Waste Reduction by Lean Construction - Office Building Case Study

Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

IOP Conference Series: Materials Science and Engineering

PAPER • OPEN ACCESS

Waste Reduction by Lean Construction - Office Building Case Study


To cite this article: Piotr Nowotarski et al 2019 IOP Conf. Ser.: Mater. Sci. Eng. 603 042061

View the article online for updates and enhancements.

This content was downloaded from IP address 179.6.33.91 on 22/10/2020 at 18:43


WMCAUS 2019 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 603 (2019) 042061 doi:10.1088/1757-899X/603/4/042061

Waste Reduction by Lean Construction - Office Building Case


Study

Piotr Nowotarski 1, Jerzy Paslawski 1, Jedrzej Skwarek 1


1
Poznan University of Technology, Plac Marii Skłodowskiej-Curie 5, 60-965 Poznań,
Poland

[email protected]

Abstract. The proper organization and planning of building processes plays an increasingly
important role in building projects, and appropriate management is becoming a more frequent
problem. Tools of quality management are very often used in other areas of business, such as
automotive, aerospace and production, unfortunately, rarely in the field of construction. The
main goal of this article is to show that individual quality management tools and Lean
Construction tools can be used in construction, and their use brings significant and visible
benefits. Authors present their work as an example of implementing these tools in building
processes at the construction of Pixel office buildings in Poznań. Authors present the basic
concepts related to quality management and the tools used in the field of Lean Construction as
well as assumptions of Lean Management. This aims to introduce the reader to the main concept,
assumptions and allows to learn the principles of lean management. The reader needs to be
aware, that all company employees and suppliers must be involved in introducing Lean
Management to the enterprise, starting with the owner and ending with the employee. It is not
possible to implement a lean philosophy into a company, without understanding the basics and
purpose for which they were introduced. Practical part of the article is devoted to a detailed
analysis construction process using the well-known Six Sigma cycle DMAIC - an abbreviation
of the words: Define - Measure - Analyze - Improve - Control. The analysis was carried out on
the basis of own knowledge and interviews with the construction management and employees of
subcontracting companies present at the construction site. Results are presented in the form of
conclusions. It can be said that using quality management tools (mainly Lean Management
principles) it is possible to visibly improve building processes and it is likely to achieve better
financial and time results during execution of works.

1. Introduction
The issue of improving the management of building processes is a complex topic. The necessity of
introducing changes has been discussed many times over the years, and the echoes of these discussions
are still present in the minds of scientists [1,2,3,4], who have been involved in topics for the last quarter
of a century. These calls for changes did not concern only the adoption of new technologies and tools,
nor the acquisition of new skills needed to support modern systems [5,6], but paid attention to systemic
and organizational problems and the need to promote sustainable development in construction [7]. One
of the methods proposed by researchers in improving construction production was and is the application
of modern management methods, e.g. Lean Management in construction.

Content from this work may be used under the terms of the Creative Commons Attribution 3.0 licence. Any further distribution
of this work must maintain attribution to the author(s) and the title of the work, journal citation and DOI.
Published under licence by IOP Publishing Ltd 1
WMCAUS 2019 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 603 (2019) 042061 doi:10.1088/1757-899X/603/4/042061

There are many publications showing the effectiveness of individual tools in the field of described
methodology [8,9,10]. One of them is DMAIC cycle that enables proper waste identification and
elimination.

2. Lean management and DMAIC


Lean Management is strategy to take out conceivable mistakes and wastes while execution of the general
processes, which is the reason why it is these days utilized for counteractive action, in case of occurring
problems. One of the techniques that can help in effective execution of good practices, which was
developed from the quality point of view is DMAIC.

DMAIC is an abbreviation from the words Define-Measure-Analyze-Improve-Control. This strategy


depends on procedure improvement as indicated by Deming cycle [11]. This philosophy offers a
structure for investigation and analysis of issues; driven by integral assets and procedures [12]. It
depends on 5 stages which ought to be executed one by one. Each step can be limited to the questions
and doubts that ought to be replied by its users, which are displayed in Figure 1.

Figure 1. Essential questions for consideration on each step of DMAIC Method [13]

The utilization of DMAIC method is getting more on more popular in processes that are connected
not exclusively to the production and manufacturing [14,15,16], yet in addition, IT [17,18,19],
healthcare [20,21,22], and numerous others just as to the construction [23,24,25]. This is the main reason
authors decided to use it for the purpose of research described in this article.

3. Case study
Authors decided to present the benefits of Lean Construction on the example of Pixel office building
construction site. The first of the cluster of five office buildings was commissioned in 2012 and is fully
leased by the largest auction company in Poland. Currently, two more were built. The investor also plans
to build two more. Buildings have 7 above-ground storeys, one technical storey and they have a shared
garage hall occupying 2 underground storeys. In the future, building No. 6 is also planned - a small
pavilion in the middle of the Pixel team, with conference functions and facilities for cyclists. Office
buildings are built according to today's ecological standards, all of them must obtain a BREEAM
certificate at the Very Good level, which shows that today's investors attach great importance to the use
of energy and the impact of buildings on the natural environment.

Research were carried out at the buildings no 4 and 5 which construction started in December 2016
and was ended in September 2018. Visualization of the buildings are presented in Fig. 2.

2
WMCAUS 2019 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 603 (2019) 042061 doi:10.1088/1757-899X/603/4/042061

Figure 2. Visualization of the objects [26]

During implementation of Lean Management principles, it was decided to use the DMAIC cycle - it
is a series of activities aimed at improving efficiency, reducing waste, optimizing processes. It is usually
used in manufacturing companies as an analysis of waste of time or excessive waste. The DMAIC cycle
is the main tool of the Six Sigma quality management method, but it is useful when implementing Lean
Construction principles at the construction site.

In each phase, many tools are used that are part of quality management. As an example, the Analyze
phase can be given: to determine the initial causes of a given problem, the Ishikawa Diagram, also
known as the fish bone diagram, is used. Immediately after that, the FMEA analysis was utilized to
identify the most problematic factors. In a simple way, when determining the weight of individual
problems, the main shortcomings of the whole process were found. At the end, 5WHY'S analysis was
performed - it helped to find the primary factors that caused the previously established causes. A cross-
section of these three methods in the Analyze phase, introduced a wide range of cause and effect. Each
of the processes was broken down into small particles from which a deep analysis could be carried out.
After the Analyze phase, the project team moved to the Improve phase. The reasons and effects
previously mentioned, as well as measurements from the Measure phase, allowed to start the
improvement phase with detailed data and focus on the possibilities to improve.

Lean Management implementation was performed on 3 processes:


 Bricklaying of walls from TeknoAmerBlok blocks
 Delivery and assembly of the building's facade
 Making concrete pots
Out of which bricklaying is presented in detail in this article.

3.1. Process description


When designing the buildings of PIXEL office park, it was decided that all walls in buildings that are
not reinforced concrete are to be built out of TeknoAmerBlok blocks. These are concrete blocks, in
recent times often used by architects who argue their penchant for them with the beauty of raw concrete.
Most of the walls created on the PIXEL site are facing, i.e. the wall is not covered with any cladding.
This creates many challenges for the bricklaying company, because the blocks must be clean and

3
WMCAUS 2019 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 603 (2019) 042061 doi:10.1088/1757-899X/603/4/042061

smooth, and the fugue between the individual blocks must be aesthetic, straight and withdrawn from the
wall by 1 cm. The example of finished wall is presented in Fig 3.

Figure 3. Finished wall on the analysed construction site.

The process starts with the delivery of material for construction. Pallets with blocks come to the
construction site with a truck and are unloaded using HDS or a tower crane. Then, the pallet is
transported to the place of proper installation.

Masonry works start from laying a layer of insulating foil or EPDM foil under the first row of blocks.
Then, using the mortar, the first layer of blocks is levelled. Subsequent works consist of building blocks
in accordance with the construction art and with several architect's assumptions.

One of the requirements is an aesthetic and even grout in the mortar layer. It has to be withdrawn from
the face wall by 1cm, and high by 1cm. The masonry team must also remember to make joints clean
when making walls, the mortar must not be on the face of the blocks. Depending on the length and
height of the wall, horizontal reinforcement is placed every few layers of mortar. They are designed to
strengthen walls and improve stability.

In the architectural design, holes were marked which should be made during the erection of walls.
Each hole shown on the project is described by a horizontal, vertical, elevation of the bottom of the hole
(relative and absolute) and the distance of the vertical axis of the hole from the walls, holes or other
characteristic points. The holes made by the masonry team are mainly intended for sanitary or electrical
installations. In addition, according to the design, door openings are made. As previously agreed, all
openings with dimensions smaller than 200x200mm, or smaller than φ200mm are cut by installation
companies after walling a given wall.

Unfortunately, not all openings in the architectural design are compatible with what is actually
needed at the construction site. The majority of openings is too large, after passing through the wall of
the installation, it turns out in some cases that the installation itself takes up about 10% of the area of
the hole. There is a problem related to the re-engagement of the masonry team to brick the majority of
the hole, and the use of additional material, sometimes in the finished wall after a design revision, some
hole cut or forge - this causes large material losses. It also happens that the hole already made is
unnecessary.

4
WMCAUS 2019 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 603 (2019) 042061 doi:10.1088/1757-899X/603/4/042061

The last stage of making the wall is to complement the gap between the last layer of the wall and the
ceiling. Filling has the function of dilation between the "working" ceiling and the wall. The gap is filled
with mineral wool, which is covered with a fireproof mass of the PROMASTOP-E type from the face
of the wall.

Figure 4. Execution of works at the construction site.

3.2. Define phase


The phase of introducing Lean Management in the analyzed process was started with the project card
(Fig. 5), in which the most important information related to the process was recorded. The project card
was created at the project meeting convened by the author, aimed at gathering information and setting
the DMAIC analysis goals. The main goal was to reduce the amount of waste on the building No. 5 in
relation to the waste generated on the building No. 4, where masonry work was started. This has a
positive effect on the construction costs of the walls on the construction site by reducing the expenditure
incurred to purchase the material. In the project team in addition to the construction engineer,
construction site manager, sanitary manager and site manager, the project manager also included a work
manager from the subcontractor - a company that executes the walls of TeknoAmerBlok blocks. As the
main scope of activity, the phase of preparation for commencement of masonry works combined with
the coordination of activities with the installation industry was adopted. The project also includes an
action plan to introduce Lean Management principles in the company.

In the Define phase, the project group determined what is the waste in the analyzed process. It was
assumed that the waste is called the blocks left after cutting the hole or cutting the block, which are not
suitable for reuse. Usually, it is eliminated by defects associated with edge piling and mortar stains on
the brick face. The size of the waste can be estimated on the basis of the amount of material ejected by
the subcontractor to the container.

5
WMCAUS 2019 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 603 (2019) 042061 doi:10.1088/1757-899X/603/4/042061

Figure 5. Project card of the project

3.3. Measure phase


The project used the buildings of concrete blocks and bricks to complete TeknoAmerBlok. Hollow
blocks come in three thicknesses: 12cm, 19cm and 24cm. The brick is full only in the thickness of 12cm.
Depending on the purpose of the wall and its fire resistance, the designer selected the appropriate
thicknesses. Table 1 presents a list of the number of square meters of blocks in accordance with the bill
made at the offer stage.

Table 1. A slightly more complex table with a narrow caption.


Material Type Use Waste Waste Total waste
[m2] [m2] [%] [%]
12cm brick 130 7 5,38
12cm airbrick 510 31 6,08
6,15
19cm airbrick 1060 72 6,79
24cm airbrick 645 36 5,58

In the Measure phase, it was decided to take base data created during the execution of walls on the
first of the two completed buildings. Figure 6 presents a list of waste and material used. These data were
adopted as a reference point for further work related to the reduction of wastage. It is worth noting that
the average value of waste for the entire construction process was 6.15%

3.4. Analyze phase


The Analyse phase was started with the Ishikawa diagram, which was to help determine the causes
leading to the creation of excessive waste. Thus, the five most important categories of causes were

6
WMCAUS 2019 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 603 (2019) 042061 doi:10.1088/1757-899X/603/4/042061

found, ie: People, Management, Material, Organization, Coordination. Figure 7 presents the results of
the analyses carried out:

Figure 6. Material use and waste.

Figure 7. Ishikawa diagram for analysed process .

Then, to determine which of the reasons for waste generation are the most important FMEA analysis,
which used to determine three specific factors taking into account the impact on cost / waste, the ability
to detect and the frequency of their occurrence. After conducting the FMEA analysis, it was found that
the most important reasons are:

 Lack of coordination between industries


 No reconciliation at the beginning of work
 Lack of coordination by designers

The WHY'S method 5 was used to further analyze the causes. It allowed to find the root causes of
the most important problems identified in the FMEA analysis which made it possible to perform some
actions influencing rate of waste in the improve phase.

7
WMCAUS 2019 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 603 (2019) 042061 doi:10.1088/1757-899X/603/4/042061

After conducting brainstorming in the above tables during the 5Why's method, the project group
distinguished three most important primary causes:

a) Lack of employees
b) Lack of joint meetings
c) Lack of integration

3.5. Improve phase


Based on the results from the previous phase, the project group proposed to the Project Manager the
following changes in the functioning of the construction process:

 Employment or transfer from another construction of at least one person from the general
supervision of the contractor
 A decision was made to accept one more person from the engineering team. The given person
will support the team in terms of inter-branch coordination, checking the correctness of the works
carried out and quality control during the works performed.
 Introduction to the schedule of weekly meetings with the bricklaying company together with the
installation subcontractor

Meetings, held once a week, will allow construction supervision and subcontractors to better
communicate, establish a daily work schedule and better synchronization of fronts of both companies.
In addition, a note from the meeting will contain a table in which will be marked places ready to brick
up. Additionally, in order to minimize problems related to communication, it was decided to introduce
the principle of informing each other also via e-mail. The messages will also be sent to the construction
manager, which will help solve possible problems in a wider circle. The team leader, ie. the Project
Manager, also decided to organize the integration trip of supervisory staff to improve communication in
the team.

The above recommendations were in the course of construction implemented after the experiments
during the works on the building No. 4. During the works on the building No. 5, a new construction
engineer was introduced, weekly meetings were initiated and attention was paid to providing
information by e-mail. The integration trip is planned after completion of the investment.

Figure 8. Material use and waste after improvements.

8
WMCAUS 2019 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 603 (2019) 042061 doi:10.1088/1757-899X/603/4/042061

3.6. Control phase


Implementation of improvements to the process aimed at reducing waste ran from March to July 2017.
As part of the inspection, during the works on the building No. 5, the measurements of the walls were
made together with the calculation of the waste generated. If too much non-reusable material was found,
the supervision was to conduct a special coordination meeting. The solutions introduced, proposed in
the IMPROVE phase, did not force supervision to organize such a meeting. In Figure 8, it can be seen
that the resulting waste decreased by almost half.

4. Conclusions
The process of introducing Lean Management principles in the wall masonry process carried out on the
construction site can be considered successful. Due to a thorough analysis of the causes and problems
by the called project group, it was possible to indicate the original causes of the resulting too large waste
during the erection of the walls of TeknoAmerBlok blocks. The conclusions are as follows:

 After the implementation of improvements, the amount of waste decreased by 6.15% to


3.39%, i.e. the waste is formed by half less.
 An additional engineer was hired, who by his work contributed to the improvement of the
analyzed process as well as to many others - for example during finishing works.
 Improved communication in the team, as well as with subcontractors, improved the
efficiency of the work of engineering staff as well as subordinate companies.

The purpose of the following analysis was achieved thanks to the implementation of the Lean
methodology using the DMAIC cycle. The solutions introduced to the bricklaying process were also
applied in other processes carried out on the PIXEL site in Poznań. According to the author, the tools
used should be implemented on the site earlier, already at the stage of "driving the first shovel".

Acknowledgment(s)
The publication was created with the support of statutory funds of Institute of Structural Engineering at
Poznan University of Technology and with the support of ConInno Academic Association

References
[1] A. Laufer, L.R. Tucker, Is construction project planning really doing its job? A critical
examination of focus, role and process. Construction Management and Economics, 1987, 5.3:
243-266.
[2] J. EGAN, Rethinking construction accelerating change. A Consultation Paper By The Strategic
Forum For Construction. 2002.
[3] L. Koskela, G. Howell, The underlying theory of project management is obsolete. In: Proceedings
of the PMI Research Conference. PMI, 2002. p. 293-302.
[4] M Gajzler, A. Dziadosz, P. Szymański. Podstawy wyboru metody wspomagającej podejmowanie
decyzji w budownictwie. Czasopismo Techniczne. Budownictwo 107 (2010): 71-84.
[5] O. Kapliński, A. Dziadosz, J. L. Zioberski. Próba standaryzacji procesu zarządzania na etapie
planowania i realizacji przedsięwzięć budowlanych. Zeszyty Naukowe Politechniki
Rzeszowskiej, Budownictwo i Inżynieria Środowiska 58.3 (2011): 11.
[6] C. DA, C. MILBERG, K. D. WALSH, Exploring lean construction practice, research, and
education. Engineering, Construction and Architectural Management, 2012, 19.5: 512-525.
[7] M. GICALA, A. SOBOTKA, Multi-criteria analysis of the construction technologies in the aspect
of sustainable development. In: MATEC Web of Conferences. EDP Sciences, 2018. p. 04001.
[8] G. BALLARD, G. HOWELL. Implementing lean construction: stabilizing work flow. Lean
construction, 1994, 101-110.
[9] B. A. Tezel, L. Koskela, P. Tzortzopoulo. Visual management in construction: Study report on
Brazilian cases. 2010.

