Industrial Cogeneration Case Studies: EM-1531 Research Project 1276-1
Industrial Cogeneration Case Studies: EM-1531 Research Project 1276-1
EM-1531
Research Project 1276-1
Prepared by
Principal Investigators
D. R. Limaye
S. Isser
B. Hinkle
N. R. Friedman
Prepared for
D IS C L A IM E R
EPRI authorizes the reproduction and distribution of all or any portion of this report and the preparation
of any derivative work based on this report, in each case on the condition that any such reproduction,
distribution, and preparation shall acknowledge this report and EPRI as the source.
NOTICE
This report was prepared by the organization(s) named below as an account of work sponsored by the
Electric Power Research Institute, Inc. (EPRI). Neither EPRI, members of EPRI, the organization(s) named
below, nor any person acting on their behalf: (a) makes any warranty or representation, express or
implied, with respect to the accuracy, completeness, or usefulness of the information contained in this
report, or that the use of any information, apparatus, method, or process disclosed in this report may not
infringe privately owned rights; or (b) assumes any liabilities with respect to the use of, or for damages
resulting from the use of, any information, apparatus, method, or process disclosed in this report.
Prepared by
Synergic Resources Corporation
Bala-Cynwyd, Pennsylvania
ABSTRACT
The objective of this study was to perform studies on a number of operating cogen
eration systems to determine application, economics and attitudes of industrial
and utility executives toward cogeneration. The study was carried out in four
tasks.
In task two, the remaining sites were contacted as to their willingness to work
with EPRI, and an industrial questionnaire was developed on technical, economic
and institutional cogeneration issues. Each of the seventeen sites was visited
during this task.
In task four, a utility questionnaire was developed and utilities with cogenera
tion systems studied in this survey, in their service territory, were contacted
as to their attitudes toward cogeneration. In addition, a compilation of a list
of operating cogeneration systems was performed during this task.
iii
EPRI PERSPECTIVE
PROJECT DESCRIPTION
This is the Phase I report of RP1276, Evaluation of Alternate Technologies for Dual
Energy Use Systems (DEUS). The remaining phases of this work are a systems analysis
of DEUS and four conceptual designs for DEUS in various industries. The project
will be completed in 1983. The initial contractor for this survey, TRW, Inc., ran
into difficulty securing information on the 17 sites surveyed. Synergic Resources
Corporation was then asked to complete the project. The work on the phase included:
PROJECT OBJECTIVES
PROJECT RESULTS
A great deal of information on DEUS systems not available elsewhere was integrated
into this report. An understanding of utility attitudes toward cogeneration, and
the reasons for those attitudes, is also included. While not complete, this report
probably contains the most comprehensive listing available of verified-operating
v
cogeneration systems in the U.S* This information base will be added to over the
next three years. The information obtained will be used as the state-of-the-art
assessment for cogeneration activities in the succeeding phases of the project.
vi
CONTENTS
Section Page
1 INTRODUCTION 1-1
Project Overview 1-1
Objectives of Cogeneration Survey 1-2
Previous Studies of Industrial Cogeneration 1-2
Utility Activities Related to Industrial Cogeneration 1-6
EPRI Activities Related to Cogeneration 1-8
References 1-10
vii
CONTENTS (Continued)
Section Page
viii
ILLUSTRATIONS
Figure Page
TABLES
Table Page
ix
EXECUTIVE SUMMARY
INTRODUCTION
The Electric Power Research Institute (EPRI) conducted a Dual Energy Use Systems
Workshop in September 1977 to develop information useful to utilities, process
industries, and others concerned with the problems and prospects of DEUS. One of
the findings of the Workshop was:
EPRI has initiated a program for the Evaluation of Dual Energy Systems Applica
tions. This program addresses both industrial cogeneration and district heating,
and its overall objectives are to:
ES-1
The first step in the EPRI DEUS program is to assess the current status of DEUS in
the United States. The first two tasks of the program consist of surveys and case
studies of industrial cogeneration and district heating systems.
The cogeneration systems studied in this project were selected after a formal
screening process. An initial list of cogenerators was prepared by TRW Inc. for
EPRI under a separate contract. Because of the difficulties in obtaining data from
some of the selected candidates. Synergic Resources Corporation performed a second
screening to add a number of case study sites and to develop additional information
on the initially identified sites.
• Currently operational.
ES-2
• In the industrial sector, preferably in the energy-intensive
manufacturing industries.
• Utility interface.
• Primary fuels.
• Ownership.
• Geographic location.
ES-3
SUMMARY OF CASE STUDY RESULTS
The cogeneration systems described in this report offer a diversity of age, size,
efficiency, type of equipment, thermal-electric load ratio, fuel used, fuel cost,
utility interface, and economic performance. Since cogeneration systems are
designed for the industrial facility which they serve, it is not surprising that
they tend to be unique. The one common quality they show is the ability to
generate electricity more efficiently than is possible for a utility power plant
by utilizing energy which would be wasted during conventional generation.
UTILITY PERSPECTIVES
Table ES-2 shows some of the general data on the utilities surveyed, including
each utility's primary fuel(s), its projected growth rate through 1990, and the
percentage of its kilowatt-hour sales which is represented by purchased power.
These data are useful in assessing the utility fuels which would be displaced by
additional cogeneration facilities. This is particularly relevant to the nation
in terms of reducing our dependence on imported oil and limited resources such as
natural gas, and to potential cogenerators considering sale of excess power to a
utility. In the past, if a cogenerator was using an expensive fuel, such as oil
or gas, the utility may have been able to generate power cheaper (using coal,
nuclear, or hydro), or to buy power from a pool more cheaply than from a
ES-4
Table ES-1
1 2 3 4 s 6 7 8 9 )0
SOUTHWEST PUBLIC/
1979 - 30 189 GI STT Electric Coal 1.20 3.0
CELANESEC
SOUTHWEST PUBLIC/
PHILLIPS 1966 - 33 NA GI GT Electric NG 2.40 3.0
1 1 1 2 1 3 14 15 16 1 7 18 19 20
AMERICAN ENKA 0.50 0.62 0.14 6,430 100 23 99.9 0 2.45 0.9
ANHEUSER BUSCH 0.30 0.77 0.11 5,600 100 41 99.9 0 2.86 1.3
(NAME WITHHELD) 0.67 0.76 0.12 5,750 100 71 99.9 0 3.06 1.4
GULF STATES
0.65 0.73 0.17 5,830 -- - 99.9 1 3.43 1.5
UTILITY COMPANY
ES-
HOLLY SUGAR 0.24 0.70 0.10 7,550 73 100 99.9 0 3.32 1.9
ST. REGIS 0.67 0.67 0.21 5,200 100 NA 99+ 48 1.72 0.6
SOUTHWEST PUBLIC/
NA 0.67 0.07 4,800 NA NA NA NA 1.80 0.6
CELANESEC
SOUTHERN
0.61 0.65 0.34 6,630 - -- 94 NA - -
CALIFORNIA EDISON
UNION CARBIDE 0.63 0.68 0.08 6,600 100 100 99.9 NA 3.60 1.7
FOOTNOTES
o Utility Relations:
I - Isolated
PO - Parallel Operation
GI - Grid Interconnected
f Fuel Cost Thermal is the cost of the fuel needed per million Btu of
process steam.
g Fuel Cost Electric is the cost of the fuel needed per million Btu of
process steam.
j The unusually high heat rate for Bowater Southern is due to the combina
tion of combustion of low efficiency fuels (black liquor, wood wastes)
and the use of the condensing mode of some turbines to generate
additional electricity.
ADDITIONAL ABBREVIATIONS
NA - Not Available.
NG - Natural Gas.
ES-7
Table ES-2
Projected Preferred
Power Generation % of KWH No. of
Avg. Annual Ownership: Overall Attitude
Utility By Fuel Type, Sales Existing
Growth I=Industry Toward Cogeneration
Thousand MWH (1978) Purchased Cogenerators
Thru 1990 U=Utility
Alabama Power Coal 18,658 Not 17 19 Not Does not promote cogeneration
Company Nuclear 5,920 available available
Hydro 3,139 (positive)
Oil & Gas Negligible
Pacific Gas & Oil £ Gas 30,500 3.5% 24 20 U Actively promoting cogenera-
Electric Hydro 13,480 tion via favorable rate
Geothermal 2,970 structures
ES-8
cogenerator. Under these conditions, the utility would have been unwilling to
buy power from the cogenerator. However, if by-product fuels, wood, or coal were
used in cogeneration, or if a utility depended heavily on oil and gas generated
power, cogenerators found utilities very willing to buy their excess power.
In general, the utilities participating in the survey would all strongly favor
DEUS in their service area if there was no reliability or safety question, if
DEUS could be firm suppliers of power at a rate which would save the utility
money, if they could gain exemptions from NEA to burn oil or gas, or get
exemptions from emission standards to burn coal, and if there was no significant
reduction of the utility's sales due to conversions to DEUS. In the absence of
this utopian scenario, some utilities still have favorable attitudes toward
cogeneration (DEUS), though they and others, whose attitudes are less favorable,
have legitimate concerns.
CONTINUING EFFORTS
ES-9
• FERC Form 12 which report for a small number of industrial
generators detailed information on the generation facility.
ES-10
SECTION 1
INTRODUCTION
PROJECT OVERVIEW
Dual Energy Use Systems (DEUS) refer to methods for using electric and thermal
energy from a common source when the two forms of energy are produced simultane
ously and in significant quantities. Because of the increasing interest in
conservation and efficient utilization of resources, dual energy use systems are
receiving a great deal of attention today. While substantial research, develop
ment and demonstration activities are currently underway, DEUS -remains a complex
issue and much more information regarding technical, economic and institutional
aspects of DEUS needs to be developed.
EPRI conducted a Dual Energy Use Systems Workshop in September, 1977, to develop
information useful to utilities, process industries, and others concerned with the
problems and prospects of DEUS. One of the findings of the Workshop was:
EPRI is now undertaking a two-pronged program to evaluate the potential for DEUS
applications for industrial cogeneration and district heating systems (2_) . This
program addresses industrial cogeneration and district heating, and its objectives
are to:
The first step in the EPRI DEUS program is to assess the current status of DEUS in
the United States. The first two tasks of the program consist of surveys and case
studies of industrial cogeneration and district heating systems. This report
describes the results of the survey of industrial cogeneration.
1-1
OBJECTIVES OF COGENERATION SURVEY
In the last decade, the energy situation in this country has undergone a signifi
cant transition. Increasing prices and declining availability of primary energy
sources, environmental constraints with the siting of power plants and the
combustion of coal, and rapidly increasing costs of electrical generation, have
all led to a substantial interest in the increased efficiency of fuel utilization
in industry. The evaluation of the potential of cogeneration in industry has been
the subject of many recent efforts undertaken by the Federal government, state
governments, electric utilities, and industrial users. A summary of some of the
more significant recent studies of industrial cogeneration is provided below.
