Bill 10 UG Water Tank and Pump Room

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 92

HH PRINCE MISHAL BIN KHALID F.

AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 03 - CONCRETE WORK


The Tenderer is referred to the Specifications and Note
Drawings for all details related to this section of the
works and he is to include for complying with all the
requirements contained therein, whether or not they
are specifically mentioned within the items

All bellow mentioned items are subject to supply, Note


install, testing and commissioning and warranty, as
per Specifications and other Tender Documents.

The Tenderer shall allow for additional items and Note


costs not specifically mentioned in this bill but
necessary for the satisfactory completion of the
contract. Particular items shall be considered to be
included in the prices of the items, No claims will be
entertained for any items shown or inferred by the
Specifications and Drawings and not included herein.

POTABLE WATER TANK

Section 03 30 00: Cast In Place Concrete

Plain concrete cylinder compressive strength 20


N/mm2 at 28 days using the cement recommended
by the Geotechnical Report, including all necessary
works complete as per Specifications

A Blinding 31 m3

B 50mm thick, screed concrete 31 m3

C Concrete haunching for storm water lifting station. 3 m3

Reinforced concrete compressive strength 35 N/mm2


using the cement approved according to the
Geotechnical Report, including reinforcement, all
necessary formwork, water stop, construction joints
and additives; complete as per ASTM A615,
Drawings and Specifications

D Raft foundations; 500mm thick, including additional


drop of 250mm thick 352 m3

E Walls: 350mm thick 8 m3

F Walls: 400mm thick 158 m3

Omrania & Associates 10/Div-03/1


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div-03/2


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 03 - CONCRETE WORK (CONT'D)

Section 03 30 00: Cast In Place Concrete

Reinforced concrete compressive strength 40 N/mm2


using the cement approved according to the
Geotechnical Report, including reinforcement, all
necessary formwork, water stop, construction joints
and additives; complete as per ASTM A615,
Drawings and Specifications

A Columns 10 m3

Reinforced concrete compressive strength 35 N/mm2


using the cement approved according to the
Geotechnical Report, including reinforcement, all
necessary formwork, water stop, construction joints
and additives; complete as per ASTM A615,
Drawings and Specifications

B Flat slab, 300mm thick 188 m3

C Columns drop head 9 m3

D Upstands 3 m3

E Concrete pads 60 m3

Omrania & Associates 10/Div-03/3


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div-03/4


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 03 - CONCRETE WORK (CONT'D)

STORM WATER LIFTING STATION AND SEWAGE


HOLDING TANK

Section 03 30 00: Cast In Place Concrete

Plain concrete cylinder compressive strength 20


N/mm2 at 28 days using the cement recommended
by the Geotechnical Report, including all necessary
works complete as per Specifications

A Blinding 4 m3

B 50mm thick, screed concrete 9 m3

Reinforced concrete compressive strength 35 N/mm2


using the cement approved according to the
Geotechnical Report, including reinforcement, all
necessary formwork, water stop, construction joints
and additives; complete as per ASTM A615,
Drawings and Specifications

C Raft foundations, 500mm thick 31 m3

D Raft foundations, 250mm thick 4 m3

E Walls: 250mm thick 5 m3

F Walls: 350mm thick 52 m3

G Flat slab, 220mm thick 14 m3

H Upstands 1 m3

Omrania & Associates 10/Div-03/5


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div-03/6


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 03 - CONCRETE WORK

COLLECTION

10/3/1

10/3/2

10/3/3

Omrania & Associates 10/Div-03/7


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Summary SR

Omrania & Associates 10/Div-03/8


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 05 - METAL WORKS

The Tenderer is referred to the Specifications and Note


Drawings for all details related to this section of the
works and he is to include for complying with all the
requirements contained therein, whether or not they are
specifically mentioned within the items

All bellow mentioned items are subject to supply, install, Note


testing and commissioning and warranty, as per
Specifications and other Tender Documents.

The Tenderer shall allow for additional items and costs Note
not specifically mentioned in this bill but necessary for
the satisfactory completion of the contract. Particular
items shall be considered to be included in the prices of
the items, No claims will be entertained for any items
shown or inferred by the Specifications and Drawings
and not included herein.

Section 05 50 00: Metal Fabrications

Galvanized steel access ladder/ ships access ladder,


including all fixing accessories complete as per Drawings
and Specifications

A Access Ladder; approximate height 4.9m, including ø20 5 Nr


mm x 300 mm wide, epoxy coated steel ladder rungs
spaced 300mm vertically.

B Access Ladder; approximate height 2.0m, including ø20 1 Nr


mm x 300 mm wide, epoxy coated steel ladder rungs
spaced 300mm vertically.

Section 05 53 00: Gratings And Floor Plates

HD. GS. recessed hinged manhole covers and frame


including fixing accessories complete as per Drawings
and Specifications

C Manhole Cover; 800 x 800 mm 2 Nr

MD. CI. recessed-type and lockable, hinged manhole


covers and frame including fixing accessories complete
as per Drawings and Specifications

D Manhole Cover; 600 x 600 mm 3 Nr

Omrania & Associates 10/Div-05/1


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Summary SR

Omrania & Associates 10/Div-05/2


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 07 - THERMAL AND MOISTURE


PROTECTION

The Tenderer is referred to the Specifications and Note


Drawings for all details related to this section of the
works and he is to include for complying with all the
requirements contained therein, whether or not
they are specifically mentioned within the items

All bellow mentioned items are subject to supply, Note


install, testing and commissioning and warranty, as
per Specifications and other Tender Documents.

The Tenderer shall allow for additional items and Note


costs not specifically mentioned in this bill but
necessary for the satisfactory completion of the
contract. Particular items shall be considered to be
included in the prices of the items, No claims will be
entertained for any items shown or inferred by the
Specifications and Drawings and not included
herein.

POTABLE WATER TANK

Section 07 13 52: Bituminous Sheet


Waterproofing

Waterproofing membrane, torchable membrane, as


shown on the Drawings. Use two plys of bituminous
sheet waterproofing with the thickness of each
layer 4mm including cant strip; complete all as per
Drawings and Specifications

A Water proofing membrane to horizontal surfaces 720 m2


and on slopes for raft foundation

B Water proofing membrane to horizontal surfaces 1250 m2


and on slopes above flat slab

C Water proofing membrane to vertical surfaces 490 m2

Omrania & Associates 10/Div-07/1


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div-07/2


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 07 - THERMAL AND MOISTURE


PROTECTION (CONT'D)

Sundries

A Protection boards (tank walls), including fixings and 490 m2


accessories complete; as per Drawings and
Specifications

B Protection boards (above flat slab), including fixings 620 m2


and accessories complete as per Drawings and
Specifications

STORM WATER LIFTING STATION

Section 07 13 52: Bituminous Sheet


Waterproofing

Waterproofing membrane, torchable membrane, as


shown on the Drawings. Use two plys of bituminous
sheet waterproofing with the thickness of each
layer 4mm including cant strip; complete all as per
Drawings SWSH-S401 and S402 and
Specifications

C Water proofing membrane to horizontal surfaces 85 m2


and on slopes for raft foundation

D Water proofing membrane to horizontal surfaces 64 m2


and on slopes above flat slab

E Water proofing membrane to vertical surfaces 205 m2

Sundries

F Protection boards (tank walls); including fixings and 205 m2


accessories compete as per Drawings and
Specifications

Omrania & Associates 10/Div-07/3


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div-07/4


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 07 - THERMAL AND MOISTURE


PROTECTION (CONT'D)

Section 07 13 53: Elastomeric Membrane


Waterproofing

Portable Water Tank Linings

Lining

A For internal walls 456 m2

B For floor slab 450 m2

C For roof slab 450 m2

Storm Water Lifting Station

Lining

D For internal walls 185 m2

E For floor slab 48 m2

F For roof slab 48 m2

Omrania & Associates 10/Div-07/5


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div-07/6


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 07 - THERMAL AND MOISTURE


PROTECTION

COLLECTION

10/7/1

10/7/2

10/7/3

Omrania & Associates 10/Div-07/7


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)


0
To Summary SR

Omrania & Associates 10/Div-07/8


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Rate
Item Description Quantity Unit Amount (SR)
(SR)

DIVISION 09 - FINISHES

The Tenderer is referred to the Specifications and Note


Drawings for all details related to this section of the
works and he is to include for complying with all the
requirements contained therein, whether or not they are
specifically mentioned within the items

All bellow mentioned items are subject to supply, install, Note


testing and commissioning and warranty, as per
Specifications and other Tender Documents.

The Tenderer shall allow for additional items and costs Note
not specifically mentioned in this bill but necessary for
the satisfactory completion of the contract. Particular
items shall be considered to be included in the prices of
the items, No claims will be entertained for any items
shown or inferred by the Specifications and Drawings
and not included herein.

Floor Finishes

Section 09 67 23: Resinous Flooring

Two coats of non-toxic epoxy resin over cementitious


waterproofing coat complete, all as per Drawing A931
and Specification

A Floor Type - F4 450 m2

Wall Finishes

Section 09 67 23: Resinous Flooring

Two coats of non-toxic epoxy resin over cementitious


waterproofing coat complete, all as per Drawing A931
and Specification.

B Walls Type - W4 420 m2

Ceiling Finishes

Section 09 67 23: Resinous Flooring

Two coats of non-toxic epoxy resin over cementitious


waterproofing coat complete, all as per Drawing A931
and Specification.

C Ceiling Type - C8 450 m2

Omrania & Associates 10/Div-09/1


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Rate
Item Description Quantity Unit Amount (SR)
(SR)

To Summary SR

Omrania & Associates 10/Div-09/2


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 10 - SPECIALITIES

The Tenderer is referred to the Specifications and Note


Drawings for all details related to this section of the
works and he is to include for complying with all the
requirements contained therein, whether or not
they are specifically mentioned within the items

All bellow mentioned items are subject to supply, Note


install, testing and commissioning and warranty, as
per Specifications and other Tender Documents.

The Tenderer shall allow for additional items and Note


costs not specifically mentioned in this bill but
necessary for the satisfactory completion of the
contract. Particular items shall be considered to be
included in the prices of the items, No claims will be
entertained for any items shown or inferred by the
Specifications and Drawings and not included
herein.

Section 10 14 00: Signage

Signage; complete as per Drawing A911 to A913


and Specifications

A Building external signage 1 No.

Omrania & Associates 10/Div-10/1


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Summary SR

Omrania & Associates 10/Div-10/2


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Qty Unit Rate (SR) Amount (SR)

DIVISION 22 - PLUMBING

The Tenderer is referred to the Specifications and Note


Drawings for all details related to this section of the
works and he is to include for complying with all the
requirements contained therein, whether or not
they are specifically mentioned within the items

All bellow mentioned items are subject to supply, Note


install, testing and commissioning and warranty, as
per Specifications and other Tender Documents.

The Tenderer shall allow for additional items and Note


costs not specifically mentioned in this bill but
necessary for the satisfactory completion of the
contract. Particular items shall be considered to be
included in the prices of the items, No claims will be
entertained for any items shown or inferred by the
Specifications and Drawings and not included
herein.

POTABLE WATER TANK

Section 22 05 00: Common Work Results For


Plumbing

Section 22 05 23: General Duty Valves For


Plumbing Piping

Isolating valve with all fixings, fitting accessories


complete as per Drawing PWT-P501 and
Specifications

A 25mm diameter with back flow prevent 1 Nr

Hose Bib; including valves, hose bib, fittings,


painted steel lockable box and accessories
complete all as per Drawing PWT-P501 and
Specifications.

B 25mm diameter with painted steel lockable 1 Nr

Omrania & Associates 10/Div-22/1


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Qty Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div-22/2


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Qty Unit Rate (SR) Amount (SR)

DIVISION 22 - PLUMBING (CONT'D)

Section 22 11 13: Facility Water Distribution


Piping

uPVC Class 5 pipeworks and fittings including civil


works, brackets, hangers, supports, all fixing
accessories and jointing; complete as per Drawing
PWT-P501 and Specifications

A 90mm diameter 55 m

B 110mm diameter 60 m

C 160mm diameter 50 m

Section 22 13 00: Facility Sanitary Sewerage

Drainage Pipe Works And Fittings

uPVC Class 5 pipeworks and fittings including civil


works, brackets, hangers, supports, all fixing
accessories and jointing; complete as per Drawing
PWT-P502 and Specifications

D 75mm diameter 40 m

E 110mm diameter 75 m

F 160mm diameter 30 m

Section 22 13 19:Sanitary Waste Piping


Specialities

Drainage Works Specialities

G Area drain; 110mm diameter 3 Nr

Channel Drain

H 1000 x 300 x 250 mm deep, Channel drain 4 Nr


including galvanized steel grating cover and frame

J 5000 x 300 x 250 mm deep, Channel drain 1 Nr


including galvanized steel grating cover and frame

Omrania & Associates 10/Div-22/3


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Qty Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div-22/4


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Qty Unit Rate (SR) Amount (SR)

DIVISION 22 - PLUMBING (CONT'D)

STORM WATER LIFTING STATION AND


SEWAGE HOLDING TANK

Section 22 05 00: Common Work Results For


Plumbing

Cast iron pipeworks and fittings including civil


works, brackets, supports, all fixing accessories
and jointing; complete as per Drawing SWSH-P501
and Specifications

A 200mm diameter, vent pipes with vent cowl and 10 m


activated carbon filter

B 300mm diameter, vent pipes with vent cowl and 5 m


activated carbon filter

Supply and installation of Ductile iron pipes with


standard strength; works includes supply,
installation and protection for pipes and fittings,
thrust blocks, leakage tests, operation surveying
works and all necessary works as per Drawing
SWSH-P501 and Specifications.

C 150mm diameter for force main 10 m

D 200mm diameter for force main 2 m

E 250mm diameter for force main 15 m

F 400mm diameter for force main 15 m

uPVC Class 5 pipeworks and fittings including civil


works, brackets, hangers, supports, all fixing
accessories and jointing; complete as per Drawing
SWSH-P501 and Specifications

G 300mm diameter 5 m

H 450mm diameter 5 m

Omrania & Associates 10/Div-22/5


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Qty Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div-22/6


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Qty Unit Rate (SR) Amount (SR)

DIVISION 22 - PLUMBING (CONT'D)

Section 22 05 00: Common Work Results For


Plumbing

Supply and install gate valves with PN 16 bars and


work shall include reinforced concrete chambers,
covers, excavation backfilling, waterproofing,
damproofing, supply and installation of all valve
accessories, surface box, stem, marker posts,
couplings and concrete support below the valve
and according to Specifications and Drawing
SWSH-P501.

Valves

A 150mm diameter 2 Nr

B 250mm diameter 2 Nr

Non-Return Valve

C 150mm diameter 2 Nr

D 250mm diameter 2 Nr

Audio Visual Alarm System

E Audio Visual Alarm System for all tanks including 1 Item


warning light and audible alarm (hidden in
plantation), audio/ visual alarm post with concrete
base, electrical pipe sleeves, cables, high effluent
sensor level float switch connected to audio/ visual
alarm complete with all accessories and fittings to
full operation as per Drawings.

Omrania & Associates 10/Div-22/7


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Qty Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div-22/8


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Qty Unit Rate (SR) Amount (SR)

DIVISION 22 - PLUMBING (CONT'D)

Utility Coordination And Tie-Ins Connections

All the utility TIE-INS/ Connections are the Note


responsibility of the contractor. Contractor shall
obtain from the Employer and/ or Supervision
Consultant the latest revision of the Infrastructure
Drawings and/ or As-Built survey of utilities to
confirm TIE-INS points.

Construction documents have shown utility TIE-INS Note


as accurately as immediately known to Engineer
any discrepancy between As-Built/ revised utility
locations and those shown in the construction
documents.

A All Utility Connections Water Supply, Drainage, 1 Item


Irrigations, Storm Water, Electricity and
Communications Network, related work shall be
competed per utility company and requirements
and make good the existing finishes.

Omrania & Associates 10/Div-22/9


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Qty Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div-22/10


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Qty Unit Rate (SR) Amount (SR)

DIVISION 22 - PLUMBING

COLLECTION

10/22/1

10/22/2

10/22/3

10/22/4

10/22/5

Omrania & Associates 10/Div-22/11


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Qty Unit Rate (SR) Amount (SR)

To Summary SR

Omrania & Associates 10/Div-22/12


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 23 - HVAC

The Tenderer is referred to the Specifications and Note


Drawings for all details related to this section of the
works and he is to include for complying with all the
requirements contained therein, whether or not
they are specifically mentioned within the items

All bellow mentioned items are subject to supply, Note


install, testing and commissioning and warranty, as
per Specifications and other Tender Documents.

The Tenderer shall allow for additional items and Note


costs not specifically mentioned in this bill but
necessary for the satisfactory completion of the
contract. Particular items shall be considered to be
included in the prices of the items, No claims will be
entertained for any items shown or inferred by the
Specifications and Drawings and not included
herein.

Heating, Ventilating And Air-Conditioning

Section 23 05 53: Identification For HVAC


Piping And Equipment

A Sundries including but not limited to supports, 1 Item


identification, tools and spares and documents.

Section 23 08 00: Commissioning Of HVAC

B Allow for Testing and Commissioning of HVAC 1 Item


system including testing, adjusting and balancing

Omrania & Associates 10/Div-23/1


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div-23/2


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 23 - HVAC (CONT'D)

POTABLE WATER TANK

Section 23 07 13: HVAC Insulation

Duct work insulation including all associated


accessories and fixings; complete as per Drawing
PWT-M101 and Specifications

A Indoor type insulation 50 m2

Chilled Water Pipe [CWP] Thermal Insulation

Chilled water pipe work insulation shall be high


rigid resin bonded pre-formed fiber glass section of
the thickness specified. Price include for fixing,
sealant, surface reinforcement and all necessary
accessories as shown on Drawing PWT-M101 and
Specifications.

B 25mm diameter 65 m

C 32mm diameter 55 m

D 40mm diameter 15 m

E 50mm diameter 5 m

Section 23 21 13: Hydronic Piping

Chilled Water System Pipework

Black steel pipes, Schedule 40; seamless Grade B


in accordance to ASTM A53 and fittings including
all necessary accessories, supports, blanking
plates; jointing, flanges, chasing in walls, pipe
protection and sealants, all in accordance with
Manufacturer's instructions complete as per
Specifications. Unit rate to include penetrations in
walls and slabs with water and fire proofing;
complete as per Drawing PWT-M101 and
Specifications

F 25mm diameter 65 m

G 32mm diameter 55 m

Omrania & Associates 10/Div-23/3


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div-23/4


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 23 - HVAC (CONT'D)

Section 23 21 13: Hydronic Piping

Chilled Water System Pipework

A 40mm diameter 15 m

B 50mm diameter 5 m

Section 23 21 14: Hydronic Specialities

Accessories

Valves And Fittings; as per Drawing PWT-M101


and Specifications

IV; Isolating Valve, Valves And Fittings; including


all fixings and accessories complete as per
Drawing and Specifications

C 50mm diameter 3 Nr

DRV/VO; Double Regulating Valve with variable


orifice, valves and fittings; complete as per Drawing
and Specifications

D 50mm diameter 1 Nr

Section 23 31 00: HVAC Ducts And Casings

Duct Work

Galvanized iron ductwork including insect screen


access, doors, duct end caps, all fittings, hangers,
supports, fixings, sealant and accessories
complete all as per Drawing PWT-M101 series and
Specifications

E Rectangular duct work 365 Kg

Section 23 37 00: Air Outlets And Inlets

Bell Mouth Openings with fixings, fitting


accessories complete as per Drawings PWT-M101
and Specifications

F BMO - 200 x 200 mm, with wire mesh screen 3 Nr

Omrania & Associates 10/Div-23/5


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div-23/6


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 23 - HVAC (CONT'D)

Section 23 82 00: Convection Heating And


Cooling Units

Chilled Water Fan Coil Units

Chilled Water Fan Coil Units; fan coil units,


including valves, hangers, supports, controls,
thermostats and all fixing and fittings; complete all
as per Drawings and related Detail Drawing PWT-
M101 and Specifications.

