SCL Report Rabin Mar06 0
SCL Report Rabin Mar06 0
SCL Report Rabin Mar06 0
A review of the Act was undertaken by Sir Michael Latham who presented his
report on 17th September 2004 to the then Construction Minister Nigel
Griffiths. The report identified key issues and suggested improvements to
both the adjudication and payment provisions. Following this, the DTI drew
up consultation proposals on improving the Act to enhance the delivery of
minimum standards in the contracting process as the construction industry
moved towards integrated construction supply teams and more collaborative
approaches to project delivery.
The consultation period ran from 22nd March until 21st June 2005. The 356
responses from the construction industry were considered and on 16th January
The post-consultation conference was part of the next step in the process,
which sees the Government working with the construction industry over the
coming months to ensure that when amendments to the Act are published for
further consultation, they are based upon a clear and thorough understanding
of all the issues and reflect the needs of the construction industry and its
clients.
One hundred and forty six key figures in the construction industry
(representing, amongst others, the Specialist Engineering Contractors’ Group,
the National Specialist Contractors’ Council, the Construction Confederation,
the Technology and Construction Solicitors’ Association, the Construction
Industry Council, the Construction Clients’ Group and the Society of
Construction Law) got together in one room to listen to some eminent
speakers discuss a variety of topics, including the future of business in the
construction industry, how the Act has been viewed by the Courts and how the
changes to be made to the Act will be implemented by using a relatively new
vehicle to reform legislation, the Regulatory Reform Order.
2 See the publication Improving Payment Practices in the Construction Industry – Analysis
of the consultation on proposals to amend Part II of the Housing Grants Construction and
Regeneration Act 1996 and Scheme for Construction Contracts (England and Wales)
Regulations 1998, Department of Trade & Industry, January 2006.
2
Against this background, attendees participated in debates on specific
Government proposals in small groups, each group then reporting back their
findings and views on the issues. It is the participation in the debates and the
feedback from them which will help reform the Act. The discussion topics,
and a summary of the feedback received at the conference, are set out below.
The current problem is that Section 110(1) of the Act does not go as far as was
intended in providing certainty about what sums are due under a construction
contract and when. The Act states that every construction contract shall
‘provide an adequate mechanism for determining what payments become due
under the contract, and when, and provide for a final date for payment in
relation to any sum which becomes due’.3 It is left to the parties to each
construction contract to agree an ‘adequate mechanism’ and incorporate it.
3 Section 110(1).
3
Those against a statutory requirement to address this issue (by imposing on
parties clear obligations on how to deal in their contracts with certification of
the sum due, with the fallback position being that if parties fail to deal with
the issue in their contracts in the way which is prescribed by statute then the
Scheme for Construction Contracts (in an amended form) will apply), wanted
the current position under the Act to remain, with guidance covering best
practice, as opposed to legislation, which the industry could follow.
In addressing the issue of payment, the Government also proposes that the
requirement for a Section 110(2) notice under the Act is removed. It is
suggested that this notice is unnecessary because if a payer does not believe
he should pay what is due under the contract he can utilise the mechanism in
Section 111.
This proposal also caused concern. Many construction contracts adopt the
position under the Act whereby a payment may be withheld without a Section
111 notice being issued if the Section 110(2) satisfies certain criteria, thus
becoming effective as a notice of intention to withhold payment. However,
this arrangement depends on a Section 110(2) notice being issued. From a
timing point of view, the construction industry seems to prefer the issue of a
Section 110(2), which can also act as a withholding notice, rather than doing
away with this notice and relying solely on the service of a Section 111 notice
to determine what payment is to be made and how much is due.
Why? Because a Section 110(2) notice must be given ‘not later than five days
after the date on which a payment becomes due ….’4 This means that the
payee receives notice at the beginning of the payment process of what is
payable, how the amount is calculated, and (where the notice is capable of
acting as a withholding notice) how much is being withheld and on what
grounds. If a period between the due date and the final date for payment is
stipulated in the contract as being, for example, 30 days, the payee receives
his notification within the first 5 days of such period and has time to consider
if he agrees what is proposed and raise any issues with the payer.
4 Section 110(2)
4
If the Section 110(2) notice is done away with and the issue of a withholding
notice is relied on to determine what is paid and when, reliance is being put on
a notice which can be issued ‘not later than the prescribed period before the
final date for payment’.5 The parties are free to decide what the prescribed
period is and in many contracts I have seen, the payer may issue a withholding
notice up to two days before the final date for payment. This is terrible news
for the payee as he may be working to budgets and cash-flow forecasts which
depend on him receiving money at certain times. If a payee only has two days
notice of what is being paid, this may not give him enough time to ascertain if
he agrees with the payment offered and raise any queries with the payer. It
also means that he can only refer the matter to adjudication if the amount is
disputed towards the end of the payment process – which will delay the
opportunity to receive money even further.
What is clear from the general views expressed at the conference, though, is
that there is consensus that the Act does not deal effectively with the question
of how and when a debt crystallises and, whatever happens, this issue must be
addressed.
There was also general agreement that final payments under a contract should
continue to be capable of being ‘final and conclusive’, so that parties could
rely on some finality at the end of a project and draw the contract to a close.
