Control Tests For Quality Concrete
Control Tests For Quality Concrete
3.1 Introduction
The principal aim of conventional in-situ testing is to ensure that
proper materials are used in desired proportions and correct steps of
workmanship are followed. Recent trends are towards switch over to
the performance-oriented system approach and quality control where
a number of items and operations have to be controlled at the right
time and in the right measures. From this point of view, the testing of
representative concrete does not represent the quality of actual in-
place concrete, quality of control cannot be regarded as a mere testing
of three concrete cubes at 28 days. In fact, to avoid inferior concrete
being placed, the concrete is to be carried out much before any cubes
become available for testing. The cubes tests relate to the concrete
specimens specially prepared for testing. What is really needed is to
carry out tests on concrete in the structure, so that the influence or
workmanship in actual placing, compaction and curing are also
reflected. However, a complete switchover to performance-oriented
specifications has not been possible, because of difficulties involved in
defining what constitutes the satisfactory performance in the absence
of suitable tests.
For in-situ testing, the aims of investigation should be clearly
established at the outset to avoid misleading test results and
consequent future disputes over results. By carefully formulating the
test program, the uncertainties can often be minimized. Since in-situ
testing of existing structures involve engineering judgment, a
complete knowledge of the range of tests available, and their
limitations and the accuracy that can be achieved is important.
There are three basic categories of concrete testing, namely,
1. Quality control: It is normally carried out by the contractor to
indicate adjustments necessary to ensure and acceptable
supplied material.
2. Compliance testing: It is performed by or for, the engineer
according to an agreed plan, to check compliance with the
specifications.
3. Secondary testing: This test is performed on the hardened
concrete in the situations where there is doubt about the
reliability of control and compliance results or they are
unavailable or inappropriate as in an old structure.
Temperature Management
Because of the important influence of concrete temperature on the
properties of fresh and hardened concrete, many specifications place
limits on the temperature of fresh concrete. Although there is no
standard method for measuring temperature of fresh concrete, certain
simple precautions should be observed. The EBCS 2 1995 has put the
following article regarding temperature of fresh concrete.
Location
The choice of location is governed primarily by the basic purpose
of the testing, e.g., for serviceability assessment the cores should
normally be taken at the points where minimum strength and
maximum stress coincide. However, in a slender member core cutting
may impair future performance and hence cores should be taken at
the nearest non-critical locations. Aesthetic consideration concerning
appearance may also sometimes influence the choice of location. For
checking specification compliance, the cores should be located to avoid
unrepresentative concrete (normally occupying top 25%in case of
columns, walls or deep beams, and top thickness of slab). The
reinforcement bars should be avoided wherever possible.
Size
For compression testing the standards require that the core
diameter be at least three times the nominal maximum size of
aggregate. The accuracy of results, generally, decreases as the ratio of
aggregate size to core diameter increases. Codes further require that a
minimum diameter of 100mm be used (75 mm in Australia). In case of
small-sized members where large holes would be unacceptable smaller
diameters are used. The choice of core diameter is also influenced by
the length of the core specimen which can be obtained. It is generally
accepted that the cores for compression testing should have a
length /diameter ratio of between 1.0 and 2.0. For reducing drilling
costs, damages, variability along length, and geometric influence on
testing, the cores should be kept as small as possible (l/d = 1.0-1.2).
However, the uncertainties in relating the core strength to cylinder or
cube strength are minimized if the core length/diameter ratio is close
to 2.0.
Figure 3.3 Schematic of conical failure zone during probe penetration test.
Both the rebound hammer and the probe damage the concrete
surface to some extent. The rebound hammer leaves and indentation
on the surface; the probe leaves a small hole and may cause minor
cracking and small craters similar to pop outs on the surface.
F
fp [Eq. 3.1]
A
A ( d 3 d 2)[4h 2 (d 3 d 2) 2 ]1 / 2 [Eq.
4
3.2]
The big disadvantage is that test must be planned in advance and the
assembly embedded in the concrete during casting. Therefore, it cannot be used to
evaluate existing structures where the quality of the concrete is suspected.