A PWT-FCU-B-01 to 05; Supply fan airflow 285 l/s; 5 Nr


fan motor rating 0.147 kW; total cooling 5.86 kW;
sensible cooling 5.17 kW; electrical supply
230V/1Ph/60Hz

Exhaust Fans; including electrical connections and


all fixing, electrical power 230V/1Ph/60Hz;
complete as per Drawings and Specifications

B EF-01; Centrifugal inline fan, belt drive; air flow 130 1 Nr


l/s; fan ESP 100 Pa; fan motor rating 0.225 kw;
electrical supply 230V/1Ph/60Hz.

Omrania & Associates 10/Div-23/7


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div-23/8


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 23 - HVAC

COLLECTION

10/23/1

10/23/2

10/23/3

10/23/4

Omrania & Associates 10/Div-23/9


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Summary SR

Omrania & Associates 10/Div-23/10


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Rate
Item Description Quantity Unit Amount (SR)
(SR)

DIVISION 26 - ELECTRICAL INSTALLATIONS

The Tenderer is referred to the Specifications and Note


Drawings for all details related to this section of the
works and he is to include for complying with all the
requirements contained therein, whether or not they
are specifically mentioned within the items

All bellow mentioned items are subject to supply, Note


install, testing and commissioning and warranty, as
per Specifications and other Tender Documents.

The Tenderer shall allow for additional items and Note


costs not specifically mentioned in this bill but
necessary for the satisfactory completion of the
contract. Particular items shall be considered to be
included in the prices of the items, No claims will be
entertained for any items shown or inferred by the
Specifications and Drawings and not included herein.

Potable And Raw Water Tank And Pump room

Low Voltage Electrical Power Installations

Section 26 05 19: LV Electrical Power


Conductors And Cables

Supply, install, test and commissioning: 600/1000


Volt grade CU/XLPE/SWA/LSZH feeder cables on LV
switchgear; sub-main circuits, final circuits, and other
related power supply source including necessary
excavations, backfilling, bedding with imported
materials, concrete encasement ground
reinstatement, busway components, cable
connections, end terminations and other related civil
works as required. All general fixings, conduits,
connections, MCCB branch circuit breakers, cable
boxes, cable glands, cable trays, neutral and
grounding connections, monitoring and metering
protection, instrumentations, and fittings work supply
accessories complete as Detail Drawings E401 to
E402 and Specifications

Source EMDB-01 | Electrical Building

1 No. (4 x 95mm² XLPE) + 1 x 50mm² G


A From EMDB-01 to ESMDB-WT 65 Lm

Omrania & Associates 10/Div-26/1


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Rate
Item Description Quantity Unit Amount (SR)
(SR)

To Collection SR

Omrania & Associates 10/Div-26/2


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Rate
Item Description Quantity Unit Amount (SR)
(SR)

DIVISION 26 - ELECTRICAL INSTALLATIONS (CONT'D)

Section 26 05 19: LV Electrical Power Conductors


And Cables

Source EMDB-01 | Electrical Building

1 No. (4 x 4mm² XLPE) + 1 x 4mm² G


A From EMDB-01 to isolator, jockey pumps control panel 80 Lm

1 No. (3-1/2 x 70mm² XLPE) + 1 x 35mm² G


B From EMDB-01 to isolator, fire pumps control panel 70 Lm

Source ESMDB-WT | U/G Water Tank & Pump Room

1 No. (4 x 10mm² XLPE) + 1 x 10mm² G


C From ESMDB-WT to isolator, potable water 15 Lm
booster pumps control panel PWPS1-CP

1 No. (4 x 10mm² XLPE) + 1 x 10mm² G


D From ESMDB-WT to isolator, potable water 15 Lm
booster pumps control panel PWPS2-CP

1 No. (4 x 10mm² XLPE) + 1 x 10mm² G


E From ESMDB-WT to isolator, potable water 15 Lm
booster pumps control panel PWPS3-CP

1No. (4 x 10mm²
ESMDB-WT XLPE)sump
to isolator, + 1 x pump
10mm²WT-SP-CP
G from
F 23 Lm

1No. (4 x 10mm²
ESMDB-WT XLPE) sump
to isolator, + 1 x 10mm² G From
pump RB-SP-CP
G 28 Lm

Omrania & Associates 10/Div-26/3


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Rate
Item Description Quantity Unit Amount (SR)
(SR)

To Collection SR

Omrania & Associates 10/Div-26/4


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Rate
Item Description Quantity Unit Amount (SR)
(SR)

DIVISION 26 - ELECTRICAL INSTALLATIONS (CONT'D)

Section 26 09 43: Network Lighting Control


System (KNX)

Supply, install, testing, commissioning Network


Lighting Control System (KNX); associated conduits,
cabling points, cables, 2 x 2 x 0.8 mm twisted cable
KNX bus connection, final circuits, wiring device
connections, end terminations. All general fixing
supports, fittings work supply accessories complete
as Detail Drawings, Schedules and Specification
related Sections

A KNX smart wall switch with bus-coupler, 1 No


weatherproof-2-folds

Section 26 23 00: LV Switchgear / Distribution


Boards

Supply, install, testing, commissioning Electrical


Distribution Boards; including electrical wiring
connections, bus bars, branch circuit breakers,
lightings and power electrical loads with circuit
breakers, incoming/ outgoing adjustable/ fixed
molded case circuit breaker MCCB; all associated
equipment fixing supports, fittings, accessories,
control switches, wiring devices, metering
instrumentations, earth fault grounding protection unit
connections, end termination accessories complete
as Detail Drawings, Schedules and Specification
related Sections

B Ref. ESMDB-WT 1 No

Section 26 27 26: Wiring Devices

Supply, install, testing, commissioning small power


wiring devices (lighting switches/ socket outlets/
disconnected switches); final circuits, conduits, cable
boxes, wiring points, small wirings, cables,
connections, end terminations. All general fixing
supports, fittings work supply accessories complete
as Detail Drawings, Schedules and Specification
related Sections

Socket Outlets

C 13A, 2P+E, 230V, single switched socket outlet; 3 No


weatherproof

Omrania & Associates 10/Div-26/5


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Rate
Item Description Quantity Unit Amount (SR)
(SR)

To Collection SR

Omrania & Associates 10/Div-26/6


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Rate
Item Description Quantity Unit Amount (SR)
(SR)

DIVISION 26 - ELECTRICAL INSTALLATIONS (CONT'D)

Section 26 27 26: Wiring Devices

Socket Outlets

A Junction box 5 No

Isolators ( including conduits, cable connections , and


all fixing supports, fitting accessories complete )

B 20A, 230V, single-phase, isolator switch with 5 No


pilot lamp; weatherproof

C 20A, 230V, single-phase, isolator switch; 10 No


weatherproof

D 30A, 400V, three-phase, isolator switch, 4 No


weatherproof

Isolators "Device Only" [ Cables Not Included ]

E 30A, 400V, three-phase, isolator switch, 5 No


weatherproof

F 30A, 400V, three-phase, isolator switch, 1 No


weatherproof - jockey pumps control panel

G 100A, 400V, three-phase, isolator switch, 1 No


weatherproof RO-CP control panel (measured cable
refer to male quarter)

H 200A, 400V, three-phase, isolator switch, 1 No


weatherproof - fire pumps control panel

Section 26 51 00, 26 52 00: Interior, Emergency


And Exit Lightings

Lighting Fixtures (BOH); as per Drawing No. E002

Lighting circuit wirings including necessary conduits,


cabling points, small wirings, cabling connections, all
fixings, supports, and fittings work supply
accessories complete as requires

J Lighting points 40 No

Omrania & Associates 10/Div-26/7


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Rate
Item Description Quantity Unit Amount (SR)
(SR)

To Collection SR

Omrania & Associates 10/Div-26/8


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Rate
Item Description Quantity Unit Amount (SR)
(SR)

DIVISION 26 - ELECTRICAL INSTALLATIONS (CONT'D)

Supply, install, testing, commissioning Lighting


Fixtures; including necessary conduits, cable boxes,
lamps, lamp holders, frames, hangers, reflectors,
wiring devices (fully equipped electric wiring
connections/ high frequency electronic ballast/ self-
maintained fully automatic type powered with back-
up battery and charger as requires). All general
fixings, supports, and fittings work supply
accessories complete as Detail Drawings, Schedules
and Specification related Sections

A Type A2; 2 x 28W, 230V, 60Hz, T5-Lamp, surface- 26 No


mounted or suspended weather-proof luminaire of
PC. Luminaire body of clear polycarbonate, flame-
resistant and recyclable, impact-resistant, UV-
stabilised. Light colour neutral white, colour
temperature 4000K, Safety class I, Protection rating
IP66, Impact resistance 6 J, Heat resistance 850 °C.
with electronic transformer, switchable. System
Dimension: 150 mm x 1200 mm. Color rendering
index RA > 80, UGR < 20.

B Type A2, EM; with battery back up and charger. 2 x 14 No


28W, 230V, 60Hz, T5-Lamp, surface-mounted or
suspended weather-proof luminaire of PC. Luminaire
body of clear polycarbonate, flame-resistant and
recyclable, impact-resistant, uv-stabilised. Light
colour neutral white, colour temperature 4000K,
Safety class I, Protection rating IP66, Impact
resistance 6 J, Heat resistance 850 °C with electronic
transformer, switchable. System Dimension: 150 mm
x 1200 mm. Color rendering index RA > 80, UGR <
20.

Omrania & Associates 10/Div-26/9


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Rate
Item Description Quantity Unit Amount (SR)
(SR)

To Collection SR

Omrania & Associates 10/Div-26/10


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Rate
Item Description Quantity Unit Amount (SR)
(SR)

DIVISION 26 - ELECTRICAL INSTALLATIONS (CONT'D)

Storm Water Lifting Station And Sewage Holding


Tank

Low Voltage Electrical Power Installations

Section 26 05 19: LV Electrical Power Conductors


And Cables

Supply, install, test and commissioning: 600/1000


Volt grade CU/XLPE/SWA/LSZH feeder cables on LV
switchgear; sub-main circuits, final circuits, and other
related power supply source including necessary
excavations, backfilling, bedding with imported
materials, concrete encasement ground
reinstatement, busway components, cable
connections, end terminations and other related civil
works as required. All general fixings, conduits,
connections, MCCB branch circuit breakers, cable
boxes, cable glands, cable trays, neutral and
grounding connections, monitoring and metering
protection, instrumentations, and fittings work supply
accessories complete as Detail Drawings SWSH-
E301, E402 and Specifications

Source ESMDB-WT UG Water Tank And Pump


Room (Cont'd)

1 No. (31/2 x 25mm² XLPE) + 1 x 16mm²G


A From ESMDB-WT to isolator, storm water 65 Lm
lifting station control SWLS-CP panel

1 No. (4 x 10mm² XLPE) + 1 x 10mm² G


B From ESMDB-WT to isolator, sewage lifting pump 55 Lm
control panel SLP-CP

Section 26 27 26: Wiring Devices

Supply, install, testing, commissioning small power


wiring devices

C 30A, 400V, three-phase, isolator switch, 1 No


weatherproof - sewage holding tank

D 100A, 400V, three-phase, isolator switch, 1 No


weatherproof storm water lifting station

Omrania & Associates 10/Div-26/11


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Rate
Item Description Quantity Unit Amount (SR)
(SR)
To Collection SR

Omrania & Associates 10/Div-26/12


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Rate
Item Description Quantity Unit Amount (SR)
(SR)

DIVISION 26 - ELECTRICAL INSTALLATIONS (CONT'D)

Water Feature N0.4 - Pump Room

Low Voltage Electrical Power Installations

Section 26 05 19: LV Electrical Power Conductors


And Cables

Supply, install, test and commissioning: 600/1000


Volt grade CU/XLPE/SWA/LSZH feeder cables on LV
switchgear; sub-main circuits, final circuits, and other
related power supply source including necessary
excavations, backfilling, bedding with imported
materials, concrete encasement ground
reinstatement, busway components, cable
connections, end terminations and other related civil
works as required. All general fixings, conduits,
connections, MCCB branch circuit breakers, cable
boxes, cable glands, cable trays, neutral and
grounding connections, monitoring and metering
protection, instrumentations, and fittings work supply
accessories complete as Detail Drawing WF4-E301
and Specifications

Source LPP-GH | Guardhouse (Cont'd)

1 No. (4 x 16mm² XLPE/SWA) + 1 x 16mm²G


A From LPP-GH to LPP-WF4 60 Lm

Sundries

B 3 x 50 mm uPVC pipe sleeve 1 No

Section 26 24 16: Panel Boards

Supply and installations electrical final distribution


boards including electrical wiring connections,
lightings and power electrical loads with circuit
breakers, and all general fixings, supports, fittings
work supply accessories, end terminations. Complete
as Detail Drawings, Single Line Diagrams and
Specification related Sections

