
• It is recommended to consider the Thermal Segregation Index developed by MnDOT in
the future.
• It is recommended to consider increasing the unit cost for incentive and disincentive pay
adjustment to motivate full utilization of the IR technologies.
140
IC Specification
Equipment Requirements
• The current IC equipment and software requirement is adequate.
• The current GPS equipment requirement is adequate.
• The IC quality control plan is adequate. It is recommended that plan be submitted to the
RE for approval.
Training Requirements
• The current IC training requirement and certification is adequate and consistent with
AASHTO PP81-17.
• It is recommended to elaborate the certification requirements: who administers such
certification and the frequency per year.
Acceptance Requirements
• The segment classification is adequate to consider data loss. However, it is recommended
to include an exception for inadequate GPS coverage, which needs to be addressed during
project selection.
• The minimum temperature requirements for vibratory passes should be re-examined since
all 2017 projects have failed to meet this requirement.
• It is recommended to consider the Caltrans IC temperature requirement that accounts for
IR temperature measurement variability on wet/dry asphalt surfaces (e.g., 20F deduction
from the temperature requirements) and instructions for handling non-compliance.
141
• It is recommended to increase the unit cost for the incentive and disincentive.
Conclusions
From the above IC-IR project data analysis and specification reviews, the following conclusions
can be made:
• The MoDOT IC-IR projects in 2017 can be considered a success in terms of building up
experiences for both MoDOT personnel and contractors.
• The IC-IR project protocol proved to be mostly effective for planning and conducting
field projects. The IC-IR data management is a key component of the Protocol to ensure
consistent data naming convention and submission. The MoDOT SharePoint is very
useful to share data files, especially when the file sizes are too large as email attachments.
• The IR implementation has shown as a real-time indicator of any temperature
segregation. In turn, the IR data and analysis reports can be used to fine tune paving
process accordingly, such as making use of MTV and adjustment of truck fleet and
paving speeds.
• There are issues with IR regarding the DMI/data sampling issues of a vendor’s system
and analysis issues with a vendor’s software. These issues can be resolved with better
training and use of the standard software, Veta, for analysis.
• The IC implementation has been mostly utilized to maximize roller coverage with some
exceptions. The latter can be resolved by planning the construction operations based on
project location and alignment, lift thickness to be constructed, type of materials, and
availability of equipment and resources, along with proper training.
• There were issues with IC roller calibration that requires better vendor’s training to
overcome.
• The GPS boundary measurements were mostly successful with occasional issues that
require sorting, inspection, and correction.
• The IC-IR data management is still tedious, especially when IC or IR data need to be
exported/transferred manually. There were occasional human errors that cause incorrect
file naming convention, etc. Better training with the Protocol and additional experiences
will resolve these issues.
• There was still a lack of submission of check lists, forms, and paving records to the
SharePoint site.
• Most of core data were not submitted to the SharePoint.
142
Recommendations
The following are recommendation to move the IC-IR implementation forward at MoDOT:
• Utilizing standards, such as Veta, for IR data analysis and reporting would resolve
several issues identified at 2017 projects.
• It is recommended to reduce the GPS boundary measurement efforts by utilizing
alignment files generated either by design software or LiDAR measurements.
• Fine tuning the IC and IR specification may help resolve several issues that occurred at
the 2017 projects, as recommended in the IC-IR specification review section. Detailed
report requirements are crucial as recommended in the specification review section.
• It is also recommended to encourage healthy competition for the IC-IR industry to allow
all technology solutions. It can be regulated by the performance requirements in the IC-
IR specifications.
• IC-IR project selection criteria may include sizes (lane miles), GPS coverage, and cellular
coverage.
• Conducting a research to determine the criteria for mean asphalt surface (vs. internal)
temperature requirements for vibratory passes.
• IC-IR training and technical support is still an essential element for a successful field
project, due to contractors’ lack of experiences and support from vendors. It should also
be noted that IC-IR systems and Veta software are evolving. It is recommended to
conduct annual MoDOT IC-IR and Veta training to qualify IC-IR quality control
technicians and to issue annual (or bi-annual) certificates.
• Within available limits, increasing unit cost for IC-IR incentive/disincentive pay schedule
may encourage industry’s fully utilization of IC-IR technologies.
• Indicating long term plans for MoDOT IC-IR implementation will encourage industry
investment in equipment, trained personnel, etc. It is recommended to target 100%
implementation of IC-IR by 2020.
143