Total 24,000,000.00: Summary of Price For 2Km Road Construction Description
Total 24,000,000.00: Summary of Price For 2Km Road Construction Description
Total 24,000,000.00: Summary of Price For 2Km Road Construction Description
Total 24,000,000.00
Project Name:-
SNNPRG SOUTH OMMO ZONE
Prject Length:- 12km
Pay Item Description Unit Quantity Unit rate Amount
SERIES 2000 SITE CLEARANCE
21.01 Clearing & Grubbing Ha
Division 2100 Total Sum -
SERIES 3000 DRAINAGE STRUCTURES
Division 3200 Excavation for Structures
Excavation for minor drainage structures(Pipes, Fords, Slab &
32.01(i) Box culverts) -
a 0-10km m2 -
2
b 10-20km m -
2
c 20-30km m -
d 30-40km m2 -
2
e >40km m -
a 0-10km m2 -
2
b 10-20km m
c 20-30km m2
d 30-40km m2
e >40km m2
34.03 (i) When the Stone is transported from 0-10km but Sand is
34.03 (ii) When the Stone is transported from 10-20km but Sand is -
34.03 (iii) When the Stone is transported from 20-30km but Sand is -
34.03 (iv) When the Stone is transported from 30-40km but Sand is -
34.03 (v) When the Stone is transported from >40km but Sand is -
a Soft Excavation m3 -
b Intermidiate Excavation m3 -
3
c Hard Rock(Using Jack Hammer) Excavation m -
Division 4200 Sub Total Sum -
SERIES 5000 PLACING GRAVEL MATERIAL
Division 5100 Gravel Wearing Coarse
a [0,5)km m3 -
b [5,10)km m3 -
3
c [10,15)km m -
3
d [15,20)km m -
e [20,25)km m3 -
3
f >25km m -
Division 5100 Sub Total Sum -
Division 8100 Structural Excavations for bridges less than 12m span
a Soft Excavation m3 -
b Intermidiate Excavation m3 -
3
c Hard Rock(Using Jack Hammer) Excavation m -
Division 8100 Sub Total Sum -
Division 8200 Form Work (For All Structural Types)
Formwork Including Falsework
i Falsework Height <4m m2 -
ii Falsework Height > 4m m2 -
Division 8200 Sub Total Sum -
Division 8300 Reinforcing Steel (For All Structural Types)
83.01 Steel Reinforcement (bending, cutting & fixing)
i Grade - 40 kg -
ii Grade - 60 kg -
Division 8300 Sub Total Sum -
Concrete for Slab & Box Culverts & Bridges Lessthan 12m
Division 8400
Clear Span
i Grade C-30 using any transportation
1.00 When Course aggregate is transporte from <75km
a When Sand transportation is <100km distance m3 -
3
b When Sand transportation is 100<d<200km distance m -
c When Sand transportation is >200km distance m3 -
2.00 When Course aggregate is transporte from >75km -
a When Sand transportation is <100km distance m3 -
3
b When Sand transportation is 100<d<200km distance m -
3
c When Sand transportation is >200km distance m -
ii Grade C-25 using any transportation -
89.01 (i) When the Stone is transported from 0-10km but Sand is
89.01 (ii) When the Stone is transported from 10-20km but Sand is -
89.01 (iii) When the Stone is transported from 20-30km but Sand is -
89.01 (iv) When the Stone is transported from 30-40km but Sand is -
89.01 (v) When the Stone is transported from >40km but Sand is -
CONSULTANT S/OMO ZONE CONSTRUCTION AND DESIGN CONTRACTOR ________________ DATE 8/31/2021
file :///co nversi on/tmp/activity_task_ scratch/539 074 848 .xl s,AN ALYSIS
Price Analysis sheet
CONSULTANT S/OMO ZONE CONSTRUCTION AND DESIGN CONTRACTOR ________________ DATE 8/31/2021
2.0 ITEM OF WORK excavating and removing existing bituminous material UNIT M2 Activity No
2.1 ITEM OF WORK excavating existing bituminous material UNIT M2 Activity No 414.00
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Unit
Item Unit QTY cost Total Labor No Rate TOTAL Equipment No Rate Total cost
Earthwork Forman 0.5 25.03 12.51 Bulldozer - D8R 1 1999.30 1999.30
Grade Checker /Data Collector 1 30.00 30.00 0.00
Unskilled Laborer 2 8.63 17.26 0.00
0.00
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 59.77 SUBTOTAL 3 = 1999.30
4. Performance Rate/Hr 166.67
5. Direct Material Cost 0.00 6. Direct Labor Cost 0.36 7. Direct Equipment cost 12.00
11.Total Direct Cost 12.35
2.2 ITEM OF WORK Cart away UNIT M2 Activity No
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Unit
Item Unit QTY cost Total Labor No Rate TOTAL Equipment No Rate Total cost
Grade Checker /Data Collector 1 30.00 30.00 Wheel Loader - 3m3 1 649.75 649.75
Dump Truck - 12m3 5 516.50 2582.50
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 30.00 SUBTOTAL 3 = 3232.25
4. Performance Rate/Hr 800.00
5. Direct Material Cost 0.00 6. Direct Labor Cost 0.04 7. Direct Equipment cost 4.04
11.Total Direct Cost 4.08
file :///co nversi on/tmp/activity_task_ scratch/539 074 848 .xl s,AN ALYSIS
Price Analysis sheet
CONSULTANT S/OMO ZONE CONSTRUCTION AND DESIGN CONTRACTOR ________________ DATE 8/31/2021
0.00 Construction (Earthwork) Forma 0.5 25.03 12.51 Dozer 200-300 FWHP 1 1999.30 1999.30
0.00 Helper I (Grade Checker /Data 1 30.00 30.00
Laborer I (Unskilled) 2 8.63 17.26
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 59.77 SUBTOTAL 3 = 1999.30
4. Performance Rate/Hr 50.00
5. Direct Material Cost 0.00 6. Direct Labor Cost 1.20 7. Direct Equipment cost 39.99
Profit 0.07 Indirect cost 0.15
11.Total Direct Cost 41.18 12. Aggregate unit cost 50.24
file :///co nversi on/tmp/activity_task_ scratch/539 074 848 .xl s,AN ALYSIS
Price Analysis sheet
CONSULTANT S/OMO ZONE CONSTRUCTION AND DESIGN CONTRACTOR ________________ DATE 8/31/2021
0.00 Construction (Earthwork) Forma 0.5 25.03 12.51 Dozer 200-300 FWHP 1 1999.30 1999.30
0.00 Helper I (Grade Checker /Data 1 30.00 30.00
Laborer I (Unskilled) 2 8.63 17.26
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 59.77 SUBTOTAL 3 = 1999.30
4. Performance Rate/Hr 50.00
5. Direct Material Cost 0.00 6. Direct Labor Cost 1.20 7. Direct Equipment cost 39.99
Profit 0.07 Indirect cost 0.15
11.Total Direct Cost 41.18 12. Aggregate unit cost 50.24
file :///co nversi on/tmp/activity_task_ scratch/539 074 848 .xl s,AN ALYSIS
Price Analysis sheet
CONSULTANT S/OMO ZONE CONSTRUCTION AND DESIGN CONTRACTOR ________________ DATE 8/31/2021
file :///co nversi on/tmp/activity_task_ scratch/539 074 848 .xl s,AN ALYSIS
Price Analysis sheet
CONSULTANT S/OMO ZONE CONSTRUCTION AND DESIGN CONTRACTOR ________________ DATE 8/31/2021
4.0 ITEM OF WORK CUT TO SPOIL (ROCK EXCAVATION) UNIT M3 Activity No 421B
file :///co nversi on/tmp/activity_task_ scratch/539 074 848 .xl s,AN ALYSIS
Price Analysis sheet
CONSULTANT S/OMO ZONE CONSTRUCTION AND DESIGN CONTRACTOR ________________ DATE 8/31/2021
Gang Leader/Data Collector 1 15.04 15.04 Hand Driven Roller 1 133.32 133.32
Unskilled Labour 10 8.63 86.30 Water Tanker - 1M3 1 30.00 30.00
0.00
0.00
file :///co nversi on/tmp/activity_task_ scratch/539 074 848 .xl s,AN ALYSIS
Price Analysis sheet
CONSULTANT S/OMO ZONE CONSTRUCTION AND DESIGN CONTRACTOR ________________ DATE 8/31/2021
OPC Cement KG 94.5 6.10 576.45 Production Foreman 1 25.03 25.03 Mixer 500 Ltr 1 213.32 213.32
Fine Aggregate LM3 0.106 ### 26.50 Mason 1 25.03 25.03 Concrete Vibrator 2 54.81 109.63
Coarse Aggregate LM3 0.19 ### 112.81 Data Collector 1 12.33 12.33 Pipe Mould 30'' 30 30.00 900.00
0.00 Helpers 6 10.36 62.14 Water Tanker 10,000 Ltr 1 30.00 30.00
0.00 Gang Leader / Data Collector 1 15.04 15.04 Courier Truck 1 723.15 723.15
0.00 Unskilled Labour 8 8.63 69.04
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 84.08 SUBTOTAL 3 = 723.15
4. Performance Rate/Hr 5.00
5. Direct Material Cost 0.00 6. Direct Labor Cost 16.82 7. Direct Equipment cost 144.63
11.Total Direct Cost 161.45
file :///co nversi on/tmp/activity_task_ scratch/539 074 848 .xl s,AN ALYSIS
Price Analysis sheet
CONSULTANT S/OMO ZONE CONSTRUCTION AND DESIGN CONTRACTOR ________________ DATE 8/31/2021
Item Unit QTY Unit Total Labor No Rate TOTAL Equipment No Rate Total cost
cost
Steel Panel M2 1.05 ### 282.07 Carp Forman I 1 25.03 25.03 0.00
Eucalyptus M 10.00 13.75 137.50 Carpenter 3 29.22 87.66
Nails KG 0.20 30.00 6.00 Unskilled Labour 6 8.63 51.78
Binding Wire 2.5mm KG 0.10 40.00 4.00
SUB TOTAL 1= 429.57 SUB TOTAL 2 = 164.47 SUBTOTAL 3 = 0.00
4. Performance Rate/Hr 3.50
5. Direct Material Cost 429.57 6. Direct Labor Cost 46.99 7. Direct Equipment cost 0.00
11.Total Direct Cost 476.56
Profit 0.07 Indirect cost 0.15
AGGREGATE UNIT COST= 581.405902622309
SUMMARY CLASS A CONCRETE
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
5362.09 153.88 110.15
Total Direct Cost 5626.11 Profit 0.07 Indirect cost 0.15
AGGREGATE UNIT COST= 6863.85927465884
file :///co nversi on/tmp/activity_task_ scratch/539 074 848 .xl s,AN ALYSIS
Price Analysis sheet
CONSULTANT S/OMO ZONE CONSTRUCTION AND DESIGN CONTRACTOR ________________ DATE 8/31/2021
Item Unit QTY Unit Total Labor No Rate TOTAL Equipment No Rate Total cost
cost
Steel Panel M2 1.05 ### 282.07 Carpenter Foreman 1 25.03 25.03 0.00
Eucalyptus M 21.00 13.75 288.75 Carpenter 10 29.22 292.19
Nails KG 0.56 30.00 16.80
Binding Wire 2.5mm KG 0.21 40.00 8.40 Unskilled Labour 20 8.63 172.60
SUB TOTAL 1= 596.02 SUB TOTAL 2 = 489.82 SUBTOTAL 3 = 0.00
4. Performance Rate/Hr 3.50
5. Direct Material Cost 596.02 6. Direct Labor Cost 139.95 7. Direct Equipment cost 0.00
11.Total Direct Cost 735.97
SUMMARY CLASS C CONCRETE
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
3102.38 252.41 110.15
Total Direct Cost 3464.94 Profit 0.07 Indirect cost 0.15
AGGREGATE UNIT COST= 4227.22784531637
file :///co nversi on/tmp/activity_task_ scratch/539 074 848 .xl s,AN ALYSIS
Price Analysis sheet
CONSULTANT S/OMO ZONE CONSTRUCTION AND DESIGN CONTRACTOR ________________ DATE 8/31/2021
file :///co nversi on/tmp/activity_task_ scratch/539 074 848 .xl s,AN ALYSIS
Price Analysis sheet
CONSULTANT S/OMO ZONE CONSTRUCTION AND DESIGN CONTRACTOR ________________ DATE 8/31/2021
0.00 Earthwork Foreman 0.5 25.03 12.51 Motor Grader 1 1299.70 1299.70
0.00 Grade Checker /Data Collector 1 30.00 30.00 Vibratory Roller 1 983.20 983.20
Water Truck Helper 1 10.36 10.36 Water Truck 1 466.50 466.50
0.00 Unskilled Labour 10 8.63 86.30
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 139.17 SUBTOTAL 3 = 2749.40
4. Performance Rate/Hr 86
5. Direct Material Cost 0.00 6. Direct Labor Cost 1.62 7. Direct Equipment cost 32.08