C Ref. LPP-MF4 1 No

Omrania & Associates 10/Div-26/13


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Rate
Item Description Quantity Unit Amount (SR)
(SR)

To Collection SR

Omrania & Associates 10/Div-26/14


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Rate
Item Description Quantity Unit Amount (SR)
(SR)

DIVISION 26 - ELECTRICAL INSTALLATIONS (CONT'D)

Section 26 27 26: Wiring Devices

Supply, install, testing, commissioning small power


wiring devices (lighting switches/socket
outlets/disconnected switches); final circuits,
conduits, cable boxes, wiring points, small wirings,
cables, connections, end terminations. All general
fixing supports, fittings work supply accessories
complete as Detail Drawings, Schedules and
Specification related Sections

Lighting Switches

A 10A, 230V, single pole, one way, one gang, 1 No


lighting switch; weatherproof

B 10A, 230V, single pole, one way, one gang, 1 No


lighting switch; weatherproof - for exhaust fan

Socket Outlets

C 13A, 2P+E, 230V, single switched socket outlet, 3 No


weatherproof

D Junction box 1 No

Isolators - weatherproof ( including conduits, cable


connections, and all fixing supports, fitting
accessories complete )

E 20A, 230V, single-phase, isolator switch; weatherproof 2 No

F 30A, 400V, three-phase, isolator switch, weatherproof 3 No

Section 26 51 00, 26 52 00: Interior, Emergency


And Exit Lightings

Lighting Fixtures (BOH); as per Drawing No. E002

Lighting circuit wirings including necessary conduits,


cabling points, small wirings, cabling connections, all
fixings, supports, and fittings work supply
accessories complete as requires

G Lighting points 2 No

Omrania & Associates 10/Div-26/15


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Rate
Item Description Quantity Unit Amount (SR)
(SR)
To Collection SR

Omrania & Associates 10/Div-26/16


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Rate
Item Description Quantity Unit Amount (SR)
(SR)

DIVISION 26 - ELECTRICAL INSTALLATIONS (CONT'D)

Supply, install, testing, commissioning Lighting


Fixtures; including necessary conduits, cable boxes,
lamps, lamp holders, frames, hangers, reflectors,
wiring devices (fully equipped electric wiring
connections/ high frequency electronic ballast/ self-
maintained fully automatic type powered with back-
up battery and charger as requires). All general
fixings, supports, and fittings work supply
accessories complete as Detail Drawings, Schedules
and Specification related Sections

A Type A2; 2 x 28W, 230V, 60Hz, T5-Lamp, surface- 1 No


mounted or suspended weather-proof luminaire of
PC. Luminaire body of clear polycarbonate, flame-
resistant and recyclable, impact-resistant, UV-
stabilised. Light colour neutral white, colour
temperature 4000K, Safety Class I, Protection rating
IP66, Impact resistance 6 J, Heat resistance 850 °C.
with electronic transformer, switchable. System
Dimension: 150 mm x 1200 mm. Color rendering
index RA > 80, UGR < 20.

B Type A2, EM; with battery back up and charger. 2 x 1 No


28W, 230V, 60Hz, T5-Lamp, surface-mounted or
suspended weather-proof luminaire of PC. Luminaire
body of clear polycarbonate, flame-resistant and
recyclable, impact-resistant, uv-stabilised. Light
colour neutral white, colour temperature 4000K,
Safety Class I, Protection rating IP66, Impact
resistance 6 J, Heat resistance 850 °C with electronic
transformer, switchable. System Dimension: 150 mm
x 1200 mm. Color rendering index RA > 80, UGR <
20.

Omrania & Associates 10/Div-26/17


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Rate
Item Description Quantity Unit Amount (SR)
(SR)

To Collection SR

Omrania & Associates 10/Div-26/18


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Rate
Item Description Quantity Unit Amount (SR)
(SR)

DIVISION 26 - ELECTRICAL INSTALLATIONS

COLLECTION

10/26/1

10/26/2

10/26/3

10/26/4

10/26/5

10/26/6

10/26/7

10/26/8

10/26/9

Omrania & Associates 10/Div-26/19


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Rate
Item Description Quantity Unit Amount (SR)
(SR)

To Summary SR

Omrania & Associates 10/Div-26/20


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 27 - COMMUNICATIONS

The Tenderer is referred to the Specifications and Note


Drawings for all details related to this section of the
works and he is to include for complying with all the
requirements contained therein, whether or not
they are specifically mentioned within the items

All bellow mentioned items are subject to supply, Note


install, testing and commissioning and warranty, as
per Specifications and other Tender Documents.

The Tenderer shall allow for additional items and Note


costs not specifically mentioned in this bill but
necessary for the satisfactory completion of the
contract. Particular items shall be considered to be
included in the prices of the items, No claims will be
entertained for any items shown or inferred by the
Specifications and Drawings and not included
herein.

Section 27 15 00: Communications Horizontal


Cabling

Analog Telephone System

Supply, install, testing, commissioning Analog


Telephone Systems; including necessary conduits,
cabling points, cable boxes, telephone outlets, Cat
3, UTP cable connections, all related building
wiring connections, end terminations. All general
fixings, supports, additional fittings work supply
accessories complete as Detail Drawings and
Specification related Sections

A Telephone outlet; wall mounted - Pump Room 1 No

Omrania & Associates 10/Div-27/1


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Summary SR

Omrania & Associates 10/Div-27/2


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

The Tenderer is referred to the Specifications and Note


Drawings for all details related to this section of the
works and he is to include for complying with all the
requirements contained therein, whether or not they are
specifically mentioned within the items

All bellow mentioned items are subject to supply, install, Note


testing and commissioning and warranty, as per
Specifications and other Tender Documents.

The Tenderer shall allow for additional items and costs Note
not specifically mentioned in this bill but necessary for
the satisfactory completion of the contract. Particular
items shall be considered to be included in the prices of
the items, No claims will be entertained for any items
shown or inferred by the Specifications and Drawings
and not included herein.

