09 Samss 021
09 Samss 021
09 Samss 021
1 Scope............................................................. 2
2 Conflicts and Deviations................................. 2
3 References..................................................... 3
4 General Requirements................................... 4
5 Qualification Tests and Requirements........... 4
6 Packaging Requirements............................... 7
1 Scope
This specification does not apply and should not be included with Purchase
Orders or requisitions for coating products that have been previously qualified per
this specification. This specification should also not be included with purchase
orders or requisitions for coated items or equipment when a Saudi Aramco
approved protective coating system has been specified.
2.1 Any conflicts between this specification and other applicable Saudi Aramco
Materials System Specifications (SAMSSs), Engineering Standards (SAESs),
Standard Drawings (SASDs), or industry standards, codes, and forms shall be
resolved in writing by the Company or Buyer Representative through the
Manager, Consulting Services Department of Saudi Aramco, Dhahran.
2.2 Direct all requests to deviate from this specification in writing to the Company
or Buyer Representative, who shall follow internal company procedure
SAEP-302 and forward such requests to the Manager, Consulting Services
Department of Saudi Aramco, Dhahran.
Page 2 of 8
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-021
Issue Date: 30 June 2014 Qualification Requirements
Next Planned Update: 30 June 2019 for Alkyd Enamel Coating System (APCS-6)
3 References
The selection of material and equipment, and the design, construction, maintenance, and
repair of equipment and facilities covered by this specification shall comply with the
latest edition of the references listed below, unless otherwise noted.
Page 3 of 8
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-021
Issue Date: 30 June 2014 Qualification Requirements
Next Planned Update: 30 June 2019 for Alkyd Enamel Coating System (APCS-6)
4 General Requirements
4.1 For purposes of this specification the Buyer's Representative shall be the
Responsible Standardization Agency (RSA).
4.2 In order to qualify a coating system as acceptable under this specification, the
coating supplier shall submit a certified test report documenting that the
proposed coating system meets the qualification tests and requirements of this
SAMSS. Preparation and testing shall be performed and/or witnessed by an
independent laboratory or inspection agency. This report shall be submitted to
the Saudi Aramco RSA for review. The RSA shall decide if the data presented
by the Supplier satisfies all the requirements.
4.3 All initial product qualification tests shall be carried out at no cost to Saudi
Aramco.
Package stability shall be determined separately for the primer and the
topcoat. When stored at 52 + 1°C for 6 months in accordance with
ASTM D1849, the sample(s) shall meet the following requirements:
a. Weight Loss - 0
b. Skinning, Pressure or Corrosion - 10
c. Settling - 6 or better
d. Grains, lumps or streaks - 8 or better
Page 4 of 8
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-021
Issue Date: 30 June 2014 Qualification Requirements
Next Planned Update: 30 June 2019 for Alkyd Enamel Coating System (APCS-6)
Spray properties shall be determined separately for the primer and the
topcoat. The primer shall be spray applied to a vertical surface at the wet
film thickness corresponding to a dry film thickness between 40 and
50 microns. The topcoat shall be spray applied to a separate vertical
surface at the wet film thickness corresponding to a dry film thickness
between 25 and 50 microns. The freshly sprayed coatings shall show no
tendency to orange peel, sag, creep or run.
When tested in accordance with ASTM D1640, the dry times shall be
according to Table 1.
5.2.1.1 Test panels shall be ASTM A36 hot rolled steel approximately
100 mm X 150 mm. Prior to preparing the surface, the
condition of the test panel shall be equivalent to SSPC-Guide
to Vis 1 Rust Grade A, Adherent Mill Scale. The minimum
thickness of the test panel shall be 5 mm.
Page 5 of 8
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-021
Issue Date: 30 June 2014 Qualification Requirements
Next Planned Update: 30 June 2019 for Alkyd Enamel Coating System (APCS-6)
5.2.2.2 After allowing the primer to cure for the minimum amount of
time recommended by the before over coating, then the topcoat
shall be mixed, applied over the primer, and its curing time
shall be in accordance with the coating manufacture.
The topcoat shall be applied to reach the maximum dry film
thickness of 50 microns. The final dry film thickness of the
primer and topcoats shall be a minimum of 125 microns and a
maximum of 200 microns. Dry film thickness shall be
measured in accordance with SSPC PA2.
Top coating by other coating system (APCS-26) over the alkyd enamel
coated steel panels, cured for 48 hours, shall be evaluated and it shall
show no evidence of wrinkling, blistering, lifting, or cohesion related
failures.
5.2.4 Adhesion
Prepare two panels in accordance with 5.2.1 and apply the complete
coating system in accordance with 5.2.2. Allow these panels to
completely cure in accordance with the dry through times in section
5.1.4. Score a line through to the metal across the width of the film
using a sharp pointed knife. The film shall then be taped perpendicular
to and across the score line with water resistant, pressure sensitive
20 mm wide adhesive tape. The tape shall be pressed in firm contact
with the film and shall extend approximately 25 mm on each side of the
score line. Allow approximately ten seconds for the test area to return to
room temperature. Grasp a free end of the tape and at a rapid speed,
strip it from the specimen by pulling the tape back upon itself at
180 degrees. No more than 1.5 mm of paint shall be removed from the
primer and/or the metal on either side of the score line.
Page 6 of 8
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-021
Issue Date: 30 June 2014 Qualification Requirements
Next Planned Update: 30 June 2019 for Alkyd Enamel Coating System (APCS-6)
Prepare two panels in accordance with 5.2.1 and apply the complete
coating system in accordance with 5.2.2. Scribe the fully cured coating
system in accordance with ASTM D1654 and expose in a salt fog cabinet
in accordance with ASTM B117, Salt Spray (Fog) Testing.
This procedure shall be continued until the test panels are exposed for
500 hours in the salt fog cabinet. At the conclusion of the test, the
coating shall be evaluated for and shall meet the criteria shown in
Table 2.
6 Packaging Requirements
Page 7 of 8
Document Responsibility: Paints and Coatings Standards Committee 09-SAMSS-021
Issue Date: 30 June 2014 Qualification Requirements
Next Planned Update: 30 June 2019 for Alkyd Enamel Coating System (APCS-6)
Revision Summary
30 June 2014 Revised the Next Planned Update, reaffirmed the content of the document, and reissued as
major revision.
Page 8 of 8