Qdoc - Tips Venkat Apdss Read
Qdoc - Tips Venkat Apdss Read
PRELIMINARY SPECIFICATIONS
ANDHRA PRADESH
DETAILED STANDARD SPECIFICATIONS
V. VENKATA NARAYANA,
Deputy Executive Engineer (R&B)
07799139399, 9440818440,
[email protected]
HOW TO BEST USE
10/8/2013 VV Narayana 4
II. The Andhra Pradesh Public Works Accounts Code.
10/8/2013 VV Narayana 5
III. The Andhra Pradesh Detailed Standard Specification.
”APDDS”
APDDS previously known as MDSS‐Madras Detailed Standard
Specification
It is an indispensable book to all Engineering Departments.
It evolves to govern all the Engineering Branches of
of the
the Government or
Autonomous bodies.
It is the authority which the contractors have to invariably follow.
Contract Act , the Constitution and other laws prevail and not APDDS,
This code consists of
1) PR
PREL
ELIM
IMIN
INAR
ARY
Y SPECIFICATIONS.
2) ST
STAN
ANDA
DARD
RD SPECIFICATIONS.
10/8/2013 VV Narayana 6
III. The Andhra Pradesh Detailed Standard Specification.
PRELIMINARY SPECIFICATIONS‐ 73 N0 ::
Embodies the contractual relationship between the Government and the
Contractor.
Are non‐statuary and are invalid before Law.
Are amenable to (inclined to) the provisions of
of Contract
Contract Act.
Additions and alterations will be approved by the Government.
STANDARD SPECIFICATIONS
SPECIFICATIONS –
– 16 Sections::
Are Technical Specification of
of works,
works, River Conservation and Road Works.
Additions and Alterations (which do not involve Legal implications) will be
approved by Chief
Chief Engineer
Engineer (General).
10/8/2013 VV Narayana 7
ENGINEERING DEPARTMENTS in ANDHRA PRADESH
Government of
of Andhra
Andhra Pradesh consists
of THREE
of THREE branches ::
I. Public Works Department,
II.. Ir
II Irri
rig
gati
tion
on Department,
III. Roads and Building Department
Department..
10/8/2013 VV Narayana 8
AUTONOMOUS BODIES OF ENGINEERING
in ANDHRA PRADESH
Government of
of Andhra
Andhra Pradesh consists of
of following
following Autonomies Bodies::
1) Panchayat Raj Engineering Department,
2) Municipal Engineering Department,
3) Water Works and Drainage Board,
4) Housing Board,
5) Tirumala‐ Tirupathi Devasthanams,
6) Roads Transport Corporation,
7) Electricity Board,
8) Police Housing Board.
10/8/2013 VV Narayana 9
IMPORTANT NOTE ON GOVERNMENT ORDER
10/8/2013 VV Narayana 10
A.P.D.S.S SECTIONS ‐ 10
10/8/2013 VV Narayana 11
PRINCIPLE of
of SUPERMACY
SUPERMACY of
of SOVEREIGN
SOVEREIGN
The A.P.D.S.S is a code which had its humble beginnings during the British
period, in the year 1922 A.D.
At that time Public Works were at low key.
The law did not develop as it is today.
The Imperial regime evolved a Code more on the principle of supremacy
of Sovereign at the expense of contractors.
Af
Aftter In
Ind
dep
epen
ende
den
nce
ce,, th
the
e Con
ontr
tra
act
cto
ors have ch
chal
alle
leng
nged
ed man
anyy of ththe
e
provisions of the code which are onerous, involving heavy obligations .
Th
The
e Co
Cour
urts
ts ha
hav
ve de
decl
clar
ared
ed so
some
me of th
the
e Pr
Prel
elim
imin
inar
ary
y Sp
Spec
ecif
ific
icat
atio
ions
ns as
invalid.
10/8/2013 VV Narayana 12
SPECIFICATIONS & COURT JUDGMENTS
PS 60.
60. Delays in commencement or progress or neglect of
of work
work and
forfeiture of
of earnest
earnest money, security deposit and withheld amounts
PS 73. Arbitration.
10/8/2013 VV Narayana 13
SHALL
The Andhr
Andhra Pr
Prade
adesh
sh St
Stand
andar
ard
d Spe
Specif
cific
icat
ation
ionss ar
are
e in
inte
tende
nded
d
to describe
a) The char
charact
acter
er of the mat
materi
erials
als to
to be used
used::
b) The met
method
hod of ex
execu
ecutio
tion
n of work:
work:
c) The contr
contract
actor’
or’ss re
resp
spons
onsibi
ibilit
lities
ies and lia
liabil
biliti
ities
es to the Pub
Public
lic,,
Govern
Governmen
mentt and his wo
workm
rkmenen and
d) General Conditions which are to be accepted by every
cont
contrract
actor
or wh
who
o exec
ecut
ute
e th
the
e wor
ork
k en
entr
trus
uste
ted
d to him by th
the
e
PWD of Andhra Pradesh.
10/8/2013 VV Narayana 15
1. Intent and Reference to A.P.S.S.
When ever
The term “Standard Specification” or
The abbreviation “A.P.S.S.”
is used in
the Estima
Estimate
te or Contr
Contract
act docu
document
ment
it shall refer to
the relevan
relevantt specificati
specification
on in A.P.S.S.
A.P.S.S. book and
its addenda volume.
10/8/2013 VV Narayana 16
2. Applicability of
of A.P.S.S.
A.P.S.S.
10/8/2013 VV Narayana 19
5. Sub‐Specifications
ALTERATION::
Superint
Superintending
ending Engineer
Engineer and Executive
Executive Engineer may alter
alter the Standard
Specification for any particular contract , which is within their powers of
sanction.
Alteration may be done when such alteration found necessary.
Correction sheet
Shall be attached to the contact form.
Shall show the
the Sta
Standar
ndard
d Specific
Specificati
ation
on number
number and the
the correcti
corrections
ons made
made..
Sh
Shal
alll be signe
signed
d by Super
Superin
inte
tend
ndin
ing
g En
Engi
gine
neer
er or Ex
Exec
ecut
utiv
ive
e En
Engi
gine
neer
er as the
case may be together with the signature of the contractor.
10/8/2013 VV Narayana 22
7. Powers of
of Superintending
Superintending Engineers and Executive
Engineers to supplement or alter A.P.S.S.
ADDITIONAL SPECIFICA
SPECIFICATION
TION ::
Su
Supe
peri
rin
nten
endi
ding
ng En
Engi
gine
neer
er an
and
d Ex
Exec
ecut
utiv
ive
e En
Engi
gine
neer
er
may made additional specification for items for
which there no Standard Specification.
Additional Specification sheet
Shall be attached to the contact form.
Shall be
be signed
signed by Super
Superint
intendi
ending
ng Engineer
Engineer or
or Ex
Executi
ecutive
ve Engine
Engineer
er as
the case may be together with the signature of the contractor .
10/8/2013 VV Narayana 23
8. Definition of
of terms
terms
EXECUTIVE ENGINEER ::
The Ex
The Exec
ecut
utiv
ive
e En
Engi
gine
neer
er re
reffer
erss to th
the
e Ex
Exec
ecut
utiv
ive
e En
Engi
gine
neer
er
being in charge of for the concerned work under execution.
Or
Dep
epar
artm
tmen
enttal as
assi
sisstan
ants
ts or su
sub
bor
ordi
din
nates to whom th
the
e
Executive Engineer have delegated certain duties.
The assistants or subordinates shall act individually within
the scope of the particular duty entrusted to him.
10/8/2013 VV Narayana 24
8. Definition of
of terms
terms
EXECUTIVE ENGINEER ::
The Executive Engineer, Superintending Engineer
or higher authority should not delegate powers
which affect agreement and contract conditions.
The duties of
of such
such assistants or subordinates will
be solely duties of
of supervision
supervision to ensure
compliance with contract conditions.
10/8/2013 VV Narayana 25
8. Definition of
of terms
terms
CONTRACTOR ::
A particular person, firm or corporation with whom an agreement has
been made by the Executive Engineer or higher authority for executing
work defined in the contract agreement.
It shall include the contractor’s authorized agent, who is maintained on
the work by the contractor.
When two more contractors are engaged on construction work in the
same vicinity, the Executive Engineer shall be authorized to direct the
manner in which each shall conduct the work so far as it effects other
contractors.
10/8/2013 VV Narayana 26
9. Evidence of
of Experience.
Experience.
10/8/2013 VV Narayana 27
10. Legal Address‐ Notices
The tenderer should give in their tender, their place of residence and postal
address.
The delivering of letter or other communication
At the above named place or
Posting in post box or
Sending by regist
registered
ered post
Shall be deemed sufficient service in serving the communication to the
contractor in writing.
The tenderer can change his address at any time by an instrument executed
by the contractor and delivered to the Executive Engineer.
There is no condition in agreement that can prevent the service of any
notice, letter, or other communication upon the contractor personally.
10/8/2013 VV Narayana 28
11. Quantities approximate and contractor
to verify nature and amount of
of work
work
Ten
ende
dere
rerrs mu
must
st sa
satis
tisfy
fy th
them
emse
selv
lves
es th
the
e ac
accu
currac
acy
y an
and
d su
sufffi
fici
cien
ency
cy of
stateme
statement
nt of quan
quantit
tities
ies an
and
d al
alll cond
condit
itio
ions
ns af
afffec
ecti
ting
ng th
the
e wor
ork
k (b
(by
y
personal examination of the site, the plans, the specification and by
other means).
After submission of tender, the tenderer shall not dispute or complain
the statement of quantities.
The tenderer
tenderer shall not assert
assert that there was any misunde
misunders
rstan
tanding
ding in
regard to the nature or amount of work to be done.
In consequence of misunderstanding , the tendered shall not apply for
extension of time for completion beyond the agreement date.
10/8/2013 VV Narayana 30
12. Approximate not to mean deviation
from drawings and specifications.
10/8/2013 VV Narayana 31
13. To compare tenders.
• The qua
uan
nti
tities in Schedule A are for a
ties
uniform comparison of Lump ‐sum tenders.
10/8/2013 VV Narayana 32
14. Purpose
10/8/2013 VV Narayana 33
15. Conformance ‐‐ (a)
10/8/2013 VV Narayana 34
15. Conformance ‐‐ (b)
10/8/2013 VV Narayana 36
15. Conformance ‐‐ (c)
10/8/2013 VV Narayana 37
15. Conformance ‐‐ (c)
10/8/2013 VV Narayana 39
16. Variations by wa
way
y of
of modifications,
modifications,
omissions or additions
additions –
– (b)
10/8/2013 VV Narayana 41
18. Signed drawings
drawings –
– no authority to the contractor
10/8/2013 VV Narayana 42
19. Finished sizes
WOOD WORK ::
The Figur
Figured
ed dimens
dimension
ion are to be the finished sizes aft
are after
er dress
dressing
ing or planni
planning
ng
or cutting, when marked as “NETT”.