9
WMCAUS 2019 IOP Publishing
IOP Conf. Series: Materials Science and Engineering 603 (2019) 042061 doi:10.1088/1757-899X/603/4/042061

[10] O. Paez, S. Salem, A. Genaid., Y. Moving from lean manufacturing to lean construction: Toward
a common sociotechnological framework. Human Factors and Ergonomics in Manufacturing
& Service Industries, 2005, 15.2: 233-245.
[11] M. Smętkowska, and B. Mrugalska, B, „Using Six Sigma DMAIC to Improve the Quality of the
Production Process: A Case Study”, Procedia-Social and Behavioral Sciences, vol. 238, pp.
590-596, 2018.
[12] S. Jevgeni, S. Eduard, and Z. Roman, “Framework for continuous improvement of production
processes and product throughput”, Procedia Engineering, vol. 100, pp. 511-519, 2015.
[13] M. Soković, D. Pavletić, and E. Krulčić, “Six Sigma process improvements in automotive parts
production”, Journal of Achievements in Materials and Manufacturing Engineering, vol.
19(1), pp. 96-102, 2006.
[14] G. V. S. S. Sharma, P. S. Rao, and B. S. Babu, “Process capability improvement through DMAIC
for aluminum alloy wheel machining”, Journal of Industrial Engineering International, vol. 1,
pp. 1-14, 2017.
[15] A. Nagi, and S. Altarazi, „Integration of value stream map and strategic layout planning into
DMAIC approach to improve carpeting process”, Journal of Industrial Engineering and
Management, vol. 10(1), pp. 74, 2017.
[16] M. Soković, D. Pavletić, and E. Krulčić, “Six Sigma process improvements in automotive parts
production”, Journal of Achievements in Materials and Manufacturing Engineering, vol.
19(1), pp. 96-102, 2006.
[17] R. Karout, and A. Awasthi, “Improving software quality using Six Sigma DMAIC-based
approach: a case study”, Business Process Management Journal, vol. 23(4), pp. 842-856, 2017.
[18] K. Biesialska, X. Franch, and V. Muntés-Mulero, “Protocol and Tools for Conducting Agile
Software Engineering Research in an Industrial-Academic Setting: A Preliminary Study”,
CESI’18, May 28, 2018, Gothenburg, Sweden, 2018.
[19] A. Tarhini, M. Yunis, A. N. El-Kassar, “Innovative sustainable methodology for managing in-
house software development in SMEs.”, Benchmarking: An International Journal, vol. 25(3),
pp. 1085-1103, 2018.
[20] G. Improta, G. Balato, M. Romano, A. M. Ponsiglione, E. Raiola, M. A. Russo, and M. Cesarelli
“Improving performances of the knee replacement surgery process by applying DMAIC
principles”. Journal of evaluation in clinical practice, 2017.
[21] J. Antony,P. Palsuk, S. Gupta, D. Mishra, and P. Barach, “Six Sigma in healthcare: a systematic
review of the literature”, International Journal of Quality & Reliability Management, vol.
35(5), pp. 1075-1092, 2018.
[22] W. T. Shirey, K. T. Sullivan, B. Lines, and J. Smithwick, “Application of Lean Six Sigma to
Improve Service in Healthcare Facilities Management: A Case Study”, Journal of Facility
Management Education and Research, Vol. 1(1), pp. 9-18. 2018.
[23] A. Karakhan, “Six sigma & construction safety: Using the DMAIC cycle to improve incident
investigations”, Professional Safety, vol. 62(6), pp. 38, 2017.
[24] Tchidi, M. F., He, Z., & Li, Y. B. (2012). Process and quality improvement using Six Sigma in
construction industry. Journal of Civil Engineering and Management, 18(2), 158-172.
[25] T. M. Beary, and T. S. Abdelhamid, “Production planning process in residential construction
using lean construction and six sigma principles”, In Construction Research Congress 2005:
Broadening Perspectives pp. 1-10, 2005.
[26] http://garvest.com/pixel accessed 20.03.2019

10

You might also like