Saudi Aramco Inspection Checklist: Cast-In-Place Concrete Formwork Stripping Inspection SAIC Q-1016 15-Nov-17 MAH-SA-C

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 3
At a glance
Powered by AI
The document outlines guidelines for stripping formwork from cast-in-place concrete based on factors like member size and geometry, concrete strength, and project specifications.

Formwork can be stripped when field-cured concrete cylinders reach the specified compressive strength, or when other guidelines based on member size and geometry are followed if no strength is specified.

Guidelines are provided for stripping times based on member size and geometry, ranging from 3 to 21 days depending on the factor.

SAUDI ARAMCO ID/PIEU - 15-Nov-2017 - REV. 2016.06.00 (Standards Cutoff -June 30, 2016) Rev. 2016.06.

00 30-Jun-16

SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

Cast-In-Place Concrete Formwork Stripping Inspection SAIC Q-1016 15-Nov-17 MAH-SA-C-


PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

HAWIYAH AND HARADH DEVELOPMENT SATELLITE GAS COMPRESSION 10 - 01996 / 0007 MOFARREH AL-HARBI & PARTNERS
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
3.6
SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
S I
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

Unless otherwise specified in the project specifications, formwork and shoring shall be left
in place to support the mass of concrete in beams, slabs and in-place structural members
until the specified concrete strength f'c is attained. SAES-Q-001
A1
(ACI 301-2010, Sec. 2.3.2.5) Sec. 3.2
Note: The preferred method of determining stripping time is by testing test cylinders that
are cured on-site or testing concrete strength in the field.

When no minimum concrete strength has been specified in the project specifications for
form removal, the following general guidelines may be used for normal weight, regular
strength concrete:
Walls, Columns, Sides of Beams & Girders 12 hours
Pan joist floors with 760mm wide pans 3 days
Pan joist floors over 760mm wide pans 4 days
Arch Centers with Live Load < Dead Load 14 days
Arch Centers with Live Load > Dead Load 7 days
Joists, Beams, Girders- Span < 3m & Live Load < Dead Load 7 days
Joists, Beams, Girders- Span < 3m & Live Load > Dead Load 14 days
SAES-Q-001
A2 Joists, Beams, Girders- Span 3-6m & Live Load < Dead Load 14 days
Sec. 3.2
Joists, Beams, Girders- Span 3-6m & Live Load > Dead Load 7 days
Joists, Beams, Girders- Span > 6m & Live Load < Dead Load 21 days
One-way floor slabs Span > 6m & Live Load > Dead Load 14 days
One-way floor slabs < 3m Span & Live Load < Dead Load 3 days
One-way floor slabs < 3m Span & Live Load > Dead Load 4 days
One-way floor slabs Span 3-6m & Live Load < Dead Load 7 days
One-way floor slabs Span 3-6m & Live Load > Dead Load 4 days
One-way floor slabs Span > 6m & Live Load < Dead Load 10 days
One-way floor slabs Span > 6m & Live Load > Dead Load 7 days
(ACI 347, Sec. 3.7.2.3)
When vertical formed surfaces require finishing, remove forms as soon as removal SAES-Q-001
A3
operations will not damage concrete. (ACI 301-2010, Sec. 2.3.2.1) Sec. 3.2
Top forms on sloping surfaces of concrete are removed as soon as removal will not allow SAES-Q-001
A4
concrete to sag. (ACI 301-2010, Sec. 2.3.2.2) Sec. 3.2
Concrete is not damaged during removal of vertical formwork for columns, walls, and SAES-Q-001
A5
sides of beams. (ACI 301-2010, Sec. 2.3.2.4) Sec. 3.2

Repairs and treatment on minor concrete damage shall be started immediately on vertical SAES-Q-001
A6
surfaces and followed immediately with specified curing. (ACI 301M-2010, Sec. 2.3.2.4) Sec. 3.2

When removal of formwork, reshoring, or backshoring is based on concrete reaching a


specified compressive strength, concrete is presumed to have reached this strength when SAES-Q-001
A7
test cylinders, field cured the same as the concrete they represent, have reached Sec. 3.2
compressive strength specified. (ACI 301-2010, Sec. 2.3.4.1)

Forms removal (stripping) shall be based on concrete's achieving minimum strength


requirements as set forth by the design engineer as verified by sample cylinders SAES-Q-001
A6
compressive strength results; Otherwise the guidelines in item A2 above are to be Sec. 7.19
followed. (ACI 347, Sec. 3.7.2.3)
REMARKS:

REFERENCE DOCUMENTS:
1- SAES-Q-001 -- Criteria for Design and Construction of Concrete Structures, 07 January 2016

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:
Mr. Tahir Muhammad
QC Inspector PID Representative
Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:
Mr. Jenny Ministerio Mr. Noe Cadavona
QC Supervisor Proponent and Others
Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:
Name, Organization,
Name, Sign and Date:
Mr. Rehman Ali Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED


SAUDI ARAMCO ID/PIEU - 15-Nov-2017 - REV. 2016.06.00 (Standards Cutoff -June 30, 2016) Rev. 2016.06.00 30-Jun-16
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Cast-In-Place Concrete Formwork Stripping Inspection SAIC Q-1016 15-Nov-17 CIVIL-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

Top forms on sloping surfaces of concrete are removed as soon as SAES-Q-001


A4
removal will not allow concrete to sag. (ACI 301-2010, Sec. 2.3.2.2) Sec. 3.2

Concrete is not damaged during removal of vertical formwork for columns, SAES-Q-001
A5
walls, and sides of beams. (ACI 301-2010, Sec. 2.3.2.4) Sec. 3.2

Repairs and treatment on minor concrete damage shall be started


SAES-Q-001
A6 immediately on vertical surfaces and followed immediately with specified
Sec. 3.2
curing. (ACI 301M-2010, Sec. 2.3.2.4)

When removal of formwork, reshoring, or backshoring is based on


concrete reaching a specified compressive strength, concrete is
SAES-Q-001
A7 presumed to have reached this strength when test cylinders, field cured
Sec. 3.2
the same as the concrete they represent, have reached compressive
strength specified. (ACI 301-2010, Sec. 2.3.4.1)

Forms removal (stripping) shall be based on concrete's achieving


minimum strength requirements as set forth by the design engineer as
SAES-Q-001
A6 verified by sample cylinders compressive strength results; Otherwise the
Sec. 7.19
guidelines in item A2 above are to be followed.
(ACI 347, Sec. 3.7.2.3)

REMARKS:

REFERENCE DOCUMENTS:
1- SAES-Q-001 -- Criteria for Design and Construction of Concrete Structures, 07 January 2016

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED