Cable Trench Installation Guide: 1.0 Index

Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

CABLE TRENCH INSTALLATION GUIDE

1.0 INDEX

1.0 INDEX
2.0 PURPOSE
3.0 GENERAL INFORMATION
4.0 PLANNING INFORMATION
5.0 CREW INFORMATION
6.0 CONTRACTOR INFORMATION
7.0 PRECASTED/ POURED-IN-PLACE TRENCH DRAWINGS

2.0 PURPOSE

This standard provides information for construction of Cable Trench. This installation is for
underground services from 2001 amps to 4000 amps.

3.0 GENERAL INFORMATION

3.1 Cable Trench is suitable for the following conditions:


• 2001 Amp to 4000 amp services.
• Trench length should be limited to 20 feet, with the service cable length limited to less
than 50' from transformer to customer panel.

4.0 PLANNING INFORMATION

ENGINEERING & CONSTRUCTION STANDARD SHEET 36 OF 8 8

CABLE TRENCH VOLUME 17

DRAWN DESIGN SUPR DATE REV INSTALLATION DRAWING NUMBER

JVV MB MB 7/05 8 GUIDE GI0011U


4.1 Location And Orientation Of Service
Pad placement and switch board pull section should maximize trench window space.

4.2 Service Entrances

The trench length must be determined, (see Section 6.8 for details).
If the entrance is inside the building, then the wall must be cut or designed to allow
the trough entry. The customer must meet NEC, Article 300-21 requirements.

A. PREFERRED #1

ENGINEERING & CONSTRUCTION STANDARD SHEET 37 OF 8 8

CABLE TRENCH VOLUME 17

DRAWN DESIGN SUPR DATE REV INSTALLATION DRAWING NUMBER

JVV MB DA 7/05 8 GUIDE GI0011U


B. PREFERRED #2

C. PREFERRED #3

D. NOT APPROVED CONSTRUCTION

ENGINEERING & CONSTRUCTION STANDARD SHEET 38 OF 8 8

CABLE TRENCH VOLUME 17

DRAWN DESIGN SUPR DATE REV INSTALLATION DRAWING NUMBER

JVV MB MB 7/05 8 GUIDE GI0011U


NOTES:
1. SPPC cable trench is not approved for installation inside a building to serve an
internal / isolated Electrical Room.
2. If an internal / isolated Electrical Room is required, the customer must install a
secondary splice can at the outer wall nearest the transformer. Refer to drawing
below.
3. Outside splice can, and all facilities inside the building, will be customer owned
and installed. Facilities must meet NEC requirements.

D1. ACCEPTABLE CONSTRUCTION

4.3 Trench Covers


There are two types of trench covers available:
• H-20 Full Traffic Rated
• Non-Traffic / Pedestrian Only

4.4 Cable Selection


Multiple runs of cable will be required to serve the load. The number of runs depends
upon the main panel rating. Number of cables per phase is based on 80% rated
panels. Add extra set(s) if 100% panel, noted by ( ) in table.
N UM BER OF CABLES
M AIN PAN EL R ATIN G
PER PHASE
2001- 2500 Amps 5 (6)
3000 Amps 6 (7)
3500 Amps 6 (8)
4000 Amps 7 (9)

See Table 8 of CB0003U, Vol. 17, Section 4, for cable ratings.

ENGINEERING & CONSTRUCTION STANDARD SHEET 39 OF 8 8

CABLE TRENCH VOLUME 17

DRAWN DESIGN SUPR DATE REV INSTALLATION DRAWING NUMBER

JVV MB DA 7/05 8 GUIDE GI0011U


4.5 Required Service Materials (to be supplied by SPPC)

ITEM STOCK NUM BER QUANITY

750 kcmil 1/C 600 Volt Cable


23- 0895 See Section 4.4
(Phase)
350 kcmil 1/C 600 Volt Cable
23- 0781 See Section 4.4
(Neutral)
750 kcmil Flat- to- Crimp Connectors 25- 1356
6 connectors per cable run *
(bolt set). Stackable lug: 25- 1315. (25- 2693)
350 kcmil Flat- to- Crimp Connectors 25- 1351
2 connectors per cable run *
(bolt set). Stackable lug: 25- 1313 (25- 2697)

Cable Ties 95- 8084 1 pkg. per 10' trench length

* Customer to furnish cable connectors at panel. SPPC to furnish bolts.

5.0 CREW INFORMATION

5.1 Cable Orientation


Cable Ties are to be set at +/- 15" intervals along the cable run. Each cable run
contains 3 different phases and a neutral.

ENGINEERING & CONSTRUCTION STANDARD SHEET 40 OF 8 8

CABLE TRENCH VOLUME 17

DRAWN DESIGN SUPR DATE REV INSTALLATION DRAWING NUMBER

JVV MB MB 7/05 8 GUIDE GI0011U


5.2 Support Arm and Tie-Down Spacing
Support arms are to be set at 30 inch spacings. The cable is fastened to each arm.

5.3 Cable Lengths


All X1 phase cables must be the same length, all X2 phase cables must be the same
length, etc. However the length of the X1cables does not have to equal the X2
lengths or the X3 lengths.
Example:

6.0 CONTRACTOR INFORMATION

6.1 Contractor Responsibility


The contractor will provide trench, furnish and install materials as listed in section 6.7.
Contractor will be responsible to submit to Jensen Precast (precasted trench ) and/or
SPPC (poured in place trench) a preliminary drawing with the following items:
• Information as shown in 6.8 with pad size.
• Submit a preliminary design worksheet to Jensen Precast and/or SPPC Inspection
group for verification of measurements and final approval. Jensen will fax final design
to SPPC Inspection Group Reno or District Planner for final acceptance.

6.2 Trench Construction


The cable trench may be precast (Preferred) or poured in place (Non Preferrred).
• Poured-in-place trench walls to be formed, do not cast against existing soil.
• Exposed edges to be finished with edging tool.
• No customer conductor, including bare ground/bonding conductors, is to be installed
in the trench.

ENGINEERING & CONSTRUCTION STANDARD SHEET 41 OF 8 8

CABLE TRENCH VOLUME 17

DRAWN DESIGN SUPR DATE REV INSTALLATION DRAWING NUMBER

JVV MB DA 7/05 8 GUIDE GI0011U


• Unistrut or equivalent to be cast in wall. See details, Section 7.1.
• Unistrut shall be hot dip galvanized and have an "A" corrosion rating.

6.3 Backfill Composition


Backfill material shall meet requirements of SPPC Standard SUB01X, Trench
Bedding and Backfill (see Volume 17, Section 3).

6.4 Service Entrance


• The contractor must check with local codes before running a service entrance.
• Service entrance into buildings must have 'fire proofing' per NEC #300.21
requirements.
• Firestopping - Building codes and standards provide strict requirements for sealing, or
firestopping, penetrations through fire-rated walls, floors, and ceilings. Approved
methods and materials must be used to reduce the chance of spreading fire, smoke, and
toxic gases thoughout the building(s). See Section 7.0, note 11.
• Firestop materials are available as:
√ Blankets,
√ Caulking compounds,
√ Cementitious compounds,
√ Collar devices and chokes,
√ Composite sheets,
√ Pillows,
√ Putty,
√ Wrap strips,
√ Sprays, and
√ Mechanical systems.

• All firestopping solutions are generally a combination of firestop materials, holding devices,
packing materials, and othe devices that make up a listed (approved) system. Aways use
an approved and engineered system to firestop a penetratrion. Contact an
appropriate firestop manufacturer with any questions.

6.5 Trench Covers


• To be stamped as shown in Sections 7.0.
• Will be coated with red oxide primer and finished with epoxy sand paint.
• All covers will be constructed in 24" lengths. If additional length is needed at the start or
end up to 6" may be added to the 24" section. Cover needing additional width above
6" will be made to fit.

ENGINEERING & CONSTRUCTION STANDARD SHEET 42 OF 8 8

CABLE TRENCH VOLUME 17

DRAWN DESIGN SUPR DATE REV INSTALLATION DRAWING NUMBER

JVV MB MB 7/05 8 GUIDE GI0011U


6.6 Drains/Sump hole
• Precast and Poured in place: Locate knockout for the drain hole and the sump hole as
shown in sections 7.0 and 7.1.

6.7 List of Materials


The materials listed below are for reference only, a detailed list of quantities should be
generated by referenceing the final drawing and the specifications shown in this standard.

M ate rials to be Supplie d by Contractor/Je ns e n Pre cas t


Poure d-In-Place (N on-Traffic) Poure d-In-Place (Traffic)
Concrete, 3000 psi strength Diamond Plate Cover Concrete, 3000 psi strength Diamond Plate Cover
@ 28 days 1/4" Thickness @ 28 days 1/2" Thickness
Structural Angle Iron 3- 1/2" Structural Tubing 3"
PVC, 6" Dia. PVC, 6" Dia.
x 3- 1/2" x 1/4" x 3" x 1/4"
4" Long Unistruts For 4" Long Unistruts For
N elson Studs, 2" N elson Studs, 2"
Holding Covers In Place Holding Covers In Place
Rebar, #4 @ 11" O C. Drain Rock, 3/4", 1 Cu. Ft. Rebar, #4 @ 11" O C. Drain Rock, 3/4", 1 Cu. Ft.
Rebar #3 @ 12" O C. 12" Sump Rebar, #3 @12" O C. 12" Sump
Penta Head Bolts Penta Head Bolts
Unistrut P4000 or Equivalent Unistrut P4000 or Equivalent
1/2" x 3- 1/2" . 1/2" x 3- 1/2" .
Cable Suport Racks, Arms, Cable Suport Racks, Arms,
Angle Iron, 3" x 4" x 1/4" Angle Iron, 3" x 4" x 1/4"
& Hardware & Hardware

ENGINEERING & CONSTRUCTION STANDARD SHEET 43 OF 8 8

CABLE TRENCH VOLUME 17

DRAWN DESIGN SUPR DATE REV INSTALLATION DRAWING NUMBER

JVV MB DA 7/05 8 GUIDE GI0011U


6.8 Determine Bus Trench Length

ENGINEERING & CONSTRUCTION STANDARD SHEET 44 OF 8 8

CABLE TRENCH VOLUME 17

DRAWN DESIGN SUPR DATE REV INSTALLATION DRAWING NUMBER

JVV MB MB 7/05 8 GUIDE GI0011U


7.0 PRECASTED/POURED IN PLACE TRENCH DRAWINGS
1. Contractor is to furnish and install concrete trench (Precasted is Preferred Installation).
2. Contractor to furnish and install unistruts as shown on plan view.
3. Contractor to provide SPPC and/or Jensen Precast with a preliminary layout to
confirm transformer and trench layout. See section 6.8.
4. Trench walls to be formed, not cast against existing soil.
5. Concrete strength to be 3000 PSI at 28 days. Rebar yield strength shall be 60KSI.
6. Non traffic 1/4" diamond plate steel cover to be stamped "NON-TRAFFIC",
"SPPCO ELECTRIC" and painted with red oxide primer and sand epoxy painted.
7. H20 traffic rated 1/2" diamond plate steel cover to be stamped "H20 TRAFFIC",
"SPPCO ELECTRIC" and painted with red oxide primer and sand epoxy painted.
8. Finish exposed concrete trench edges with edging tool.
9. Backfill material shall be adjusted to ± 2% of optimum moisture content, placed and
compacted in 8" lifts to 95% of maximum dry density per ASTM-0-1557.
10. Unistrut or equivalent (1-5/8"X 13/16"shall be cast into wall sections with spacing
locations (vertical/horizontal) and a length to fit wall sections as specified on SPPC
standard drawings. Unistrut shall be HDG unistrut P400 or equal and shall be "A"
rated corrosion resistant.
11. The trench may not be extended into the building unless approved by local Inspection
authority and adequate seal against water/fire is provided. (SEE NEC 300.21)

ENGINEERING & CONSTRUCTION STANDARD SHEET 45 OF 8 8

CABLE TRENCH VOLUME 17

DRAWN DESIGN SUPR DATE REV INSTALLATION DRAWING NUMBER

JVV MB DA 7/05 8 GUIDE GI0011U


7.1 Trench Section Details (Pedestrian / H20 Traffic Rated)

ENGINEERING & CONSTRUCTION STANDARD SHEET 46 OF 8 8

CABLE TRENCH VOLUME 17

DRAWN DESIGN SUPR DATE REV INSTALLATION DRAWING NUMBER

JVV MB MB 7/05 8 GUIDE GI0011U


7.2 Trench Section Details

ENGINEERING & CONSTRUCTION STANDARD SHEET 47 OF 8 8

CABLE TRENCH VOLUME 17

DRAWN DESIGN SUPR DATE REV INSTALLATION DRAWING NUMBER

JVV MB DA 7/05 8 GUIDE GI0011U

You might also like