Gantt Chart - : Activity Preceding Duration (WKS) Cost

A Gantt chart is a horizontal bar chart that displays time relationships and the duration of tasks or activities in a project. It shows the start and finish dates of the different activities and their dependency on each other. An example Gantt chart is given that shows activities, their duration, preceding activities, costs, and cash flow over time for a project with a total cost of 9 million.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
37 views2 pages

Gantt Chart - : Activity Preceding Duration (WKS) Cost

A Gantt chart is a horizontal bar chart that displays time relationships and the duration of tasks or activities in a project. It shows the start and finish dates of the different activities and their dependency on each other. An example Gantt chart is given that shows activities, their duration, preceding activities, costs, and cash flow over time for a project with a total cost of 9 million.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

• Gantt Chart - is a horizontal bar chart that graphically

displays time relationships. In effect, it is


a “scale” model of time because the bars
are different lengths depending upon the
amount of time they represent. It is
sometimes called bar chart, scheduling
chart, time chart or time model.
Example:
Activity Preceding Duration (wks) Cost
A - 2 P 200,000.00
B A 4 1,000,000.00
C B 3 800,000.00
D B 3 900,000.00
E C,D 1 400,000.00
F A,D 3 700,000.00
G D 6 1,500,000.00
H A 4 1,200,000.00
I G 2 300,000.00
J G 3 750,000.00
K G 5 1,100,000.00
L E,F,H,I,J,K 1 150,000.00
Total Cost ==> 9,000,000.00
D U R A T I O N ( W E E K S )
Activity Cost Rel. Wt. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
A P 200,000.00 2.222 2.222

5.556 5.556
B 1,000,000.00 11.112
5.926 2.963
C 800,000.00 8.889
D 900,000.00 10 6.667 3.333
4.444
E 400,000.00 4.444
7.778
F 700,000.00 7.778
8.334 8.333
G 1,500,000.00 16.667
6.667 6.666
H 1,200,000.00 13.333
1.667 1.666
I 300,000.00 3.333
2.778 5.555
J 750,000.00 8.333
2.444 4.778
K 1,100,000.00 12.222
1.667
L 150,000.00 1.667
TOTAL 9,000,000.00 100%
Accomplishment(%) 14.445 24.815 26.852 15.222 18.666
Cummulative Accomplishment (%) 14.445 39.260 66.112 81.334 100

Cash Flow 1,300,050 2,223,350 2,416,680 1,369,980 1,679,940


Cummulative Cash Flow 1,300,050 3,533,400 5,950,000 7,320,060 9,000,000