11.Total Direct Cost 33.70
SUMMARY BURROW TO FILL LOCATION
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
20.00 2.12 65.81
Total Direct Cost 87.94 Profit 0.07 Indirect cost 0.15
AGGREGATE UNIT COST= 107.2849055879
file :///co nversi on/tmp/activity_task_ scratch/539 074 848 .xl s,AN ALYSIS
Price Analysis sheet
CONSULTANT S/OMO ZONE CONSTRUCTION AND DESIGN CONTRACTOR ________________ DATE 8/31/2021
0.00 Pavement Foreman 0.5 25.03 12.51 Motor Grader 1 1299.70 1299.70
0.00 Helper 1 30.00 30.00 Vibratory Roller 1 649.75 649.75
Water Truck Helper 2 10.36 20.71 Water Truck 2 466.50 933.00
0.00 Unskilled Labour 10 8.63 86.30
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 149.53 SUBTOTAL 3 = 2882.45
4. Performance Rate/Hr 81.00
5. Direct Material Cost 0.00 6. Direct Labor Cost 1.85 7. Direct Equipment cost 35.59
11.Total Direct Cost 37.43
SUMMARY CAPPING LAYER
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
20.00 2.35 64.70
Total Direct Cost 87.04 Profit 0.07 Indirect cost 0.15
AGGREGATE UNIT COST= 106.194607071627
file :///co nversi on/tmp/activity_task_ scratch/539 074 848 .xl s,AN ALYSIS
Price Analysis sheet
CONSULTANT S/OMO ZONE CONSTRUCTION AND DESIGN CONTRACTOR ________________ DATE 8/31/2021
0.00 Load Counter/Data Collector 1 15.04 15.04 Wheel Loader - 3m3 1 649.75 649.75
0.00 0.00 Dump Truck - 16m3 6 516.50 3099.00
0.00 0.00
0.00 0.00
0.00
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 15.04 SUBTOTAL 3 = 3748.75
4. Performance Rate/Hr 160.00
5. Direct Material Cost 0.00 6. Direct Labor Cost 0.09 7. Direct Equipment cost 23.43
11.Total Direct Cost 23.52
14.6 ITEM OF WORK G. Wearing Course Placing UNIT M3 Activity No
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Unit
Item Unit QTY cost Total Labor No Rate TOTAL Equipment No Rate Total cost
Item Unit QTY Unit Total Labor No Rate TOTAL Equipment No Rate Total cost
cost
0.00 Pavement Foreman 0.5 25.03 12.51 Motor Grader 1 1299.70 1299.70
0.00 Helper 1 30.00 30.00 Vibratory Roller 1 749.85 749.85
Water Truck Helper 2 10.36 20.71 Water Truck 2 466.50 933.00
0.00 Unskilled Labour 20 8.63 172.60
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 235.83 SUBTOTAL 3 = 2982.55
4. Performance Rate/Hr 77.00
5. Direct Material Cost 0.00 6. Direct Labor Cost 3.06 7. Direct Equipment cost 38.73
8.Small Plant &Tool Cost( 2%) 1.00
11.Total Direct Cost 41.80
SUMMARY NATURAL SUBBASE LAYER
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
20.00 3.69 67.85
Total Direct Cost 91.54 Profit 0.07 Indirect cost 0.15
AGGREGATE UNIT COST= 111.676866587379
file :///co nversi on/tmp/activity_task_ scratch/539 074 848 .xl s,AN ALYSIS
Price Analysis sheet
CONSULTANT S/OMO ZONE CONSTRUCTION AND DESIGN CONTRACTOR ________________ DATE 8/31/2021
Item Unit QTY Unit Total Labor No Rate TOTAL Equipment No Rate Total cost
cost
0.00 Pavement Foreman 1 25.03 25.03 Motor Grader 1 1299.70 1299.70
0.00 Grade Checker /Data Collector 1 30.00 30.00 Vibratory Roller 1 649.75 649.75
Water Truck Helper 2 10.36 20.71 Water Truck 2 466.50 933.00
0.00 Unskilled Labour 25 8.63 215.75
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 291.49 SUBTOTAL 3 = 2882.45
4. Performance Rate/Hr 70.00
5. Direct Material Cost 0.00 6. Direct Labor Cost 4.16 7. Direct Equipment cost 41.18
11.Total Direct Cost 45.34
SUMMARY ROAD BASE LAYER
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
20.97 9.58 191.29
Total Direct Cost 221.84 Profit 0.07 Indirect cost 0.15
AGGREGATE UNIT COST= 270.649140922144
file :///co nversi on/tmp/activity_task_ scratch/539 074 848 .xl s,AN ALYSIS
Price Analysis sheet
CONSULTANT S/OMO ZONE CONSTRUCTION AND DESIGN CONTRACTOR ________________ DATE 8/31/2021
file :///co nversi on/tmp/activity_task_ scratch/539 074 848 .xl s,AN ALYSIS
Price Analysis sheet
CONSULTANT S/OMO ZONE CONSTRUCTION AND DESIGN CONTRACTOR ________________ DATE 8/31/2021
0.00 Load Counter/Data Collector 1 30.00 30.00 Wheel Loader - 3m3 1 649.75 649.75
0.00 0.00 0.00 Dump Truck - 12m3 4 516.50 2066.00
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 30.00 SUBTOTAL 3 = 2715.75
4. Performance Rate/Hr 240.00
5. Direct Material Cost 0.00 6. Direct Labor Cost 0.13 7. Direct Equipment cost 11.32
11.Total Direct Cost 11.44
16.7 ITEM OF WORK G. ASPHALT BATCHING UNIT m2 Activity No
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Item Unit QTY Unit Total Labor No Rate TOTAL Equipment No Rate Total cost
cost
Bitumen KG 50 32.10 1604.99 Plant Foreman 1 70.00 70.00 Asphalt Plant - 100TPH 1 36988.00 36988.00
0.00 Load Counter/Data Collector 1 30.00 30.00 Wheel Loader - 3m3 1 649.75 649.75
Unskilled Labour 25 8.63 215.75
SUB TOTAL 1= 1604.99 SUB TOTAL 2 = 315.75 SUBTOTAL 3 = 37637.75
4. Performance Rate/Hr 28.80
5. Direct Material Cost 1604.99 6. Direct Labor Cost 10.96 7. Direct Equipment cost 1306.87
11.Total Direct Cost 2922.82
16.8 ITEM OF WORK H. ASPHALT HAULING TO PLACING UNIT m2 Activity No
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Item Unit QTY Unit Total Labor No Rate TOTAL Equipment No Rate Total cost
