CE 103
Surveying
4 cr.hr.
4 classes per week
Md. Azijul Islam
Lecturer
Department of Civil Engineering
BUET, Dhaka-1000
[Room 652, Civil Engineering Building]
Course Teachers:
• Dr. Mohammad Shariful Islam = 1 cr.hr
• Snigdha Afsana = 1 cr.hr
• Md. Azijul Islam = 1 cr.hr
• Azmayeen Rafat Shahriar = 1 cr.hr
October 2, 2017 CE_103 Md. Azijul Islam 2
Topics to be covered
• Reconnaissance and project survey,
• Photogrammetry: introduction of terrestrial
photography,
• Aerial photography, reading of photo mosac, scale.
October 2, 2017 CE_103 Md. Azijul Islam 3
Reference Book
• Class Lecture
• Handout
• Reference Books:
Surveying (vol-I & vol-II) : B.C. Punmia, Ashok K.
Jain& Arun K. Jain
A text book of Surveying: M. Shahjahan and M. A. Aziz
October 2, 2017 CE_103 Md. Azijul Islam 4
Reconnaissance
and
Project Survey
October 2, 2017 CE_103 Md. Azijul Islam 5
What is Surveying?
• Surveying is a technique of finding the relative position of
different features on the surface by taking measurements and
finally representing them on a sheet of paper known as plan
or map.
• Surveying is a pro-active action for collecting
information/data for either enabling a decision making
process or for executing an activity in a Project
October 2, 2017 CE_103 Md. Azijul Islam 6
Project Surveying
• Project Surveying includes all field works and requisite
calculations together with maps, profiles and other related
drawings involved in planning and construction of any
engineering project.
• The project should be planned in such a way that it may be
constructed and operated with the greatest economy and
utility.
October 2, 2017 CE_103 Md. Azijul Islam 7
A Route/ Project Survey
Consists of Following Sequence
of Surveys
Reconnaissance Survey or “REKI”
Preliminary Surveys
Detailed Engineering Survey or Location Survey
Construction Survey
October 2, 2017 CE_103 Md. Azijul Islam 8
Reconnaissance Survey
Carried out during Project Conceptual Stage
The details are required for Feasibility Report
A technically feasible shortest & cost-effective route is identified
Various important features and information about the route that may
affect the Project anyway are listed
All the available maps of the territory should be collected and studied
October 2, 2017 CE_103 Md. Azijul Islam 9
Reconnaissance Survey (desk-top study)
Extensive use of existing maps
Few alternatives are chalked outs
Comparative merits/demerits are listed
GIS Packages are extremely helpful
Extensive Use of Satellite Imagery now-a-days
October 2, 2017 CE_103 Md. Azijul Islam 10
Preliminary Surveys
• The survey in which more precise information
is required for the choice of best location
for the project and to estimate the exact
quantities and costs of project is known as
Preliminary Survey.
• Preliminary Surveys are done along all the
possible routes.
October 2, 2017 CE_103 Md. Azijul Islam 11
Detail Engineering Survey or Project
Survey or Location Survey
• This activity is taken up during approval
stage, when approval is considered
almost certain
• Prior to this, route was on maps and
paper. This is the first field activity taken
up for Pipeline Projects
October 2, 2017 CE_103 Md. Azijul Islam 12
Detailed Route Survey
• In this activity, route is progressively staked on
ground preferably from one obligatory point and
demarcated with control points and related reference
points.
• Exact distances between control points,
deflection/included angles, elevations etc. are
accurately measured and recorded by
theodolite/total stations
• The levels are taken at every 50/10/5 M distance of
the staked route
October 2, 2017 CE_103 Md. Azijul Islam 13
Different project survey
• Irrigation project
• Hydrographic project
• Sewer Pipeline, canal, highways and railway
projects
• Tunnel Project
• House setting
October 2, 2017 CE_103 Md. Azijul Islam 14
Irrigation Project
Preliminary Survey:
Preliminary survey includes determination of the following:
a) Source of supply: Catchment area of the stream
b) Area of the land proposed to be irrigated
From
c) Possible sites of dams in a reservoir project
contour
d) Possible sites of weirs sluices, headways of canals and maps of
other hydraulic structures
the area
e) Alignment of canals
f) Quality of land and water for irrigation from taking
samples and testing in the laboratory
g) Collection of rainfall, gauge and discharge records of the
stream from hydrological department
h) Possible corps and water requirements from agricultural
department
i) Drainage requirements
October 2, 2017 CE_103 Md. Azijul Islam 15
Irrigation Project
After collecting all the data, a project report
is prepared along with a rough cost of the
project.
Financial aspect is then examined and cost
benefit ratio is worked out
October 2, 2017 CE_103 Md. Azijul Islam 16
Irrigation Project
Detailed Survey:
After the feasibility of the project has been
established, detailed survey of the following is
essential:
a) Location of head works, guide bands,
alignment of canals, distributaries and water
courses
b) Location of falls, cross drainage works and
canal escapes
c) Alignment of drainage canal
d) In case of reservoir project, detailed
geological investigations should be made.
October 2, 2017 CE_103 Md. Azijul Islam 17
Irrigation Project
Construction survey:
The final construction survey includes the
following operations:
a) Topographical survey of the site, preparing
site plan for acquisition of land
b) Setting up of pillars for demarcation and also
to serve as reference line
c) Establishment on ground B.M. pegs for
carrying on construction and giving
alignment of the structure
d) Preparing running bills of the work executive
monthly
October 2, 2017 CE_103 Md. Azijul Islam 18
Irrigation project in Bangladesh
The Ganges-Kobadak Irrigation
Project
• The Ganges-Kobadak Irrigation
Project (G-K Project) Located in the
districts of Kushtia, Chuadanga,
Jhenaidaha and Magura.
• flood control drainage and irrigation
project covering a gross area of
197,486 ha
• started in 1954 and put into partial
operation in 1962 and finally
completed in 1981 at a cost of Tk
828 million
October 2, 2017 CE_103 Md. Azijul Islam 19
Irrigation project in Bangladesh
Dhaka-Narayanganj-Demra (DND) Project
• located between the cities of Dhaka and
Narayanganj and bounded by the
buriganga and the shitalakshya river
• started in 1964 and completed in 1968 at
a cost of Tk 22.9 million
• A dual purpose pumping station is located
at Shimrail having a total capacity of 4.2
cumec
• The project provides flood control for
4,860 ha, irrigation for 6,070 ha, pumped
drainage for 4,860 ha and gravity drainage
for 2,470 ha of land
October 2, 2017 CE_103 Md. Azijul Islam 20
Irrigation project in Bangladesh
Tista Barrage Project
• located in the districts of
Rangpur, Lalmonirhat and
Nilphamari
• covers a gross area of 132,000
ha, of which the irrigable area
is 111,406 ha
• supplies irrigation water by
diverting the flow of the Tista
with a barrage across it
through a gravity canal system
October 2, 2017 CE_103 Md. Azijul Islam 21