Construction Methods and Project Management Reviewer
Construction Methods and Project Management Reviewer
in a novel way, to undertake a unique scope of work, of a given specification, within the
constraints of cost and time, so as to achieve a beneficial change defined by quantitative
and qualitative objectives.
PROJECT MANAGEMENT - is defined as the art and science of coordinating people, equipment,
materials, money, and schedules to complete a specified project on time
and within the approved cost. It is a combination of tools & techniques
such as PERT, CPM & Gantt Chart and managerial control methods.
FOUR QUESTIONS
• Who?
• Does What?
• When?
• How much?
• GANTT CHART AND S-CURVES - quite old but still quite good
• PERT / CPM - Program Evaluation and Review Techniques
- Critical Path Method
KINDS OF ESTIMATES
b. PROJECT COST - cost derived from activities that serve the project as a whole but for
some reason cannot be assigned to any specific task
- EX: field office, temporary facilities, computers, permits, radios, CR,
bunk house
c. INDIRECT COST - expenses that are not controllable in the site and is best left to the
judgement of the top management
- EX: bond and insurance premiums, tax, profits, contingency, price
escalation
TYPES OF WORKERS
1. Skilled
2. Semi-Skilled
3. Laborer
CONSTRUCTOR - is the general term used to define the professional responsible for all
construction activities
ORGANIZATIONAL CHART
CONCRETE WORKS
CONSTRUCTION JOINTS
REINFORCING STEEL BAR
• 10 mm
• 12 mm
• 16 mm
• 20 mm
• 25 mm
• 28 mm
• 32 mm
• 36 mm
• 40 mm and above (SPECIAL ORDER)
• 6m
• 7.50 m
• 9m
• 10.50 m
• 12 m
BAR CUTTING
POSSIBLE SHAPES
1. Straight Bar
2. Bar with 180 deg bend both ends
3. Bar with 180 deg bend one end and straight other end
4. Bar with 90 deg on both ends
5. Bar with 90 deg on one end and straight other end
6. Bar with 45 deg bend one end and straight other end
7. Bar 45 deg one end and 90 deg bend another end
8. Bar with 45 deg bend both ends
BEAM
COLUMN
STIRRUPS AND LATERAL TIES
BILL OF MATERIALS AND WORK BREAKDOWN
Work Breakdown Statement – is a categorized list of tasks with an estimate of resources required to
complete the task
BID PRICES IN BILL OF QUANTITIES FORMAT
BAR CHART
Gantt Chart
- are both methods for predicting the cost and completion time of projects.
- It is a useful tool for almost anything which requires planning.
PERT (Project Evaluation and Review Technique) - is usually concerned just with the time taken
1. Network Construction
2. Determination of Critical Path
3. Time-Costs Tradeoffs and Crashing
Network – is defined as a set of nodes connected by edges, where something flows along the edges.
3. An activity cannot start until all activities leading to its predecessor event have been completed.
4. The length of the arrow is NOT proportional to the duration of the activity it represents.
Ex: A project has seven well-defined activities: A, B, C, D, E, F, and G. Their order relationships are
as follows:
• A, B, and C are starting activities and may take place after a start event.
• D and F must wait for the completion of A.
• E follows C.
• G follows B, D and E.
• F and G complete the project
5. Dummy activities or arrows are used to keep the sequence logically correct in some instances
Dummy – is an artificial activity represented by broken arrow. It does not require any time.
• Dummy activities may also help avoid ambiguous cases such as when two or more
activities have the same beginning and end events.
Ex: A is the starting activity and may take place after a start event. B and C must follow A, and D
must follow B and C.
𝐸𝐹 = 𝐸𝑆 + 𝑑𝑢𝑟𝑎𝑡𝑖𝑜𝑛 𝑜𝑓 𝑎𝑛 𝑎𝑐𝑡𝑖𝑣𝑖𝑡𝑦
3. LS (Late Start) – the latest possible time an activity may start without delaying the project
completion date.
4. LF (Late Finish) – the latest possible time an activity may be scheduled to finish without delaying
the project.
𝐿𝐹 = 𝐿𝑆 + 𝑑𝑢𝑟𝑎𝑡𝑖𝑜𝑛 𝑜𝑓 𝑎𝑛 𝑎𝑐𝑡𝑖𝑣𝑖𝑡𝑦
Forward Pass
- the ES of the succeeding activity will be the latest of the immediately preceding activities’ EF’s.
- Early Starts (ES) and Early Finishes (EF) are determined in the forward pass.
Backward Pass
- the earliest Late Start of the succeeding activities will be the Late Finish of the preceding activity.
- Late Finishes (LF) and Late Starts (LS) are determined in the backward pass
PERT/CPM Network Diagram
SEATWORK:
From the tabulated information shown below, construct the network diagram and answer the following
questions: