CONTRACT BRIEF 7/28/2021 AS PER SITE

NO OF DAYS ACTUAL
CONTRACT CONTRACT COMMENCEMENT COMPLETION
CONTRACT CONTRACT REFERENCE ISSUED DATE SIGNED DATE DATE DATE DAYS EXTENDED UP COMMENCEMENT
TO DATE DATE
ORIGINAL CONTRACT - SPECIAL
A UO805BCP1-SCA-00007-Rev.00 STRUCTURE PROJECT 6/3/2020 6/4/2020 4/30/2020 9/20/2020 143.00 (311.00) 5/13/2020

A.1 VO-01 EOT 8/31/2020 9/3/2020 9/20/2020 12/31/2020 102.00 (209.00) 5/13/2020
A.2 VO-02 CJ 9/22/2020 9/29/2020 4/30/2020 12/31/2020 245.00 (209.00) 5/13/2020
A.3 VO-03 CJ 11/5/2020 11/1/2020 4/30/2020 12/31/2020 245.00 (209.00) 5/13/2020
A.4 VO-04 CJ 12/23/2020 12/27/2020 4/30/2020 12/31/2020 245.00 (209.00) 5/13/2020
A.5 VO-05 CJ 1/30/2021 2/10/2021 4/30/2020 12/31/2020 245.00 (209.00) 5/13/2020

A.6 VO-06 CARPARK TUNNEL, RAMP & SERVER 11/5/2020 11/9/2020 11/5/2020 12/31/2020 56.00 (209.00) 5/13/2020
ROOM
A.7 VO-07 CJ, MJ & PIPE PENETRATION 6/3/2020 3/14/2021 6/3/2020 12/31/2020 211.00 (209.00) 5/13/2020

ORIGINAL CONTRACT - TJ SHELTER


B UO727DBLP-SCA-00745-REV.00 PROJECT
2/28/2021 5/6/2021 12/1/2020 3/30/2021 119.00 (120.00)

B.1 VO-01 FM SHELTER 3/23/2021 4/5/2021 3/30/2021 (120.00)


B.2 VO-02 TJ SHELTER ADDITIONAL QTY 4/19/2021 5/2/2021 3/30/2021 (120.00)

ORIGINAL CONTRACT - CITIZEN & VIP


C UO727DBLP-SCA-00785-REV.00 TUNNEL PROJECT 5/24/2021 3/25/2021 3/1/2021 7/27/2021 148.00 (1.00)