Term Report Mepco
Term Report Mepco
Supervised By:-
i
TRAINING REPORT OF MEPCO MULTAN
This report is presented by
ShahidJaved 2K17-ELET-010
Muhammad Bilal Khan 2K17-ELET-012
Sift-e-Elahi 2K17-ELET-021
Muhammad Nouman 2K17-ELET-039
Under the guidance of our supervisor and approved by all the members of the
committeehas been presented to and accepted by the NFC institute of engineering
and technology Multan in fulfillment of the requirements of the four years degree
of B.S Electrical Engineering & Technology.
(Electrical Engineering)
ii
TO WHOM IT MAY CONCERN
It is certified that
Name Roll No.
ShahidJaved 2K17-ELET-010
Sift-e-Elahi 2K17-ELET-021
Students of B.S Electrical Engineering & Technology from NFC Institute of Engineering &
Technology Multan has done internship report in our organization.
Our organization certified this report.
___________________
Rana Muhammad Sarfaraz
Asstt. Director (T&MP)
MEPCO H/Qs Multan
iii
INDUSTRIAL TRAINING REPORT
ShahidJaved 2K16-ELET-010
Muhammad Bilal
2K16-ELET-012
Khan
Sift-e-Elahi 2K16-ELET-021
Muhammad
2K16-ELET-039
Nouman
iv
ABSTRACT
Now a days everything up on the power. So, give reliable supply to the
consumer. In distribution systems one of the major parts is “Substations”. An
electrical substation is a subsidiary station of an electricity, generation, transmission
& distribution where voltage is transformed from high to low level & vice versa.
Supply the regular maintenance & checking is necessary from that we conclude
weather it is suitable or not for the desired operation.
v
ACKNOWLEDGEMENT
First of all, I will like to thank Allah, who blessed us with ability and
wisdom to complete this project. Especially, thanks to MEPCO who
provided us an opportunity of enhancing our professional experience and
their members and especially workers so that they have cooperated with
us. I also want to thanks to my worthy teachers, then I thankful to staff
who cooperated with me.
vi
TABLE OF CONTENTS
Chapter#1………………………………………………………………………..……...1
1.1Introduction:………………………………………..………………………….….1
1.2.1Inputs:……..………………………………………………………………..………1
1.2.2Outputs:……….…………………………………………………………………...1
1.6 Mission:……………………………………………………………………………..…5
Chapter # 2…………….……………………………………….………………………….6
2.1Schedule of Training:…………………………………………….……………...6
2.2Duties as a Trainee:………………………………………………………….…..6
Chapter # 3………………….…………………………………………………………….8
vii
3.5.2Power Transformer Specifications:……………………………...12
3.6CURRENT TRANSFORMER:……………………….……………………...13
3.7Potential transformer:………………………………………………….....15
3.8Conductors:……………………………………………………………………….16
3.9Insulators:..………………………………………………….…………………….16
3.10Isolators:………………………………………………………..…………………17
3.10.1Test of isolator:………………………………………………..…………….17
3.11Bus bars:……………………..…………………………………...……………….18
3.12Lightning Arrester:……………………..………………………………………18
3.13Circuit Breakers:………………………………………………………………...19
3.14.3Distance Relay………………………………………………………..........22
3.14.4Electromagnetic relay:…………………………………….………………23
3.15Protective Relays:……………………………..…….………………..……….23
viii
3.16Earthing Switch:……………………………………………………………24
3.17Battery room………………………………………………………………..25
3.20.5EEPROM :………………………………………………………………..…..29
3.20.6Micro-Controller:……………………………………………………..….29
Chapter # 4…………………………………………………………………………....36
ix
4.5Safety works at grid station:………………………………………………37
Chapter#6………………………………………………………………………………40
CONCLUSION………………………………………………..…………………………40
x
List of Figures
Fig1. 1MEPCO Jurisdiction Map……………………………………………………….4
Fig 3. 2 PowerTransformers........................................................................................................................
xi
List of Tables
Table 1. 1 Operation Circles ........................................................................................................................
xii
Chapter 1
The Company got the certificate of incorporation of business on 14th May, 1998 and
the certificate of commencement of business on 01 July, 1998. After that the
company started the commercial operations, the principal activity of the company is
distribution and supply of electricity to public within defined geographical
boundaries.
The Company also provides the Electricity in rural areas, under the project called
“Village Electrification and European Commission “Through these projects’
electricity has been provided in mostly rural areas.
13
1.2.1Inputs:-
The inputs of MEPCO includes the raw form of electricity coming from the power
stations and WAPDA and the purchased electricity from NEPRA. The then distribute
this electricity throughout the Multan division.
1.2.2Outputs:-
The output of MEPCO is the processed form of electricity that is in the state of
distribution and is distributed through grid stations and transformer. They distribute
this electricity through outmultan division to various sub divisions.
Operation Circles
14
Table 1. 1 Operation Circles
1. Multan Circle
2. Sahiwal Circle
Grid Stations
POWER TRANSFORMERS
1. 132/66KV. 13
2. 132/11KV 127
3. 66/11KV 44
184
Total
Total installed Capacity 2858MVA
15
LENGTH OF TRANSMISSION LINES
1.132 KV 2809KM
2. 66 KV 1479 KM
HT/LT LINES
1.6Mission:-
To ensure convenient availability of high quality power in area of
responsibility, in order to alleviate the poverty, improve quality of life
and make the Industrial and Agriculture Sector competitive in the
World Market.
Chapter 2
Training duty was assigned in general duty with timing from 08:00 hrs. to
1
14:00 hrs. Having lunch break from 11:30 hrs.to 12:00 hrs.
In the construction division, visit different sites that how the lines are
4 run to the consumers end and how the line conductor are replaced.
How the lines are tighten on the poles.
18
Chapter 3
The interconnected network of sub stations is called the grid, and may ultimately
represent an entire multi-state region. In this configuration, loss of a small section,
such as loss of a power station, does not impact the grid as a whole, nor does it
impact the more localized neighborhoods, as the grid simply shifts its power flow to
compensate, giving the power station operator the opportunity to effect repairs
without having a blackout.
19
3.1.2Disadvantages of the Grid System:-
During load shedding, capacity of industries connected with the grid is reduced
which cause to industrial development problem.
For maintenance, qualified staff is required and for that reason our country
has to spend more money to call expert engineers from other countries.
20
3.3 Functions of a Grid Station:-
Current Transformer
Potential Transformer
Conductors& Insulators
Isolators
Bus bars
Lightning arresters
Circuit breakers
Relays
Capacitor banks
Earthing Switch
21
3.5 Power Transformers:-
The Power transformer is a one kind of transformer, that is used to
transfer electricalenergy in any part of the electrical or electronic circuit
between the generator and the distribution primary circuits. These
transformers are used in distribution systems to interface step up and
step down voltages. The common type of power transformer is liquid
immersed and the life span of these transformers is around 30 years.
Power transformers can be classified into three types based on the
ranges. They are small power transformers, medium power transformers
and large power transformers.
The range of large power transformers can be from 100MVA & beyond
These transformers transform the voltage. It holds a low voltage, high current circuit
at one side of the transformer and on the other side of the transformer it holds high
voltage low current circuit. Power transformer depends on the principle of Faradays
22
induction. They describe the powersystem into zones where every gear connected to
the system is sized per the ratings set by the power transformer.
• Phase is 3Ø
• Frequency if 60Hz,50Hz
• Power transformers are used in the high voltage transmission network to step
up and step down the voltage. These transformers are generally used for the
purpose of transmission of heavy loads.
24
• These transformers are used as a step up devices for transmission, so that the
I2r loss can be reduced to a specified power flow.
5. Open Circuit
6. Short Circuit
7. Winding Resistance
25
Fig 3. 4 Current transformer
1. In C.T primary side winding will be thin wire which results having low rotation.
2. In C.T secondary side winding will be thick wire which results having high
rotation.
3. The C.T system can reduce the current which can be required the meters and
relays.
Ratio Test
Hi-Pot Test
26
3.7 Potential transformer:-
Potential transformer or voltage transformer gets used in electrical
power systemfor stepping down the systemvoltageto a safe value
which can be fed to low ratings meters and relays. Commercially
available relaysand meters used for protection and metering, are
designed for low voltage. This is a simplest form of potential
transformer definition.Voltage transformers (VT), also called potential
transformers (PT), are a parallel connected type of instrument
transformer. They are designed to present negligible load to the supply
being measured and have an accurate voltage ratio and phase
relationship to enable accurate secondary connected metering.
Fig 3. 6 Conductors
3.9 Insulators:-
The metal which does not allow free movement of electrons or electric
charge is called as an insulator. Hence, insulators resist electricity with
their high resisting property. There are different types of insulators
such as suspension type, strain type, stray type, shackle, pin type and
so on.
Fig 3. 7 Insulators
28
A few types of insulators are shown in the above figure. Insulators are
used for insulation purpose while erecting electric poles with
conductors to avoid short circuit and for requirements.