Section 28 31 00: Fire Detection And Alarm Systems

Supply, install, testing, commissioning Fire Alarm And


Detection Systems; associated supply accessories
including necessary RS conduits, pull and junction
boxes, cabling points, 2-core/ 1.5mm2 fire rated cable
connections, end terminations, all related building
safety wiring connections are selected methods,
standardized deals with NFPA72 regulations. All
general fixings, additional fittings work supply
accessories complete as Detail Drawings and
Specification related Sections

Underground Water Tank And Pump Room

A Addressable fire alarm smoke detector - optical 1 No

B Addressable manual call point 1 No

C Addressable fire alarm sounder with strobe light, 1 No


wall mounted

Omrania & Associates 10/Div-28/1


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div-28/2


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 28 - ELECTRONIC SAFETY AND


SECURITY (CONT'D)

Section 28 31 00: Fire Detection And Alarm Systems

Water Feature N0.4

A Addressable fire alarm smoke detector - optical 1 No

B Addressable manual call point 1 No

C Addressable fire alarm sounder with strobe light, 1 No


wall mounted

Omrania & Associates 10/Div-28/3


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div-28/4


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 28 - ELECTRONIC SAFETY AND


SECURITY

COLLECTION

10/28/1

10/28/2

Omrania & Associates 10/Div-28/5


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Summary SR

Omrania & Associates 10/Div-28/6


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 31 - EARTHWORK

The Tenderer is referred to the Specifications and Note


Drawings for all details related to this section of the
works and he is to include for complying with all the
requirements contained therein, whether or not they
are specifically mentioned within the items

All bellow mentioned items are subject to supply, Note


install, testing and commissioning and warranty, as
per Specifications and other Tender Documents.

The Tenderer shall allow for additional items and Note


costs not specifically mentioned in this bill but
necessary for the satisfactory completion of the
contract. Particular items shall be considered to be
included in the prices of the items, No claims will be
entertained for any items shown or inferred by the
Specifications and Drawings and not included herein.

Section 31 23 00: Excavation And Fill

Excavation

Excavation commencing at clearance level.


Dimensions and depths are according to the levels
shown in the Drawings; the excavation works,
excavation in all kinds of soil and rocks and
necessary shoring and protection of works,
dewatering, any treating work for to the ground level
(termite control), any work under the ground water
level including load excavated material and remove
from site to a suitable location approved by the
Engineer's. Complete as per Drawings and
Specifications

A Excavation to receive foundation bases 3510 m3

Backfill with selected fill

Filling well compacted in layers by approved material


as per Specifications; including compaction process,
tests and all necessary work completely as per the
recommendation of the Soil Report and the
Engineer's approval

B Around foundations 500 m3

Disposal of excavated material

C Remove off-site to approved location 3510 m3

Omrania & Associates 10/Div-31/1


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Summary SR

Omrania & Associates 10/Div-31/2


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 46 - WATER AND WASTE WATER


EQUIPMENT

The Tenderer is referred to the Specifications and Note


Drawings for all details related to this section of the
works and he is to include for complying with all the
requirements contained therein, whether or not
they are specifically mentioned within the items

All bellow mentioned items are subject to supply, Note


install, testing and commissioning and warranty, as
per Specifications and other Tender Documents.

The Tenderer shall allow for additional items and Note


costs not specifically mentioned in this bill but
necessary for the satisfactory completion of the
contract. Particular items shall be considered to be
included in the prices of the items, No claims will be
entertained for any items shown or inferred by the
Specifications and Drawings and not included
herein.

Section 46 07 53: Packaged Waste Water


Treatment Equipment

A Sewage Holding Tank (SHT); submersible pumps- 1 Set


set one lead and one standby, each capacity 30
Cu.m/Hr at 14 M-Head, submersible pumps with
float switches for automatic operation, pressure
gauges, interconnecting pipes and fittings, valves,
control panel, stainless steel lifting chains, electrical
cables, 50mm diameter pump rail, all accessories
and fittings complete as per Drawings and
Specifications

B Storm Water Lifting Station (SWLS); submersible 1 Set


pumps-set one lead and one lag, each capacity
190 Cu.m/Hr at 12 M-Head, submersible pumps
with float switches for automatic operation,
pressure gauges, interconnecting pipes and
fittings, valves, control panel; stainless steel lifting
chains, electrical cables, 50mm diameter pump rail,
all accessories and fittings complete as per
Drawings and Specifications

Omrania & Associates 10/Div 46 /1


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div 46 /2


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 46 - WATER AND WASTE WATER


EQUIPMENT (CONT'D)

Section 46 07 53: Packaged Waste Water


Treatment Equipment

Potable Water And Miscellaneous Equipment;


comprising interconnecting pipework, valves,
fittings, gauges, sensors, expansion fittings,
concrete base, anti-vibrators, frequency converter
for variable speed, complete with expansion tank,
pressure gauges, switches, dry running protection
and control panel and other accessories to make
system fully functional. Alarm signals including
pump tripped, power supply, and water abnormal
levels shall be provided and transmitted to pump
controller panel and repeated to BMS. Complete all
as Drawing PWT-P701, and Specification

Potable Water Booster Pump Set-1

A One lead, one lag and one standby pumps, auto 1 Set
alternating, multi-stage, vertical and centrifugal
type. Pumps to be mounted on common base
frame pumps to be stainless steel Grade 316.
Capacity: Each pump capacity: 8.0 Cu.m/Hr at 71
M-head. Pumps set to be complete with pressure
gauges and switches, vibration isolators,
interconnecting pipe work, valves and check
valves, control panel, dry-running protection and
variable frequency drive for automatic operation.

Potable Water Booster Pump Set-2

B One lead, one lag and one standby pumps, auto 1 Set
alternating, multi-stage, vertical and centrifugal
type. Pumps to be mounted on common base
frame pumps to be stainless steel Grade 316.
Capacity: Each pump capacity: 7.0 Cu.m/Hr at 48
M-Head. Pumps set to be complete with pressure
gauges and switches, vibration isolators,
interconnecting pipe work, valves and check
valves, control panel, dry-running protection and
variable frequency drive for automatic operation.

Omrania & Associates 10/Div 46 /3


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div 46 /4


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 46 - WATER AND WASTE WATER


EQUIPMENT (CONT'D)

Section 46 07 53: Packaged Waste Water


Treatment Equipment

Potable Water Booster Pump Set-2

A One lead, one lag and one standby pumps, auto 1 Set
alternating, multi-stage, vertical and centrifugal
type. Pumps to be mounted on common base
frame pumps to be stainless steel Grade 316.
Capacity: Each pump capacity: 14.0 Cu. m/Hr at 41
M-head. Pumps set to be complete with pressure
gauges and switches, vibration isolators,
interconnecting pipe work, valves and check
valves, control panel, dry-running protection and
variable frequency drive for automatic operation.

Pump Room Sump Pumps

B One lead and lag pumps, centrifugal, vertical, 1 Set


submersible with float switches for auto-alternating
operation. Each pump capacity: 12.0 Cu.m/Hr at 15
M-Head. Pumps set to be complete with pressure
gauges, interconnecting pipes and valves, audio/
visual alarm and control panel pumps to be have,
lifting chains, electrical cabling and accessories.

Brine Reject Sump Pumps (PWT)

C One lead and lag pumps, centrifugal, vertical, 1 Set


submersible with float switches for auto-alternating
operation. Each pump capacity: 5.0 Cu.m/Hr at 18
M-Head. Pumps set to be complete with pressure
gauges, interconnecting pipes and valves, audio/
visual alarm and control panel pumps to be have,
lifting chains, electrical cabling and accessories.