However, it was felt that to promote fairness, all final payments should clearly
be marked as ‘FINAL’ by the payer (putting the payee on notice that a final
payment is being made) and that a final payment should be capable of being
challenged within a set time period prescribed in the contract. The JCT
contracts currently have a 28 day period within which a final payment can be
5 Section 111(2)
5
challenged and attendees generally felt that it was sensible that a provision
along these lines was retained in all construction contracts.
The general position at the conference was ‘yes’, the use of such accounts
should be prohibited. The ability of contracting parties to agree terms which
negate the effect of adjudication was a regulatory loophole that needed
closing.
The problem at the moment is that parties may contract on terms which allow
adjudicators’ awards to be paid into trustee stakeholder accounts pending final
determination of the dispute in the courts or by way of arbitration. This
prevents adjudication from being used in the way it was intended under the
Act. It may also have cash-flow consequences for the party in the dispute
which has suffered at the hands of the other.
There were limited circumstances where it was felt by some that the use of
such accounts should be accepted. These included circumstances where there
was a risk that the recipient of the award would become insolvent before the
dispute was finally determined and where an award of public money was
made.
However, it was agreed that the TCC’s guidance on when it is likely to stay an
adjudicator’s decision is sufficiently clear6 and, therefore, why should it not
be left to the courts alone to decide when a stay in enforcing an adjudicator’s
decision should be granted?
Interestingly, not many attendees had direct experience of the use of trustee
stakeholder accounts. One person who had had experience said that whilst the
contractual provision authorising the use of a trustee stakeholder account in a
dispute allowed the receipt of money into the account, there was no
corresponding provision explaining how the money would eventually be
released from the account!
‘Evidenced in writing’
The question was: is it correct that any amendment to Section 107 of the Act
on contracts evidenced in writing would need to take account of the courts’
emphasis on certainty of all the contract terms for adjudication to be
workable?
6 See Wimbledon Construction Company Ltd v Derek Vago [2005] EWHC 1086 (TCC).
6
This question did not form part of the formal consultation process but the
Government is interested in the views of the construction industry and is
considering amending the Act to deal with the Court of Appeal’s decision in
RJT Consulting Engineers Ltd v DM Engineering (Northern Ireland) Ltd.7
The Court of Appeal held that on the proper construction of Section 107, it
was the terms, and not merely the existence of a construction contract, which
had to be evidenced in writing in order for the contract to fall within the scope
of the Act. The whole of the agreement had to be evidenced in writing, not
part of it, as writing provided certainty which was important when
adjudication, which would have to take place under a demanding timetable
and agreed procedure, was envisaged.
Respondents during the consultation process took issue with this decision on
three grounds – with which attendees at the conference generally agreed.8
7 RJT Consulting Engineers Ltd v DM Engineering (Northern Ireland) Ltd [2002] EWCA
Civ 270.
8 See the Analysis referred to in note 2.
7
any parts of the contract which are not fully agreed in writing but
are covered by the Scheme should not prohibit the contract from
falling within the ambit of the Act.
The thrust of the argument is that unless the requirements relating to contracts
being evidenced in writing are changed, many contracts may not be caught by
the Act which undermines the Act’s intentions. Without clarity of this issue, it
may be easy for a party to argue that there are terms which are not recorded
and, therefore, the whole contract is not in writing so the Act does not apply.
Those at the conference agreed that Section 107 should be amended so that
the UK has less stringent requirements for contracts to be evidenced in
writing. Where there is a mixture of written and oral terms, or even wholly
oral terms, these contracts should not be excluded from the ambit of the Act.
All contracts, no matter what their form, should be capable of being
adjudicated.
Suspension
In relation to the suspension proposals, the following questions were asked.
Should the remobilisation period be limited to a maximum period notified in
the notice of suspension? Should the suspending party seek the payer’s
agreement to provide certain services under the contract during the suspension
period to ensure statutory obligations are met and to reduce the costs of
remobilisation? Should the Act enhance the existing right of suspension to
allow the suspending party to claim for loss and expense?
Where the breach is likely to go on for some time, the suspending party will
probably go off-site and secure work on another project, using and committing
his resources elsewhere, and making it harder for him to return to the site
quickly. It was felt that there is no good reason for forcing the innocent party
into a position where at the outset of the suspension, he must commit to
coming back on site within a maximum period. The only duty of the innocent
party in this respect should be to return to site as soon as reasonably possible,
ensuring that a return to site was, for the purposes of recovering loss and
expense, subject to all the usual rules of mitigation of costs.
The additional costs incurred by the suspending party in carrying out his
statutory obligations (the cost of providing these services is likely to be more
than originally priced for because labour and materials are not permanently
on-site) should be recoverable by the suspending party through a loss and
expense claim.
Shortly after the issues had been debated, the conference concluded and, I
might add, without any blood being spilt! In fact, people addressed the floor
and said that given the bad times and the bad relationships within the industry
which existed prior to the Act coming into force, it was amazing to see so
many different players in the industry get together in one room, quite
9
amicably, to discuss the future of the UK construction industry. Certainly my
impression from this exciting event, which was probably the best conference I
have been to in my career to date, was that the industry is keen to resolve its
differences and that, in respect of the issues raised at the conference, the
players are not necessarily too far apart in their views to make this an
impossibility.
March 2006
The views expressed by the author in this report are hers alone, and do not
necessarily represent the views of the Society of Construction Law or the editor.
Neither the author, the Society, nor the editor can accept any liability in respect of
any use to which this paper or any information or views expressed in it may be put,
whether arising through negligence or otherwise.
10