3.10Isolators:-
Isolator is a manually operated mechanical switch that isolates the
faulty section or the section of a conductor or a part of a circuit of
substation meant for repair from a healthy section in order to avoid
occurrence of more severe faults. Hence, it is also called as a
disconnector or disconnecting switch. There are different types of
isolators used for different applications such as single-break isolator,
doublebreak isolator, bus isolator, line isolator, etc.
Fig 3. 8 Isolator
3.10.1Test of isolator:-
Megger(insulation Resistance
Hi-Pot
Contact Resistance
29
3.11 Bus bars:-
In RYK switch yard there are two 132 KV bus bars. By using
these bus bars export and import electric power to WAPDA.
The main purpose of installing two bus bars is that if any fault
occurs in one bus bar then we can use second bus bar without
interrupting our power supply. And if we want to does
maintenance work so we also use second bus bar.
These are different types like single bus, double bus and ring bus.
3.12Lightning Arrester:-
A lightning arrester is a device used on electrical power systems and
telecommunications systems to protect the insulation and
conductors of the system from the damaging effects of lightning.
The typical lightning arrester has a high-voltage terminal and a ground
terminal.
30
Fig 3. 10 Lightning Arrester
Hi-pot
31
Fig 3-11 SF6 Circuit Breaker
Hi-pot
Timming
Contact resistance
32
3.14.1Over current relay:-
33
3.14.3Distance Relay:-
34
3.14.4Electromagnetic relay:-
A relay is an electromagnetic switch operated by a relatively small electric
current that can turn on or off a much larger electric current. The heart of a
relay is an electromagnet (a coil of wire that becomes a temporary magnet
when electricity flows through it)
Protective Relays:-
A relay is a device that “detects” the fault and “directs” the circuit
breaker to isolate the faulty part/equipment from the system.
3.15Function of Relay:-
A relay performs three functions.
Sensing.
Comparing.
Tripping.
It senses the “fault”. This is done by the relay to “respond” to the change if
any, in the currents passing through it.
35
It compares the current through it with the designed value of current. It
responds only if the current through it is different from its designed current
rating.
If the current through it is different from its designed current rating, it sends
information to the circuit breaker for tripping.
36
3.16Earthing Switch:-
The Earthing Switch is a manually operated device with safety interlocking keys,
designed to ground electrical circuit on both side of AC Vacuum Circuit Breaker
when the AC Vacuum Circuit Breaker is open. This ensures the safety of the
maintenance personnel during maintenance and routine checking.
• Compact design.
37
3.17BATTERY ROOM:-
Batteries are very important part of the grid. It works as a standby
storage device, that provides D.C power to the grid’s dc supply
equipment in case of failure of A.C supply. Different protection devices
i.e relays, circuit breakers and other control equipment of relay room,
11KV control room, 132KV control room and yard operates on 110 D.C
volt supply that is normally supplied by a rectifier. In case of failure of
A.C power batteries works as a standby source of 110 D.C supply. No. of
cells installed = 552 Volt/cell, 150 AH
4. Short Circuit
5. Open Circuit
6. Winding Resistance
1. Timing Test
Current Stepdown
Protection
Metering
These devices are the most important component for the electricity
supplier companies. They play key role in revenue generation for these
39
corporations. Old Energy Meters were only able to calculate Energy
units but with the advancement of technology, numerous functionalities
are added in it. In present complex electricity scenario, objective of an
Energy Meter is not just capturing the Energy Units.
• Load Control
• Tariff Distribution
• Energy Audit
The goal of this circuit is to give 5 volts to the whole system. Power supply
can be provided to the system through any of the ways written in this article.
To Energize LCD and EEPROM without even power supply, a battery is an only
option. For that purpose, a non-rechargeable Lithium battery should install
inside to energize it for at least 4-5 years.
There are many ways to measure current and for this purpose various kinds
of sensors are available in the market. To measure current, sensor should be
40
applied in series of the Live wire so that whole current can be passed through
sensor. Current transformer is the best option in this case due to its
economical price and efficiency.
There are two main methods to measure voltage. One is through the voltage
divider and the other through potential transformer. When voltage is too
high like more than 500 volts then a potential transformer should be used to
isolate the sensitive circuit from high voltage. But in case of 220 volts a
voltage divider circuit is better option. Many Energy Meter manufacturers use
thisvoltagedividermethodto make voltage measuring circuit.