Omrania & Associates 10/Div 46 /5


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div 46 /6


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 46 - WATER AND WASTE WATER


EQUIPMENT (CONT'D)

Section 46 07 53: Packaged Waste Water


Treatment Equipment

Water Storage Tank

Insulated GRP hot sheet mould compound


sectional panel tank mounted on 500mm thick,
concrete plinths with 100mm steel I-beam, with
internal flange including steel beam, water tank
sensing system, motorize valves, digital display,
access manholes of 500mm high, access ladders
both inside and outside, inside ladder SS316, vent/
over works, vent/overflow, pipes fittings, valves
stainless steel pipe with bell mouth fittings,
discharge fittings, paddle flanges, float valve with
float ball, climbing rungs; manhole cover and
frames, water proofing and non toxic epoxy
paintings; complete all as per Drawing and
Specifications.

A Portable water and fire storage tank; including 1 Set


partition (PWFST 1 and 2), 269 Cu.m (3 Days
storage)

B Raw water storage tank; including partition (RWST 1 Set


1 and 2), 249 Cu.m (3 Days storage)

Electric Driven Fire Pump (Duty)

C 1-Duty, horizontal, split-case fire pump on steel 1 Set


base, accessories and controls, UL listed and FM
approved all in accordance with NFPA20 and
related codes. Capacity: 500 Gpm @ 175 Psi.
Pump to be installed on concrete base complete
with base mounting anti-vibration pads, valves,
relief valves, pressure gauges, interconnecting
pipework, controller, electrical wiring and all other
accessories as per NFPA 20.

Omrania & Associates 10/Div 46 /7


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div 46 /8


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 46 - WATER AND WASTE WATER


EQUIPMENT (CONT'D)

Section 46 07 53: Packaged Waste Water


Treatment Equipment

Electric Driven Fire Pump (Stand-By)

A 1 Stand-by, horizontal, split-case fire pump on steel 1 Set


base, accessories and controls, UL listed and FM
approved all in accordance with NFPA 20 and
related codes. Capacity: 500 Gpm @ 175 Psi.
Pump to be installed on concrete base complete
with base mounting anti-vibration pads, valves,
relief valves, pressure gauges, interconnecting
pipework, controller, electrical wiring and all other
accessories as per NFPA 20.

Jockey Fire Pump

B One vertical, multi-stage booster pump on common 1 Set


steel base including controls suitable for jockey of
main fire pump. Capacity: 12 Gpm. @ 180 Psi.
Pumps set to be complete with pressure gauges
and switches, vibration isolators, interconnecting
pipe work, valves and check valves, control panel,
dry-running protection and variable frequency drive
for automatic operation.

Circulating Water Pump Set - For Potable Water


Storage Tank And Raw Water Storage Tank

C One duty pumps, auto alternating, inline and 4 Nr


centrifugal type. Pumps to be mounted on common
base frame pumps to be stainless steel grade 316.
Each pump capacity: 5 Cu.m/Hr at 4.0 M-Head;
power rating 1 Kw; power 230V/1Ph/60Hz. Pumps
set to be complete with pressure gauges and
switches, vibration isolators, interconnecting pipe
work, valves and check valves, control panel, dry-
running protection and variable frequency drive for
automatic operation.

Omrania & Associates 10/Div 46 /9


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div 46 /10


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 46 - WATER AND WASTE WATER


EQUIPMENT (CONT'D)

Section 46 07 53: Packaged Waste Water


Treatment Equipment

Chlorination Dosing Set

A Dosing set to include diaphragm-type positive 1 Set


displacement pump of adjustable feed rate,
translucent chemical tank with drain and electric
mixer, valves, pipework and controls. Capacity: 6.4
Lph with max 6.9 bar pressure. Tank = 500 L.
Electric mixer (1/3 Hp) mounted on top of tank.

Anti-Scalant Dosing Set

B Dosing set to include diaphragm-type positive 1 Set


displacement pump of adjustable feed rate,
translucent chemical tank with drain and electric
mixer, valves, pipework and controls. Capacity: 6.4
Lph with max 6.9 bar pressure. Tank = 500 L.
Electric mixer (1/3 Hp) mounted on top of tank.

Existing R.O. System Equipment For Re-Used

Reverse osmosis (R.O.) system operate in


automatic function. The Contractor shall provide an
electronically monitoring scheme that will give
signal. To the pump to start if there no raw water in
the storage tank to full.

Reverse osmosis (R.O.) system interconnecting


pipes, fitting valves, and check valves, vibration
isolators, pressure gauges and others accessories
related to the above mentioned item, shall be
replaced by the new ones.

C Existing raw water filter feed pumps 1 Set

D Existing sand filters 1 Nr

E Existing PH adjustment dosing set 2 Set

F Existing de-chlorination dosing set 1 Set

G Existing cartridge filters 1 Nr

Omrania & Associates 10/Div 46 /11


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div 46 /12


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 46 - WATER AND WASTE WATER


EQUIPMENT (CONT'D)

Section 46 07 53: Packaged Waste Water


Treatment Equipment

Existing R.O. System Equipment For Re-Used

A Existing high pressure pump 1 Set

B Existing Reverse Osmosis (R.O.) 1 Set

C Existing chlorination dosing set 1 Set

D Existing flush tank 1 Nr

Omrania & Associates 10/Div 46 /13


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Collection SR

Omrania & Associates 10/Div 46 /14


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

DIVISION 46 - WATER AND WASTE WATER


EQUIPMENT

COLLECTION

10/46/1

10/46/2

10/46/3

10/46/4

10/46/5

10/46/6

10/46/7

Omrania & Associates 10/Div 46 /15


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Item Description Quantity Unit Rate (SR) Amount (SR)

To Summary SR

Omrania & Associates 10/Div 46 /16


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Ref Description AMOUNT (SR)

SUMMARY

1 Division 03 - Concrete Work

2 Division 05 - Metal Works

3 Division 07 - Thermal And Moisture Protection

4 Division 09 - Finishes

5 Division 10 - Specialities

6 Division 22 - Plumbing

7 Division 23 - HVAC

8 Division 26 - Electrical Installations

9 Division 27 - Communications

10 Division 28 - Electronic Safety And Security

11 Division 31 - Earthwork

12 Dvision 46 - Water And Waste Water Equipment

Omrania & Associates 10/Sum/1


HH PRINCE MISHAL BIN KHALID F. AL-SAUD RESIDENCE
BILL
RIYADH
N0.10 - UG WATER TANK & PUMP ROOM

Ref Description AMOUNT (SR)

SUMMARY

To General Summary

Omrania & Associates 10/Sum/2

You might also like