cost
0.00 0.00 DUMP TRUCK 4 516.50 2066.00
0.00
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 0.00 SUBTOTAL 3 = 2066.00
4. Performance Rate/Hr 233.74
5. Direct Material Cost 0.00 6. Direct Labor Cost 0.00 7. Direct Equipment cost 8.84
11.Total Direct Cost 8.84
16.9 ITEM OF WORK I. ASPHALT PLACING-5CM UNIT m2 Activity No
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Item Unit QTY Unit Total Labor No Rate TOTAL Equipment No Rate Total cost
cost
file :///co nversi on/tmp/activity_task_ scratch/539 074 848 .xl s,AN ALYSIS
Price Analysis sheet
CONSULTANT S/OMO ZONE CONSTRUCTION AND DESIGN CONTRACTOR ________________ DATE 8/31/2021
file :///co nversi on/tmp/activity_task_ scratch/539 074 848 .xl s,AN ALYSIS
Price Analysis sheet
CONSULTANT S/OMO ZONE CONSTRUCTION AND DESIGN CONTRACTOR ________________ DATE 8/31/2021
17.0 ITEM OF WORK 1M*1M*1M GABION MESH WITH STON UNIT M3 Activity No
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Unit
Item Unit QTY cost Total Labor No Rate TOTAL Equipment No Rate Total cost
stone m3 1 ### 281.25 Mason Foreman 1 25.03 25.03 0.00
Gabion Mesh 1*1*1 m3 1 ### 380.00 Mason 2 35.63 71.26 0.00
Unskilled Labour 20 8.63 172.60
SUB TOTAL 1= 661.25 SUB TOTAL 2 = 268.89 SUBTOTAL 3 = 0.00
4. Performance Rate/Hr 2.50
5. Direct Material Cost 661.25 6. Direct Labor Cost 107.56 7. Direct Equipment cost 0.00
Profit 0.07 Indirect cost 0.15
11.Total Direct Cost 768.81 12. Aggregate unit cost 937.94
18.0 ITEM OF WORK Conctete UNIT M3 Activity No
18.1 ITEM OF WORK C-15 Conctete/sub st/with out form work Major UNIT M3 Activity No
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Item Unit QTY Unit Total Labor No Rate TOTAL Equipment No Rate Total cost
cost
Cement KG 294 6.10 1793.40 Concrete Foreman 1 25.03 25.03 Concrete Mixer .5m3 2.00 213.32 426.64
Fine Aggregate M3 0.46 ### 115.00 Mason 4 35.63 142.52 Vibrator 4 54.81 219.25
Coarse Aggregate M3 0.80 ### 475.00 Carpenter 2 29.22 58.44 Water Tanker 12000-140 0.5 30.00 15.00
Unskilled Labour 52 8.63 448.77
SUB TOTAL 1= 2383.40 SUB TOTAL 2 = 674.75 SUBTOTAL 3 = 660.89
4. Performance Rate/Hr 6.00
5. Direct Material Cost 2383.40 6. Direct Labor Cost 112.46 7. Direct Equipment cost 110.15
11.Total Direct Cost 2606.01
Profit 0.07 Indirect cost 0.15
AGGREGATE UNIT COST= 3179.32882968037
19.0 ITEM OF WORK Site Clearing light UNIT Ha Activity No 411.00
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Unit
Item Unit QTY cost Total Labor No Rate TOTAL Equipment No Rate Total cost
Earthwork Forman 1 25.03 25.03 Dozer 200-250 FWHP 1 1999.30 1999.30
Grade Checker /Data Collector 1 30.00 30.00 Hand Tools 1 0.00
Unskilled Laborer 2 8.63 17.26
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 72.29 SUBTOTAL 3 = 1999.30
4. Performance Rate/Hr 4225.00
5. Direct Material Cost 0.00 6. Direct Labor Cost 0.02 7. Direct Equipment cost 0.47
9. Profit 0.07 10. Indirect cost 0.15
11.Total Direct Cost 0.49 12. Aggregate unit cost 0.60
20.0 ITEM OF WORK Site Clearing heavy UNIT Ha Activity No 411.00
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Unit
Item Unit QTY cost Total Labor No Rate TOTAL Equipment No Rate Total cost
Earthwork Forman 1 25.03 25.03 Dozer 200-250 FWHP 1 1999.30 1999.30
Grade Checker /Data Collector 1 30.00 30.00 Hand Tools 1 0.00
Unskilled Laborer 2 8.63 17.26
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 72.29 SUBTOTAL 3 = 1999.30
4. Performance Rate/Hr 3025.00
5. Direct Material Cost 0.00 6. Direct Labor Cost 0.02 7. Direct Equipment cost 0.66
9. Profit 0.07 10. Indirect cost 0.15
11.Total Direct Cost 0.68 12. Aggregate unit cost 0.84
21.0 ITEM OF WORK tree cutting diam( 20-50cm) UNIT Ha Activity No 411.00
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Item Unit QTY Unit Total Labor No Rate TOTAL Equipment No Rate Total cost
cost
Earthwork Forman 1 25.03 25.03 Dozer 200-250 FWHP 1 1999.30 1999.30
Grade Checker /Data Collector 1 30.00 30.00 Hand Tools 1 0.00
Unskilled Laborer 2 8.63 17.26
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 72.29 SUBTOTAL 3 = 1999.30
4. Performance Rate/Hr 150.00
5. Direct Material Cost 0.00 6. Direct Labor Cost 0.48 7. Direct Equipment cost 13.33
9. Profit 0.07 10. Indirect cost 0.15
11.Total Direct Cost 13.81 12. Aggregate unit cost 16.85
22.0 ITEM OF WORK tree cutting diam( >50cm) UNIT Ha Activity No 411.00
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Item Unit QTY Unit Total Labor No Rate TOTAL Equipment No Rate Total cost
cost
Earthwork Forman 1 25.03 25.03 Dozer 200-250 FWHP 1 1999.30 1999.30
Grade Checker /Data Collector 1 30.00 30.00 Hand Tools 1 0.00
Unskilled Laborer 2 8.63 17.26
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 72.29 SUBTOTAL 3 = 1999.30
4. Performance Rate/Hr 75.00
5. Direct Material Cost 0.00 6. Direct Labor Cost 0.96 7. Direct Equipment cost 26.66
9. Profit 0.07 10. Indirect cost 0.15
11.Total Direct Cost 27.62 12. Aggregate unit cost 33.70