A LCD is the face of Energy Meter. It gives reading to the meter readers. Any
small and cheap LCD can serve the purpose here. Normally following things
are required to display on the LCD of single phase energy meters:
41
EEPROM is another important part of Energy Meters. It stores MDI and
total kWH consumption for every 30 minutes. So that retrieval of
consumed units could be possible in case of any discrepancy.
3.20.6Micro-Controller:-
These energy meters are obsolete now but some countries are still using
it due to its cheapness and robustness. They are also called as Disk
meter because a disk is present inside the Energy Meter which rotates
when current flows through it. This rotation is captured by the dial and
enhance its readings as per the amount of current flown. The dial of the
Disk Meter shows only kWh usage since the time of Energy Meter
installation.
They came in both 3 phase and single phase types. Current rating for 3
Phase Disk Type Energy Meter is normally up to 100 Amps. A simple 3
phase disk type energy meter is present in the diagram below:
Digital Energy Meters came in single phase and 3 phase both types.
Single phase type digital energy meters normally just display and store
MDI and Energy units and that’s all.
43
On the other hand, digital 3 phase energy meters give tariff based
energy units storing as well. As the rate of the unit is more at Peak
Load times than at off peak load times. So, Energy meters must store
energy units in two slots i.e. peak slot (T1) and off peak slot (T2) to
differentiate the timing of electricity usage. This is the reason that
they are also called as TOD (Time of Day) Energy meters.
44
3.21.2Types of Energy Meters with respect to load level:-
There are three types of Energy Meters with respect to load level:
LT (Low Tension) Meters are those which can handle large load currents
through externally present CT (current transformers). They are called as
45
LT meters because they operate on not more than 440 volts. These
meters are exactly same as WC meters but the only difference is their
CT is not present inside the meter. A bulky high capacity CT installed in
the series of this meter. This CT first step down the high current to the
feasible level then the other CT present inside the meter step down the
current even more, so that it can be measured easily.
46
Difference between WC, LT and HT meters
3 Phase 440
Voltage Level 3 Phase 440 V 3 Phase 11kV
V
47
3.21.4Types of Energy meters with respect to Class Accuracy:-
Chapter # 4
48
module assembly, fuse module assembly, circuit breaker module assembly,
and much more! This system also includes a heavy-duty workstation with
built-in power supply that allows learners to easily connect components and
build hands-on skills.
• Sources told that hot and muggy weather is overloading the system and
causing the technical glitches.
Voltage surges/spikes :-
Voltage surges/spikes are the opposite of dips – a rise that may be nearly
instantaneous (spike) or takes place over a longer duration (surge). A voltage
surge takes place when the voltage is 110% or more above normal. The most
common cause is heavy electrical equipment being turned off. Under these
conditions, computer systems and other high tech equipment can experience
flickering lights, equipment shutoff, errors or memory loss. Possible Solutions
are surge suppressors, voltage regulators, uninterruptable power supplies,
power conditioners.
49
Voltage Dips:-
Under voltages:-
• Illumination
• Floors, floor openings, passageways, stairs Exits
50
• Installation of equipment Protective groundingGuarding live parts
4.6Rules to provide
substation safety:-Rule no. 1 (clearance):-
Enough clearance from energized parts should be provided to avoid
accidental contact with them. If that can’t be met, live parts should be
guarded or enclosed.
Rule no. 2 (minimum height):-
A minimum height from the ground to any ungrounded part of an
electrical installation should be 8’-6”, so a person staying on the ground can’t
touch a substation element or its part which may become energized
accidentally. For example, the bottom of a post insulator supporting an
energized bus does not normally have any potential.
However, if bus flashover to the ground over insulator occurs, touching the
bottom of the insulator may become unsafe. That’s why an 8’-6” distance
from the bottom of insulator to the ground should be provided.
Rule no. 3 (illumination):-
There should be sufficient illumination for personnel to clearly see their
surroundings and perform any work safely. Required illumination levels
are specified in grid.
51
Rule no. 6 (grounding, as always):-
All substation metallic structures, fences, and equipment tanks should
be connected to a station ground grid which should be designed to ensure
that step and touch potential values are lower than the ones stipulated in the
applicable standards.
Chapter #6
CONCLUSION:-
Now from this report we can conclude that electricity plays an
important rolein our life. We are made aware of how the
transmission the transmission of electricity is done. We too came
to know about the various parts of the substation system. The
three wings of electrical system viz. generation, transmission and
distribution are connected to each other and that too very
perfectly.
52
Thus, for effective transmission and distribution a substation must:
53