1-2
The first major recent evaluation of cogeneration was performed by the Dow
Chemical Company in its Industrial Energy Center Study (3_) . This study evaluated
the potential for industrial cogeneration, as well as the legal and institutional
barriers to its use. The study investigated both industrial and central station
cogeneration, but examined only steam turbine topping as the cogeneration option.
The data used in this study for evaluating industrial steam requirements were
based on the Stanford Research Institute's study of energy consumption patterns (4_)
which appears to have overestimated industrial steam requirements. The Dow study
did not attempt to estimate the extent to which institutional problems will
inhibit cogeneration. Thermo-Electron Company performed a detailed evaluation of
in-plant generation in the paper, chemicals and petroleum industries (_5) which
represent a substantial portion of total industrial steam use. The Thermo-
Electron study estimated the maximum technological potential for in-plant
electricity generation for each of these three industries using both topping and
bottoming cycles. This study assumed that all industrial steam has potential for
cogeneration and that the technological maximum electrical generation is
determined only by the temperature and pressure required in the process steam
output. As a result, the study estimates of potential cogeneration are
excessively high. A more recent report by Thermo-Electron (6j attempts to
estimate the feasible level of industrial cogeneration using some of the results
from the earlier study. This second study reports an estimated fuel saving of
1.5 quads and electrical generation of 42,800 MW in 1985.*
1-3
As part of the comprehensive assessment of the U.S. energy situation from 1985 to
2010, the Committee on Nuclear and Alternative Energy Systems (CONAES) of the
National Academy of Sciences assembled an industry resource group to identify and
evaluate industrial energy conservation options. This group examined industrial
cogeneration as one of the major conservation activities and concluded that the
expected implementation of cogeneration would be 30 to 40 percent of the maximum
technological potential (8). The expected annual fuel savings of cogeneration
under several alternative scenarios regarding economic growth and future energy
prices were lower than the earlier studies conducted by Dow, Thermo-Electron, and
RPA. A comparative evaluation of these studies was recently published by Oak Ridge
National Laboratory (9)'. This evaluation concluded that there were significant
problems which would limit the potential for cogeneration and that "the energy
savings potential projected for cogeneration is largely dependent on the optimism
of the forecaster with respect to the tractability of the problems involved" (9).
The Federal government has been actively involved in studying and promoting
cogeneration in the last several years. Starting with the early efforts of the
Federal Energy Administration and the Energy Research and Development Administra
tion, the Federal involvement with cogeneration has expanded significantly since
the formation of the Department of Energy (DOE). DOE has established a research,
development and demonstration program to accomplish its objective of improving
energy efficiency and conservation in the industrial sector. In cooperation with
the National Aeronautics and Space Administration (NASA), DOE has recently
completed the Cogeneration Technology Alternatives Study (CTAS) which evaluated
current and emerging technological options for cogeneration. The objectives of
CTAS were to identify and evaluate the most attractive advanced conversion systems
for implementation in industrial cogeneration in the 1985 to 2000 time period
using coal or coal-derived fuels. The CTAS effort concluded that the most
attractive advanced energy conversion systems are steam turbines with fluidized
bed combustion of coal, and gas turbines and combined cycles with the use of coal-
derived liquid fuels (10).
The Department of Energy is also sponsoring two other programs in the industrial
cogeneration area. The first one of these is the Industrial Cogeneration
Optimization Program (11) to characterize five major energy-intensive industries
relative to energy use patterns and to select optimum cogeneration system con
cepts for one or more of these industries. The second program is the Industry
1-4
Evaluation and Demonstration of Cogeneration Systems (1_2). The objectives of this
program are to provide near term, highly visible and original cogeneration system
evaluations and demonstrations to increase industry's interest in cogeneration and
to expedite technology transfer. Another objective of this program is to provide
industry and DOE with first-hand experience in dealing with institutional and
economic impediments to industrial cogeneration.
The DOE also assembled a task force to study cogeneration commercialization. This
task force concluded that:
DOE also sponsored a number of special meetings with industry and environmental
representatives in 1978 to solicit their views on commercialization strategies
from the government's perspective. The meetings were coordinated by four separate
contractors who submitted independent reports. It is interesting to note that the
contractors reported these findings (14):
• The National Energy Act offers only modest potential for increased
cogeneration development.
1-5
attempting to investigate the feasibility of cogeneration (such as Reference 15)
and site-specific studies performed by other organizations (such as the study for
12 plants in California conducted by Jet Propulsion Lab described in Reference 16).
The evaluation of cogeneration potential has also been the subject of studies by
state agencies in Missouri (17) , Illinois (18), Massachusetts (19) , and
Minnesota (20). The Bonneville Power Administration has completed an evaluation
of the potential for cogeneration in the three states of Washington, Oregon and
Idaho (21). Most of these studies have looked at cogeneration from the industry
perspective and have identified numerous benefits as well as limitations of
industrial cogeneration.
In the last several years there has been an increased awareness and interest on
the part of the electric utility industry in cogeneration programs. Some of the
recent activities of three major electric utilities are summarized below.
Southern California Edison (SCE) has long been active in the field of cogeneration.
SCE has viewed cogeneration as an opportunity for conservation and load management
and has actively sought and developed cogeneration potential in their service
territory. The California Energy Commission has recently set a goal requiring
that 10 percent of all electric energy generated in the state be from cogeneration
by 1990. The Commission has required all the utilities in the state to develop
new rate schedules for service to cogenerators and for purchase of power from
cogenerators. In response to this, SCE has identified 612 MW of cogeneration
potential in their service territory. A number of feasibility studies are
currently underway and it is estimated that 25 percent of the identified potential
can be developed by 1990. SCE has set its own goal for developing cogeneration on
their system as 5 percent of their total generation in 1990.
The Tennessee Valley Authority (TVA) has recently completed a preliminary assess
ment of the potential for cogeneration in their service area over the next 20
years (22)■ The principal findings and conclusions of the TVA study are:
1-6
• The best near-term cogeneration potential is in the pulp and paper
and chemical industries.
Public Service Electric and Gas Company (PSE&G) of New Jersey has completed an
assessment of cogeneration potential using utility-owned oil-fired combustion
turbine installations for industrial customers using 100,000 pounds per hour or
more of process steam (23). This study was performed in response to two other
studies of industrial cogeneration potential in New Jersey prepared by the Center
for Environmental Studies at Princeton University (24) and the Public Interest
Research Group (25). These two studies had used survey data and theoretical
assumptions to estimate the total cogeneration potential in New Jersey at approxi
mately 5,000 to 8,000 megawatts. The PSE&G study was based on site-specific
evaluations of its industrial customers and concluded that only 18 customers
represented a potential for cogeneration amounting to a total of only 430 MW.
Other conclusions of the PSE&G study include:
The significant difference between the PSE&G estimates and the other studies
illustrates the importance of site-specific analysis for cogeneration.
1-7
EPRI ACTIVITIES RELATED TO COGENERATION
The Electric Power Research Institute (EPRI) has also been actively involved in
several recent efforts related to cogeneration. In 1977, EPRI conducted the Dual
Energy Use Systems (DEUS) Workshop in Yarmouth, Maine, to develop useful informa
tion for utilities, industries and others concerned with the problems of and
potential for DEUS. Some of the significant conclusions of the participants at
this workshop were:
Since the DEUS workshop, EPRI has completed two other projects related to cogenera
tion. One of these, sponsored by EPRI1s Energy Demand Program, led to the develop
ment of an econometric model for forecasting in-plant electric generation in the
industrial sector (26). The second one, sponsored by the Fuel Cell Program,
evaluated the potential for Dual Energy Use Systems using fuel cells (27).
In 1979, EPRI initiated this Evaluation of Dual Energy Use Systems Applications,
specifically to address some of the issues raised at the DEUS Workshop. A
conceptual overview of the overall study approach in this project is shown in
Figure 1-1. The program addresses both industrial cogeneration and district
heating. The first step in this program is an understanding of the techno-
economic and institutional factors affecting the success of DEUS. The first two
tasks are aimed at accomplishing this objective and consist of surveys and case
studies of industrial cogeneration and district heating. Subsequent tasks include:
1-8
Demand Patterns SYSTEMS ANALYSIS
Fuel Avail./Prices APPLICATION
Location DEFINITION
Growth Charact.
ASSESS CANDIDATE
MARKET RD&D
Institutional RANKING
POTENTIAL ASSESSMENT
Aspects SYSTEM
SYSTEM
Operational
REQMTS.
Characteristics
DEFINITION
H
I SURVEY Conservation
KD
SYSTEM
Operational
CHAR.
Characteristics
DEFINITION
CONCEPTUAL RD&D
Utility Rates DESIGNS REQMTS.
SUBSYSTEM
—► Generation Options
REQMTS.
CONCEPTUAL DESIGNS
This report describes the results of the surveys and case studies of industrial
cogeneration.
REFERENCES
1. Electric Power Research Institute, Dual Energy Use System Workshop Summary,
EM-718-SR, Palo Alto, California, March 1978.
3. Dow Chemical Company, et al., Industrial Energy Center Study, prepared for
the National Science Foundation, June 1975.
10. U.S. Department of Energy, CTAS - Overview and Summary of Results, Briefing
Paper, July 1979.
14. As reported by TRW Inc. to the Tennessee Valley Authority in the TVA study on
cogeneration.
1-10
15. Harvey Campbell, "Industrial Cogeneration: Vulcan Materials Company
Experience," in Proceedings of the Symposium on Cogeneration Opportunities,
St. Louis, Missouri, June 1978.
18. Current project being performed by Thermo Electron Company for the State of
Illinois.
21. Rocket Research Company, Industrial Electrical Cogeneration Potential for the
Bonneville Power Administration Service Area, Report submitted to BPA,
January 1979.
23. Public Service Electric and Gas Company, Industrial Cogeneration, Newark,
New Jersey, 1978.
25. Cindy Miller, The Case for Industrial Cogeneration, New Jersey Public Interest
Research Group, 1977.
27. R. Wakefield, D. Limaye, et al., Assessment of Dual Energy Use System (DEUS)
Fuel Cell Applications, EPRI, 1979.
1-11
'CM
SECTION 2
INTRODUCTION
The cogeneration systems studied in this project were selected after a formal
screening process. An initial list of cogenerators was prepared by TRW and
screened using these criteria {1). Because of the difficulties in obtaining
data from some of the selected candidates, Synergic Resources Corporation per
formed a second screening to add a number of case study sites.
• Currently operational.
2-1
In addition, the candidates as a group were selected to represent a diversity of:
• Utility interface
• Primary fuels
• Ownership
• Geographic location.
A list of the selected case study candidates is given in Table 2-1. Figure 2-1
shows the location of these systems.
Age
The oldest cogeneration system in this study began generating in 1929; the newest
began cogenerating in 1979 (see Table 2-2, Column 1). Of the eight plants which
began cogenerating before 1950, seven have expanded capacity since their original
start up; however, only one plant constructed since 1950 has expanded capacity.
When older plants were in need of replacement equipment, the operators tended to
undertake expansions at the same time. It is interesting to note that five
plants initiated operation or expanded operations after the oil embargo of 1973,
suggesting that rapid increases in fuel and electricity prices encouraged
consideration of cogeneration.
Size
Size differences between systems were somewhat minimized since plants under 10 MW
capacity were generally excluded from the survey. The cogeneration system
2-2
Table 2-1
2-3
[north DAKOTA TENNlSJli
i f
ftOWA
Tcoloraoo
\ 16
ALASKA
1 2 3 4 5 6 7 8 9 10
SOUTHWEST PUBLIC/
1979 - 30 189 GI STT Electric Coal 1.20 3.0
CELANESEc
SOUTHWEST PUBLIC/
1966 - 33 NA GI GT Electric NG 2.40 3.0
PHILLIPS
NAME OF FIRM
11 12 13
ALPHA
14
NET
15 1 16
DEMAND MET BY
17 18
UNSCHEDULED
19
FUEL COST
20
FUEL COST
CAPACITY SYSTEM VALUE HEAT COGENERATION (%) AVAILABILITY
OUTAGES THERMAL ELECTRIC
FACTOR EFFICIENCY Btu(e)/ RATE <%)
(hrs/yr) ($/106 Btu)1 (C/KWH)®
Btu(t)e Btu/KWH THERMAL ELECTRICAL
AMERICAN ENKA 0.50 0.62 0.14 6,430 100 23 99.9 0 2.45 0.9
ANHEUSER BUSCH 0.30 0.77 0.11 5,600 100 41 99.9 0 2.86 1.3
(NAME WITHHELD) 0.67 0.76 0.12 5,750 100 71 99.9 0 3.06 1.4
CO
i
GENERAL FOODS 0.40 0.73 0.15 7,650 62 100 85 0 3.16
-H
GULF STATES
0.65 0.73 0.17 5,830 - - 99.9 1 3.43 1.5
UTILITY COMPANY
HOLLY SUGAR 0.24 0.70 0.10 7,550 73 100 99.9 0 3.32 1.9
PACIFIC GAS
0.47 0.60 0.46 9,100 - - 99.9 NA - -
S ELECTRIC
ST. REGIS 0.67 0.67 0.21 5,200 100 NA 99+ 48 1.72 0.6
SOUTHERN
0.61 0.65 0.34 6,630 - - 94 NA - -
CALIFORNIA EDISON
UNION CARBIDE 0.63 0.68 0.08 6,600 100 100 99.9 NA 3.60 1.7
FOOTNOTES
o Utility Relations:
I - Isolated
PO - Parallel Operation
GI - Grid Interconnected
f Fuel Cost Thermal is the cost of the fuel needed per million Btu of
process steam.
g Fuel Cost Electric is the cost of the fuel needed to generate 1 kWh of
electricity.
j The unusually high heat rate for Bowater Southern is due to the combina
tion of combustion of low efficiency fuels (black liquor, wood wastes)
and the use of the condensing mode of some turbines to generate
additional electricity.
ADDITIONAL ABBREVIATIONS
NA - Not Available.
NG - Natural Gas.
2-7
capacities varied from 7.5 MW to 90 MW, with an average value of 43 MW (Table 2-2,
Column 3). The average annual generation was 240,000 megawatt-hours with an
average capacity factor of 0.63. Capacity factors are somewhat misleading in this
context, since some cogeneration equipment, such as extraction/condensing steam
turbines, can have different capacities depending upon the mode of operations.
Utility Interface
The type of connection between the utility and the cogeneration system depends on
ownership of the system, utility attitudes toward purchase of cogenerated power,
and the industry's perception of utility reliability. Only one system was isolated
from the grid (Table 2-2, Column 5). Utility owned or operated systems were grid
integrated while industry operated units were usually run in parallel to the grid
except when the utility was willing to purchase power. Whether a plant was
electric or thermal load-following was independent of relations with the utility.
Such relations depended more on the design of the system and the requirements of
the industrial customer.
System Design
The amount and operating conditions of the steam boilers also varied between
systems. Brayton cycles had the option of supplementary firing in the waste heat
boilers to produce additional steam. Combined cycle systems supplemented steam
flow from the waste heat boiler to the turbogenerator by adding additional steam
from direct-fired boilers. Expansion valves allowed the option of diverting steam
from the turbines directly to process if needed. The reason for these various
2-8
combinations is to provide the necessary flexibility to handle any possible
contingency. Unfortunately, increased flexibility usually required increased
capital costs and in some cases, decreased operating efficiency types.
Efficiency
Operating Mode
The design of the system and its operating mode will affect efficiency (Table 2-2,
Column 7). Depending on the requirements of the customer, the operator of a
cogeneration facility will need to manage the steam and/or electric production to
meet demands upon the system. If the system is thermal load following, peak
steam demands can be met by diverting steam from the turbines or using a separate
boiler to generate additional steam. To meet peak electric demands, a gas turbine
might be operated at a higher power level or a steam turbine could be run in a
condensing mode.
Heat Rate
The net heat rate is an indirect measure of efficiency (Table 2-2, Column 14).
The heat rate is defined as the amount of fuel required (in Btu) to generate one
kilowatt-hour of electricity. In normal electricity generation, heat rate is
calculated by dividing the Btu content of the fuel consumed by the total generation
in kilowatt-hours. For a cogeneration unit, determining the net heat rate is
somewhat more complex. It requires assigning part of the fuel consumed to
electricity and the rest to thermal energy production (see Figure 2-2). A typical
heat rate for an efficient utility power plant would be around 10,500 Btu/KWH (2).
About 5,000 Btu are lost in the steam after it passes through the turbogenerator.
Cogeneration is an attempt to avoid the second of these losses by using the steam
for process heat instead of merely having it condensed and recycled to the boiler
2-9
LOSSES
(PS Btu)
FUEL
TURBINE
(F Btu) (S Btu) (E Btu)
GENERATOR
FEEDWATER
B(F-S) + (S-PS)
KWHs Generated
KWHs Generated
Note that for a utility power plant, gross heat rate is equivalent to net heat rate
since B = 1 and PS = 0.
Figure 2-2. Illustration of Net Heat Rate Calculation for Steam Turbine Topping
For a Brayton cycle, the determining factor is the efficiency of the gas turbine
in generating electricity. The Rankine cycle plants had net heat rates which
ranged from 4,800 to 11,190, the two Brayton cycle plants heat rates were 6,630
and 7,030, and the combined cycle plants were 5,050 and 5,200, while the two
parallel cycle designs had values of 4,500 and 6,600. Due to the wide variety of
system types and electric/thermal energy ratios, the preceding figures demonstrate
that there is a wide range of net heat rate values for actual plants.
2-10
Reliability
One common aspect to all the cogeneration units in the survey was the satisfaction
of the owners and operators with the reliability of the systems. Unscheduled
outages were reported to be infrequent and of short duration. One reason for this
fine performance was the redundancy built into many of the systems. The use of
multiple boilers and turbogenerators means that the loss of one component will not
result in a forced outage, while the smaller size and relative simplicity of
cogeneration equipment makes repair easier and quicker than for large central
power station equipment.
Fuel Costs
In Table 2-2, Column 20 lists the cost of the fuel needed to generate a kilowatt-
hour of electricity. This number does not include operating and maintenance costs
(usually around 3 to 5 mills/kWh) and amortization of capital costs. The latter
is difficult to determine because of the age of the systems and the various
methods used to calculate capital charges and depreciation rates. By adding an
estimate for ownership and maintenance costs to the fuel costs, the resultant
figure can be considered the cost of cogeneration. It is interesting to note
than the companies with the lowest cogeneration cost burn either coal or waste
products from paper production (bark, hog fuel, black liquor). When these
cogenerators are compared with the corresponding utility company, the utility's
fuel mix consisted of mostly coal and nuclear except for St. Regis/Houston
Lighting & Power (see Table 2-3). This tendency implies that cogenerators are
not necessarily using extra oil or gas by cogenerating with these fuels and
replacing coal or nuclear generation. In fact, some cogenerators currently using
natural gas have suggested that they might discontinue cogenerating electricity
if their utility switched to coal or nuclear power.
LIMITATIONS
It is important to note that some of the data given in this report should be
considered limited in applicability. The data in these case studies were gathered
from a variety of sources, but are limited by the accuracy and detail of the
information furnished by the cogenerating industry or utility. Since most
companies do not conduct close monitoring of their thermal flows, steam production
figures are usually estimated. Some companies had detailed knowledge of their
fuel consumption, but most cogenerators provided estimates for daily or monthly
averages. In many cases, it was impossible to determine the existence and
quantity of steam driven mechanical drives. When questionable or incomplete data
2-11
Table 2-3
2-12
were submitted, follow-up interviews were attempted, and numbers were estimated
when it was not possible to clarify discrepancies. In addition, the age of many
systems created difficulties in obtaining economic data, while some companies
considered this information proprietary.
The complexity of some systems also led to situations where power plant managers
could not or would not collect the information which was requested. In their
day-to-day efforts, they apparently concentrated on maximizing availability,
reliability, and meeting demands as they occur, without worrying about developing
a detailed description of the system's heat balance. Since many of the facilities
have already been amortized, companies were not overly concerned with achieving
optimum performance of their units as long as they determined that the cogenera
tion system was generating the electricity and steam needed, when they needed it,
and was doing it competitively with the cost of purchased power and steam.
Therefore, the companies are unwilling to invest in equipment or personnel needed
to carefully monitor their cogeneration systems. Nonetheless, the data given in
Table 2-2 can be considered a general description of the performance of cogenera
tion systems, which is as accurate as available data permit without a systematic
instrumentation and monitoring program.
Two companies had recently completed plants, and though operating experience was
not available, sufficient data concerning economics and expected technical
performance was provided to make some comparisons. Shell Oil Company added a
60 MWe, 2 million pound per hour gas-fired boiler-turbogenerator combination at its
refinery in Deerpark, Texas, in 1979. During the same year, a 30 MWe, 1.3 million
pound per hour coal-fired boiler-turbogenerator system went on line for the
Celanese Chemical Company in Pampa, Texas. Table 2-4 presents some characteristics
of these two systems. Some of the Celanese figures have been estimated, while
most of the values for the Shell unit were derived from information provided by the
company.
Some modifications were made in formulating the data to compensate for the
tendency toward optimism when estimating the expected performance of a new
facility. It was felt that the adoption of more conservative estimates would
result in operating and economic data which reflected more realistic operating
conditions. For the Shell plant, a boiler efficiency of 85 percent was assumed in
place of the 89 percent implied by figures supplied by the company. Shell's
2-13
Table 2-4
2-14
estimate of operation time of 8,566 hours per year was replaced by 7,884 hours
per year, and the plant was assumed to operate at 90 percent of capacity instead
of 100 percent. Twenty-five percent of the capital cost of the Shell unit was
assumed to be attributable to cogeneration.
The Celanese plant was estimated to operate for 7,008 hours per year at 90 percent
of capacity, instead of 7,884 hours at 100 percent capacity. The capital cost of
the Celanese facility includes the cost of baghouses but excludes flue gas
desulphurization. Twenty percent of the unit's cost was assigned to the cogenera
tion components. The system was designed for excess thermal production to provide
capacity for future expansions — 20 percent of the output from the turbine is
diverted to feedwater heating, lowering system efficiency.
All other costs for the two systems were split between electrical generation and
process steam in proportion to the fuel consumed in producing each end product,
as shown below:
A five-year payback was used and capital charges were calculated as 20 percent of
the proportion of capital costs assigned to each end product. Though Celanese
sells steam to Southwest Public Service Company, owner of the turbogenerator, and
buys electricity from the utility, it was assumed that the company owned the
whole system to simplify the comparison. The low estimate for fuel costs is based
on a price of $6 per ton for 0.4 percent sulphur coal, 10,000 Btu/pound, and $18
per ton transportation costs. The high estimate increases these prices by 50 per
cent.
From data supplied by Shell and the St. Regis Paper Company, the average cost of
electricity from Houston Lighting & Power in 1978 was about 2.3 cents/KWH.
Houston Lighting and Power had increased rates to large industrial customers over
20 percent in 1979, and a similar increase is expected in 1980, due to the utility's
dependence on natural gas (_3). This implies an electricity cost of 3.3 to 3.6 cents
per KWH by the end of 1980. Southwest Public Service had estimated that the average
cost of electricity for Celanese in 1979 would be 3.0 cents/KWH. Thus, even under
the high fuel cost scenario, the companies could generate electricity at a lower
2-15
cost than their respective utility. When a cogenerator and a utility are both
experiencing rapid escalation in fuel prices, the greater heat rate of the utility
will result in a greater increase in generation costs than for the cogenerator.
2-16
SECTION 3
UTILITY PERSPECTIVES
BACKGROUND
Cogeneration of electricity and thermal power is not a new idea, developed in the
wake of the oil crisis of the 1970's. Though bottoming-cycle technologies have
only recently been developed to the commercial level, the earliest development in
industrial electrification included cogeneration systems. Indeed, from the 1880's
through 1910, industries met most of their electricity needs through on-site
generation and more than half of this was produced by topping cycle cogeneration
plants. Electric utility service was, during this period, frequently expensive
and unreliable. On-site generation was more reliable, or at least under the
control of the industrial user. Cogeneration then was a logical auxiliary to on
site generation which was very economical.
Today, on-site industrial cogeneration systems in this country are common only in
a few industries where thermal and electric demands are favorably balanced and
3-1
coincident, and where cheaper fuels are available or utility power is not
available. These industries, interestingly, are generally the highest energy
users in the industrial sector. Previous studies have shown that cogeneration is
more feasible in the chemical, steel, petroleum refining, pulp and paper, food
processing, the textile industries. Together, these industries account for about
75 percent of all energy used in the manufacturing sector in the U.S. They also
account for most of the existing cogeneration facilities in America, as is
evidenced by the case studies presented in Section 2.
UTILITIES SURVEYED
Table 3-1 shows some of the general data on the utilities surveyed, including each
utility's primary fuel(s), its projected growth rate through 1990, and the percent
age of its kilowatt-hour sales which is represented by power purchased from the
grid connections. These data are useful in assessing the utility fuels which
would be displaced by additional cogeneration facilities. This is particularly
relevant to the nation in terms of reducing our dependence of imported oil and
limited resources such as natural gas, and to potential cogenerators considering
sale of excess power to a utility. In the past, if a cogenerator was using an
expensive fuel, such as oil or gas, the utility may have been able to generate
3-2
Table 3-1
Projected Preferred
Power Generation % of KWH No. of
Avg. Annual Ownership: Overall Attitude
Utility By Fuel Type, Sales Existing
Growth I=Industry Toward Cogeneration
Thousand MWH (1978) Purchased Cogenerators
Thru 1990 U=Utility
Alabama Power Coal 18,658 Not 17 19 Not Does not promote cogeneration
Company Nuclear 5,920 available available
Hydro 3,139 (positive)
Oil & Gas Negligible
Pacific Gas & Oil & Gas 30,500 3.5% 24 20 U Actively promoting cogenera
Electric Hydro 13,480 tion via favorable rate
Geothermal 2,970 structures
3-3
power cheaper (using coal, nuclear, or hydro), or to buy power from a pool more
cheaply than from a cogenerator. Under these conditions, the utility would have
been unwilling to buy power from the cogenerator. However, if by-product fuels,
wood, or coal were used in cogeneration, or if a utility depended heavily on oil
and gas generated power, cogenerators found utilities very willing to buy their
excess power.
With the passage of the Public Utilities Regulatory Policy Act (PURPA), utilities
are now required to purchase power from cogenerators at rates which are non-
discriminatory. Cogenerators can therefore find a market for their excess power.
However, the purchase price paid by a utility will depend on its alternative
options of generating power or purchasing from the power pool. The fuel mix of
the utility is therefore quite important in shaping its policies towards cogenera
tion.
The projected growth rates of these utility systems vary somewhat; however, it is
important to note that the utilities are all projecting positive growth (even
those which did not disclose their projections, indicated positive growth).
Responses from utilities experiencing a decrease in the peak demands may have
shown a considerably different attitude toward increased industrial cogeneration,
which would reduce the utility's peak demand further.
Also presented in Table 3-1 are data indicating the number- of existing cogenera
tors in each utility's service area. Utility attitudes toward ownership of
cogeneration plants and toward industrial cogeneration in general are also noted
in Table 3-1. Though the preferred ownership arrangements are shown, what is not
shown is that some utilities (Pacific Gas and Electric, TVA, and Southern
California Edison included) are willing to consider other ownership arrangements
under certain circumstances. Further discussion of utility attitudes with respect
to particular facets of cogeneration systems is presented in the following
section.
3-4
• Safety of interconnection equipment and utility personnel.
In general, the utilities participating in the survey would all strongly favor
DEUS in their service area if:
Even with these unresolved concerns, some utilities still have favorable attitudes;
toward cogeneration (DEUS). The following sections are an attempt to summarize
the major issues from the utility perspective.
Reliability and maintenance of DEUS are really two factors which are very closely
related from the viewpoint of the utility. Reliability, as used here, is less a
reflection on the quality and dependability of the cogeneration equipment than it
is a concern with industry (cogenerator) operation in accordance with utility
needs. There is concern with long-term dependability upon the electric generating
capacity of the DEUS by the utility, and uncertainty regarding the availability of
that capacity when the utility needs it, or can use it economically. Industry and
utility interests may be working at cross purposes from time to time and negoti
ation of a firm and effective contract between both parties is of primary concern
in any cogeneration system which will sell excess power. In addition, with an
industry-owned and operated DEUS, there is always some concern that the operator
of any particular plant may shut down and go out of business, leaving the utility
without some capacity it had depended upon. These concerns have led some utilities
to desire utility ownership of DEUS.
3-5
Maintenance of a DEUS is a concern to utilities primarily with respect to the
responsibility for it, industry or utility. Most utilities surveyed felt that
industry should maintain industry-owned and operated facilities, and perhaps
should maintain jointly-owned facilities sited at the industrial location. Other
utilities, generally those favoring utility ownership of DEUS facilities, prefer
utility operation and maintenance. This viewpoint is partially a product of good
experience in utility operating and maintenance and partially a concern with
industry competence to perform maintenance properly and at times operate in a
manner compatible with utility needs. However, one utility does point out that,
although they favor utility maintenance at this time, if they were to have many
cogenerators spread all around their service area, the maintenance of all of them
would become very costly.
Some utilities have established rather stringent maintenance procedures which must
be followed by industrial cogenerators. One utility in particular cites problems
experienced with an Industry-owned DEUS which supplied a high reactive load to the
utility grid, and is very concerned about operation and maintenance procedures on
all DEUS in its service area. This utility's attitude has been seriously dampened
with regard to any further cogenerators. However, due to the strict standards now
being used by this utility in evaluating the reliability, maintainability, and
safety of DEUS facilities, it is unlikely that they will experience similar
problems again.
It should be noted that the concerns expressed in the foregoing discussion are,
for the most part, in regard to DEUS facilities which sell power to the utility
grid, and that those cogenerators which do not sell power or those which are
isolated from the power grid are of much less concern to the utilities.
3-6
Safety of Utility Equipment and Personnel
Only a few utilities mention their concerns with these safety matters, however,
most of the utilities have policies which express these concerns implicitly. For
example, most utilities will perform the installation of interconnection gear
themselves, in some cases they will bear the cost also. All have standards, at
least, for safe interconnection, and most retain control of the intertie. Those
who support utility ownership of DEUS facilities use safety of interconnections
as support for their position. One utility reported past problems with inter
connection equipment and also expressed that its concern for safe interties is to
some degree associated with its concern for employee safety. In the case of a
utility power outage, power from a DEUS feeding the grid could endanger employees
working to repair power lines. In general, more agreement was expressed by the
surveyed utilities with regard to interconnection safety than on any other subject.
Loss of Customers
Although all of the utility systems in this survey are growing systems, most are
not growing as fast as was once anticipated. One, in particular, expressed the
concern that they would not like to lose many (any) more industrial customers from
their load base. This utility has experienced the loss of several industrial
customers over the last few years, not to cogeneration, but to other cities, due
to regional economics beyond the control of any utility company. Erosion of the
industrial base of utility service area could harm the operational economics of
any utility, although this point was not explicitly mentioned by other utilities.
Even utilities which are struggling to meet their area electricity demands by using
old and expensive oil and gas fired equipment, or by purchasing power from power
pools during peak periods, would not be happy to lose a single industrial customer
because of the base load character of industrial electricity use. It is only the
high peaking customers, or demands, which these utilities might by happy or
unconcerned about losing.
DEUS Ownership
Most surveyed utilities favored industry ownership of DEUS facilities with utility
owned and controlled intertie. Apparently, this position is believed to encourage
financial responsibility on the part of the industry and reduce the losses to the
utility should the industry or plant fold. One utility feels that it is beyond
the scope of their chartered activities to own DEUS facilities. Others are more
receptive to either option. Two utilities strongly favor utility ownership,
apparently because they wish to have full control of their generating capacity and,
3-7
at least in one case, because such an arrangement has been very satisfactory in
the past. Another utility, which generally favors industry ownership of DEUS, is
also exploring the possibility of using combustion turbines which the utility
currently owns for utility-owned cogeneration arrangements. These combustion
turbines are excess peaking capacity that the utility purchased some years ago
when its projected growth rate was much higher. Now, with the additions to its
base load capacity, the utility has very little use for these turbines, and is
willing to relocate them to the site of an industry where a DEUS would be
economically favorable to both the customer and the utility.
Four of the utilities surveyed have established buy-back rates for cogenerated
power. These are based on each utility's system energy or fuel costs and are
adjusted to encourage on-peak deliveries. The other utilities which have experi
ence in purchasing cogenerated power indicated that they will determine rates on
a case-by-case basis by individual contract negotiation. All of these utilities
expressed a willingness to provide additional payment for cogeneration power
offered as firm capacity. Most utilities expressed the opinion that cogeneration
power for sale to utilities should be an economic advantage to both the DEUS owner
and the utility. That is, DEUS should, be able to sell power for more than it
costs to generate, and for less than it would cost the utility to generate (or
purchase) replacement power. This criterion is considered a possible barrier to
cogeneration in some utility service areas dominated by nuclear and coal fueled
power plants. At least one utility feels that its low generation costs are a
barrier to oil or gas fired cogeneration, while environmental regulation will
probably prohibit coal-fired DEUS in its service area.
3-8
62 dollars per kW of capacity per year for firm generating capacity offered on a
10-year contract basis. Contracts can also be arranged for firm capacity available
during June, July and August, when PG&E sees its highest peaks.
Virtually all of the utilities surveyed have schedules for standby power for use as
backup to DEUS operators. One utility would determine these rates case-by-case and
one provided no response to this question. Standby power rates apparently distin
guish clearly the utilities which encourage DEUS from those which do not. Among
the utilities not promoting cogeneration, standby power charges ranged from $3.75
to over $6.00 per kW of standby capacity per month. In contrast, those utilities
supporting DEUS development through special provisions such as interruptibility or
rachets on contract demand, could allow standby capacity (demand charges) to be
virtually free. Other plans offered by these utilities charge as little as 75
cents to $1.00 per kW per month.
SUMMARY
Only four of the utilities surveyed are actively promoting cogeneration. Two of
them are in California and are following the directive of the California Public
Utility Commission which takes a very positive attitude regarding alternative
energy sources. In addition, these California utilities purchase a very high
percentage of the power they sell, which often is more expensive than cogenerated
power. And, of course, the cogenerated power would not displace current utility
capacity.
One of the others is the Tennessee Valley Authority, a Federal agency, whose
charter directs it to minimize power costs to its customers. TVA is promoting
cogeneration to get industrial customers to shift from oil or natural gas to coal,
wood, municipal solid waste, or other substitute fuel and to increase the effi
ciency of fuel resource utilization. Electrical capacity developed by cogenerators
will help to maintain lower rates by deferring the construction of expensive new
power plants in the future.
3-9
Six other utilities accept cogeneration proposals but do not actively promote them.
Their lukewarm attitudes are based on a variety of circumstances. One utility
feels caught in the bind of dual regulatory constraints. Cogeneration facilities
would likely use gas or oil and would therefore require exemptions from the
National Energy Act of 1978. These exemptions would be difficult to obtain since
cogenerated power would be displacing nuclear and coal-generated utility power.
However, should the cogenerator select coal as a fuel for his facility, EPA New
Source Performance Standards would be difficult and expensive to meet. This
utility has relatively low rates because of its nuclear and coal-based power, such
that cogeneration is less likely to be economically feasible in this system.
Technical problems with past and current cogeneration has dampened the enthusiasm
of another utility. This utility is establishing high standards for new cogenera
tors to meet, particularly with respect to interconnections, which may drive up
the cost of cogeneration systems. There is also a desire to stay out of the
operation phase of cogeneration in order to avoid labor disputes.
Only one utility was genuinely uninterested in cogeneration, although there are
currently several systems operating in its service area. This utility declined to
discuss any of their reasons for this attitude.
Each of the utilities in this survey has a unique set of circumstances including
regulatory environment, types of fuels relied upon, customer make-up, and growth in
demand. Additionally, each utility in this group has had experiences with DEUS
facilities, and these experiences have influenced their current opinions on the
subject. There is no general theme which carries through all utilities surveyed
regarding cogeneration, except that: When a DEUS is technically and environmentally
feasible, and of economic advantage to both industry and utility, then the utility
will support it.
Another common concern of most utilities is the uncertainty that they feel regarding
legislative and regulatory action affecting cogeneration. The thrust of most of the
recent legislation is to encourage energy conservation; but there are questions
regarding availability of oil and gas to cogenerators, higher prices for deregulated
3-10
oil and gas to cogenerators (and utilities) which affect DEUS economic viability,
and environmental regulation with respect to coal use (and use of other waste
fuels) by cogenerators. Together, these factors create a confused picture
regarding the viability and desirability from the viewpoint of the utilities.
3-11
SECTION 4
The following pages provide the information for the industrial cogeneration case
studies in a standard format.
AMERICAN ENKA COMPANY
The company stated that the payback period was three years — however, it
mentioned a return on investment of greater than 10 percent with no mention of
how much in excess of that number. Operation and maintenance costs seemed
higher (7 mills/kWh) than reported for most units, but this may have been due to
problems with coal burning; however, cost of electricity was 1.4 cents/kWh.
4-2
AMERICAN ENKA COMPANY
IDENTIFICATION
COAL
COAL MECHANICAL
DRIVES
COAL REFRIGERATION
MACHINES
150 PSIG
410 PSIG
4-3
PRODUCTION/USE CHARACTERISTICS
ECONOMIC CHARACTERISTICS
ADDITIONAL COMMENTS:
4-4
ANHEUSER-BUSCH, INC.
4-5
ANHEUSER-BUSCH, INC.
IDENTIFICATION
SYSTEM DESCRIPTION:
4-6
PRODUCTION/USE CHARACTERISTICS
ECONOMIC CHARACTERISTICS
ADDITIONAL COMMENTS:
4-7
BOWATER SOUTHERN PAPER CORPORATION
The Bowater system uses extraction condensing turbines to generate much of its
electricity, lowering the heat rate. The company also uses a sizeable fraction
of steam production in the power plant. It also supplies a portion of steam for
process directly. This allows the company greater flexibility in operating the
system but at a lower efficiency. The system is extremely reliable, with the
gnly unscheduled outage in 22 years being the loss of one turbine for 4 months.
4-8
BOWATER SOUTHERN PAPER CORPORATION
IDENTIFICATION
PLANT NAME:____ Bowater Southern________________________________________
SYSTEM DESCRIPTION:
850 PSI6/860°F [
?150 PSIG/3#0*F
—►
SO PSIG/320°F
NATURAL GAS
^6011
BA,tK r~u
WOOD
WASTE
II
LhhJ
»
BLACK
LIQUOR 1_____ 1 ^
Lj
c]
◄----------------
4-9
PROPUCTION/USE CHARACTERISTICS
FUEL USED ITypo(s))- Residual Oil, Natural Gas, Wood Waste, Black Liquor
RELATIONSHIP WITH UTILITY: Purchased power cost was 2.5 C/kWh plus
standby service charge. TVA offered to pay same price for power sold to
utility
ADDITIONAL COMMENTS:
4-10
(A PAPER COMPANY IN PENNSYLVANIA)
This company, whose name has been withheld for confidentiality reasons, has been
cogenerating since 1934. Originally, the system was coal-fired, but was con
verted to residual fuel oil in 1965. The system is relatively simple with one
extraction turbine and one extraction condensing turbine. Reliability is
extremely high; they considered forced outages to be negligible. The company is
pleased with the system, but it is considering converting back to coal. An
anticipated change in product to a higher quality paper will require a higher
proportion of electricity. The company is undecided about whether to increase
electricity generation. The company currently cogenerates about 70 percent of
its electricity needs, and purchases the rest from the local utility.
4-11
(A PAPER COMPANY IN PENNSYLVANIA)
IDENTIFICATION
PLANT NAME: Not Disclosed___________________________________________
SYSTEM DESCRIPTION:
490 PSI6/660°F
RESIDUAL
50 PSIG
CONDENSATE
4-12
PRODUCTION/USE CHARACTERISTICS
ECONOMIC CHARACTERISTICS
ADDITIONAL COMMENTS:
4-13
GENERAL FOODS CORPORATION - ATLANTIC GELATIN DIVISION
The system cost $3.2 million or $427 per kilowatt of capacity. However, the load
factor is only 40 percent. The company expected the system to have a 5-year
payback, which seems very optimistic.
4-14
GENERAL FOODS CORPORATION - ATLANTIC GELATIN DIVISION
IDENTIFICATION
PLANT NAME: Atlantic Gelatin Division
SYSTEM DESCRIPTION:
30 PSIG
¥
NATURAL GAS
4-15
PRODUCTION/USE CHARACTERISTICS
UNSCHEDULED OUTAGES:____None_______________________________________________
ECONOMIC CHARACTERISTICS
RELATIONSHIP WITH UTILITY: Will buy all excess power during peak
and shoulder periods at 80% of current fossil fuel charges - off peak
purchase option
ADDITIONAL COMMENTS:
4-16
GULF STATES UTILITIES COMPANY
The Gulf States Utilities Company, Louisiana Station #1, is an example of the
mutually beneficial operation of a cogeneration plant by a utility for industrial
customers. The Louisiana Station has been cogenerating successfully for almost
half a century. At present, it is supplying steam for neighboring Exxon and
Ethyl Corporation plants while burning waste gas from the Exxon Refinery.
Gulf States has been gradually replacing the older, less efficient boilers and
turbines in the generating station. The utility condenses some steam, but it
uses most of the steam for process. The condensing option along with direct
steam lines for process allow greater flexibility in meeting both steam and
electric demands. The system has proved extremely reliable with the only forced
outage in its history occurring during a storm in 1960. Industrial customers
have expressed confidence in the system — Exxon has a 7-year contract with Gulf
States. The utility considers the station profitable to operate. One problem
for the utility may be the drastic increase in fuel costs — it was purchasing
natural gas at 30 cents per million Btu, but contracts expired in 1979, resulting
in an immediate increase to $2.60 per million Btu. Ironically, this will mean an
increased profit on the cogeneration unit in comparison with gas-fired conven
tional generation plants owned by Gulf States due to the increase value of the
fuel savings.
4-17
GULF STATES UTILITY COMPANY
IDENTIFICATION
PLANT NAME:
Louisiana Station #1
SYSTEM DESCRIPTION:
Rankine Cycle - Steam Turbine Topping. 2.55 MW extraction turbines
steam input 1,500 psig/960°F, 4.20 MW turbines, 1 extraction,
3 extraction/condensing, steam input 600 psig/750°F, steam to process
135 psig/450°F.
c 135 PSIG/450°F
4-18
PRODUCTION/USE CHARACTERISTICS
ECONOMIC CHARACTERISTICS
ADDITIONAL COMMENTS:
Steam, some electric sold to Exxon and Ethyl Corp. — they provide most of
the fuel, pay operating costs.
4-19
HOLLY SUGAR CORPORATION
4-20
HOLLY SUGAR CORPORATION
IDENTIFICATION
SYSTEM DESCRIPTION:
BOILERS
NATURAL
1 f 47 PSIG
4-21
PRODUCTION/USE CHARACTERISTICS
OPERATING STAFF:______NA______________________________________________________
ECONOMIC CHARACTERISTICS
ADDITIONAL COMMENTS:
4-22
PACIFIC GAS & ELECTRIC - TOSCO
The Pacific Gas & Electric (PG&E) cogeneration facility at Avon, California, is
one of the oldest systems covered in the survey. Started in 1939, it has operated
for 40 years and it is expected to continue to function for at least another
decade. The facility supplies steam for Tosco Corporation's refinery (owned by
Lyon Oil Company), while burning waste gases from the refinery. The system
consists of a direct-fired boiler feeding an extraction condensing turbine and
generator set. Electricity in excess of Tosco's requirements is fed to PG&E grid.
Not only has the unit performed reliably for 40 years, but PG&E reports that it
is still very reliable, with forced outages being rare events of short duration.
The utility's opinion of its experience with the facility is enthusiastic and
they are extremely impressed with its endurance and reliability. Despite the
unit's low efficiency relative to other cogeneration systems (57 percent), the
utility considers it to be profitable to operate.
4-23
PACIFIC GAS & ELECTRIC - TOSCO
IDENTIFICATION
SYSTEM DESCRIPTION:
PGA!
TOSCO REFINERY
REFINERY WASTE GASES
PROCESS STEAM
4-24
PRODUCTION/USE CHARACTERISTICS
ECONOMIC CHARACTERISTICS
ADDITIONAL COMMENTS:
4-25
POTLATCH CORPORATION
The system is presently fueled by natural gas, wood waste and bark, and black
liquor in a recovery boiler. The system has been very reliable and the company
is generally satisfied with its performance, though the economics of the system
have been disappointing. Since the local electric utility, Washington Water and
Power Company, relies on hydroelectric power generation, it is able to supply
electricity at only 8 mills per kWh, an extremely low price. Despite Potlatch's
extensive use of waste fuels, the high cost of natural gas (40 percent of fuel
consumption for the DEUS), raises generation costs above the utility. However,
the limited availability of hydroelectric power is forcing utilities in the
Northwest to invest in nuclear power and electricity costs are expected to
increase rapidly.
Due to the expected rate increases and the company's satisfaction with its
present cogeneration system. Potlatch is planning to add a 550,000 pound per hour
wood-burning boiler and 30 MW turbogenerator in the early 1980's at a cost of
$89 million. With this addition, the Lewiston facility will be generating almost
all of its electricity demand.
4-26
POTLATCH CORPORATION
IDENTIFICATION
SYSTEM DESCRIPTION:
170 PSIG ^
600 PSIG/500°F
BOILERS □
70 PSIG ^
BLACK
LIQUOR
70 PSIG
WOODWASTE
BARK
□
4-27
PRODUCTIQN/USE CHARACTERISTICS
ECONOMIC CHARACTERISTICS
ADDITIONAL COMMENTS:
4-28
RIVERSIDE CEMENT COMPANY
The cogeneration system at the Riverside Cement Company plant at Oro Grande,
California, is the only example of a bottoming cycle in this report. The system
consists of five waste heat boilers rated at 20,000 pounds per hour and two oil-
fired 40,000 pounds per hour boilers. They feed two 7.5 MW condensing turbines.
Since the production of steam in the waste heat boilers is directly related to
the production rate in the cement kilns, the direct-fired boilers are used to
supply additional steam for generating power to meet plant requirements.
The cement kilns are fired with coal and natural gas. In order to reduce oil
consumption, the company is planning to add two 25,000 pounds per hour waste
heat boilers to replace some of the steam from the direct-fired boilers. System
efficiency calculations are irrelevant, because waste heat, which could not be
used for other purposes in appreciable quantities, is a major heat source. The
reported heat rate of 11,000 Btu/kWh is acceptable in this situation, since the
oil heat is a fraction (21 percent) of the energy used for generation.
4-29
RIVERSIDE CEMENT COMPANY
IDENTIFICATION
SYSTEM DESCRIPTION:
675 PSIG/790°F
CONDENSATE
TO BOILERS
4-30
PRODUCTION/USE CHARACTERISTICS
ECONOMIC CHARACTERISTICS
ADDITIONAL COMMENTS:
Plan to add two 25,000 Ibs/hour waste heat boilers to replace oil-fired
boilers.
4-31
ST. REGIS PAPER COMPANY
The Southland Division of St. Regis Paper Company owns and operates this plant,
producing newsprint and kraft paper. The cogeneration system is quite complex,
employing two 12.5 MW gas turbines whose exhaust is sent to waste heat boilers
producing steam for a high pressure steam header along with gas-fired, black
liquor recovery, bark and sludge fired boilers. Ninety percent of the steam is
then fed into two backpressure turbines, while 10 percent goes to process at
intermediate pressure. Fuel consumption figures were estimated using data from
St. Regis concerning natural gas consumption and waste fuels. St. Regis is
generally happy with the performance of the cogeneration system, but the
company is uncertain about the possibility of expansion due to the rising costs
of natural gas.
The company reports the charges for electricity and steam as 3.6 cents/kWh and
$1 per million Btu of steam, even though they buy natural gas at $2.25 per million
Btu. Based on the amounts of electricity and steam generated, conventional cost
accounting would indicate the marginal cost of electricity (fuel and O&M) should
be around 1.3 cents/kWh, while, even if waste fuels are included in calculating
the marginal cost of steam, it would be at least $1.70 per million Btu. Using
natural gas to fire a boiler would give a marginal cost of steam of $2.67 per
million Btu. Since St. Regis considers cogeneration to be economical, the
reported charges may be the result of internal accounting procedures.
4-32
ST. REGIS PAPER COMPANY
IDENTIFICATION
SYSTEM DESCRIPTION:
875 PSIG
4-33
PRODUCTION/USE CHARACTERISTICS
ECONOMIC CHARACTERISTICS
ADDITIONAL COMMENTS:
4^34
SHELL OIL COMPANY
Shell is obviously satisfied with its cogeneration system, considering that the
company was willing to invest $125 million for the latest expansion which went
on-line in 1979. Refinery gas and pyrolysis pitch account for more than 50 per
cent of the fuel for the DEUS, even including the latest expansion. The
redundancy of the system is responsible for its high degree of reliability, and
the desire to retain this quality has discouraged Shell from retiring the gas
turbines and older boilers despite their relative inefficiency. Shell expects
the system to stay economic for another decade or two, but they expect that the
eventual utility shift to coal and nuclear generation will make the cogeneration
system obsolete.
SHELL OIL U.S.A.
IDENTIFICATION
SYSTEM DESCRIPTION:
Dual system. Gas turbines with waste heat recovery producing steam
at 250 psi. The combination of boilers producing various steam
pressures for turbine input-average, 1250 psi/1000°F (output 650 psi/
750°F), and other process steams.
4-36
PRODUCTION/USE CHARACTERISTICS
ANNUAL COGENERATION SYSTEM OUTPUTS: ELECTRIC 342,634 MWH
UNSCHEDULED OUTAGES* ^ ^ year for each holler (23) , none for system
OPERATING STAFF- 4 men per shift new units, unknown for total system
ECONOMIC CHARACTERISTICS
4-37
CELANESE CHEMICAL COMPANY - SOUTHWESTERN PUBLIC SERVICE COMPANY
The Celanese cogeneration plant has only recently begun operation and,
unfortunately, it has not been operating for a sufficient length of time to
generate data. Therefore, data on heat balance and economics have been estimated
from articles published jointly by Celanese Chemical Company and Southwestern
Public Service Company.
The plant utilizes two 650,000 pounds per hour pulverized coal-fired boilers,
which feed steam to a 30 MW backpressure turbine and generator. Since the
capacity of the system exceeds the process demands of the plant, approximately
20 percent of the steam produced will be used for feedwater heating after passing
through the turbine. This allows maximum electrical generation for the present
while providing sufficient excess capacity for expansion. A load shedding system
was installed in case of a boiler outage, while a high-speed bypass expansion
valve system guards against turbine trip-out. Four existing gas-fired boilers
will be maintained in a semi-mothballed condition in case of a coal boiler
outage.
Celanese owns the boilers but Southwestern Public Service Company (SPS) retains
ownership of the turbogenerator. It has been arranged that Celanese would sell
steam to SPS, while the utility would sell part of the electricity back to
Celanese for 2.6 cents/kWh, including a standby power charge. The return for
Celanese was calculated to be almost 30 percent — however, they assumed that the
plant would operate 90 percent of the time at 100 percent capacity — which
appears to be overly optimistic.
4-38
CELANESE CHEMICAL COMPANY - SOUTHWESTERN PUBLIC SERVICE COMPANY
IDENTIFICATION
SYSTEM DESCRIPTION:
1450 PSIO/950°F
□ 650 PSIG/750°F.
PULVERIZED
COAL
*□
PULVERIZER
COAL
4-39
PRODUCTION/USE CHARACTERISTICS
FUEL USED (Type(s))- Lew sulfur Wyoming coal (assuming 75% efficiency)
ECONOMIC CHARACTERISTICS
*$15 million for cogeneration, rest for conversion to coal. Celanese owns
boilers -- SPS owns turbogenerator. Rate of return for Celanese to be
> 20%, for SPS > 15%.
4-40
PHILLIPS PETROLEUM COMPANY - SOUTHWESTERN PUBLIC SERVICE COMPANY
The steam generation plant at the Phillips Petroleum Company, Butadiene plant has
entered into an unusual arrangement with Southwestern Public Service Company in
1966. A 33 MW gas turbine, owned by the utility, was connected with the steam
plant. Exhaust gases from the gas turbine were fed to the seven 250,000 pound
per hour boilers and one 400,000 pound per hour boiler. The exhaust gases were
used as combustion air. Fuel savings have ranged from 15 to 25 percent.
4-41
PHILLIPS PETROLEUM COMPANY - SOUTHWESTERN PUBLIC SERVICE COMPANY
IDENTIFICATION
PLANT NAME:
Plains Butadiene Plant
SYSTEM DESCRIPTION:
COMBUSTION
TO PROCESS
NATURAL □
GAS
4-42
PRODUCTION/USE CHARACTERISTICS
ECONOMIC CHARACTERISTICS
ADDITIONAL COMMENTS:
4-43
SOUTHERN CALIFORNIA EDISON COMPANY
The Garden State Generating Station of Southern California Edison (SCE) was the
utility's first venture into cogeneration. The customer is the Pomona plant of
the Garden State Paper Company. The system consists of a 14.5 MW gas turbine
generator unit and a waste heat boiler equipped with supplementary firing. The
boiler is capable of supplying the paper company's steam requirements without
utilization of the gas turbine exhaust. The boiler is available for 8,600 hours
per year, but the turbine for only 8,100 hours. This is still an availability
factor of 94 percent, superior to most central power generation plants.
Even though the system has a relatively high net heat rate (6,330 Btu/kWh), it
is still much better than Southern California Edison could achieve with a
conventional generating unit. Assuming 10,200 Btu/kWh for conventional
generation and a fuel cost of $2.50 per million Btu, SCE saves $750,000 per year
on fuel costs on the unit, if it is assumed that the utility breaks even on
steam sales.
