PAVEMENT DESIGN REPORT ZiroCTSB
PAVEMENT DESIGN REPORT ZiroCTSB
PAVEMENT DESIGN REPORT ZiroCTSB
ARUNACHAL PWD
Widening of existing road to 2 lane NH
standards along with improvement and
realignment from Potin to Pangin via
Yachuli, Ziro, Daporizo, Aalong
(Package-2, Design chainage from
Km44.350 to Km 77.950) on NH-13 in
Arunachal Pradesh on EPC mode m
Pavement Design Report
Table of Contents
1 INTRODUCTION ......................................................................................................... 4
5.1 Embankment and Subgrade Material ....................... Error! Bookmark not defined.
5.2.1 Cement Treated Sub-Base (CTSB) and Cement Treated Base (CTB) ............... 8
5.2.2 Aggregates for Wet Mix Macadam (WMM) .... Error! Bookmark not defined.
10 CONCLUSION ........................................................................................................... 30
1 INTRODUCTION
Ministry of Road Transport and Highways (MoRT&H) through PWD AP has
awarded the construction of “ Widening of existing road to 2 lane NH standards along with
improvement and realignment from Potin to Pangin via Yachuli, Ziro, Daporizo, Aalong
(Package-2, Design chainage from Km44.350 to Km 77.950) on NH-13 in Arunachal
Pradesh on EPC mode under Arunachal Pradesh package of SARDP-NE to the executing
agency M/s Dineshchandra R Agarwal Infracon Pvt. Ltd.
The Development of the Project Highway shall include design and construction as
described in this Schedule-B and in Schedule-C of the Contract agreement.
The Project Highway shall be designed and constructed in conformity with the
Specifications and Standards specified in Annex - I of Schedule-D of the contract agreement.
The EPC Contractor shall be responsible for engineering surveys, investigation and
detailed engineering designs and prepare the working drawings for all the components
relevant for the improvement and up-gradation of the Project Highway to fulfil the scope of
the project. These shall comply with design specifications and standards given in Schedule–
D. The designs for different project facilities shall follow the locations and indicative designs
given in Schedule–C and shall comply with design specifications and standards outlined in
Schedule–D.
The guidelines for design of pavement for the project stretch as per Clause 5 of
Schedule B of the contract agreement are as follows:
(i) Pavement design shall be carried out in accordance with Section 5 of IRC:37-2018.
(iii) Design Requirements: Design requirement for the flexible pavement shall be in
accordance with the clauses of IRC: SP-73-2018, and IRC: 37-2018 or the latest version of
both.
(iv) Design Period and strategy : Flexible pavement for new pavement or for widening and
strengthening of the existing
pavement shall be designed for a minimum design period of 15 years. Stage construction
5.3.2 Design Traffic : The pavement shall be designed for a design traffic of 20 million
5.3.3 Subgrade Soil: The requirements for the Subgrade’s CBR specified in IRC: SP-73-
2015, IRC: 37-2012 and MoRTH (Specification of Roads and Bridges) shall be satisfied.
In this instant proposal, the pavement design has been carried out as out as per the
guidelines of of IRC 37:2018 as per the requirement of clause 5.3 of the contract agreement.
The Design Director and his team have carried out detailed surveys and
investigations to finalize the pavement design of project road in conformity with the
stipulations of IRC. This report highlights the “Pavement Design” undertaken for the project
road in greater details.
The commercial traffic, gain its peak from October to March mainly due to tourism.
Further, defense vehicles frequent on the road because of the strategic importance.
October onwards carrying mainly the quarry materials, coats and bamboo to
Bangladesh So the upgrading of this road to National Highway (NH) standard for the present
is quite reasonable keeping the provision for ultimate State highway standard.
The condition of the existing road is in depleted condition and the alignment is
serpentine with many geometric deficiencies. The 2-laning of the proposed road will remove
the geometric deficiencies and will provide smooth movement of traffic.
