Work Breakdown Structures

This document provides a work breakdown structure (WBS) for constructing a 2 storey residential house. The WBS outlines the major project components of site work, foundation, framings/formworks, walls, roofing, and utilities. It further breaks down the work for each component into specific tasks such as excavation, pouring concrete, framing walls and roof, laying utilities, inspections, and finish work. The WBS is intended to define and group the total scope of work to be carried out in building the house.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
253 views2 pages

Work Breakdown Structures

This document provides a work breakdown structure (WBS) for constructing a 2 storey residential house. The WBS outlines the major project components of site work, foundation, framings/formworks, walls, roofing, and utilities. It further breaks down the work for each component into specific tasks such as excavation, pouring concrete, framing walls and roof, laying utilities, inspections, and finish work. The WBS is intended to define and group the total scope of work to be carried out in building the house.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

ACTIVITY 4

OUTPUT
WORK BREAKDOWN STRUCTURES (WBS)

2 STOREY RESIDENTIAL HOUSE

SITE FOUNDATION FRAMINGS/ WALLS ROOFING UTILITIES FINISH


FORMWORKS WORK

Layout Grade Excavate Install Lay


Sheeting G.I. sheets

Erect Pour Remove Hang Tape & Electric Gas Water


Forms concrete Forms Sheetrock Bed

Floor Sub- Stud Frame Do Do Do


Joist floor Walls Roof rough-in rough-in rough-in
work work work

Install Install Install Install Get Get Get


1st 1st 1st 1st building building building
Floor Floor Floor Floor inspect inspect inspect

Install Install Install Install Do Do Do


2nd 2nd 2nd 2nd Finish Finish Finish
Floor Floor Floor Floor work work work

Install Install Install Paint Lay wall Lay floor


cabinets Appliances furnace walls tiles tiles