23.0 ITEM OF WORK strump removal(20-50) UNIT Ha Activity No 411.00
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Unit
Item Unit QTY Total Labor No Rate TOTAL Equipment No Rate Total cost
cost
Earthwork Forman 1 25.03 25.03 Dozer 200-250 FWHP 1 1999.30 1999.30
Grade Checker /Data Collector 1 30.00 30.00 Hand Tools 1 0.00
Unskilled Laborer 2 8.63 17.26
SUB TOTAL 1= SUB TOTAL 2 = 72.29 SUBTOTAL 3 = 1999.30
4. Performance Rate/Hr 142.50
5. Direct Material Cost 0.00 6. Direct Labor Cost 0.51 7. Direct Equipment cost 14.03
9. Profit 0.07 10. Indirect cost 0.15
11.Total Direct Cost 14.54 12. Aggregate unit cost 17.74
24.0 ITEM OF WORK strump removal(>50) UNIT Ha Activity No 411.00
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Unit
Item Unit QTY cost Total Labor No Rate TOTAL Equipment No Rate Total cost
Earthwork Forman 1 25.03 25.03 Dozer 200-250 FWHP 1 1999.30 1999.30
Grade Checker /Data Collector 1 30.00 30.00 Hand Tools 1 0.00
Unskilled Laborer 2 8.63 17.26
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 72.29 SUBTOTAL 3 = 1999.30
4. Performance Rate/Hr 36.00
5. Direct Material Cost 0.00 6. Direct Labor Cost 2.01 7. Direct Equipment cost 55.54
9. Profit 0.07 10. Indirect cost 0.15
11.Total Direct Cost 57.54 12. Aggregate unit cost 70.20
25.0 ITEM OF WORK Bolder removal diam( 50-100cm) UNIT Ha Activity No 411.00
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Item Unit QTY Unit Total Labor No Rate TOTAL Equipment No Rate Total cost
cost
Earthwork Forman 1 25.03 25.03 Dozer 200-250 FWHP 1 1999.30 1999.30
Grade Checker /Data Collector 1 30.00 30.00 Hand Tools 1 0.00
Unskilled Laborer 2 8.63 17.26
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 72.29 SUBTOTAL 3 = 1999.30
4. Performance Rate/Hr 47.50
5. Direct Material Cost 0.00 6. Direct Labor Cost 1.52 7. Direct Equipment cost 42.09
9. Profit 0.07 10. Indirect cost 0.15
11.Total Direct Cost 43.61 12. Aggregate unit cost 53.21
26.0 ITEM OF WORK Bolder removal diam( >100cm) UNIT Ha Activity No 411.00
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Item Unit QTY Unit Total Labor No Rate TOTAL Equipment No Rate Total cost
cost
Earthwork Forman 1 25.03 25.03 Dozer 200-250 FWHP 1 1999.30 1999.30
Grade Checker /Data Collector 1 30.00 30.00 Hand Tools 1 0.00
Unskilled Laborer 2 8.63 17.26
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 72.29 SUBTOTAL 3 = 1999.30
4. Performance Rate/Hr 29.69
5. Direct Material Cost 0.00 6. Direct Labor Cost 2.43 7. Direct Equipment cost 67.34
9. Profit 0.07 10. Indirect cost 0.15
11.Total Direct Cost 69.78 12. Aggregate unit cost 85.13
27.0 ITEM OF WORK seeting out of Horizontal allignment UNIT Ha Activity No 411.00
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Unit
Item Unit QTY Total Labor No Rate TOTAL Equipment No Rate Total cost
cost
General Forman 1 30.82 30.82 Total Station 1 100.00 100.00
Surveyor 1 29.84 29.84
Unskilled Laborer 2 8.63 17.26
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 77.92 SUBTOTAL 3 = 100.00
4. Performance Rate/Hr 100.00
5. Direct Material Cost 0.00 6. Direct Labor Cost 0.78 7. Direct Equipment cost 1.00
9. Profit 0.07 10. Indirect cost 0.15
11.Total Direct Cost 1.78 12. Aggregate unit cost 2.17
28.0 ITEM OF WORK seeting out of vertical allignment UNIT Ha Activity No 411.00
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Unit
Item Unit QTY Total Labor No Rate TOTAL Equipment No Rate Total cost
cost
General Forman 1 25.03 25.03 Total Station 1 100.00 100.00
Surveyor 1 29.84 29.84
Unskilled Laborer 2 8.63 17.26
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 72.12 SUBTOTAL 3 = 100.00
4. Performance Rate/Hr 81.25
5. Direct Material Cost 0.00 6. Direct Labor Cost 0.89 7. Direct Equipment cost 1.23
9. Profit 0.07 10. Indirect cost 0.15
11.Total Direct Cost 2.12 12. Aggregate unit cost 2.58
29.0 ITEM OF WORK slotting( cutting and leveling) UNIT M3 Activity No 421B
31.0 ITEM OF WORK fill with excavated material 0.1-1 km UNIT M3 Activity No
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Unit
Item Unit QTY cost Total Labor No Rate TOTAL Equipment No Rate Total cost
0.00 Earthwork Foreman 0.5 25.03 12.51 Motor Grader 1 1299.70 1299.70
0.00 Grade Checker /Data Collector 1 30.00 30.00 Vibratory Roller 1 0.00 0.00
Water Truck Helper 1 10.36 10.36 Water Truck 1 466.50 466.50
0.00 Unskilled Labour 10 8.63 86.30
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 139.17 SUBTOTAL 3 = 1766.20
4. Performance Rate/Hr 20
5. Direct Material Cost 0.00 6. Direct Labor Cost 6.96 7. Direct Equipment cost 88.31
11.Total Direct Cost 95.27 Profit 0.07 Indirect cost 0.15
AGGREGATE UNIT COST= 101.94
file :///co nversi on/tmp/activity_task_ scratch/539 074 848 .xl s,AN ALYSIS
PROJECT :
LOCATION :
CLIENT :
CONTRACTOR :
CONSULTANT :
DATE :
DISTANCE FROM AA :
ASSUMED OVERHEAD :
ASSUMED PROFIT :
WEATHER REGION= :
NORMAL WORKING HOURS= :
AVERAGE MONTHLY LEAVE, MEETING DAYS,
ETC= :
WD AVAILABLE BEFOR ADJUSTMENTS :
WD AVAILABLE AFTER ADJUSTMENTS :