4-44
SOUTHERN CALIFORNIA EDISON COMPANY
IDENTIFICATION
Brayton Cycle - Combustion turbine with waste heat boiler equipped for
supplementary firing. Capacity is 120,000 pph at 75 psig.
BOILER
EXHAUST
GASES 75 PSIG
NATURAL
NATURAL
4-45
PRODUCTION/USE CHARACTERISTICS
ECONOMIC CHARACTERISTICS
ADDITIONAL COMMENTS:
4-46
STAUFFER CHEMICAL COMPANY
The information for the Stauffer Chemical Company plant in Henderson, Nebraska,
was very scanty, consisting of a description of the gas turbine in a Federal
Energy Regulatory Commission Docket and a telephone conversation with the power
plant manager. The system utilizes a gas turbine with exhaust gases feeding
into a waste heat boiler with supplementary firing. Steam from this boiler is
combined with steam from a direct-fired boiler and fed into a backpressure
turbine to produce additional electricity. The exhaust from the backpressure
turbine is routed to process steam. There are a number of advantages to this
type of system. It can produce electricity at a lower heat rate than a gas
turbine while producing more electricity per unit of steam than a normal Rankine
cycle. A combined cycle system provides additional flexibility in simultaneous
management of electric and steam demand — by adjusting the firing rate of the
gas turbine and the direct-fired boiler, the electric/steam ratio can be manipu
lated with a minimum loss in system efficiency. It also provides increased
reliability, since the loss of one component would still allow production of
steam and electricity.
4-47
STAUFFER CHEMICAL COMPANY
IDENTIFICATION
SYSTEM DESCRIPTION:
NATURAL
GAS *o—•-
□
4-48
PRODUCTION/USE CHARACTERISTICS
ANNUAL COGENERATION SYSTEM OUTPUTS: ELECTRIC 180,000 MWH
ECONOMIC CHARACTERISTICS
off-peak months.
ADDITIONAL COMMENTS:
UNION CARBIDE CORPORATION
The Union Carbide plant in Texas City produces a wide variety of products,
ranging from alcohols and olefins to plastics. Corresponding to the size and
function of the plant, the cogeneration system, incorporated in the design since
its inception in 1941, is a large, sprawling system consisting of gas turbines
and steam turbines located in four different powerhouses. Union Carbide considers
the system very reliable and is pleased with the operation of the system. Despite
the fact that some of the boilers are almost 40 years old, they are still
supplying steam and have an expected life of 15 to 20 additional years. The
only problem is with gas turbine performance, since they require delicate control
for optimum generation.
The gas turbines are equipped with heat recovery boilers and have capacities of
13 to 15 MW. Steam turbine sizes are 3, 4, and 9 MW. Unfortunately, Union
Carbide was reticent in providing a detailed description of the system. They
also considered natural gas consumption, total costs and operation and mainten
ance costs to be proprietary. Therefore, it was necessary to estimate fuel
consumption and system efficiency using heat rate, the partial description given,
and the figure given by Union Carbide for process steam use.
Union Carbide is satisfied with its return on past investments, but feels that
the rise in natural gas prices makes future cogeneration questionable, especially
with gas turbines. The company is now concentrating on heat recovery applications
and waste heat utilization.
4-50
UNION CARBIDE CORPORATION
IDENTIFICATION
SYSTEM DESCRIPTION:
Brayton Cycle - gas turbine with exhaust gases to waste heat boilers
producing process steam. Rankine cycle - natural gas fired boilers
produce steam at 1000 psig/600°F to turbogenerators exhaust steam at
200 psig and 70 psig for process.
WASTE HEAT
BOILER
1000 PSIG/600°F
600 PSIG
70 PSIG
2 0 PSIG
CONDENSATE
4-51
PRODUCTION/USE CHARACTERISTICS
ECONOMIC CHARACTERISTICS
4-52
SECTION 5
• Department of Energy
• Electric Utilities
• Gas Utilities
• Equipment Manufacturers
Table 5-1 shows the inventory of known cogeneration facilities. This inventory is
part of a Cogeneration Data Base being developed for EPRI. Efforts are currently
underway to expand this inventory and develop additional information on each
facility.
Table 5-2 shows a second list of cogenerators (using natural gas) that have filed,
or have indicated their intention to file, to the Federal Energy Regulatory
Commission (FERC) for a cogeneration exemption. Some of these cogenerators are
already included in the inventory in Table 5-1. Additional information will be
gathered when the applications for the cogeneration exemption are completed, and
will be included in the Cogeneration Data Base.
5-1
Table 5-1
TYPE OF CAPACITY
NAME OF FIRM LOCATION
SYSTEM* (MW)
NEW ENGLAND
Atlantic Gelatin Woburn, MA S 7.5
General Electric Lyon, MA S 65.0
Greater Lawrence Industrial Lawrence, MA S 17.0
Assoc.
James River Mass., Inc. Fitchburg, MA s 13.5
Mass. Bay Transit Authority South Boston, MA s 120.0
United Shoe Machinery Beverly, MA s 10.0
TOTAL NEW ENGLAND 233.0
MIDDLE ATLANTIC
AMSTAR Brooklyn, NY s 10.4
Bethlehem Steel Lackawanna, NY s 47.5
Eastman Kodak Rochester, NY s 113.7
International Paper Hudson, NY s 27.5
International Paper Ticonderoga, NY s 30.0
Procter & Gamble Port Ivory, NY s 10.5
American Cyanamid Bound Brook, NJ s 14.5
ARCO Polymers, Inc. Monaca, PA s 35.0
Avtex Fibers Meadville, PA s 17.0
Bethlehem Steel Bethlehem, PA S,I 44.0
Container Corp. of America Philadelphia, PA s 11.0
Crucible Steel Midland, PA s 24.0
Gulf Oil Philadelphia, PA s 36.0
Scott Paper Chester, PA s 10.4
Shenago, Inc. Pittsburgh, PA s 10.0
St. Joseph Zinc Josephtown, PA s 100.0
U.S. Government Philadelphia, PA s 22.5
U.S. Steel Clairton, PA s 35.0
U.S. Steel Fairless, PA s 60.0
U.S. Steel Northhampton, PA s 10.0
U.S. Steel Pittsburgh, PA s 65.0
U.S. Steel Pittsburgh, PA s 62.0
Westvaco Tyrone, PA s 17.1
TOTAL MIDDLE ATLANTIC 813.1
5-2
Table 5-1 (Continued)
5-3
Table 5-1 (Continued)
TYPE OF CAPACITY
NAME OF FIRM LOCATION
SYSTEM* (MW)
SOUTH ATLANTIC
DuPont Wilmington, DE S 22.5
Getty Oil Delaware City, DE S 100.0
Bethlehem Steel Sparrow Point, MD s 140.0
Cheasapeake Corp. of Virginia West Point, MD s 56.7
American Sugar Baltimore, MD s 10.0
U.S. Naval Gun Factory Washington, DC s 12.5
Dan River Mills Danville, VA s 19.4
Union Camp Franklin, VA s 81.5
Westvaco Covington, VA s 65.0
R. J. Reynolds Winston-Salem, NC s 32.5
Brunswick Pulp Paper Brunswick, GA s 26.0
Buckeye Cellulose Joley, FL s 32.5
Monsanto Textiles Pensacola, FL s 16.3
Sugar Growers of Florida Bella Glade, FL s 15.0
TOTAL SOUTH ATLANTIC 629.9
5-4
Table 5-1 (Continued)
TYPE OF CAPACITY
NAME OF FIRM LOCATION
SYSTEM* (MW)
5-5
Table 5-1 (Continued)
TYPE OF CAPACITY
NAME OF FIRM LOCATION
SYSTEM* (MW)
MOUNTAIN
FMC Green River, WY S 42.0
Amalgamated Twin Falls, ID S 10.9
Potlatch Lewiston, ID S 10.0
Stauffer Chemical Henderson, NV S, G 24.0
TOTAL MOUNTAIN 86.9
PACIFIC
Crown Zellerback Omak, WA S 12.0
ITT Rayonier Gray Harbor, WA S 10.8
Longview Fiber Longview, WA S 71.0
Simpson Timber Simpson, WA S 11.0
Weyerhauser Longview, WA S 81.0
Weyerhauser Aberdeen, WA S 15.0
Weyerhauser Everett, WA s 12.5
Brook Scanlon Bend, OR s 17.5
Roseburg Lumber Dillard, OR s 45.0
Weyerhauser Springfield, OR s 25.0
Applied Energy San Diego, CA s 14.0
Dow Chemical Pittsburgh, CA G 48.0
Kerr-McGee Trona, CA s 100.1
Holly Sugar Brawley, CA s 7.5
Louisiana-Pacific Eureka, CA s 27.5
Riverside Cement Oro Grande, CA s 15.0
Pacific Gas & Electric Martinez, CA s 46.0
Pacific Gas & Electric Oleum, CA s 87.0
Pacific Gas & Electric Avon, CA s 50.0
Stauffer Chemical Pinnades, CA G 15.5
Georgia Pacific Fort Bragg, CA S 14.0
TOTAL PACIFIC 725.4
5-6
Table 5-2
NAME OF COGENERATOR NATURAL GAS SUPPLIER NAME OF COGENERATOR NATURAL GAS SUPPLIER
American Can Co. Wise Public Service - Inland Steel Co. NIPSCO
Southern Natural Gas
International Salt Co. United Gas
American Cyanamid - Bound Public Service Electric &
Jones & Laughlin Steel NIPSCO
Brook Gas
Kennecott Minerals Co. El Paso
American Cyanamid - Atlanta Gas Co.
Savannah Kerr McGee Chemical Pacific Gas & Electric
American Optical Co. Boston Gas McLouth Steel Corp. Michigan Consolidated
AMOCO Oil Mississippi River Trans- Molycorp Inc. Gas Co. of New Mexico
mission
Monsanto Co. Illinois Power - Laclade -
Asmara Oil Public Service - Colorado United
Avtex Fibers Inc. National Fuel Gas Morton Salt ARKLA - Entex
BASF Wyandotte Michigan Consolidated Gas Morton Salt National Fuel - Pacific Gas
& Electric
Bethlehem Steel - Bethlehem United Gas Industries
N.L. Industries Mountain Fuel
Bethlehem Steel - Burns NIPSCO
Harbor Parke Davis - Warner Michigan Power
Lambert
Bethlehem Steel - Lackanana National Fuel Distribution
Co. Peachtree General - Cont. Georgia Natural Gas
Forest
Bethlehem Steel - Spassons Baltimore Gas & Electric
Point Phelps Dodge Corp. El Paso
Boise Southern United Gas Proctor & Gamble Gas Service Co.
