Saudi Aramco Inspection Checklist: Cast-In-Place Concrete Formwork Stripping Inspection SAIC Q-1016 15-Nov-17 MAH-SA-C
Saudi Aramco Inspection Checklist: Cast-In-Place Concrete Formwork Stripping Inspection SAIC Q-1016 15-Nov-17 MAH-SA-C
Saudi Aramco Inspection Checklist: Cast-In-Place Concrete Formwork Stripping Inspection SAIC Q-1016 15-Nov-17 MAH-SA-C
00 30-Jun-16
HAWIYAH AND HARADH DEVELOPMENT SATELLITE GAS COMPRESSION 10 - 01996 / 0007 MOFARREH AL-HARBI & PARTNERS
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
3.6
SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
S I
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Unless otherwise specified in the project specifications, formwork and shoring shall be left
in place to support the mass of concrete in beams, slabs and in-place structural members
until the specified concrete strength f'c is attained. SAES-Q-001
A1
(ACI 301-2010, Sec. 2.3.2.5) Sec. 3.2
Note: The preferred method of determining stripping time is by testing test cylinders that
are cured on-site or testing concrete strength in the field.
When no minimum concrete strength has been specified in the project specifications for
form removal, the following general guidelines may be used for normal weight, regular
strength concrete:
Walls, Columns, Sides of Beams & Girders 12 hours
Pan joist floors with 760mm wide pans 3 days
Pan joist floors over 760mm wide pans 4 days
Arch Centers with Live Load < Dead Load 14 days
Arch Centers with Live Load > Dead Load 7 days
Joists, Beams, Girders- Span < 3m & Live Load < Dead Load 7 days
Joists, Beams, Girders- Span < 3m & Live Load > Dead Load 14 days
SAES-Q-001
A2 Joists, Beams, Girders- Span 3-6m & Live Load < Dead Load 14 days
Sec. 3.2
Joists, Beams, Girders- Span 3-6m & Live Load > Dead Load 7 days
Joists, Beams, Girders- Span > 6m & Live Load < Dead Load 21 days
One-way floor slabs Span > 6m & Live Load > Dead Load 14 days
One-way floor slabs < 3m Span & Live Load < Dead Load 3 days
One-way floor slabs < 3m Span & Live Load > Dead Load 4 days
One-way floor slabs Span 3-6m & Live Load < Dead Load 7 days
One-way floor slabs Span 3-6m & Live Load > Dead Load 4 days
One-way floor slabs Span > 6m & Live Load < Dead Load 10 days
One-way floor slabs Span > 6m & Live Load > Dead Load 7 days
(ACI 347, Sec. 3.7.2.3)
When vertical formed surfaces require finishing, remove forms as soon as removal SAES-Q-001
A3
operations will not damage concrete. (ACI 301-2010, Sec. 2.3.2.1) Sec. 3.2
Top forms on sloping surfaces of concrete are removed as soon as removal will not allow SAES-Q-001
A4
concrete to sag. (ACI 301-2010, Sec. 2.3.2.2) Sec. 3.2
Concrete is not damaged during removal of vertical formwork for columns, walls, and SAES-Q-001
A5
sides of beams. (ACI 301-2010, Sec. 2.3.2.4) Sec. 3.2
Repairs and treatment on minor concrete damage shall be started immediately on vertical SAES-Q-001
A6
surfaces and followed immediately with specified curing. (ACI 301M-2010, Sec. 2.3.2.4) Sec. 3.2
REFERENCE DOCUMENTS:
1- SAES-Q-001 -- Criteria for Design and Construction of Concrete Structures, 07 January 2016
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Concrete is not damaged during removal of vertical formwork for columns, SAES-Q-001
A5
walls, and sides of beams. (ACI 301-2010, Sec. 2.3.2.4) Sec. 3.2
REMARKS:
REFERENCE DOCUMENTS:
1- SAES-Q-001 -- Criteria for Design and Construction of Concrete Structures, 07 January 2016