An allowance
allowance 1.50 mm will be permitted
permitted for planning
planning for each planned
planned finished
finished
of wood‐work, when not marked as “NETT”.
This allowance will only be permitted in case of Sections 15mm thick or over.
10/8/2013 VV Narayana 43
20. To be the best quality
10/8/2013 VV Narayana 44
20. To be the best quality
10/8/2013 VV Narayana 45
21. Convention for proportions
10/8/2013 VV Narayana 46
22. Measurement and mixing
MEASUREMENTS ::
Loose materials (sand, cement, broken stone) shown in proportions
must be measured in properly constructed measuring boxes.
Or in such other manner as shall be instructed by the Executive
Engineer.
Measurement is not to be done in loose heaps when intimate mixes
such as mortar, concrete etc., are to be formed.
10/8/2013 VV Narayana 47
22. Measurement and mixing
MIXING ::
Mixing must always be done on closely constructed
platforms.
During mixing, no foreign material can be incorporated.
The platforms must be approved by the Executive
Engineer.
The contractor shall borne the cost of
of Measuring
Measuring Boxes
and Platforms.
10/8/2013 VV Narayana 48
23. Data
The
(i) Mat
Materi
erials
als and
(ii) Labour
10/8/2013 VV Narayana 49
24. Lay‐out of
of material
material stacks
Be
Beffore start of the work, the contractor shall submit a
detailed SISITE
TE SU
SUR RVE Y to the
VEY the Ex
Exec
ecut
utiv
ive
e En
Engi
gine
neerer (c
(cle
lear
arly
ly
indi
indiccati
tin
ng pososit
itiion
onss and ar
area
eass wh
wher
ere
e ma
matter
eria
ialls sh
shal
alll be
stacked and shed built).
That SI
SITE
TE SU
SUR
RVEY sh
VEY shou
ould
ld be ap
appr
prov
oved
ed by th
the
e Ex
Exec
ecut
utiv
ive
e
Engineer.
The contractor shall deposit the materials for the purpose
of the work on the GROUND approved in Site survey.
10/8/2013 VV Narayana 50
25. Source of
of purchase
purchase of
of materials
materials and stores
10/8/2013 VV Narayana 51
26.Contractor liable for materials
supplied by the Government
Th
The
e con
ontr
trac
acttor sh
shal
alll be res
espo
pons
nsib
ible
le for al
alll ma
matter
eria
ials
ls an
and
d
other things supplied by Government from the time he
takes delivery of them.
He shall use them only for the purpose of this contract.
He shall make good any loss , damage, wastage or undue
wear and tear
tear tha
thatt may take
take place from whatev
whatever
er cause.
He shall pay to Government for such losses and damages
etc., such sum as the Executive Engineer may determine.
10/8/2013 VV Narayana 52
27. Test inspection and rejection of
defective materials and work
work – – (a)
10/8/2013 VV Narayana 53
27. Test inspection and rejection of
defective materials and work
work – – (b)
10/8/2013 VV Narayana 54
27. Test inspection and rejection of
defective materials and work
work – – (c)
The Executive Engineer shall have power to reject at any
stage, any work which he considers to defective in quality
of material or workmanship.
He shall have power to reject wrought (finished) materials,
even though the same were passed previously in an un
worked condition.
The Executive Engineer shall give written instructions to
the contractor to take down and remove rejected
materials from work site.
10/8/2013 VV Narayana 55
27. Test inspection and rejection of
defective materials and work
work – – (c)
10/8/2013 VV Narayana 56
27. Test inspection and rejection of
defective materials and work
work – – (c)
10/8/2013 VV Narayana 57
27. Test inspection and rejection of
of defective
defective
materials and work
work –
– (d) Works opened for inspection.
10/8/2013 VV Narayana 59
27. Test inspection and rejection of
of defective
defective
materials and work
work –
– (d) Works opened for inspection.
In case Foun
Foundati
dations
ons or any
any other Urgent
Urgent wor
works
ks
The contractor shall open the foundations for immediate inspection
and issue notice to the Executive Engineer.
The
Th e Ex
Exec
ecut
utiv
ive
e En
Engigine
neerer sh
shal
alll in
insp
spec
ectt th
the
e wo
work
rk wi
with
thin
in rea
easo
sona
nabl
ble
e
time.
In case the Executive Engineer do not inspect the work in th the
e
reasonable time, the contractor may cover up the work.
After covering it , it is not required to open.
In case it is required to open, it shall be done at the expense of the
Government.
10/8/2013 VV Narayana 62
28. Defects, shrinkage etc., after completion
The contractor comply with and shall amend and make good
such defects etc. within a specified time.
The expenses for such rectifications
Shall be done at
at the cost of contr
contracto
actorr or
The Executive Engineer may fix reduced rates and pay the same.
In case the Contractor fails to attend such defects
Th
The
e Ex
Exec
ecut
utiv
ive
e En
Engi
gine
neer
er ma
mayy em
empl
ploy
oy other
other pe
perrso
sons
ns to am
amen
end
d an
and
d
make
mak e good such
such and
and pa
payy to him.
him.
The payment shall be made at the cost of contractor.
10/8/2013 VV Narayana 64
28. Defects, shrinkage etc., after completion
10/8/2013 VV Narayana 65
29. Executive Engineer’s decision
10/8/2013 VV Narayana 67
30. Dismissal of
of Workmen
Workmen
10/8/2013 VV Narayana 71
33. Defining Contract Schedule Rates
10/8/2013 VV Narayana 72
34. Carriage
Carriage –
– (a)
Rates for finished item of work shall include cost of
Conveyance and all leads,
Lifts,
Loading,
Unloading and
Stacking
The stacking shall be done in the manner and at place
order by the officer
order officer immediat
immediatee char
charge
ge of the work.
In case circumstances necessitate provision for a separate
schedule item for above operations, such will be specified
in the tender notice or schedule.
10/8/2013 VV Narayana 73
34. Carriage
Carriage –
– (a)
10/8/2013 VV Narayana 74
34. Carriage
Carriage –
– (b)
10/8/2013 VV Narayana 77
35. Construction plant
The Contr
Contractor
actor
Shall Provide and install all necessary construction plant,
Shall use such methods and appliances for performance of
all operations connected with the work.
In the opinion of the Executive Engineer and in order to
To secure a satisfactory quality or work and rate of progress
and
To ensure the completion of work within the specified time.
time .
The Contractor shall include in his tender price for all the above
operations on providing and installation of construction plant.
10/8/2013 VV Narayana 78
35. Construction plant
At any time
Before the commencement of work or
During the progress of work , or any part of it.
IF the Executive Engineer opines that
The methods or
The appliances .
Appear to be insufficient or in appropriate for securing
The quality of work required or
The said progress of work
The Executive Engineer may order the contractor
To increase their efficiency and
To improve their character.
The contractor shall comply with such orders.
10/8/2013 VV Narayana 79
35. Construction plant
10/8/2013 VV Narayana 82
36. Scaffolding instructions
The Contractor
Contractor shall provide
provide all requisite
requisite scaffolding
scaffolding at his expense.
The scaffolding shall be double, i.e., it must have two sets of upright
supports.
The contractor shall ensure the safety of work people.
He mu
musst comompl
ply
y wi
with
th sa
saffet
ety
y in
insstr
truc
ucti
tion
onss is
issu
sued
ed by ththe
e Ex
Exec
ecut
utiv
ive
e
Engineer to ensure
ensure safe
safety
ty..
The contractor will be entirely responsible for any damage or injuries
to persons or property resulting from ill ‐erected scaff
scaffolding,
olding, def
defective
ective
ladders
ladders,, or otherwise arising
arising out of his def
default
ault in this respect.
respect.
10/8/2013 VV Narayana 83
37. Temporary instructions
The contractor shall pay fee and provide water and light as
required from Municipal mains or other sources.
He shall pay all charges for storage tanks, meters for the use
of the works and work men.
He may arrange otherwise and inform the Executive Engineer
in writing the same.
The water shall not be harmful to the work, shall be free from
organic matter, and free from salts or other substances likely
to interfere with setting of mortar.
10/8/2013 VV Narayana 85
39. Latrines for work people
10/8/2013 VV Narayana 87
41. Tools and seigniorage
The contr
tra
actor shall pay import duti
tie
es, toll
llss, octroi, duti
tie
es,
seigniorages, quarry fees, etc., on all materials and articles that he
may use.
An exemption if specially stated otherwise in the tender notice and
subsequently in the contract.
The contractor shall pay sales tax under the provisions of AP General
Sales Tax, as in force for the time being.
The rates for various items of work shall remain unaffected by any
change that may be made from time to time in the rates of sales tax.
Similarly in case of Custom duties.
10/8/2013 VV Narayana 88
42. Setting out works
10/8/2013 VV Narayana 89
43. Cleaning up during progress and delivery
10/8/2013 VV Narayana 91
44. Observance of
of Laws
Laws –
–
Local regulation & notices ‐ Attachments
The contract
contractor
or shall comply
comply with any requirem
requirementent of law when
Excavation have been made or
Obstacles have been put in public through fares or
In places
places where there
there is any likelihood of accidents
likelihood
And he sh
And shal
alll pr
prov
ovid
ide
e su
suit
itab
able
le ho
hoar
ardi
ding,
ng, li
ligh
ghti
ting
ng an
and
d wa
watc
tch
h ma
man
n as
necessary.
10/8/2013 VV Narayana 95
45. Accidents‐ Hoarding, Lighting,
Observations –
Observations – Wat
atchmen
chmen [(b)]
It shall be the con
contra
tractor’
ctor’ss sole responsibili
responsibility
ty to protect
protect the Publi
Publicc and
his employees
employees against
against accidents from
from any
any cause.
cause.
The con
contra
tractor
ctor shall
shall indemnify (secure)
(secure) the Governmen
Governmentt against
against any
claims for damages or injury to person or property from any accidents.
The contractor shall execute the ‘Indemnity Bond’ for the payment of
claims coming under
(a) Workmen’s Compensation Act, 1923,
(b) Minimum Wages Act, 1948,
(c ) Payment of Wages Act. 1936,
(d) Contract Labour (Regular and Abolition) Act, 1970 and
(e ) All other such Acts in force that may be enacted from time ‐to‐time
during the currency of the agreement.
10/8/2013 VV Narayana 96
45. Accidents‐ Hoarding, Lighting,
Observations –
Observations – Wat
atchmen
chmen (c )
Th
The
e co
con
ntr
trac
acto
torr sh
shal
alll in
inti
tima
mate
te in wr
writ
itin
ing
g to th
the
e con
once
cern
rned
ed Se
Sect
ctio
ion
n
Officer of P.W.D. within 24 hours on occur
occurrence of an ACCIDENT.
rence
Which results in the death of any of employee of contractor,
Which is so serious as to be likely to result in the death of any employee of
the contractor
contractor..
The contractor’s shall indemnify Government against all loss, damage,
penalties or fines sustained
sustained by
by the Government
Government as a consequence
consequence
The contractor’s failure to give intimation of accident as detailed above or
The Government’s failure to give notice under Workmen’s Compensation
Act or
The Government’s failure to conform to the provisions of the said Act in
regard to such accident.
10/8/2013 VV Narayana 97
45. Accidents‐ Hoarding, Lighting,
Observations –
Observations – Wat
atchmen
chmen (d)
10/8/2013 VV Narayana 98
46. Blasting
The contractor shall leave all holes in masonry and floors for insertion of
Wa
Water
ter services,
Gas and Electrical connections and
Sanitary fittings
In the exact positions indicated by the Executive Engineer during the
progress of work.
As soon as the fittings have been installed, these holes must be built up
at the contractor’s cost in a workman like manner.
In case
where installations are made during construction of building,
The Executive Engineer opines that settlement in accounts will not thereby occur
The holes must be built up.
10/8/2013 VV Narayana 104
50. Contractor’s risk and insurance
The contr
contract
actor
or shall mai
maint
ntain
ain,, the work execu
executed
ted by him, at his own
cost until the work is taken over by the Executive Engineer.
Accordingly the contractor shall arrange his own insurance against fire
and other usual risks during such period unless otherwise specified.
The con
contra ctor sha
tractor hall
ll no
nott be li
liab
able
le for all or any loss or damage
occasioned by or arising out of acts of GOD, and in particular
Unprecedented flood, Volcanic eruption,
Earthquake or other convulsion of nature,
Invasion,
The act of foreign enemies hostilities
Or warlike operations, rebellion
Military or usurped power
power..
10/8/2013 VV Narayana 105
51. Holidays
All ol
old
d cur
curio
iosi
sitie
ties,
s, re
reli
lics
cs,, co
coins
ins,, mi
mine
nerral etc. fou
ound
nd in
excavating or pulling down, shall be the property of the
Government.
All these should be handed over to the Executive
Engineer.
The Executive Engineer’s attention shall be called before
demolition of any ANCIENT MASONRY or OLD WORK.
With
tho
out the wr
writ
ittten cons
nsen
entt of Ex
Exec
ecu
uti
tiv
ve En
Eng
gin
inee
eerr th
the
e
contractor shall
Not assign the contract,
Nor sublet any portion of the contract.
An ORDER BOOK shall be kept at the PWD office on the site of
of the
the work.
All orders (as far as possible) regarding the work are to entered in this
BOOK.
All ENTRIES shall be signed and dated by the PWD department officer in
direct charge of
of the
the work and by the contactor.
In important cases, the Executive Engineer or the Superintending
Engineer will COUNTER SIGN the entries
entries..
The ORDER BOOK shall not be removed from the work.
With the written permission of
of the
the Executive Engineer the ORDER BOOK
can be removed.
10/8/2013 VV Narayana 112
58. Date of commencement
of commencement and completion
The contractor shall have the right to withdraw from the contract
and obtain refund of
of his
his security
If
If the
the intimation of
of handing
handing over of
of site
site is delayed more than
TWO MONTHS from the date of
of acceptance
acceptance of
of the
the agreement by
competent authority.
10/8/2013 VV Narayana 114
59. Delays and extension of time
of time
In th
the
e ev
even
entt of th
the
e Ex
Exec
ecut
utiv
ive
e En
Engi
gine
neer
er fai
aili
ling
ng to is
issu
sue
e ne
nece
cess
ssar
ary
y
instructi
instructions
ons and ther
there
e by causin g DELAYS OR HINDRANCES to the
causing
contractor , the contractor shall have the right to claim an assessment
of such delay by the Superintending Engineer of the Circle.
The decision
decision of the Superint
Superintendin
ending
g Engineer
Engineer is final and binding.
binding.
Th
The
e con
ontr
trac
acttor sh
shal
alll Lo
Lodg
dge
e in wr
writ
itin
ing
g wi
with
th Exec
ecu
uti
tiv
ve Engi
gin
nee
eerr a
statement of claim for any DELAY or HINDRANCE referred to above
within Fourteen Days (14 days) from its commencement.
If the contractor do not Lodge, the Extension of Time will not be
allowed.
Whenever
Authorized alterations or additions are made during the progress
of work,
Th
The
e Exec
ecu
uti
tiv
ve Engi
gin
nee
eerr opi
pin
nes th
tha
at in con
onse
seq
quen
ence
ce of su
such
ch
alterations or additions justify extension of time,
Such ext
xte
ension will be granted in wr
wriiti
tin
ng by the Executiv
ive
e
Engin
Eng inee
eerr or ot
oth
her com
omppet
eten
entt au
auth
thor
orit
ity
y wh
when
en or
ord
der
erin
ing
g su
such
ch
alterations or additions.
If
If,, at any time the Executive
Executive Engineer opines that
that the contractor
contractor is
Delaying commencement of work,
Violating any of the provisions of the contract,
Delaying the progress of work, as defined by the statement “Rates
of Progress”
Progress” in the “Articles
“Articles of Agreement”
Agreement”
The Executive Engineer shall ADVISE th
the
e con
ontr
trac
acto
torr in writ
writin
ing
g an
and
d
demand compliance.
If the contractor neglects to comply with such demand within seven (7)
days after receipt of such notice,
IT shall be lawful for the Executive Engineer to determine the contract
To com
ompl
ply
y wi
with
th th
the
e de
dema
mand
nd refer
errred to in su
sub
b‐cl
clau
ause
se(a
(a)) of th
this
is
clause or
To mainta
maintain
in the “Rate
“Ratess of Pr
Prog
ogre
ress
ss”” specif
specifie
ied
d in th
the
e “Ar
“Artic
ticle
less of
Agreement + Extension of Time that may have been allowed ,
The Executive Engineer shall permit the contractor to proceed with
the WHOLE or PART and continue and complete the WHOLE or SUCH
PART of work.
Such permission shall not be deemed to be a waiver in any respect by
the Executive Engineer of the right of forfeiture under this clause.
10/8/2013 VV Narayana 120
60. Delays in commencement or progress or
neglect of work
of work and forfeiture of earnest
of earnest money,
security deposit and withheld amounts‐(b)
Should the amount so certified be less than the amount which would
have been due to the original contractor on completion of that part of
work by him
The difference shall not be paid to the contractor.
Should the amount so certified be more than the amount which would
have been due to the original contractor on completion of that part of
work by him
The difference shall be recovered from the original contractor by the
Government.
Such recovery shall not exceed 5% of the total Contract amount.
CLARIFICATION
Execution of balance work after determination of
of balance of Contract
Contract
under clause 60(c ) of
of P.S.
P.S. to A.P.D.S.S
Clarification has been made as to the mode of
of execution
execution of
of the
the
balance work and rate at which it may be let out.,
The Executive Engineer shall have the right to allot the balance work on
nomination to any other contractor at his discretion in order to maintain
the “Rate of Progress”.
The Executive Engineer need not invi
invite
te tend
tender
er so long as the balance
work executed satisfactorily at the rate in the agreement of the original
contractor.
10/8/2013 VV Narayana 124
60. Delays in commencement or progress or
neglect of work
of work and forfeiture of earnest
of earnest money,
security deposit and withheld amounts‐(c)
CLARIFICATION
10/8/2013
the site, the plant and materials.
VV Narayana 129
61. Suspension of the
of the works by the Contractor
Al
Alll su
such
ch pl
plan
antt an
and
d ma
mate
teri
rial
al ar
are
e at th
the
e di
disp
spos
osal
al of th
the
e Go
Gov
ver
ernm
nmen
entt
absolutely for the purpose of completing the work .
If the Government exercise the above power and take possession of
work, plant and materials
They may engage any other person to complete works.
They may exclude contractors, his agents from entry upon Power to
post watchmen or access to the site.
They may allow the contractor or any person nominated by him at
alll rea
al easo
sona
nabl
ble
e ti
time
mess to in
insp
spec
ect,
t, su
surv
rvey
ey an
and
d me
meas
asur
ure
e th
the
e wor
orks
ks
already executed by the contractor.
10/8/2013 VV Narayana 130
61. Suspension of the
of the works by the Contractor
The Government shall take all necessary steps for completing the works
without undue delay or expense
Using the above plant and materials taken into possession and
Obtaining additional plant and materials as the Executive Engineer
decides
decid es neces
necessary
sary
For due fulfillment and completion of the work.
Upo
Uponn co
compl
mpleti
etion
on of the work,
work, the Execut
Executive
ive Enginee
Engineerr sha
shall
ll cer
certify
tify the
amount of expense incurred, due to the fault of the contractor
In having the work completed by other persons and
Ha
Havi
ving
ng cr
cred
edit
ited
ed th
the
e co
cont
ntrrac
acto
torr wi
with
th th
the
e value of mat
alue material
erialss only
utilized in the work.
10/8/2013 VV Narayana 131
61. Suspension of the
of the works by the Contractor
Should the amount so certified be less than the amount which would
have been due to the original contractor on completion of that part of
work by him
The difference shall not be paid to the contractor by the Government.
Should the amount so certified be more than the amount which would
have been due to the original contractor on completion of that part of
work by him
The difference
difference shall be paid by the contractor
contractor to the Government.
Government.
Should the amount so certified be less than the amount which would
have been due to the original contractor on completion of that part of
work by him
The difference shall not be paid to the contractor by the Government.
Should the amount so certified be more than the amount which would
have been due to the original contractor on completion of that part of
work by him
The difference
difference shall be paid by the contractor
contractor to the Government.
Government.
The Government shall not be liable to make any payment on account of
the use of such
such plant
plant fo
forr the completio
completion
n of the work.
work.
The Governm
Governmentent give
give notice in writing at any time to the contra
contractor
ctor to
remove any of his plant or materials from the site and not required for
completion of the works.
If such plant or materials are not removed within fourteen days (14
days) of notice,
The Government may remove and sell the same and
Credit the amount to the contractor the money so obtained less the
cost of removal and sale,
In cas
ase
e th
the
e Go
Gov
ver
ernm
nmen
entt sh
shal
alll exer
erci
cise
se th
the
e po
pow
wer con
onttai
aine
ned
d in th
this
is
clause 61 and shall complete the work by other persons
Th
The
e Ex
Exec
ecut
utiv
ive
e En
Engi
gine
neer
er sh
shal
alll ce
cert
rtif
ify
y wh
what
at am
amou
ount
nt ha
had
d be
been
en re
reas
ason
onab
ably
ly
earned or reasonably
earned reasonably gained
gained to the contracto
contractorr in respect
respect of the work then
actually done by him
And such certificate shall be final and binding on the contractor.
When the Government shall exercise the power contained in this clause
61 and shall take into possession of work and site
The portion of the work done by the contractor shall be maintained by the
Governmen
Govern mentt at the risk and expens
expense
e of contr
contract
actor
or un
until
til the whole
whole of the
work is completed by ot oth
her agency and the Government take into
possession of total work.
10/8/2013 VV Narayana 135
62. Payment on lump‐sum basis or by final
measurement or unit prices‐ (a)
PAYMENT ::
Paym
ymen entt for th
the
e wor
ork
k done by th
the
e contr
trac
acttor wiwilll be
made on the basis of Measurements recorded in (i)
Measurement Books or (ii) Level field books.
MEASUREMENTS ::
Supervisor or above rank officer should Record.
As
Assi
sisstan
antt En
Engi
gine
neer
er or ab
abov
ove
e ran
ank
k of
offi
fice
cerr sh
shouould
ld Ch
Chececk
k
Measure.
When variations by wa
way
y of
of extras
extras made
Up on request of
of the
the Executive Engineer to the
contractor to furnish him all
Invoices,
Accounts,
Receipts and
Other vouchers
INTERMED
INTE RMEDIA
IATE
TE PAYMEN
YMENTT
The Executive Engineer or the sub‐divisional officer shall issue
certificates at reasonably frequent intervals.
Within fou
ourt
rtee
eenn da
dayys (14 days) of each certificate, an
intermediate payment will be made by the Executive Engineer
of the sub‐divisional officer a sum equal to 92 of the value
of work.
Th
The
e ba
bala
lanc
nce
e7 will be wi
will with
thhe
held
ld an
and
d ret
etai
aine
ned
d as a se
secu
curi
rity
ty for
the due fulfillment of the contractor.
FINAL PAYMENT
The Executive Engineer or the sub‐divisional officer shall
issue certificates on completion of the entire works.
The contractor will receive the final payment of all moneys
due to him under or by virtue of contractor except
Earnest Money Deposit retained as security and
A sum equal to 2 ½ of total value of work done
Provided there
Provided there is no rec
recov
overy
ery fr
from
om or fo
forf
rfeitur
eiture
e by the contracto
contractorr to
be made under clause 60.
10/8/2013 VV Narayana 154
68. Payments and certificates
DEPOSITS
The Amount withheld from the final bills is retained under
“Deposits”.
This deposit and the earnest money deposit will be paid to the
contractor after a period of six months (6 months) as all defects
shall have been made good according to true intent and meaning
thereof.
In case of works like Conveyance of materials, supply of materials, silt
clearance, the deposit amount could be refunded after the work is
completed in accordance with the terms of the Agreement.
10/8/2013 VV Narayana 155
68. Payments and certificates
This certi
certificate sh
ficate shal
alll no
nott rel
elie
iev
ve th
the
e con
ontr
trac
acto
torr fr
from
om hi
hiss
liability to make good defects as provided by the contractor.
10/8/2013 VV Narayana 156
68. Payments and certificates
ROUNDING RULES
In cal
alcu
cula
lati
ting
ng the amount of each item in the bill for
the
payment
Fractions of below five paisa shall be omitted,
Five paisa or over shall be reckoned as ten paisa.
In calculating the total on each bill for payment
Fractions of less than half rupee shall be disregarded,
Half rupee and over shall be reckoned as one rupee.
10/8/2013 VV Narayana 157
[68. Payments and certificates]
MECHANICAL CONTRACTS
This clause
clause 68 will
will not apply
apply to the contr
contracts
acts fo
forr
Designing, Manufacture, Supply, Erection, Testing
Where SPECIAL CONDITIONS are incorporated.
As per the SPECIAL CONDITION
Retention of 10% of the contract value for twelve
months (12 months) and
Payment made up to 90% of the contract value on
10/8/2013
erection and testing. VV Narayana 158
69. Interest on money due to contractor(a)
Before payment of the final bill shall be made on the contract, the
contractor agrees that he will sign and deliver a valid release and
discharge certificate to the Executive Engineer either in
Measurem
Measu rement
ent Book or other
other wise as demand
demanded.
ed.
A valid release and discharge from any and all claims and demands
whatsoever for all matters arising out of, are connected with the
contract.
No
Noth
thin
ing
g in th
this
is cla
claus
use
e sh
shal
alll di
disc
scha
harg
rge
e an
and
d re
rele
leas
ase
e th
the
e co
cont
ntrrac
acto
torr
from his liabilities under the contract.
Th
The
e con
ontr
trac
acto
torr sh
shal
alll pr
prod
oduc
uce
e a ce
cert
rtif
ific
icat
ate
e fr
from
om th
the
e in
inco
come
me tax
authorities that all I.T. payable by him up‐to‐da
date
te has been
been duly
duly paid
paid
in the case of contract whose value is over Rs.10,000.
It is further expressly agreed that Executive Engineer in supplying
the fin
ina
al measurement certif
ific
ica
ate, need not be found by th
the
e
preceding measurements and paymen
payments.ts.
The final measurements, if any, of the Executive Engineer shall be
Final
Conclusive and
Binding on the contractor.
The paym
yme
ent will be made forthwith to th
the
e person or
persons entitled to receive and give a discharge for the
payme
payment
nt suc
such
h tha
thatt .
All accepted and acceptance works be measured up and paid for
The rates provided in the contract schedule, where such apply, or
Mo
Mosst rec
ecen
entt sc
sche
hedu
dule
le of rat
ates
es of th
the
e di
divi
visi
sion
on ap
appr
pro
oved by th
the
e
10/8/2013
competent authority. VV Narayana 165
73. Arbitration
ISSUES of Arbitration
As to the interpretation of the contract
As to any matter or thing arising there under except
As to the matters left to the sole discretion of the
Executive Engineer under clauses 20, 22, 27(c ), 36, 37 and
40 of PS
As to the withholding by the Executive Engineer or payment
of any bill to which the contractor may claim to be entitled.
The Aw
Awar
ard
d of su
such
ch Ar
Arb
bit
itrrator sh
shal
alll be fi
fin
nal an
and
d bi
bind
ndin
ing
g on the
parties unless contested by either party in Court of Law.
In cases where the Executive Engineer has entered into the contract on
behalf
beha lf of th
the
e Go
Gov
ver
erno
norr, in th
thee fi
firrst in
inst
stan
ance
ce,, th
the
e di
disp
sput
utee or di
difffer
eren
ence
ce
shall be referred by or through the Executive Engineer to the
Supe
peririn
nten
enddin
ing
g En
Enggin
inee
eerr of th
the
e Cir ircl
cle
e and his de deccis
isio
ion
n th
ther
eree upon
obtained before referring such dispute or difference to arbitration under
this clause.
Progress of the work shall not be suspended or delayed on account
of the reference of any D/D to the Superintending Engineer or to
Arbitration under this clause.
10/8/2013 VV Narayana 169
73. Arbitration
The de
deci
cissio
ion
n of th
the
e Ex
Exec
ecut
utiv
ive
e En
Engi
gin
nee
eerr or th
the
e Su
Supe
peri
rin
nten
endi
din
ng
Engine
Engineer
er of ththe
e Ci
Cirrcl
cle
e on su
such
ch D/
D/D
D sh
shal
alll be co
conc
nclu
lusi
siv
ve an
and
d un
unti
till
reversed by the Superintending Engineer or Arbitrator.
The Arbitr
Arbitrato
atorr shall fix a period to
to file a statemen
statementt of the case.
Wi
With
thin
in th
the
e ab
abov
ove
e fi
fixxed pe
peri
riod
od ei
eith
ther
er party
part y ma
may y fi
file
le bef
befor
ore
e th
the
e
arb
arbit
itrrator a statem
emen
entt of th
the
e cas
ase
e an
and
d al
alsso al
alll the dococuume
men
nts
relating to or having a bearing on the case.
If reasonably possible, the Arbitrator shall set that the award is
passed within fouourr mon
onth
thss (4 mon
onth
ths)
s) from the date of his
entering up on the reference.
10/8/2013 VV Narayana 170
73. Arbitration
NOTE
NOTE 2: (C
(COUR
OURT
T FEE ST
STAMPS
AMPS))
The Application of contractors seeking arbitration should bear a Court fee
stamp as per Andhra Pradesh Court Fees , but stamp duty need be levied.
The Award passed by arbitrator shall be on stamped paper.
The value of that Stamped paper shall be according to the value of claim
to which the award relates.
If the aggrieved (distressed ) party goes to a Court of Law challenging the
award, he should pay necessary Court fee.
NOTE
NOTE 3: (MODI
(MODIFICA
FICATION
TION by G.O
G.O.Ms.No
.Ms.No.158
.158 TR&B, dt 13‐7‐92)
Ex
Except
cept as otherw
otherwise
ise provided
provided in the contrac
contractt an
any
y dispute and differen
differences
ces
arising out of or relating to the contract shall be referred to adjudification
as follows.
I. (i) Se
Settl
tle
ements of
of al
all Claims up to
to Rs
Rs. 50,
50,00
000
0 in
in va
value by
by
way of Arbitration to be referred as follows :
(a) Claims upto Rs. 10,000 value.
Superint
Superintendin
ending
g Engineer
Engineer of another Circle
Circle in the Dept.
(b) Claims
Claims Rs. 10,000
10,000 to 50,000
50,000 in value.
value.
Another Chief Engineer of the same Department.
10/8/2013 VV Narayana 178
[73. Arbitration]
NOTE
NOTE 3: (MODI
(MODIFICA
FICATION
TION by G.O
G.O.Ms.No
.Ms.No.158
.158 TR&B, dt 13‐7‐92)
Th
The
e ar
arbi
bitr
trat
atio
ion
n pr
proc
ocee
eedi
ding
ngss wi
will
ll be co
cond
nduc
ucte
ted
d in ac
acco
corrda
danc
nce
e wi
with
th th
the
e
provisions of the Arbitration Act, 1940 as amended from time to time.
The Arbitrator shall invariably give reasons in the award.
II.. Se
II Sett
ttle
leme
ment
ntss of
of al
alll Cl
Clai
aims
ms ab
abov
ove
e Rs.
Rs. 50,
50,000
000 in val
alue
ue ::
All these shall be decided by the Civil Court of competent jurisdiction by
way of regular suit and NOT by ARBITRATION .
A reference for adjudication under this Clause shall be made by either
party to the contract within six months from the date of intimating the
contractor of the preparation of final bill or his having accepted payment.
10/8/2013 VV Narayana 179
WHY this EXERCISE
1. Teaching is the best way of
of learning.
learning.
2. Power point is best tool for teaching.
3. Hence I opted for PPT in order to learn PS to APDSS.