M/s Dineshchandra R Agarwal Infracon Pvt. Ltd has been awarded the contract
for the construction of the road through international competitive bidding.
Map 1: Map showing the state of Arunachal Pradesh and Project Alignment
4 DRAINAGE CONDITION
The project road passes through the thickly populated areas of Ziro-Hapoli. The
current drainage system in the built up area is insufficient to drain out the water from the
township to the adjacent low lying areas. Sufficient CD works and covered side drains on
both sides have been proposed to mitigate the situation. Baring the thickly populated area of
Ziro-Hapoli the alignment passes through paddy field and hilly areas where the water could
be drained out easily by providing proper CD works and open side drains.
forming the foundation for the pavement. It should be well compacted to derive optimal
strength and to limit the rutting caused due to additional densification of the layer during
the service life. It shall be compacted to attain a minimum of 97 per cent of the laboratory
maximum dry density obtained corresponding to heavy compaction as per IS:2720 Part-8
[17] for Expressways, National Highways, State Highways,
The materials used in ankments, subgrades, earthen shoulders and miscellaneous
backfills shall be soil, moorum, gravel, a mixture of these or any other material approved
by the Engineer. Such materials shall be free of logs, stumps, mots, rubbish or any other
ingredient likely to deteriorate or affect the stability of the ankment subgrade.
The following materials are not suitable for subgrade construction:
Materials from swamps, marshes and bogs
Peat, log, stump and perishable material: any soil that, classifies as OL, OI, OH
or Pt in accordance with IS:1498
Materials susceptible to spontaneous combustion;
Materials in a frozen condition;
Clay having liquid limit exceeding 70 and plasticity index exceeding 45; and
Materials with salts resulting in leaching in the ankment.
Expansive clay exhibiting marked swell and shrinkage properties ("free swelling
index" exceeding 50 per cent when tested as per IS: 2720 - Part 40} as a fill
material.
5.1.1 Cement Treated Sub-Base (CTSB) and Cement Treated Base (CTB)
As per clause 5.7.1.i.(b) of IRC:SP:72:2007 , Cement treated soil sub-base conforming to
clause 403 of MOSRTH Specifications.
For use in a sub-base course, the material shall have a grading shown in Table 400-4;
it shall have a uniformity Coefficient not less than 5, capable of producing a well closed
surface finish.
The table 404-4 of MoRTH Standard and Specification , 5th revision is shown below:
As per clause 402.3 of MoRTH Standard and Specifications, the quantity of cement to be
added as per cent by weight of the dry soil shall be specified in the Contract. The mix design
shall be done on the basis of 7-day unconfined compressive strength (UCS) and/or durability
test under 12 cycles of wet-dry conditions. The laboratory strength values shall be at least
1.5 times the minimum field UCS value stipulated in the Contract.
Macadam, (DBM), for use mainly, but not exclusively, in base/binder and profile
corrective courses. The work shall consist of construction in a single or multiple layers of
DBM on a previously prepared base or sub-base. The thickness of a single layer shall be 50
mm to100 mm. The aggregates shall satisfy the physical requirements specified in Table
below for dense bituminous macadam.
Where crushed gravel is proposed for use as aggregate, not less than 90% by weight of the
crushed material retained on the 4.75 mm sieve shall have at least two fractured faces.
Max 27%
Fine aggregates shall consist of crushed or naturally occurring mineral material, or a the
combination of the two, passing the 2.36 mm sieve and retained on the 75 micron sieve.
These shall be clean, hard, durable, dry and free from dust, and soft or friable matter, organic
or other deleterious matter. Natural sand shall not be allowed in binder courses. However,
natural sand upto 50 percent of the fine aggregate may be allowed in base courses. The fine
aggregate shall have a sand equivalent value of not less than 50 when tested in accordance he
with the requirement of IS:2720 (Part 37). The plasticity index of the fraction passing the in
0.425 mm sieve shall not exceed 4, when tested in accordance with IS:2720 (Part 5). Filter
shall consist of finely divided mineral matter such as rock dust, hydrated lime or cement
approved by the Engineer. The filler shall be graded within the limits indicated in Table 500-
9.
The filler shall be free from organic impurities and have a plasticity Index not greater than 4.
The Plasticity Index requirement shall not apply if filler is cement or lime. Where the
aggregates fail to meet the requirements of the water sensitivity test in Table 500-8, then 2
percent by total weight of aggregate, of hydrated lime shall be used and percentage of fine
aggregate reduced accordingly. When tested in accordance with IS:2386 Part 1 (wet sieving
method), the:l combined grading of the coarse and fine aggregates and filler for the particular
mixture shall 3 fall within the limits given in Table 500-10 for grading 1 or 2 as specified in
the Contract. To avoid gap grading, the combined aggregate gradation shall not vary from the
lower limit on one sieve to higher limit on the adjacent sieve.
**The Water Sensitivity test is only required if the minimum retained Coating in the stripping
test is less than 95%
(ii) As per clause 5.2 of Schedule B, Type of pavement: Flexible Pavement will be
designed in accordance with the IRC:37-2018.
(iii) As per clause 5.3 of Schedule B, Design Requirements: Design requirement for the
flexible pavement shall be in accordance with section 5 of the IRC: SP-73-2015, and the IRC:
37-2018 or the latest version of both.
(iv) As per clause 5.3.1 of Schedule B, Design Period and strategy : Flexible pavement for
new pavement or for widening and strengthening of the existing pavement shall be designed
for a minimum design period of 15 years. Stage construction shall not be permitted.
(v) As per clause 5.3.2 of Schedule B, The design traffic specified in the IRC: SP-73-2015
Section 5.4.1 (i) shall be applied. IRC SP:73 2015 clause 5.4.1(i) specifies a minimum traffic
intensity of 20 msa.
(vi) As per clause 5.3.3 of Schedule B, The requirements for the Subgrade’s CBR specified in
IRC: SP-73-2015, IRC: 37-2018 and MoRTH (Specification of Roads and Bridges) shall be
satisfied.
From the Above Graph The effective 90 percentile CBR is calculated as = 9.88 %. Therefore,
the CBR of the subgrade= 8 %. (As per Schedule B)
Where,
N = Cumulative number of standard axles to be catered for in the design in terms of msa.
r = Annual growth rate of commercial vehicles in decimal (e.g., for 5 per cent annual
growth rate, r = 0.05) as per IRC 37-2018, clause no. 4.2.2.
Layers Thickness
BC 50
SAMI 50
CTB 100
CTSB 200
TX 160 Geogrid laid over subgrade
7.2.1 General
For the given traffic volume, which is expected in the design life, there can be large number
of combinations for the pavement depending on the availability of materials. A strong
subgrade and a strong base along with fatigue and rut resistant bituminous are very important
for a good performing pavement.
Allowable strains for the expected traffic are calculated using the fatigue and rutting models
given IRC 37:2018 (Equation 6.1 to 6.5). With the assumed pavement crust, the strains at
critical locations are calculated using IITPAVE software. The adequacy of the design is
checked by comparing these strains with allowable strains as predicted by the fatigue and
rutting models. A satisfactory pavement design is achieved through iterative process by
varying layer thickness/ pavement layer materials.
The elastic modulus (E) of the CTSB material may be estimated from the unconfined
compressive strength (UCS) of the material. The cementitious sub-base (CTSB) should have
a 7-day UCS of1.5 to 3.0 MPa as per IRC:SP:89. Third point loading test flexural modulus
ECGSB of 28-daycured CTSB material can be estimated using equation 7.2 of IRC-37:2018.
It should be maintained that the laboratory strength should be 1.5 times the design CTSB
strength in field. For atypical cement treated granular sub-base materials, the ECGSB can
vary from 2000 to 6000 MPa. Since the sub-base acts as a platform for the construction
vehicles carrying 30 to 35 tonnes of construction material, low strength cemented sub-base
would crack under the heavy construction traffic and a design value of 600 MPa is
recommended for the analysis and design of pavements with CTSB layers. The poisson value
of the CTSB layer should be considered to be 0.25.
CTB
the thickness of cement treated bases shall not be less than 100 mm. The procedure to be
followed for the estimation of the thickness of the CTB layer required to cater to the
construction traffic has been illustrated in Annex II. The elastic modulus of cementitious
bases depends upon the quality of materials. Low grade aggregates such as moorum and
kankar may give lower modulus at lower cement contents. Fine grained soil may require
larger quantity of cementitious additive for higher strength and may develop wider cracks
upon curing. Equation 7.2 of IRC 37:2018 may be used for estimating the elastic modulus of
ECTB from the 28-day unconfined compressive strength (UCS) of CTB material also.
Poisson’s ratio value of CTB material may be taken as 0.25. Strength of cementitious layers
keeps on rising with time and an elastic modulus of 5000 MPa may be considered for analysis
of pavements with CTB layers having 7/28 day unconfined compression strength values
ranging between 4.5 to 7 MPa. While the conventional cement treated layer should attain the
above strength in 7 days, lime and lime-flyash stabilised granular materials and soils should
achieve the strength in 28 days since the strength gain in such materials is slow (IRC:SP:89).
SAMI
In case of pavements with CTB, a crack relief layer, provided between the bituminous layer
and the cementitious base, delays the reflection of crack from the CTB layer in to the
bituminous layer. The crack relief layer may consist of dense graded crushed aggregates of
100 mm thickness conforming to MORTH [23] specifications for wet mix macadam (WMM)
or the Stress Absorbing Membrane Interlayer (SAMI) of elastomeric modified binder applied
at the rate of 10 – 12 kg / 10 m2 covered with 0.1 m3 of 11.2 mm aggregates. For the
pavement analysis, the SAMI layer is not considered as a structural layer, i.e., it shall not be
included in the pavement composition for pavement analysis.
BC Layer
According to IRC-37:2018, for expressways and national highways, even if the design traffic
is 20 MSA or less, VG40 or modified bitumen shall be used for surface course and VG40
bitumen shall be used for the DBM. In view of the overlap in the viscosity ranges specified in
IS:73 for VG30 and VG40 bitumen, it is recommended that the VG40 bitumen used in the
surface, binder and base bituminous courses shall have a minimum viscosity of 3600 Poise at
600 C temperature to safeguard against rutting. The design of pavement shall be carried out
based on the actual values obtained with field designed DBM/BM mix subject to the
maximum values indicated in Table 9.2 for the selected mix (DBM/BM mixes with selected
unmodified binder) for an average annual pavement temperature of 35 0C. For the climatic
conditions prevailing in the plains of India, the Average Annual Pavement Temperature is
expected to be close to 20 ‘C. Volume of air voids and Bitumen Content is considered to be 3
and 11.5 percent respectively.
MoRTH through Indian Roads Congress has recently published “Guidelines for use of
Geosynthetics in road pavements and associated works” IRC: SP:59-2019. The code provided
guidelines for use of geogrid for pavement stabilization and optimization by considering the
enhancement of performance caused due to the lateral restraint provided by the geogrid.
Use of geogrids is a well-researched and proven solution for stabilizing & optimising the
pavements. Majority of studies indicate appreciable improvement in pavement performance
due to use of geogrid in pavement. The development of the interlock at the soil – grid
interface restricts the movement of soil particles (as shown in fig 1), this stabilisation effects
helps increases the stiffness of the unbound layers thus improves the modulus of layer. This
has been well established through extensive research and full-scale trafficking trials done
across the world.
IRC: SP-59-2019 acknowledges this and provides various alternative design methods for
flexible pavement design using geogrids in Chapter 3. The design methods proposed are: 1.
Modified AASHTO design method following Layer Coefficient Ratio (LCR) (Clause 3.1.2.2)
2. Mechanistic Empirical Pavement Design (MEPD) method following Modulus
Improvement Factor (MIF) for geogrid reinforced flexible pavements (Clause 3.1.3)
Based on the design criteria and parameters mentioned in the Design Brief, following section
using Tensar TX geogrid to form MSL is proposed. The design is carried out using the
Modulus Improvement Factor (MIF) Method as given in IRC SP 59 – 2019 (as suggested in
IRC 37:2018) Pavement Life has been calculated with 90% reliability and corresponding
Transfer functions given in IRC 37. –
Where,
NR = Subgrade Rutting Life (Cumulative number of standard Axles of 80 KN load that can
be served by the pavement before a rutting depth of 20 mm or more occurs.)
ϵv = Vertical Compressive strain at the top of the subgrade calculated using linear elastic
layered theory by applying the standard axle load at the selected surface.
IITPAVE software is used in these guidelines for the analysis of pavements. For the
computation of stresses, strains and defections in the pavement, thicknesses and elastic
properties (elastic modulus and Poisson’s ratio) of different layers are the main inputs. For
the calculation of vertical compressive strain on top of the subgrade, horizontal tensile strain
at the bottom of the bottom bituminous layer and the horizontal tensile strain at the bottom of
cement treated base (CTB) layer, the analysis is done for a standard axle load of 80 kN
(single axle with dual wheels). Only one set of dual wheels, each wheel carrying 20 kN load
with the centre to centre spacing of 310 mm between the two wheels, applied at the pavement
surface shall be considered for the analysis. The shape of the contact area of the tyre is
assumed in the analysis to be circular. The uniform vertical contact stress shall be considered
as 0.56 MPa.
Where,
The factor ‘C’ is an adjustment factor used to account for the effect of variation in the mix
volumetric parameters (effective binder volume and air void content) on the fatigue life of
bituminous mixes [9] and was incorporated in the fatigue models to integrate the mix design
considerations in the fatigue performance model.
CTB layer. The number of standard axle loads derived from equation 3.5 by substituting the
computed tensile strain value along with other inputs shall be less than the design traffic.
Where,
Where,
Nfi = Fatigue Life of CTB material which is maximum repetitions of axle load of class “i”
CTB can sustain
t= Tensile stress at the bottom of the CTB layer due to a given axle load class
Mrup = Modulus of Flexural strength of CTB material
The cumulative fatigue damage (CFD) caused by different repetitions of axle loads of
different categories and different magnitudes expected to be applied on the pavement during
its design period is estimated using equation 3.7.
ni = Expected (during the life time of the pavement) repetitions for axle load class i.
9.2.1 Output Page of IIT Pave for Subgrade Rutting and Bituminous Fatigue is
shown below:
9.3 Analysis
Performance Criterion Permissible Maximum Design Check
Vertical Strain at 454.95E-06 297.3E-06 SAFE
subgrade
Tensile Strain at 222.9E-06 23.88E-06 SAFE
Bituminous Layer
Tensile strain at CTB 76.66E-06 70.77E-06 SAFE
Tensile Stress
Single Axle Wheel Load Repititions at the bottom Fatigue Life
Axle Load Class Stress Ratio ni/Ni
Load (Wi) (ni) of CTB (Ni)
Sigma(t)
185-195 190 47500 60000 0.62 0.442857143 2.59E+06 0.02
175-185 180 45000 80000 0.6 0.43 3.86E+06 0.02
Assuming that the load near the rear tandem axle of the dumper is 240 KN and that of the
front axle is 80 KN
Therefore, allowable subgrade strain for 10000 standard axles of Dumper = 2.43E-03
The cemented sub-base shall be cured for a minimum of three days before the construction of
the next layer. In case sufficient strength of cementitious sub-base is not achieved as per the
requirement of IRC SP:89-2010 in 3 days of curing, 7 days curing shall be done for sub-base
before the construction of the upper layer can be started.
11 CONCLUSION
The trial section selected is good for construction
Layers Thickness
BC 50
SAMI 50
CTB 100
CTSB 200
TENSAR TriAX Geogrid:160