Chevron USA Inc. Pacific Gas & Electric Riverside Cement - Amcord Pacific Gas & Electric
Carrier Corp. Peoples Natural Gas South Carolina Industries Carolina Pipeline
FMC Corp. Alkali Mountain Fuel Upson Co. N.Y. State Gas & Electric
Franklin Heating Peoples Natural Gas Warner Lambert - Parke Michigan Consolidated
Davis
Gates Rubber Co. Public Service
Western Electric Peoples - NIGAS
General Electric Boston Gas# NIGAS
White Pine Copper Michigan Power
Georgia Kraft Southeast Alabama
5-7
plant level information on capacity, type of generating system, and annual
generation. The detailed Form 4 data for 1978 was obtained from FERC and analyzed
to develop the statistical summary in Table 5-3, which shows the number of plants,
capacity and 1978 generation by Census Region.
• SIC 22 - Textiles
Table 5-4 shows the 1978 capacity and generation by SIC Code by Census Region.
The major electric utilities (Class A and B) report purchased power (amount and
cost) to FERC on Form 1. The 1976, 1977 and 1978 forms filed by the Class A and
B utilities were examined to develop the information provided in Table 5-5.
Unfortunately, the FERC Public Information Room does not have a complete set of
all forms filed by the utilities — hence the gaps in Table 5-5.
Gas turbine topping cycles will generally produce a higher ratio of electricity to
steam than a steam turbine topping cycle, but with a lower system efficiency. Gas
turbines are limited (within current state-of-the-art systems) to natural gas or
5-8
Table 5-3
TYPE OF GENERATION
REGION TOTAL*
HYDRO STEAM GAS TURBINE INTERNAL COMB.
NUMBER OF PLANTS
New England 8 26 0 6 38
Middle Atlantic 4 46 0 4 51
East North Central 3 76 1 7 86
West North Central 4 21 0 4 29
Wouth Atlantic 7 74 0 7 86
East South Central 1 24 0 2 27
West South Central 1 57 13 10 73
Mountain 3 25 0 11 38
Pacific 6 33 2 5 46
U.S. TOTAL 37 382 16 56 474
CAPACITY OF PLANTS
(MW)
New England 240 937 0 8 1,186
Middle Atlantic 44 1,561 0 62 1,668
East North Central 88 3,777 20 50 3,935
West North Central 43 723 0 17 783
South Atlantic 161 2,660 0 15 2,836
East South Central 8 803 0 3 813
West South Central 1 4,403 574 963 5,941
Mountain 4 856 0 185 1,045
Pacific 58 989 64 24 1,135
U.S. TOTAL 647 16,710 657 1,328 19,342
ANNUAL GENERATION**
New England 1,267 3,023 0 1 4,290
Middle Atlantic 245 6,410 0 293 6,948
East North Central 415 15,162 0 86 15,663
West North Central 191 3,303 0 43 3,536
South Atlantic 697 13,726 0 24 14,447
East South Central 338 4,413 0 7 4,488
West South Central 5 17,309 3,022 2,689 23,024
Mountain 17 3,256 0 314 3,581
Pacific 233 2,959 98 94 3,383
U.S. TOTAL 3,407 69,289 3,120 3,549 79,366
*Totals may not equal sum of the respective row since some industrial plants
employ combinations of different types of generation techniques.
5-9
Table 5-4
SIC CODE*
20 26 28 29 32 33 99
NUMBER OF PLANTS
New England 0 9 1 0 0 1 9
Middle Atlantic 2 10 4 3 1 17 8
East North Central 6 22 7 5 4 16 12
West North Central 2 2 1 2 1 2 6
South Atlantic 2 20 15 0 2 3 14
East South Central 0 10 2 0 0 6 2
West South Central 0 13 19 16 5 15 2
Mountain 1 2 3 0 0 16 1
Pacific 1 14 3 1 1 0 3
TOTAL 14 102 45 27 14 76 57
CAPACITY (MW)
New England 0 413 11 0 0 11 347
Middle Atlantic 21 197 115 93 15 718 246
East North Central 101 556 452 132 186 1,380 638
West North Central 49 54 23 41 12 30‘ 399
South Atlantic 26 1,299 409 0 134 267 366
East South Central 0 383 162 0 0 155 49
West South Central 0 700 1,891 826 413 1,436 341
Mountain 11 37 84 0 0 755 14
Pacific 13 352 164 20 15 0 68
*SIC Codes:
5-10
Table 5-5
Alabama Power Aluminum Co. of America DP 3,812 0.19 2,452 0.19 856 0.25
Republic Steel 476 0.12
U.S. Pipe & Foundry 2,026 0.25
Jim Walter Resources DP 11 0.25 46 0.25
Alabama River Pulp Co. DP 432 0.40
Alpena Power Huron Portland Cement 0 18,000 1.00 9,936 1.00 9,187 1.00
Arizona Public Service Co. Phelps Dodge Corp. FP 7 2.50 6 2.50 6 3.15
-11
Bangor Hydro-Electric Co. Diamond International DP 3,101 1.01 2,490 0.99 370 0.84
Great Northern Nekoosa DP 6,611 1.00
Carolina Power & Light Co. Rocky Mountains Mills DP 180 0.25 76 0.25 432 0.28
Sonoco Products DP 8 0.15 37 0.15 17 0.15
Central Hudson Gas & Electric Corp. Beacon Terminal Supply DP 35 1.84 81 1.70
Central Illinois Light & Power Hiram Walker DP 388 1.00 666 1.35 1,680 1.49
Central Vermont Public Service Corp Bethel Mills, Inc. DP 477 0.40 103 0.40
Table 5-5 (Continued)
Consumer Power Co. Dow Chemical Co. FP 6,083 0.84 3,221 0.69 1,057 0.47
Ul
ZT-
Delmarva Power & Light Co. Getty Oil Co. DP 58,143 2.21 84,082 2.46 63,285 2.51
Detroit Edison University of Michigan DP 2,380 0.93 2,075 0.94 3,076 0.97
Fitchburg Gas & Electric James River Mills, Inc. DP 391 0.90 949 0.647
Hawaiian Electric Co. Waialua Agriculture Co. DP 240 1.25 736 0.99 664 1.19
Hawaii Electric Light Co. Hilo Coast Proc. DP 290 0.40 101 0.40
Houston Light & Power Co. Texas Gulf Sulfur DP 640 0.54 325 0.52 133 0.50
Indianapolis Power & Light Co. General Motors 0 78 0.60 21 0.61 2,693 0.60
Kansas Power & Light Co. Bowersock Mills & Power 4,693 0.71
Lake Superior Distribution Co. Flambeau Paper DP 144 0.44 324 0.51
Maui Electric Co. Hawaiian Com. Sugar FP 7 6.26 709 0.67 10 6.80
Dole Co. FP 6,190 4.61 6,327 4.83 6,418 5.28
Table 5-5 (Continued)
Minnesota Power & Light Co. U.S. Steel DP 13/614 0.58 8,659 0.74 1,612 0.71
Northwest Paper DP 69 0.15 327 0.30 157 0.30
179 0.22
Blandin Paper DP 480 NA
Monongahela Power Co. Union Carbide DP 4,201 2.08 1,106 2.12 18,815 2.39
New England Power Georgia Pacific DP 1,020 0.57 518 0.56 195 0.64
Metropolitan Dist. Comm. DP 23,114 0.59
-14
Northern Indiana Public Service Co. Star Milling & Electric Co. FP 550 0.61 490 0.60
H. G. Rinkel & Son FP 319 0.58 120 0.50
Bethlehem Steel DP 4,480 0.37 2,596 0.41
Northern States Power Co. Ford Motors DP 27,472 0.35 39,805 0.35
Pacific Gas & Electric Co. Georgia Pacific DP 7,734 0.21 7,939 1.44 24,191 2.00
Brooks Scanlon DP 4,290 0.30 15,800 0.99
International Paper DP 2,669 0.22 272 0.90
ST-
Portland General Electric Co. Hanford Industries FP 40,311 0.80 42,286 0.80
Centralia FP 9,826 0.70 12,465 0.47
Lake Oswego DP 2,608 0.72
Publishers Paper Co. DP 350 0.86
Rochester Gas & Electric Co. Eastman Kodak DP 523 0.30 1,824 0.31 803 0.75
San Diego Gas & Electric Co. West Kootney 4,334 0.58
Encina Unit 5 FP 267,464 2.78
South California Edison Long Beach Combined Cycle 12,335 2.00 18,812 2.33
South Indiana Gas & Electric Hoosier Energy Division 0 188 2.52 495 1.89
Alcoa General Corp. 0 1,805 1.76
0 946,328 0.03
Toledo Edison Interlake Steel FP 1,117 13.75 1,563 11.74 883 9.80
Libby-Owens-Ford Co. 124 6.24
Utah Power & Light Co. National Lead Industries - DP 557 1.10
Magnesium Division
Temple Granite Quarry DP 818 —
U.S. Steel - Geneva Steel DP 1,533 0.45
Division
Table 5-5 (Concluded)
Western Massachusetts Electric Co. Premoid Corp. 494 1.00 397 1.34
Wisconsin Electric Power Co. Niagara of Wisconsin DP 680 0.15 838 0.25
Wisconsin Power & Light Co. Miller Duane FP 500 1.00 530 1.00 362 1.00
Wisconsin Public Service Corp. Scott Paper DP 338 0.39 162 0.50 378 0.42
Table 5-7
TYPE OF AMOUNT IN
INDUSTRY
PROCESS RESIDUAL TRILLION BTU
Source: Resource Planning Assoc., The Potential for Cogeneration in Six Major
Industries by 1985, 1977
5-18
distillate oil as fuels — both of which are becoming scarce and more expensive.
Steam turbines need only a source of steam, which allows new technologies for
steam production to be retrofitted to the system (such as fluidized bed combustion
for coal or municipal waste).
Seventy-five percent of the industrial plants and the steam used is consumed by
plants with alpha values less than 0.2. This ratio can be supplied by steam with
inlet conditions at 900 psi/900°F to a backpressure turbine with outlet conditions
to process as saturated steam at 150 psi. Though this would require boilers
producing steam at somewhat higher pressures and temperatures than many plants now
use, these are not extremely demanding conditions. One problem that arises with
these low electric-steam ratios is whether to design the system to merely meet
thermal loads or whether to design the system to generate excess electricity for
sale outside the plant. The conditions offered by utility companies concerning
standby charges and prices for cogenerated electricity will have a decisive influ
ence on the design of a cogeneration system. In the case of plants with high alpha
values, this decision is avoided; instead, the problem becomes whether to use
steam turbines and meet part of the electric demand or employ gas turbines or some
combination of the two and attempt to match electric and thermal demand.
One factor which can keep cogeneration economic under these circumstances is the
use of process residuals as fuels. By using a fuel whose cost is essentially zero
5-19
(though a value may be assigned to the product even though actually utilizing it
for other purposes would be difficult), low cost steam can be produced which can
be utilized to generate inexpensive electricity. The low boiler efficiencies of
some of these fuels (55 percent for pulp and paper wastes) is unimportant in this
case. There is an advantage in designing a waste fueled system; the low cost of
steam allows utilization of features such as condensing turbines to improve load
management which would be considered too inefficient under other circumstances.
5-20