Cost for Compensation/m3
Hauling distance for cart away site
Hauling distance from quarry to Crusher site
Hauling distance from Crusher to site
Hauling distance from structural backfill quarry to site
Hauling distance from subbase quarry to site
Hauling distance from capping material quarry to site
Hauling distance from borrow material quarry to site
Hauling distance from Crusher site to Asphalt Batching
plant
Hauling distance from Asphalt Batching plant to site
2KM ROAD PROJECT AVERAGE DAYS LOS
JINKA
________________ 2. SUNDAY
________________ 3. HOLIDAY
S/OMO ZONE CONSTRUCTION AND DESIGN 4. 1/2 SATURDAY
31-Aug-21 5. LEAVE, MEETING,
LOST WDs
WD AVAILABLE BEFO
750 1. DUE TO WEATHER
15% REGION
7% I
III II
8 III
3 IV
238 LOST DUE TO WEATH
200.5 WD AVAILABLE AFTE
20
2
2
5
1
2
2
1
2
2
AVERAGE DAYS LOST
2. SUNDAY
3. HOLIDAY
4. 1/2 SATURDAY
5. LEAVE, MEETING, ETC.
LOST WDs
WD AVAILABLE BEFOR ADJUSTMENTS
1. DUE TO WEATHER
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
17.5 17.5 12.5 7.5 2.5 5 10
12.5 17.5 10 2.5 2.5 5
7.5 12.5 7.5 5
12.5 III 3
37.5 IV 4
200.5 5
6
7
7
7
7
7
7
7
7
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
ROAD CONSTRUCTION WORKS BENCH MARK HOURLY PRODUCTIVITY
SERIA
TYPE OF TASKS UNDER EACH
L UNIT
OPERATION OPERATION
NO
CLEARING &
1 Clearing & Grubbing HA
GRUBBING
ROAD BED
2 Road Bed Preparation M2
PREPARATION
SERIA
L TYPE OF OPERATION
TASKS UNDER EACH OPERATIONUNIT
NO
LM3
LM3
LM3
SERIA
L TYPE OF OPERATION
TASKS UNDER EACH OPERATIONUNIT
NO
PIPE INSTALLATION
17 Pipe Diameter - 36''/900mm PCS
CLASS B
BEDDING
PIPE INSTALLATION
18 Pipe Diameter - 36''/900mm PCS
CLASS C
BEDDING
Paved Waterway M2
Box Culvert KG
Slab Culvert KG
Bridge Structure KG
Concrete Class C M3
22 FORM WORK Slab Culvert M2
Box Culvert M2
Bridge Structure M2
STRUCTURAL
24 Normal Excavation LM3
EXCAVATION
STRUCTURAL
25 Excavated Material CM3
BACKFIL
MATERIAL
MACHINE CREW REQUIREME
NT
DESCRIPTIO
DESCRIPTION NO UNIT QTY
N
Bulldozer - D8R 1
Bulldozer - D8R 1
Motor Grader 1
Vibratory Roller 1
Water Truck 1
Bulldozer - D8R 1
Bulldozer - D8R 1
Bulldozer - D8R 1
Bulldozer - D8R 1
Motor Grader 1
Vibratory Roller 1
Water Truck 1
Bulldozer - D8R 1
MATERIAL
MACHINE CREW REQUIREME
NT
DESCRIPTIO
DESCRIPTION NO UNIT QTY
N
Bulldozer - D8R 1
Bulldozer - D8R 1
Wheel Loader - 3m3 1
Dump Truck - 12m3 3
Crushing Plant - 75TPH 1
Wheel Loader - 3m3 1
DESCRIPTIO
DESCRIPTION NO UNIT QTY
N
Tamrock Drilling Machine 1
MATERIAL
MACHINE CREW REQUIREME
NT
DESCRIPTIO
DESCRIPTION NO UNIT QTY
N
Mixer 500 Ltr 1 OPC Cement KG 113.4
Concrete Vibrator 2 Fine Aggregat LM3 0.127
Pipe Mould 36'' 30 Coarse Aggreg LM3 0.227
Water Truck 0.5 Reinforcemen KG 24.57
Water Tanker 10,000 Ltr 1 Reinforcemen KG
Tie Wire 1. KG 0.491
Mixer 500 Ltr 1 OPC Cement KG 147
Concrete Vibrator 2 Fine Aggregat LM3 0.165
Pipe Mould 36'' 30 Coarse Aggreg LM3 0.294
Water Truck 0.5 Reinforcemen KG 32.865
Water Tanker 10,000 Ltr 1 Reinforcemen KG
Tie Wire 1. KG 0.657
Mixer 500 Ltr 1 OPC Cement KG 176.4
Concrete Vibrator 2 Fine Aggregat LM3 0.197
Pipe Mould 36'' 30 Coarse Aggreg LM3 0.353
Water Truck 0.5 Reinforcemen KG 54.411
Water Tanker 10,000 Ltr 1 Reinforcemen KG
Tie Wire 1. KG 1.088
Courier Truck 1
Courier Truck 1
Courier Truck 1
Stone M3 1.45
Cement Morta M3 0.33
Stone M3 1.45
Cement Morta M3 0.33
Stone M3 0.29
Cement Morta M3 0.066
Reinforcemen KG 1.05
Tie Wire KG 0.02
Reinforcemen KG 1.05
Tie Wire KG 0.02
Reinforcemen KG 1.05
Tie Wire KG 0.02
Reinforcemen KG 1.05
Tie Wire KG 0.02
Excavator 1
Dump Truck - 12m3 3
Excavator 1
Dump Truck - 12m3 4
Excavator 1
Dump Truck - 12m3 7
Excavator 1
Dump Truck - 12m3 3
Compressor 1 Power Jel KG 0.16
Jack Hammer 2 ANFO KG 0.64
Blasting Machine Detonator PCS 0.02
Detonating Co M 0.7
Hand Driven Roller 1
Water Tanker - 1M3 1
Hand Driven Roller 1 Borrow Materi LM3 1.43
Water Tanker - 1M3 1
Concrete Mixer 360 Ltrs 1 Cement KG 617.4
Water Truck 0.5 Fine Aggregat M3 1.01
Water Tanker 10,000 Ltrs 1
Concrete Mixer 360 Ltrs 1 Cement KG 463.05
Water Truck 0.5 Fine Aggregat M3 1.13
Water Tanker 10,000 Ltrs 1
HOURL
Y ERA
MANPOWER CREW
PRODU CODE
CTION
BENCH TENDER
DESCRIPTION NO
MARK ING
Earthwork Foreman 1 0.15 0.15 411
Grade Checker /Data Collector 1
Unskilled Labour 2
Earthwork Foreman 1 500 500 418
Grade Checker /Data Collector 1
Water Truck Helper 1
Unskilled Labour 2
HOURL HOURL
Y Y
ERA
MANPOWER CREW
CODE
PRODU PRODU
CTION CTION
DESCRIPTION NO
Earthwork Foreman 0.5 114 114 421A
Data Collector 1
Load Counter/Data Collector 2 240 240 SUR
HOURL HOURL
Y Y
ERA
MANPOWER CREW
CODE
PRODU PRODU
CTION CTION
DESCRIPTION NO
Production Foreman 1 3 3 SUR
Mason 1
Bar Bender 6
Data Collector 1
Bar Bender Helpers 6
Unskilled Labour 25
Production Foreman 1 3 3 SUR
Mason 1
Bar Bender 8
Data Collector 1
Bar Bender Helpers 8
Unskilled Labour 25
Production Foreman 1 3 3 SUR
Mason 1
Bar Bender 13
Data Collector 1
Bar Bender Helpers 13
Unskilled Labour 25
Gang Leader / Data Collector 1 2.7 2.7 SUR
Unskilled Labour 8
Gang Leader / Data Collector 1 2.7 2.7 SUR
Unskilled Labour 8
Gang Leader / Data Collector 1 2.0 2.0 SUR
Unskilled Labour 8
HOURL HOURL
Y Y
ERA
MANPOWER CREW
CODE
DESCRIPTION NO PRODU PRODU
CTION CTION
120 120 SUR
Grade Checker/Data Collector 2
SUR = 1.5 Ha/day - 10 Hrs for D8R ERA Standard Performance Day = 7 Hours
ERA = 350Bm3/day
1 Earthwork Foreman for 2 Dozers
33m/hr diam 75mm & 2.5m x 2.5m Plot size … 11.25m x 50m x 5m ….. 6 x 21 = 126 holes
100TPH/1.5
EQUIVALENT TO HAULING
Hauling Distance = 1 Km Loader Cycle Time = 45 sec/1.5 Lm3
Dump Truck Speed = 15 Km/hr Bank/Loose = 0.6
ERA = 21 LM3/HR
ERA = 39 LM3/HR
1.5KM/10 Hours
BASIC ASSUMPTIONS REMARK
33m/hr diam 75mm & 2.5m x 2.5m Plot size … 11.25m x 50m x 5m ….. 6 x 21 = 126 holes
EQUIVALENT TO HAULING
Hauling Distance = 1 Km Loader Cycle Time = 45 sec/1.5 Lm3
Dump Truck
Standard Speed = 15 Km/hr
Mix Design Bank/Loose = 0.6
0-3(45%), 0-3(3m3/hr), 3-6(4m3/hr), 6-12(6m3/hr), 12-19(13m3/hr)
3-6(10%), 6-12(20%), 12-19(25%) Sand Making Recrushing = 7m3/hr
Standard Mix Design
0-3(45%), 3- 0-3(5m3/hr), 3-6(8m3/hr), 6-12(10m3/hr), 12-19(12m3/hr)
6(10%), 6-12(20%), 12-19(25%) Sand Making Recrushing = 7m3/hr
33m/hr diam 75mm & 2.5m x 2.5m Plot size … 11.25m x 50m x 5m ….. 6 x 21 = 126 holes
EQUIVALENT TO HAULING
Hauling Distance = 1 Km Loader Cycle Time = 45 sec/1.5 Lm3
Dump Truck Speed = 15 Km/hr Bank/Loose = 0.6
Hauling Distance = 20 km Loader Cycle Time = 45 sec/3 Lm3
Average DT Speed = 35 km/hr
15 M3 / Day - 10 Hrs
15 M3 / Day - 10 Hrs
1 = 126 holes
2.4 192
160
1 = 126 holes
1 = 126 holes
, 12-19(13m3/hr)
), 12-19(12m3/hr)
1.506024
1.66 2375.46 25000
84
0.938095 65.66667 78.8
109.2
1.516667
1 = 126 holes
LIGHT DUTY EQUIPMENT
SERIAL
TYPE OF LIGHT DUTY EQUIPMENT HOURLY RENTAL HOURLY FUEL TYPE OF FUEL HOURLY
RATE COMSUMPTION (Lt.) FUEL COST/ Lt. EQUIPMENT RATE
NO
1 CONCRETE MIXER - 500 LTR 200.00 0.80 DIESEL 16.65 213.32
2 CONCRETE MIXER - 360 LTR 150.00 0.50 DIESEL 16.65 158.33
3 CONCRETE VIBRATOR 50.00 0.25 BENZINE 19.25 54.81
4 AIR COMPRESSOR 300.00 5.00 DIESEL 16.65 383.25
5 TYRE AIR COMPRESSOR 100.00 0.25 DIESEL 16.65 104.16
6 AIR BLOWER 200.00 - - 0 200.00
7 PLATE COMPACTOR 100.00 0.60 BENZINE 19.25 111.55
8 TAMPING COMPACTOR 100.00 0.60 BENZINE 19.25 111.55
9 HAND DRIVEN ROLLER 120.00 0.80 DIESEL 16.65 133.32
10 FLOODLIGHT GENERATOR 25.00 0.80 DIESEL 16.65 38.32
11 FARM TRACTOR WITH TRAILER 63.00 4.00 DIESEL 16.65 129.60
12 FRONT END DUMPER 85.00 1.50 DIESEL 16.65 109.98
13 WELDING GENERATOR 30.00 0.80 DIESEL 16.65 43.32
14 WELDING TRANSFORMER 30.00 - - 0 30.00
15 BREAKING JACK HAMMER 30.00 - - 0 30.00
16 DRILLING JACK HAMMER 40.00 - - 0 40.00
17 HYDRAULIC ROCK BREAKER 750.00 - - 0 750.00
18 BLASTING MACHINE 50.00 - - 0 50.00
19 WATER TANKER 10,000 LTR 30.00 - - 0 30.00
20 WATER TANKER 5,000 LTR 25.00 - - 0 25.00
21 WATER TANKER 1,000 LTR 20.00 - - 0 20.00
22 WATER PUMP 10.00 0.25 BENZINE 19.25 14.81
23 HCB MACHINE 15.00 - - 0 15.00
24 CONCRETE PIPE MOULD - 36'' 30.00 - - 0 30.00
25 CONCRETE PIPE MOULD - 42'' 30.00 - - 0 30.00
26 CONCRETE PIPE MOULD - 48'' 30.00 - - 0 30.00
27 TOTAL STATION 100.00 - - 0 100.00
28 LEVELLING INSTRUMENT 15.00 - - 0 15.00
29 BASE STATION RADIOS 15.00 - - 0 15.00
30 VEHICLE MOUNTED RADIOS 9.00 - - 0 9.00
31 HAND HELD RADIOS 2.00 - - 0 2.00
Mobilization &
Hourly Rental Demobilization Hourly Rental
S.No Equipment Type Unit Rate at Source Cost (%) Rate at Project
1 CONCRETE MIXER - 500 LTR Birr 120.00 5% 126
2 CONCRETE VIBRATOR Birr 37.50 5% 39
3 WATER TANKER 10,000 LTR Birr 31.25 5% 33
4 WATER TANKER 1,000 LTR Birr 31.25 5% 33
5 WATER PUMP Birr 31.25 5% 33
6 AIR COMPRESSOR Birr 31.25 5% 33
Distance to
S.No Equipment Type Unit Location Name Cost at Source Site (km) Qt/unit
7 STEEL PANNEL M2 Addis Ababa 40 0.31
8 WOODEN PLUNK - 25MM M2 Addis Ababa 90 0.21
9 EUCALAPTUS - 10/15MM M Addis Ababa 4 0.002
Transport Cost at
Factor Cost/Unit Project
1 126.25 546
1 - 500
1 - 60
1 - 60
1 - 40
1 - 36
1 - 30
1 9.97 10
1 - 30,000
1 5.60 386
1 - 104
1 - 800
- 50
1 - 174
1 - 174
1 - 60
1 - 600
1 - 17
1 - 19
Transport Cost at
Factor Cost/Unit Project
Total
Daily
Cost
165 20.59 126.52
200 25.03 197.476449615312 365.40
247 30.82 450.00
234 29.22 426.60
200 25.03 192.69
200 25.03
200 25.03
99 12.33
120 15.04
120 15.04
285 35.63
200 25.03 165 162.7397
200 25.03
200 25.03 59400 162.7397
83 10.36
69 8.63
239 29.84
28800
62.5
37.5
300
Transport Cost at
Factor Cost/Unit Project
1.5 - 40
1 - 90 1.2
1.50 - 4 108
18
10
11
31
50
51
52
53
54
55
56
57
51
58
59
60
61
14
15
16
17
17
17
19
20
21
28
22
29
30
25
26
27
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
22
23
24
HOURLY
SERIAL
LABOUR BY TRADE SALARY +
NO
BENEFITS
Earthwork
0.00 Foreman 0.5 15.00 7.50
0.00
Unskilled
0.00 Labour 12 3.13 37.56
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 45.06
4. Performance Rate/Hr 70
6. Direct Labor
5. Direct Material Cost 0.00 Cost 0.64
11.Total Direct Cost 18.02
Total Direct Cost 18.02 Profit 0.07
AGGREGATE UNIT COST=
Activity No
3.EQUIPMENT COST
SUBTOTAL 3 = 1216.35
CONSULTANT S/OMO ZONE CONSTRUCTION AND DESIGN CONTRACTOR ________________ DATE 8/31/2021
file:///conversion/tmp/activity_task_scratch/539074848.xls,Surface Treat
Price Analysis sheet
CONSULTANT S/OMO ZONE CONSTRUCTION AND DESIGN CONTRACTOR ________________ DATE 8/31/2021
m3 1 20.00 20.00 Quarry Foreman 1 25.03 25.03 Tamrock Drilling Mach 1 1849.65 1849.65
Data Collector 1 30.00 30.00
0.00 Unskilled Labour 2 8.63 17.26
SUB TOTAL 1= 20.00 SUB TOTAL 2 = 72.29 SUBTOTAL 3 =
4. Performance Rate/Hr 147.32
5. Direct Material Cost 20.00 6. Direct Labor Cost 0.49 7. Direct Equipment cost 12.56
11.Total Direct Cost 33.05
16.2 ITEM OF WORK B. Quarry Production-Blasting UNIT m2 Activity No
ITEM OF WORK B. Quarry Production-Blasting LOCATION Tigray
UNIT m3
Activity No 421B
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Unit
Item Unit QTY Total Labor No Rate TOTAL Equipment No Rate Total cost
cost
Power Jel KG 0.16 161.90 25.90 Blasting Technician 1 60.00 60.00 Blasting Machine 1 50.00 50.00
ANFO KG 0.64 131.90 84.42 Assistant/Data Collector 1 12.33 12.33 Truck 1 723.15 723.15
Detonator PCS 0.02 90.00 1.80 Unskilled Labour 15 8.63 129.45
Detonating Cord M 0.7 45.00 31.50 0.00
SUB TOTAL 1= 143.62 SUB TOTAL 2 = 201.78 SUBTOTAL 3 = 773.15
4. Performance Rate/Hr 147.32
5. Direct Material Cost 143.62 6. Direct Labor Cost 1.37 7. Direct Equipment cost 5.25
11.Total Direct Cost 150.24
16.3 ITEM OF WORK C. Quarry Production-Rock Breaking UNIT m2 Activity No
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Unit
Item Unit QTY Total Labor No Rate TOTAL Equipment No Rate Total cost
cost
0.00 Data Collector 1 12.33 12.33 Excavator with Hydraulic breaker
1 1316.35 1316.35
0.00
0.00 0.00
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 12.33 SUBTOTAL 3 = 1316.35
4. Performance Rate/Hr 120.00
5. Direct Material Cost 0.00 6. Direct Labor Cost 0.10 7. Direct Equipment cost 10.97
11.Total Direct Cost 11.07
16.4 ITEM OF WORK D. Hauling to Crushing Plant UNIT m2 Activity No
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Unit
Item Unit QTY Total Labor No Rate TOTAL Equipment No Rate Total cost
cost
0.00 Load Counter/Data Collector 1 12.33 12.33 Chain Excavator - 1.5m 1 1316.35 1316.35 Hauling Distance (km)=
0.00 Dump Truck - m3 4 516.50 2066.00 Dump Truck Speed(Km/hr) =
Loader Cycle Time (sec/3
0.00 0.00 0.00 Lm3)=
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 12.33 SUBTOTAL 3 = 3382.35 Bank/Loose =
4. Performance Rate/Hr 120.00 dump Truck capacity (m3)(Km/h
5. Direct Material Cost 0.00 6. Direct Labor Cost 0.10 7. Direct Equipment cost 28.19 Loader Capacity (m3)=
11.Total Direct Cost 28.29 Loading Time (sec/vehicle)
16.5 ITEM OF WORK E. Material Crushing UNIT m2 Activity No Hauling time (s)=
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST
Unit
Item Unit QTY Total Labor No Rate TOTAL Equipment No Rate Total cost
cost
0.00 Load Counter/Data Collector 1 30.00 30.00 Wheel Loader - 3m3 1 649.75 649.75 Hauling Distance (km)=
0.00 0.00 0.00 Dump Truck - 12m3 6 516.50 3099.00 Dump Truck Speed(Km/hr) =
Loader Cycle Time (sec/3
SUB TOTAL 1= 0.00 SUB TOTAL 2 = 30.00 SUBTOTAL 3 = 3748.75 Lm3)=
4. Performance Rate/Hr 240.00 Bank/Loose =
5. Direct Material Cost 0.00 6. Direct Labor Cost 0.13 7. Direct Equipment cost 15.62 dump Truck capacity (m3)(Km/h
11.Total Direct Cost 15.74 Loader Capacity (m3)=
SUMMARY Aggragte Loading Time (sec/vehicle)
1.MATERIAL COST 2.LABOUR COST 3.EQUIPMENT COST Hauling time (s)=
163.62 7.53 221.16
Total Direct Cost 392.31 Profit 0.07 Indirect cost 0.15
AGGREGATE UNIT COST= 478.617251917186
file:///conversion/tmp/activity_task_scratch/539074848.xls,Surface Treat
Consultant:- NOMY ENGINEERING
Date:-march, 2017 AVARAGE MAN POWER PRICE STUDY
COST PER DAY OF DIFFERENET STUDIES AVERAGE DAILY COST AVERAGE HOURLY COST
No Descrption STUDY ONE STUDY TWO STUDY THREE STUDY FOUR STUDY FIVE STUDY SIX WITH APPROXIMATION WITH APPROXIMATION
1 General forman 250 200 200 300 280 270 250 31 250
4 Daily labor 80 70 75 65 60 70 70 9
6 Assistance Carpenter 80 70 75 65 60 70 70 9
7 Electrician 150 140 180 200 150 140 160 20